+ All Categories
Home > Documents > Extract from the Construction Management Plan · 2017. 5. 1. · until design specification...

Extract from the Construction Management Plan · 2017. 5. 1. · until design specification...

Date post: 20-Jan-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
21
A document which outlines the purpose and processes associated with ECI at SCIRT. Lessons learned from one of New Zealand’s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011 - 2016. This document has been provided as an example of a tool that might be useful for other organisations undertaking complex disaster recovery or infrastructure rebuild programmes. For more information about this document, visit www.scirtlearninglegacy.org.nz Extract from the Construction Management Plan Story: Early Constructor Involvement (ECI) Theme: Programme Management
Transcript
Page 1: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design

A document which outlines the purpose and processes associated with ECI at SCIRT.

Lessons learned from one of New Zealand’s most challenging civil engineering projects:

rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of

Christchurch 2011 - 2016.

This document has been provided as an example of a tool that might be useful for other organisations undertaking complex disaster recovery or infrastructure rebuild programmes.

For more information about this document, visit www.scirtlearninglegacy.org.nz

Extract from the Construction Management Plan

Story: Early Constructor Involvement (ECI)

Theme: Programme Management

Page 2: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 3: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 4: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 5: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 6: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 7: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 8: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 9: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 10: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 11: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 12: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 13: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 14: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 15: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 16: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 17: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 18: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 19: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 20: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design
Page 21: Extract from the Construction Management Plan · 2017. 5. 1. · until design specification determined Items unable to be ordered 3.0 Procurement 3.1 4.0 4.1 Long Lead Items (Design

Recommended