PLASTERBOARD PLASTERBOARD DOUBLE 3mm Important The manufacturer strongly recommends timber studs or a minimum 0.75 BMT metal stud on both sides of the opening. Ensure that the frame opening is square, level, and measures: Single Door width +15mm maximum Double Door width +18mm maximum Door height +8mm at header +25mm at floor level. (Depending on floor clearance. Check with the project manager on site to confirm floor coverings.) SCAN CODE TO VIEW INSTALLATION VIDEO EzyJamb EZC Installation Instructions Step 1 For Sales and Technical Inquiries, please contact EZ Concept Australia T: (03) 9737 2500 | E: [email protected] | W: ezconcept.com.au DOOR WIDTH + 15mm PLASTERBOARD SURFACE DOOR OPENING FLOOR LEVEL Elevation DOOR HEIGHT + 33MM (+ 8mm at header, +25mm at floor level) Elevation DETAIL "D" "D" "E" LEVEL 200mm DETAIL "C" "B" DETAIL "E" FLOOR LEVEL Head Installation Instructions 2A Fasten hinge side first, making sure jamb is level and as tight against stud opening as possible. Then screw at 200mm centers up stile, screwing back through plasterboard into stud work. See detail B Double screw all ends as Detail D. and beside hinge position - both above and below hinge if using concealed hinges as Detail E. Step 2 Step 2A Head joiner as inserted in jamb. Locate head into joiner and make flush with jamb so the head joiner is not seen. Remove the remaining head joiner out of the strike jamb into the end of the head (as shown) to receive the strike jamb. PLASTERBOARD SCREW WOOD OR STEEL STUD EZYJAMB JAMB DETAIL EzyJamb EZC Installation Instructions EZ_AU_II_WB_JAN18
Transcript
Page 1: EZYJAMB EZC INSTALLATION INSTRUCTIONS Step 2 … · • Single Door width +15mm maximum • Double Door width +18mm maximum • Door height +8mm at header +25mm at floor level (depending

SP

EC

DA

TA

Version

Dimension A

Hinges Available from Manufacturer

EZC CLASSIC ADJUSTDOOR FRAME(FOR 44mm DOORS)

20 GAUGE EZYJAMB TRIMLESS DOOR FRAME(FOR 44mm DOORS)

STANDARD STRIKE PLATE HEIGHT FROM FINISHEDFLOOR TO CENTERLINE:for for 2040mm door, 910mmfor 2400mm door, 960mm

|

PLASTERBOARD

PLASTERBOARD

STEEL DOORFRAME

(EVERY 200mm)

PLASTERBOARD

DOUBLE

TYPICAL CORNER ASSEMBLY

STRIKE OPTIONS:

TYPICAL T-STRIKEASSEMBLY

3mm

3mm

INSTALLATION DETAIL

1. INVISIBLE TYPE:RocYork RY-30, RY-45, RY-50, RY-80Tectus 340Soss 216 & 416 2. EZY-JAMB STANDARD HINGESAll standard hinges are surface applied

4” Stainless Steel (SS)4” Satin Chrome (SC)4” Oil Rubbed Bronze (OB)

Specifications20 Gauge galvanneal steel door frame adjustable for wall thicknesses upto 225mm.

Fire Rated for upto US 90minute.UK FD30 andFD60 pending

4-7/8" ASA Strike2-3/4" T-Strike2-3/4" Deadbolt Strike

EZY

UK

_EZC

_SD

_011

7

Information contained within this document supersedes all previous versions and is subject to change without notice. 1/1

For Sales and Technical Enquiries, please contact Ezyjamb UK T: 02034889655 | E: [email protected] | W: www.ezyjamb.co.uk

ImportantThe manufacturer strongly recommends timber studs or a minimum 0.75 BMT metal stud on both sides of the opening.

Ensure that the frame opening is square, level, and measures:

• Single Door width +15mm maximum• Double Door width +18mm maximum• Door height +8mm at header +25mm at floor level.

(Depending on floor clearance. Check with the project manager on site to confirm floor coverings.)

SCAN CODE TO VIEW INSTALLATION VIDEO

EzyJamb EZC Installation Instructions

Step 1

For Sales and Technical Inquiries, please contact EZ Concept AustraliaT: (03) 9737 2500 | E: [email protected] | W: ezconcept.com.au

CLEAN LINES!… The Flush Finish Door Jamb System

Step 1

Ensure that the stud opening is square and level and measures:• Single Door width +15mm maximum• Double Door width +18mm maximum• Door height +8mm at header +25mm at floor level (depending on floor clearance. Check with the Project Manager on site to confirm floor coverings.)

Important: The manufacturer strongly recommends a timber stud or a 0.75 BMT metal stud on both sides of the opening.

DOOR WIDTH + 15mmPLASTERBOARD SURFACE

DOOR OPENING

FLOOR LEVEL

Elevation

Step 2

Fasten hinge side first, making sure jamb is level and as tight against stud opening as possible. Then screw at 200mm centers up stile, screwing back through plasterboard into stud work See Detail 'B' and 'C'. Double screw all ends as Detail D. and beside hinge position - both above and below hinge as Detail E.

Elevation

PLASTERBOARDSCREW

WOOD OR STEEL STUD

EZYJAMB

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm(8")

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

SEE STEP 2A

DOOR HEIGHT + 33MM

(+ 8mmat header,+25mm

at floor level)

Installation Instructions

EZY

_IN

STI

_161

2201

5

www.ezconcept.co.uk Phone 020 3488 9655

Step 1Ensure that the structural opening is square, level, and is the correct size.

Manufactured by STUDCO Building Systems

SCAN CODE TO VIEW INSTALLATION VIDEO

EZYJAMB EZC INSTALLATION INSTRUCTIONSStep 2

• Fasten hinge side first, making sure jamb is level andas tight against stud opening as possible. • Then screw at 200mm centers up stile, screwing backthrough drywall into stud jamb. • Double screw all ends as Detail D. and beside hingeposition - both above and below hinge if using concealedhinges as Detail E.

Elevation

SCREW

DOUBLE WOOD ORSTEEL STUD

DOUBLE WOOD ORSTEEL STUD

EZY JAMB

EZY JAMBEZY JAMB

DOOR

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

Step 2AHead Installation Instructions

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so thehead joiner is not seen.

Remove the remaining head joiner out of the strike jamb intothe end of the head (as shown) to receive the strike jamb.

2A

FRAME WIDTH + 15mmFOR STRUCTURAL OPENING

OPENING

FLOOR LEVEL

Elevation

FRAMEHEIGHT + 10mm

FORSTRUCTURAL

OPENING

3mm

DRYWALL

Important: Important:

When installing the Astra Concealed closer it is important to double screw above and below the closer and add extra �xings to the side of the closer.

Make sure the structural opening has double studs,the manufacturer strongly recommends wood studs or a minimum 20 gauge .030 metal studs on both sides of the opening. UK Fire Standards require no more than 3mm gap around the top and sides of the door, please take this into consideration when installing EZY Jamb. The provided instructions allow for this, leaving the required minimum clearance of 5mm at the bottom of the door.

www.ezconcept.co.uk Phone 020 3488 9655

Step 1Ensure that the structural opening is square, level, and is the correct size.

Manufactured by STUDCO Building Systems

SCAN CODE TO VIEW INSTALLATION VIDEO

EZYJAMB EZC INSTALLATION INSTRUCTIONSStep 2

• Fasten hinge side first, making sure jamb is level andas tight against stud opening as possible. • Then screw at 200mm centers up stile, screwing backthrough drywall into stud jamb. • Double screw all ends as Detail D. and beside hingeposition - both above and below hinge if using concealedhinges as Detail E.

Elevation

SCREW

DOUBLE WOOD ORSTEEL STUD

DOUBLE WOOD ORSTEEL STUD

EZY JAMB

EZY JAMBEZY JAMB

DOOR

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

Step 2AHead Installation Instructions

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so thehead joiner is not seen.

Remove the remaining head joiner out of the strike jamb intothe end of the head (as shown) to receive the strike jamb.

2A

FRAME WIDTH + 15mmFOR STRUCTURAL OPENING

OPENING

FLOOR LEVEL

Elevation

FRAMEHEIGHT + 10mm

FORSTRUCTURAL

OPENING

3mm

DRYWALL

Important: Important:

When installing the Astra Concealed closer it is important to double screw above and below the closer and add extra �xings to the side of the closer.

Make sure the structural opening has double studs,the manufacturer strongly recommends wood studs or a minimum 20 gauge .030 metal studs on both sides of the opening. UK Fire Standards require no more than 3mm gap around the top and sides of the door, please take this into consideration when installing EZY Jamb. The provided instructions allow for this, leaving the required minimum clearance of 5mm at the bottom of the door.

www.ezconcept.co.uk Phone 020 3488 9655

Step 1Ensure that the structural opening is square, level, and is the correct size.

Manufactured by STUDCO Building Systems

SCAN CODE TO VIEW INSTALLATION VIDEO

EZYJAMB EZC INSTALLATION INSTRUCTIONSStep 2

• Fasten hinge side first, making sure jamb is level andas tight against stud opening as possible. • Then screw at 200mm centers up stile, screwing backthrough drywall into stud jamb. • Double screw all ends as Detail D. and beside hingeposition - both above and below hinge if using concealedhinges as Detail E.

Elevation

SCREW

DOUBLE WOOD ORSTEEL STUD

DOUBLE WOOD ORSTEEL STUD

EZY JAMB

EZY JAMBEZY JAMB

DOOR

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

Step 2AHead Installation Instructions

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so thehead joiner is not seen.

Remove the remaining head joiner out of the strike jamb intothe end of the head (as shown) to receive the strike jamb.

2A

FRAME WIDTH + 15mmFOR STRUCTURAL OPENING

OPENING

FLOOR LEVEL

Elevation

FRAMEHEIGHT + 10mm

FORSTRUCTURAL

OPENING

3mm

DRYWALL

Important: Important:

When installing the Astra Concealed closer it is important to double screw above and below the closer and add extra �xings to the side of the closer.

Make sure the structural opening has double studs,the manufacturer strongly recommends wood studs or a minimum 20 gauge .030 metal studs on both sides of the opening. UK Fire Standards require no more than 3mm gap around the top and sides of the door, please take this into consideration when installing EZY Jamb. The provided instructions allow for this, leaving the required minimum clearance of 5mm at the bottom of the door.

www.ezconcept.co.uk Phone 020 3488 9655

Step 1Ensure that the structural opening is square, level, and is the correct size.

Manufactured by STUDCO Building Systems

SCAN CODE TO VIEW INSTALLATION VIDEO

EZYJAMB EZC INSTALLATION INSTRUCTIONSStep 2

• Fasten hinge side first, making sure jamb is level andas tight against stud opening as possible. • Then screw at 200mm centers up stile, screwing backthrough drywall into stud jamb. • Double screw all ends as Detail D. and beside hingeposition - both above and below hinge if using concealedhinges as Detail E.

Elevation

SCREW

DOUBLE WOOD ORSTEEL STUD

DOUBLE WOOD ORSTEEL STUD

EZY JAMB

EZY JAMBEZY JAMB

DOOR

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

Step 2AHead Installation Instructions

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so thehead joiner is not seen.

Remove the remaining head joiner out of the strike jamb intothe end of the head (as shown) to receive the strike jamb.

2A

FRAME WIDTH + 15mmFOR STRUCTURAL OPENING

OPENING

FLOOR LEVEL

Elevation

FRAMEHEIGHT + 10mm

FORSTRUCTURAL

OPENING

3mm

DRYWALL

Important: Important:

When installing the Astra Concealed closer it is important to double screw above and below the closer and add extra �xings to the side of the closer.

Make sure the structural opening has double studs,the manufacturer strongly recommends wood studs or a minimum 20 gauge .030 metal studs on both sides of the opening. UK Fire Standards require no more than 3mm gap around the top and sides of the door, please take this into consideration when installing EZY Jamb. The provided instructions allow for this, leaving the required minimum clearance of 5mm at the bottom of the door.

Head Installation Instructions

2A

• Fasten hinge side first, making sure jamb is level and as tight against stud opening as possible.

• Then screw at 200mm centers up stile, screwing back through plasterboard into stud work. See detail B

• Double screw all ends as Detail D. and beside hinge position - both above and below hinge if using concealed hinges as Detail E.

Step 2 Step 2A

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so the head joiner is not seen.

Remove the remaining head joiner out of the strike jamb intothe end of the head (as shown) to receive the strike jamb.

CLEAN LINES!… The Flush Finish Door Jamb System

Step 1

Ensure that the stud opening is square and level and measures:• Single Door width +15mm maximum• Double Door width +18mm maximum• Door height +8mm at header +25mm at floor level (depending on floor clearance. Check with the Project Manager on site to confirm floor coverings.)

Important: The manufacturer strongly recommends a timber stud or a 0.75 BMT metal stud on both sides of the opening.

DOOR WIDTH + 15mmPLASTERBOARD SURFACE

DOOR OPENING

FLOOR LEVEL

Elevation

Step 2

Fasten hinge side first, making sure jamb is level and as tight against stud opening as possible. Then screw at 200mm centers up stile, screwing back through plasterboard into stud work See Detail 'B' and 'C'. Double screw all ends as Detail D. and beside hinge position - both above and below hinge as Detail E.

Elevation

PLASTERBOARDSCREW

WOOD OR STEEL STUD

EZYJAMB

JAMB DETAIL DETAIL "D"

"D"

"E"

LEVEL

200mm(8")

DETAIL "C"

"B"

DETAIL "E"

FLOOR LEVEL

SEE STEP 2A

DOOR HEIGHT + 33MM

(+ 8mmat header,+25mm

at floor level)

Installation Instructions

EZY

_IN

STI

_161

2201

5

EzyJ

amb

EZC

Inst

alla

tion

Inst

ruct

ions

EZ

_AU

_II_

WB_

JAN

18

Page 2: EZYJAMB EZC INSTALLATION INSTRUCTIONS Step 2 … · • Single Door width +15mm maximum • Double Door width +18mm maximum • Door height +8mm at header +25mm at floor level (depending

www.ezconcept.co.uk Phone 020 3488 9655

Installation Detail

Information printed in this document or communicated by the designers, manufacturers, distributors or any agent issubject to change without notice to allow further development in design, manufacture and technology.

Step 4Insure the perforated side strips sit flat against thedrywall to enable the jamb sections to be easily plasteredinto the wall surface. All the corners must beplaster taped and plastered in as Detail F.Finish the jamb with drywall compound. Hang the door inposition leaving about 3mm clearance from the top andthe hinged side using the Ezy Jamb Standard or InvisibleHinges. Surface mount the striker plate into position toalign with the latch plate punching.

FLOOR LEVEL

DOOR

DETAIL"F"

DRYWALL

EZY JAMB

DOOR

3mm DRYWALL

DOUBLE STUD

3mm

SET INTO WALLSURFACE

Elevation

Step 3Fasten the final vertical section (strike jamb) below the headsection. Insure that the spacing between the two verticalsections are spaced evenly at the required distance.

FLOOR LEVEL

Elevation

EQUAL DISTANCE

EQUAL DISTANCE

EQUAL DISTANCE

STRIKE PLATE INSTALLATION DETAIL

TYPICAL T-STRIKEASSEMBLY

Fasten the final vertical section (strike jamb) below the headsection. Ensure that the spacing between the two verticalsections are spaced evenly at the required distance.

ie: 820 door, spacing is 825mm 720 door, spacing is 725mm

Step 3

For Sales and Technical Inquiries, please contact EZ Concept AustraliaT: (03) 9737 2500 | E: [email protected] | W: ezconcept.com.au

[email protected]

Step 2A

Head Installation Instructions

Head joiner as inserted in jamb.

Locate head into joiner and make flush with jamb so the head joiner is not seen.

Remove the remaining head joiner out of the strike jamb into the end of the head (as shown) to receive the strike jamb.

Step 3

Fasten the final vertical section (strike jamb)below the head section. Ensure that the spacing between the two vertical sections are spaced evenly at the required distance.

ie: 820 door, spacing is 825mm 720 door, spacing is 725mm

FLOOR LEVEL

Elevation

EQUAL DISTANCE

EQUAL DISTANCE

EQUAL DISTANCE

EXAMPLE OF 820mm DOOR - 825mm

EZY

_IN

STI

_161

2201

5

EZY

_IN

STI

_161

2201

5

Ensure the perforated side strips sit flat against the plasterboard to enable the jamb sections to be easily plastered into the wall surface.

All the corners must be paper taped and plastered in as Detail F.

Finish the jamb with plasterboard compound. Hang the door inposition leaving about 3mm clearance from the top and the hinged side using the EzyJamb Standard or Invisible Hinges.

Surface mount the striker plate into position to align with the latch plate punching.

Lift-Off Hinge Options

Step 4

SP

EC

DA

TA

Version

Dimension A

Hinges Available from Manufacturer

EZC CLASSIC ADJUSTDOOR FRAME(FOR 44mm DOORS)

20 GAUGE EZYJAMB TRIMLESS DOOR FRAME(FOR 44mm DOORS)

STANDARD STRIKE PLATE HEIGHT FROM FINISHEDFLOOR TO CENTERLINE:for for 2040mm door, 910mmfor 2400mm door, 960mm

|

PLASTERBOARD

PLASTERBOARD

STEEL DOORFRAME

(EVERY 200mm)

PLASTERBOARD

DOUBLE

TYPICAL CORNER ASSEMBLY

STRIKE OPTIONS:

TYPICAL T-STRIKEASSEMBLY

3mm

3mm

INSTALLATION DETAIL

1. INVISIBLE TYPE:RocYork RY-30, RY-45, RY-50, RY-80Tectus 340Soss 216 & 416 2. EZY-JAMB STANDARD HINGESAll standard hinges are surface applied

4” Stainless Steel (SS)4” Satin Chrome (SC)4” Oil Rubbed Bronze (OB)

Specifications20 Gauge galvanneal steel door frame adjustable for wall thicknesses upto 225mm.

Fire Rated for upto US 90minute.UK FD30 andFD60 pending

4-7/8" ASA Strike2-3/4" T-Strike2-3/4" Deadbolt Strike

EZY

UK

_EZC

_SD

_011

7

Information contained within this document supersedes all previous versions and is subject to change without notice. 1/1

For Sales and Technical Enquiries, please contact Ezyjamb UK T: 02034889655 | E: [email protected] | W: www.ezyjamb.co.uk

www.ezconcept.co.uk Phone 020 3488 9655

Installation Detail

Information printed in this document or communicated by the designers, manufacturers, distributors or any agent issubject to change without notice to allow further development in design, manufacture and technology.

Step 4Insure the perforated side strips sit flat against thedrywall to enable the jamb sections to be easily plasteredinto the wall surface. All the corners must beplaster taped and plastered in as Detail F.Finish the jamb with drywall compound. Hang the door inposition leaving about 3mm clearance from the top andthe hinged side using the Ezy Jamb Standard or InvisibleHinges. Surface mount the striker plate into position toalign with the latch plate punching.

FLOOR LEVEL

DOOR

DETAIL"F"

DRYWALL

EZY JAMB

DOOR

3mm DRYWALL

DOUBLE STUD

3mm

SET INTO WALLSURFACE

Elevation

Step 3Fasten the final vertical section (strike jamb) below the headsection. Insure that the spacing between the two verticalsections are spaced evenly at the required distance.

FLOOR LEVEL

Elevation

EQUAL DISTANCE

EQUAL DISTANCE

EQUAL DISTANCE

STRIKE PLATE INSTALLATION DETAIL

TYPICAL T-STRIKEASSEMBLY

Installation Detail

CLEAN LINES!… The Flush Finish Door Jamb System

Step 4

Ensure the perforated side strips sit flat against the plasterboard to enable the jamb sections to be easily set into the wall surface. All the corners must be taped and plastered/jointed in as Detail F. Finish the jamb with approved plaster/jointing compound. Hang the door in position leaving about 3mm clearance from the top and the hinged side using the EZYJamb Standard or Invisible Hinges. Surface mount the striker plate into position to align with the latch plate punching.

200mm

PLASTERBOARD

WOOD OR STEEL WALL

STUD

SCREW FASTEN ONLY

REINFORCEDROLLED EDGE PERFORATED

SIDE STRIPSADJUSTABLE SIDE SECTION FRICTION FITTED TO STOP

STEEL JAMB

DOOR

HINGE

PLASTER/JOINTING COMPOUND

VARYING SIZES

SCREWSLATCH PLATE

LATCH PLATE INSERT

Standard Herline EZYJamb Lift-Off hinges Rocyork concealed hinges

For all semi solid and solid core doors, outerleaf of hinge must be fixed to stile so that at least two screws are fixed back to the walls’ primary structure.

Installation Detail

Hinges Available

PLASTER

HINGE

DOOR

SCREW BACKTO SUBSTRATE

STEEL JAMB

SCREW FIXING ONLY

TIMBER OR STEEL WALL

STUD

FLOOR LEVEL

DOOR

DETAIL"F"

PLASTERBOARD

EZYJAMB

DOOR

3mm PLASTERBOARD

STUD

3mm

Elevation

SET INTO WALL SURFACE

2008

SCREWS

EZY

_IN

STI

_161

2201

5

SP

EC

DA

TA

Version

Dimension A

Hinges Available from Manufacturer

EZC CLASSIC ADJUSTDOOR FRAME(FOR 44mm DOORS)

20 GAUGE EZYJAMB TRIMLESS DOOR FRAME(FOR 44mm DOORS)

STANDARD STRIKE PLATE HEIGHT FROM FINISHEDFLOOR TO CENTERLINE:for for 2040mm door, 910mmfor 2400mm door, 960mm

|

PLASTERBOARD

PLASTERBOARD

STEEL DOORFRAME

(EVERY 200mm)

PLASTERBOARD

DOUBLE

TYPICAL CORNER ASSEMBLY

STRIKE OPTIONS:

TYPICAL T-STRIKEASSEMBLY

3mm

3mm

INSTALLATION DETAIL

1. INVISIBLE TYPE:RocYork RY-30, RY-45, RY-50, RY-80Tectus 340Soss 216 & 416 2. EZY-JAMB STANDARD HINGESAll standard hinges are surface applied

4” Stainless Steel (SS)4” Satin Chrome (SC)4” Oil Rubbed Bronze (OB)

Specifications20 Gauge galvanneal steel door frame adjustable for wall thicknesses upto 225mm.

Fire Rated for upto US 90minute.UK FD30 andFD60 pending

4-7/8" ASA Strike2-3/4" T-Strike2-3/4" Deadbolt Strike

EZY

UK

_EZC

_SD

_011

7

Information contained within this document supersedes all previous versions and is subject to change without notice. 1/1

For Sales and Technical Enquiries, please contact Ezyjamb UK T: 02034889655 | E: [email protected] | W: www.ezyjamb.co.uk

CLEAN LINES!… The Flush Finish Door Jamb System

Step 4

Ensure the perforated side strips sit flat against the plasterboard to enable the jamb sections to be easily set into the wall surface. All the corners must be taped and plastered/jointed in as Detail F. Finish the jamb with approved plaster/jointing compound. Hang the door in position leaving about 3mm clearance from the top and the hinged side using the EZYJamb Standard or Invisible Hinges. Surface mount the striker plate into position to align with the latch plate punching.

200mm

PLASTERBOARD

WOOD OR STEEL WALL

STUD

SCREW FASTEN ONLY

REINFORCEDROLLED EDGE PERFORATED

SIDE STRIPSADJUSTABLE SIDE SECTION FRICTION FITTED TO STOP

STEEL JAMB

DOOR

HINGE

PLASTER/JOINTING COMPOUND

VARYING SIZES

SCREWSLATCH PLATE

LATCH PLATE INSERT

Standard Herline EZYJamb Lift-Off hinges Rocyork concealed hinges

For all semi solid and solid core doors, outerleaf of hinge must be fixed to stile so that at least two screws are fixed back to the walls’ primary structure.

Installation Detail

Hinges Available

PLASTER

HINGE

DOOR

SCREW BACKTO SUBSTRATE

STEEL JAMB

SCREW FIXING ONLY

TIMBER OR STEEL WALL

STUD

FLOOR LEVEL

DOOR

DETAIL"F"

PLASTERBOARD

EZYJAMB

DOOR

3mm PLASTERBOARD

STUD

3mm

Elevation

SET INTO WALL SURFACE

2008

SCREWS

EZY

_IN

STI

_161

2201

5

TYPICALSTRIKER PLATE ASSEMBLY

CLEAN LINES!… The Flush Finish Door Jamb System

Step 4

Ensure the perforated side strips sit flat against the plasterboard to enable the jamb sections to be easily set into the wall surface. All the corners must be taped and plastered/jointed in as Detail F. Finish the jamb with approved plaster/jointing compound. Hang the door in position leaving about 3mm clearance from the top and the hinged side using the EZYJamb Standard or Invisible Hinges. Surface mount the striker plate into position to align with the latch plate punching.

200mm

PLASTERBOARD

WOOD OR STEEL WALL

STUD

SCREW FASTEN ONLY

REINFORCEDROLLED EDGE PERFORATED

SIDE STRIPSADJUSTABLE SIDE SECTION FRICTION FITTED TO STOP

STEEL JAMB

DOOR

HINGE

PLASTER/JOINTING COMPOUND

VARYING SIZES

SCREWSLATCH PLATE

LATCH PLATE INSERT

Standard Herline EZYJamb Lift-Off hinges Rocyork concealed hinges

For all semi solid and solid core doors, outerleaf of hinge must be fixed to stile so that at least two screws are fixed back to the walls’ primary structure.

Installation Detail

Hinges Available

PLASTER

HINGE

DOOR

SCREW BACKTO SUBSTRATE

STEEL JAMB

SCREW FIXING ONLY

TIMBER OR STEEL WALL

STUD

FLOOR LEVEL

DOOR

DETAIL"F"

PLASTERBOARD

EZYJAMB

DOOR

3mm PLASTERBOARD

STUD

3mm

Elevation

SET INTO WALL SURFACE

2008

SCREWS

EZY

_IN

STI

_161

2201

5

CLEAN LINES!… The Flush Finish Door Jamb System

Step 4

Ensure the perforated side strips sit flat against the plasterboard to enable the jamb sections to be easily set into the wall surface. All the corners must be taped and plastered/jointed in as Detail F. Finish the jamb with approved plaster/jointing compound. Hang the door in position leaving about 3mm clearance from the top and the hinged side using the EZYJamb Standard or Invisible Hinges. Surface mount the striker plate into position to align with the latch plate punching.

200mm

PLASTERBOARD

WOOD OR STEEL WALL

STUD

SCREW FASTEN ONLY

REINFORCEDROLLED EDGE PERFORATED

SIDE STRIPSADJUSTABLE SIDE SECTION FRICTION FITTED TO STOP

STEEL JAMB

DOOR

HINGE

PLASTER/JOINTING COMPOUND

VARYING SIZES

SCREWSLATCH PLATE

LATCH PLATE INSERT

Standard Herline EZYJamb Lift-Off hinges Rocyork concealed hinges

For all semi solid and solid core doors, outerleaf of hinge must be fixed to stile so that at least two screws are fixed back to the walls’ primary structure.

Installation Detail

Hinges Available

PLASTER

HINGE

DOOR

SCREW BACKTO SUBSTRATE

STEEL JAMB

SCREW FIXING ONLY

TIMBER OR STEEL WALL

STUD

FLOOR LEVEL

DOOR

DETAIL"F"

PLASTERBOARD

EZYJAMB

DOOR

3mm PLASTERBOARD

STUD

3mm

Elevation

SET INTO WALL SURFACE

2008

SCREWS

EZY

_IN

STI

_161

2201

5

EZYJamb lift-off hinges allow forremoval of a hinged door withouthaving to unscrew the hinges.The lift-off hinges are finished inbrushed stainless steel for a look withclass and style and are easy to fit.Lift-off Hinges are available in bothleft and right handing andrecommended for internal use.

The Lift-off channelsupplied is designedto fit over the headerstop and affixed withconstruction adhesive.

STEP 1

INSTALLATION INSTRUCTIONS

ELEVATION

ENSURE THAT THE DOOR OPENING ISSQUARE AND PLUMB AND MEASURES:• Door width + 15mm maximum• Door height + 33mm

(depending on floor clearance)

Manufactured by STUDCO AUSTRALIA PTY LTD

www.ezyjamb.com.auT: 1300 399 5262

STEP 4

ELEVATION

Ensure the perforated side strips sit flat against theplaster to enable the jamb sections to be easily setinto the wall surface. ALL THE CORNERS MUSTBE PAPER TAPED AND SET IN AS Detail D.

Set jamb with approved plaster compound. Hangthe door in position leaving about 2mm clearancefrom the top and the hinged side using the EZYJambHirline Hinge.

Surface mount the striker plate into position to alignwith the latch plate punching.

INSTALLATION DETAIL

Information printed in this document or communicated by the designers, manufacturers, distributors or any agent is subject to change without notice to allow further development in design, manufacture and technology.

EZYJamb lift-off hinges allow for removal of a hinged door without having to unscrew the hinges. The lift-off hinges are finished in brushed stainless steel for a look with class and style and are easy to fit.Lift-off Hinges are available in both left and right handing and recommended for internal use.

The Lift-off channel supplied is designed to fit over the header stop and affixed with construction adhesive.

EZYJamb

Lift-off Channel Lift-off Channel Installed

Right (AUSTRALIAN HANDING)

Left (AUSTRALIAN HANDING)

LIFT-OFF HINGE OPTION

(+ 8mmat header,+25mm

at floor level)

STEP 1

INSTALLATION INSTRUCTIONS

ELEVATION

ENSURE THAT THE DOOR OPENING ISSQUARE AND PLUMB AND MEASURES:• Door width + 15mm maximum• Door height + 33mm

(depending on floor clearance)

Manufactured by STUDCO AUSTRALIA PTY LTD

www.ezyjamb.com.auT: 1300 399 5262

STEP 4

ELEVATION

Ensure the perforated side strips sit flat against theplaster to enable the jamb sections to be easily setinto the wall surface. ALL THE CORNERS MUSTBE PAPER TAPED AND SET IN AS Detail D.

Set jamb with approved plaster compound. Hangthe door in position leaving about 2mm clearancefrom the top and the hinged side using the EZYJambHirline Hinge.

Surface mount the striker plate into position to alignwith the latch plate punching.

INSTALLATION DETAIL

Information printed in this document or communicated by the designers, manufacturers, distributors or any agent is subject to change without notice to allow further development in design, manufacture and technology.

EZYJamb lift-off hinges allow for removal of a hinged door without having to unscrew the hinges. The lift-off hinges are finished in brushed stainless steel for a look with class and style and are easy to fit.Lift-off Hinges are available in both left and right handing and recommended for internal use.

The Lift-off channel supplied is designed to fit over the header stop and affixed with construction adhesive.

EZYJamb

Lift-off Channel Lift-off Channel Installed

Right (AUSTRALIAN HANDING)

Left (AUSTRALIAN HANDING)

LIFT-OFF HINGE OPTION

(+ 8mmat header,+25mm

at floor level)

EzyJ

amb

EZC

Inst

alla

tion

Inst

ruct

ions

EZ

_AU

_II_

WB_

JAN

18


Recommended