Facilities Modernization Program Funded by Measure B Project Report. November 19, 2012. PROJECT PROGRESS REPORT Student Services & Central Administration. LAS POSITAS COLLEGE November 19, 2012. Project Team: Architect : Steinberg Architects - PowerPoint PPT Presentation
Popular Tags:
4
Facilities Modernization Program Funded by Measure B Project Report November 19, 2012
Transcript
Page 1: Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization ProgramFunded by Measure B

Project Report

November 19, 2012

Page 2: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction

Project Update:• Ceiling tile is being installed on the 2nd floor. 85% complete.• Sheet Vinyl is complete on the 2nd floor. Tile installation in the 1st floor kitchen and servery areas are complete.• Interior trim is 85% complete. Kitchen Equipment is 75% installed.• Ceilings in the dining areas are underway.• Site concrete is 95% complete. Irrigation and planting are complete. Paver installation has started.

Occupancy: Spring 2013

LAS POSITAS COLLEGENovember 19, 2012

Page 3: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: Suarez & Munoz Construction, Inc.

Project Update:• Concrete Pathways 100% Complete, with parts of the pathways open. Library and Grand Stairs 98%

Complete • Underground Electrical and Lighting are 100% Complete• Boulders for the wet fountain have been placed, with the dry art area completed and are open to students

and faculty• Underground mainlines and laterals are 100% completed.• Grading work is 90% completed with planting continuing with completion to be 11/29/12

Occupancy: 11/30/12

LAS POSITAS COLLEGENovember 19, 2012

Page 4: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc

Project Update:• New Science Bldg 1850 Complete, Punch List work in progress• Bldg 1800 Remodel Complete, Punch List work in progress• Closeout in progress

Occupancy: 09/2012