Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
1
Feasibility Report
On
Gasoline Hydrotreatment Unit (GTU )
and Associated Facilities
Bharat Petroleum Corporation Ltd. Mumbai Refinery
March 2016
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
2
Index
Chapter 1 Executive Summary
Chapter 2 Introduction
Chapter 3 Objectives
Chapter 4 Basis and Assumptions
Chapter 5 Evaluation of Alternatives
Chapter 6 Project Description
Chapter 7 Process Description
Chapter 8 Utilities & Offsites
Chapter 9 Unit Capacities
Chapter 10 Catalyst
Chapter 11 Unit Plot Layout
Chapter 12 Project Schedule
Chapter 13 Cost Estimates
Chapter 14 Benefits and Profitability
Annexure-1 Government Policy of Auto fuels upgradation
Annexure-2 Proposed BS V/VI MS specification
Annexure-3 Proposed Plot Plan for GTU
Annexure-4 Project Cost Estimate
Annexure-5 IDC calculation for the project
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
3
Chapter 1 - Executive Summary
Objective:
In order to meet the government mandate of producing 100% BS-VI MS w.e.f 1st April 2020 ,
Bharat Petroleum Corporation Limited, Mumbai Refinery (BPCL-MR) intends to set up a
Gasoline Hydro Treatment Unit (GTU) of 0.9 MMTPA capacity This is in line with the
guidelines established in Auto Fuel Policy and Vision 2025 as well as communication from
MOP&NG, R-29011/23/2012-OR-I. GTU would hydrotreat cracked Gasoline ex CCU /FCCU
and the Gasoline product from new GTU will conform to BS-VI specification of max. 10
ppmw sulphur.
Along with GTU, the following associated facilities will be revamped/modified as
per requirement, based on adequacy study :
Revamp of DHT Amine Regeneration Unit to treat additional Rich amine from GTU.
Revamp of existing Sour Water Stripper Units to treat additional sour water generated
from GTU.
Existing HGU-2 (Hydrogen Generation Unit) and SRU are being revamped under DHT
project .These units will cater to the requirements of Hydrogen and processing of acid gas
respectively,for GTU.
Background:
Mumbai Refinery has an installed crude processing capacity of 12 MMTPA. The Refinery
configuration has undergone several modifications over the years to include various secondary
processing units and currently has the capability of producing BS-III/IV grades of MS and
HSD which are in line with the present Auto Fuel (AF) Policy. MR has recently undertaken / is
implementing the following major projects:
Continuous Catalyst Regeneration Reformer (CCR): The unit has been commissioned in
March 2014. This project enables production of 1.1 / 0.9 MMTPA of BS-III/BS-IV MS
respectively (total 2.0 MMTPA).
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
4
New Crude / Vacuum Distillation Unit (CDU4): A state-of-the-art integrated crude and
vacuum unit has been commissioned in Nov 2015. The project has improved the Fuel &Loss,
yields,safety and reduced energy consumption significantly vis-à-vis the old Crude Distillation
Units.
Conversion of Catalytic Reforming Unit (CRU) to Isomerization Unit (ISOM): With the
implementation of ISOM unit, MR would be capable of producing total BS-IV (2.4 MMTPA)
and meeting 2017 Auto Fuels (AF) mandate for MS.
Installation of Diesel Hydrotreatment Unit (DHT) and associated facilities to produce
100% BS IV HSD: MR is implementing this project to produce 100% BS IV HSD for meeting
2017 HSD Auto Fuels (AF) mandate.
MOP&NG had constituted an expert committee under the chairmanship of Member, Planning
Commission, Govt. of India for preparing “Auto Fuel Vision and Policy 2025 (AFVP 2025)”.
Members of oil industry were also part of the committee / working groups. Based on this
expert committee recommendation, it is proposed to introduce total BS-VI AF in the entire
country by 1st April 2020.
With implementation of DHT and with catalyst change in existing Diesel Hydro
desulphurisation (DHDS) Unit, MR would be capable of producing total BS-V / BS-VI HSD.
In order to select the best configuration of refinery to meet the MS product quality as per BS-
VI MS specifications, an internal study using Aspen Linear Programme Model (PIMS) was
conducted. Based on the study, it was found essential to set up a GTU (Gasoline
Hydrotreatment Unit ) of 0.9 MMTPA capacity along with associated facilities to meet the AF
mandate.
Benefit of the proposal:
Installation of GTU is an absolute business necessity for meeting the proposed specifications
of 100% BS VI MS for the entire country w.e.f 1st April 2020 while ensuring strategic
supply security for BPCL. This proposal is a mandatory product quality improvement project
which will ensure product security for MS and sustaining crude throughput at 13 MMTPA.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
5
Plot Plan:
It is proposed to set up GTU in the old Catalytic Reforming Unit (CRU)/New Solvent Unit
(NSU ) plot area, which would be dismantled post commissioning of Isomerisation unit . Based
on preliminary indications plot area required for 0.9 MMTPA GTU is 4000-5000 Sq Meters.
Refer Annexure -3 for the proposed plot for GTU.
Utilities & offsites:
Utility requirements of GTU facilities like Power, Cooling Water, Raw Water, Plant Air,
Instrument Air, Nitrogen, Steam, DM Water, BFW, Condensate etc can be met from existing
systems.
Fuel requirement will be met with RLNG, which is environmentally neutral.
Environmental Impact:
Environmental Impact Assessment (EIA) and Quantitative Risk Assessment (QRA) study will
be carried out in order to obtain Environmental Clearance for the project.
Capital Cost:
As per preliminary estimates, Capital cost for putting up the GTU and associated facilities with
+/- 30% accuracy is about Rs. 554 Crores. Breakup of capital cost estimate is provided in
Chapter-13.
BPCL Board has accorded approval on 12.2.2016 for Installation of GTU and associated
facilities to produce 100% BS-VI MS.
Schedule:
Schedule for the project activities is as follows:
Sr. No. Activity Description Proposed Schedule
A
Project Management Consultant (PMC ) and
Engineering Procurement & Construction
Management (EPCM) Consultant
1. Award of PMC/EPCM Contract May-2016
2. Prepare + / - 10% Cost Estimate Feb-2017
3. Order Long Lead Items Nov-2016
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
6
4. Mechanical Completion Dec-2019
B Environmental Clearance
1. Award Contract for EIA / RRA Studies May-2016
2. Complete EIA / RRA Studies Aug -2016
3. Environmental Clearance Sept-2016
C Basic Engineering Design Package (BEDP)
1. Licensor Selection & Approval July-2016
2. BEDP Jan-2017
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
7
Chapter 2 - Introduction
BPCL-MR has an installed crude processing capacity of 12 MMTPA. The Refinery
configuration has undergone several modifications over the years to include various secondary
units and currently has the capability of producing BS-III/IV grades of MS and HSD which are
in line with the present Auto Fuel (AF) Policy.
MOP&NG has constituted an expert committee under the chairmanship of Member, Planning
Commission, Government of India for preparing “Draft Auto Fuel Vision and Policy 2025”.
Members of oil industry also form a part of the committee / working groups. Various meetings
were held and the report is in advanced stage of completion. The expert committee proposes to
introduce total BS-IV AF in the entire country by 1st April 2017 & total BS-V/VI AF by 1st
April 2020.However, there is no difference in fuel quality between BS-V and BS-VI (Refer
Annexure-2).
With implementation of DHT and with catalyst change in existing Diesel Hydro-
desulphurisation (DHDS) Unit, MR would be capable of producing total BS-V / BS-VI HSD..
In order to select the best configuration of refinery to meet the MS product quality as per BS-
V/VI MS specifications, an internal study using Aspen Linear Programme Model (PIMS) was
conducted. Based on the study, it was found essential to set up a GTU (Gasoline
Hydrotreatment Unit ) of 0.9 MMTPA capacity along with associated facilities to meet the AF
mandate.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
8
Chapter 3 - Objective
The objective of the proposal is to install Gasoline Hydrotreatment Unit (GTU) of 0.9 MMTPA
capacity at BPCL-MR in order to meet the government mandate of producing 100% BS-VI MS
w.e.f. 1st April 2020.
Impurities such as sulphur will be removed from the feed stocks by reaction with Hydrogen at
high pressure and high temperature to meet the BS-VI specification for MS.
Installation of a GTU is necessary for meeting the proposed specifications of 100% BS-VI MS
for the entire country as per Auto Fuel mandates w.e.f. 1st April 2020. In the absence of GTU,
MR would be capable of producing only 1.1 MMTPA of BS-VI MS post ISOM and the
balance MS to the extent of 1.2 MMTPA will be of BS-IV quality.
The above situation would entail exports of 1.2 MMTPA BS-IV MS and simultaneous imports
of equivalent quantity of BS-VI MS to meet the market requirements supplied by MR
Along with GTU, the following associated facilities will be revamped/modified as
per requirement based on adequacy study :
Revamp of DHT Amine Regeneration Unit to treat additional rich amine from GTU.
Revamp of existing Sour Water Stripper Units to treat additional sour water generated
from GTU.
Existing HGU-2 (Hydrogen Generation Unit) and SRU are being revamped under DHT
project .These units will cater to the requirements of Hydrogen and processing of acid gas
respectively, for GTU.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
9
Chapter 4 – Basis & Assumptions
4.1 Capacity:
In order to select the best configuration of refinery to meet the MS product quality as per BS-
VI MS specifications, an internal study using Aspen Linear Programme Model (PIMS) was
conducted. Based on this study it was established that in order to meet the BS-VI MS quality as
per government mandate for Auto Fuels, GTU with a capacity of 0.9 MMTPA (2700 MT/D).
needs to be installed at BPCL-MR.
4.2 Feed Stock:
Feed stocks for Gasoline Hydrotreatment Unit (GTU) will be a mix of Cracked Gasoline from
CCU and FCCU units.
Hydrogen requirement for the unit will be catered by HGU-2 ,which is being revamped under
DHT project.
4.3 Yields:
In the absence of GTU Unit, under the present conditions, BPCL-MR is capable of producing
only 1.1 MMTPA of BS-VI MS and the balance MS to the extent of 1.2 MMTPA will be of
BS-IV quality. Production of BS-VI MS pre and post GTU is as follows :
MMTPA Before GTU Post GTU
BS-IV MS 1.2 0.0
BS-VI MS 1.1 2.3
Total MS 2.3 2.3
4.4 Cost:
Capital cost for putting up the GTU and associated facilities with +/- 30% accuracy is about Rs
554 Cr. Breakup of capital cost estimate is provided in Chapter-13.
4.5 Financing:
A debt to equity ratio of 1.5:1 is considered.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
10
4.6 Interest Rate:
The interest rate of 10 % is considered.
4.7 Production Build-up / Sales realization:
The Sales realization has been assumed as 90% from the first year of commissioning and 100%
for each subsequent year.
4.8 Pollution Abatement:
Modern process units are heat integrated to minimize the fuel consumption and have higher
efficiency furnace. In view of only fuel gas / Regasified Liquefied Natural Gas (RLNG) firing
in GTU furnaces the project will have marginal impact on the environment.
Further, low NOx burners will be installed in GTU furnaces which will help in reducing NOx
emissions.
No continuous effluent generation from GTU is envisaged. Any intermittent effluent
generation will be treated in the existing ETP.
The very purpose of installing GTU is to remove pollutants / impurities such as sulphur and
trace metal from the feed stocks. This will help in reducing emission of air pollutants such as
Sulphur Oxides (SOx ).
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
11
Chapter 5 – Evaluation of Alternatives
It has been proposed by the expert committee on ‘Auto Fuel Vision and Policy 2025” to
introduce total BS-VI Auto Fuel (MS & HSD) from 1st April 2020 and discontinue supply of
BS-IV MS & HSD in Indian domestic market. With the present configuration of BPCL-MR, it
is capable of producing 1.2 MMTPA of BS-IV MS and 1.1 MMTPA of BS-VI MS.
In order to meet the proposed requirement of supplying total BS-VI MS from refinery,
following options were considered;
Option-1: Exports of 1.2 MMTPA BS-IV MS and simultaneous imports of equivalent
quantity of BS-VI MS.
Impact of implementing this option:
The combined handling of 2.4 MMTPA of MS will require hiring of huge infrastructure
facilities. Further, the reduced BS-VI MS availability of 1.1 MMTPA will have overall impact
on supply security for BPCL, which is critical for marketing interests. BPCL will have huge
constraints in terms of product availability which will lead to higher dependencies of sourcing
BS-VI MS. Any delay in availability of product is bound to have adverse impact in meeting the
market requirements.
Option-2: Installation of VGO Hydrodesulphurisation unit for meeting the proposed
specifications of 100% BS-VI MS for the entire country .
Impact of implementing this option:
Based on internal study using Aspen Linear Programme Model (PIMS) it was established that
current refinery configuration does not call for hydro-treatment of entire VGO. Only cracked
Gasoline from CCU and FCCU require hydro-treatment to meet BS VI specifications. VGO
HDS is a high capital intensive project with lower returns.
Option-3: Installation of a GTU for meeting the proposed specifications of 100% BS-VI
MS for the entire country.
Impact of implementing this option:
As per the proposed Auto Fuel Policy, after the full roll-out of BS-IV MS by April 2017, it is
expected that BS-VI Grades will be introduced in the entire country by April 2020. The
availability of GTU at BPCL-MR will be crucial since it will be extremely useful in producing
the BS-VI Grades. Otherwise the import / export losses would further worsen the situation.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
12
Based on the above and considering the overall impact on supply security for BPCL, Option-3
has been selected.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
13
Chapter 6 – Project Description
The facilities envisaged in the project comprise of Gasoline Hydrotreatment Unit (GTU) of
0.9 MMTPA capacity along with associated facilities.
The GTU project comprises of a Selective Hydrogenation Unit (SHU), fractionation of
gasoline into light cut and heavy cut gasoline followed by Selective Hydro Desulphurisation
(Selective HDS) and Stabilisation of ultra low sulphur heavy cut gasoline.
Along with GTU, the following associated facilities will be revamped/modified as
per requirement, based on adequacy study :
Revamp of DHT Amine Regeneration Unit to treat additional Rich amine from GTU.
Revamp of existing Sour Water Stripper Units to treat additional sour water generated
from GTU.
Existing HGU-2 (Hydrogen Generation Unit) and SRU are being revamped under DHT
project .These units will cater to the requirements of Hydrogen and processing of acid gas
respectively, for GTU.
Pre-project activities
Pre-project activities envisaged are as follows :
Award of PMC/EPCM Contract
Licensor selection
Environmental Impact Assessment (EIA) / Rapid Risk Analysis (RRA) study
Obtain Environmental Clearance
Preparation of BEDP by the selected licensor
Parallel implementation of EPCM activities (Detailed Engineering / procurement of long
lead items / Preparation of cost estimate having + / - 10% accuracy)
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
14
Chapter 7 – Process Description
The GTU project comprises of a Selective Hydrogenation Unit (SHU), fractionation of gasoline
into light cut and heavy cut gasoline followed by Selective Hydro Desulphurisation (Selective
HDS) and Stabilisation of ultra low sulphur heavy cut gasoline.
Cracked gasoline from CCU and FCCU is routed to the unit. This gasoline after boosting
pressure is mixed with Hydrogen recycle /Hydrogen makeup gas and processed in Selective
Hydrogenation Unit (SHU).
The reactions taking place in SHU are diolefin saturation, Sulphur compound boiling point shift
and Olefin isomerisation. The Sulphur in feed stream will be converted primarily to heavy
mercaptans and heavy Sulphur compounds (having high boiling point).
The effluent from SHU is fed to a Splitter column wherein the Light Gasoline component with
ultra low Sulphur is separated from top and will be routed to MS pool.
The bottom cut of Splitter column having heavy mercaptans and other heavy Sulphur compounds
is fed to Selective Hydro Desulphurisation (Selective HDS) section along with Hydrogen recycle
/Hydrogen makeup.
The reactions taking place in this section are Deep Desulphurization, minimum Olefin saturation
and control of Mercaptan recombination.
The effluent from Selective HDS is routed to Stabiliser column. The top product of stabilizer is
purge gas which will be routed for further treatment. The bottom product of Stabiliser is Ultra
low sulphur Heavy Gasoline which will be routed to MS pool.
The hydrotreated Gasoline product will have sulphur of max 10 ppm wt.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
15
PRELIMINARY BLOCK FLOW DIAGRAM
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
16
Chapter 8 – Utilities & Offsites
This section gives details of utilities, based on preliminary estimate by one of the Licensors for the
GTU and associated facilities. However adequacy will be established based on detail design
engineering.
8.1 Utilities
8.1.1 Fuel
It is envisaged that energy requirement of GTU and associated facilities will be primarily met from
clean and environment friendly RLNG / Refinery Fuel Gas (having nil H2S content). As per the
preliminary estimate 12 MT/D of RLNG/FG will be required in GTU.
8.1.2 Hydrogen
The Hydrogen requirement of GTU is approx 10 MT/D. This will be sourced from existing HGU-2 /
CCR.
8.1.3 Power
The power requirement for the proposed facilities is 4 MW. This will be sourced from existing Gas
Turbines which supply power to the entire refinery.
8.1.4 Steam
Net steam requirement will be around 720 MT/D which will be met from existing steam generation
system .
8.1.5 Cooling Water
Estimated requirement of environment friendly closed recirculating sea cooling water system is 70
m3/hr with makeup sea water requirement of approx 5 m3/hr. This will be met from existing system
after confirmation during Detailed design engineering stage.
8.1.6 Raw Water
The Raw Water requirement for the new facilities is approximately 6 m3/hr. This includes makeup
raw water required for steam generation and wash water injection. This requirement shall be met
using existing systems after confirmation during Detailed Design Engineering stage.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
17
8.1.7 Other utilities
Requirement of other utilities viz. Nitrogen, Instrument Air, Plant Air, DM water, Boiler Feed
Water, Condensate system etc. shall be met using existing systems after confirmation during
Detailed Design Engineering stage.
8.2 Offsites
Adequacy of existing facilities like Closed Blow Down, Oily Water Sewer, and Contaminated Rain
Water System, Flare System etc. will be checked during Detail Design Engineering stage.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
18
Chapter 9 – Unit Capacities
It is proposed to install Gasoline Hydrotreatment Unit (GTU ) of 0.9 MMTPA .Adequacy check of
associated facilities will be carried out based on which revamp of DHT ARU and DHDS/RMP SWS
will be carried out if required. Details of the same are tabulated as below;
Unit Description Existing Capacity Proposed Capacity
Gasoline Hydrotreatment Unit (GTU) New Unit 0.9 MMTPA
Revamp of DHDS/RMP SWS Unit 700/900 MT/D Units will be revamped
if required based on
adequacy study
Revamp of DHT Amine Regeneration
Unit 4250 MT/D
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
19
Chapter 10 – Catalyst
Details of catalyst for GTU Unit based on preliminary inputs are tabulated below :
Catalyst Description Proposed
Quantity 1st Cycle Life
MT Years
SHU Reactor HR 845 60.5 4
1st Stage Hydro DeSulphurisation HR 806 22.75 4
2nd Stage Hydro DeSulphurisation HR 806 22.75 4
Total 106
(165 m3)
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
20
Chapter 11 – Unit Plot Layout
It is proposed to set up GTU in the old Catalytic Reforming Unit (CRU)/New Solvent Unit (NSU )
plot area, which would be dismantled post commissioning of Isomerisation unit . Based on
preliminary indications plot area required for 0.9 MMTPA GTU is 4000-5000 Sq Meters. Refer
Annexure -3 for the proposed plot for GTU.
Hydrogen requirement for GTU will be supplied from existing HGU-2 ,which is being revamped
under DHT project. Hence no new plot area is required.
Sour water generated from GTU unit will be treated in existing Sour Water Strippers. Existing
units will be revamped if required based on adequacy study . Hence no new plot area is required
for SWS Unit.
Rich amine from GTU will be treated in existing DHT ARU which will be revamped if required
based on adequacy study. Hence no new plot area is required for ARU.
Acid gas generated from ARU & SWS will be treated in existing SRU trains. Hence no new plot
area is required for SRU.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
21
Chapter 12 – Project Schedule
Detailed schedule for project activities is as follows :
Sr. No. Activity Description Proposed Schedule
A
Project Management Consultant (PMC ) and
Engineering Procurement & Construction
Management (EPCM) Consultant
1. Award of PMC/EPCM Contract May-2016
2. Prepare + / - 10% Cost Estimate Feb-2017
3. Order Long Lead Items Nov-2016
4. Mechanical Completion Dec-2019
B Environmental Clearance
1. Award Contract for EIA / RRA Studies May-2016
2. Complete EIA / RRA Studies Aug -2016
3. Environmental Clearance Sept-2016
C Basic Engineering Design Package (BEDP)
1. Licensor Selection & Approval July-2016
2. BEDP Jan-2017
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
22
Chapter 13 – Project Cost Estimate
13.1 Introduction
As per preliminary estimates, Capital cost for putting up the GTU and associated facilities with +/-
30% accuracy is about Rs 554 Cr. Breakup of capital cost estimate is as follows;
No Activity description Capex, Rs
Crores
1
Plant and Machinery:
GTU
SWS / ARU modifications
300
26
2 Sub Total P&M 326
3
Miscellaneous incl Catalyst & Chemicals, Utilities & Offsites,
Buildings, Lab equipments, ODC facilities, Construction site
requirement, Owner’s construction period expenses, Start up
and Commissioning, etc @ 25% of P&M
81
4 License, Basic Engineering, EPCM, etc @ 21.3% of P&M 69
5 TOTAL 476
6 Contingency (@10.0% of 5) 48
7 CAPEX Sub Total 524
8 IDC
20
9 Total CAPEX 544
10 Associated REVEX 10
11 Total Project Cost 554
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
23
Chapter 14 – Benefits and Profitability
14.1 Installation of GTU is an absolute business necessity for meeting the proposed specifications
of 100% BS VI MS for the entire country w.e.f. 1st April 2020 while ensuring strategic supply
security for BPCL. This is in line with the guidelines established in Auto Fuel Policy and Vision
2025 as well as communication from MOP&NG, R-29011/23/2012-OR-I.
This proposal is a mandatory product quality improvement project which will ensure product
security for MS and sustaining BPCL–MR crude throughput at 13 MMTPA.
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
24
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
25
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
26
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
27
ANNEXURE -3
Proposed Plot Plan for GTU
Bharat Petroleum Corporation Ltd. Mumbai Refinery
Feasibility Report on Gasoline Hydrotreatment Unit and Associated Facilities
28