+ All Categories
Home > Documents > FEDERAL GOVERNMENT OF NIGERIA - World...

FEDERAL GOVERNMENT OF NIGERIA - World...

Date post: 25-Jun-2018
Category:
Upload: hoangkhue
View: 222 times
Download: 0 times
Share this document with a friend
124
FEDERAL GOVERNMENT OF NIGERIA FEDERAL MINISTRY OF WATER RESOURCES TRANSFORMING IRRIGATION MANAGEMENT IN NIGERIA (TRIMING) PROJECT – P123112 RESETTLEMENT POLICY FRAMEWORK (RPF) FINAL REPORT February 19, 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • FEDERAL GOVERNMENT OF NIGERIA

    FEDERAL MINISTRY OF WATER RESOURCES

    TRANSFORMING IRRIGATION MANAGEMENT IN NIGERIA (TRIMING) PROJECT P123112

    RESETTLEMENT POLICY FRAMEWORK (RPF)

    FINAL REPORT

    February 19, 2013

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb371432Typewritten TextRP1585

  • 1

    TABLE OF CONTENTS

    LIST OF TABLES ................................................................................................................................... 3 LIST OF FIGURES ................................................................................................................................. 3 LIST OF ACRONYMS & ABBREVIATIONS .............................................................................................. 4 FOREWORD .......................................................................................................................................... 5 DEFINITION OF KEY TERMS ................................................................................................................. 8 EXECUTIVE SUMMARY ....................................................................................................................... 11 CHAPTER ONE: INTRODUCTION ........................................................................................................ 17

    1.1 Background ........................................................................................................................... 23 1.2 Objectives for Consultancy ..................................................................................................... 24 1.3 Scope of Work ....................................................................................................................... 24 1.4 Principles and Objectives of World Banks Resettlement Policy .................................................. 25 1.5 The Need for Transforming Irrigation Management in Nigeria (TRIMING) project Resettlement Policy Framework (RPF) ............................................................................................................................. 27 1.6 TRIMING Project and the Principle of Involuntary Resettlement ................................................. 28 1.7 Technical Approach and Methodology ..................................................................................... 29

    1.7.1 Review of Literature/Existing RPF .................................................................................... 29 1.7.2 Stakeholders/Public Consultation ..................................................................................... 30 1.7.4 Organizing and Integrating Data ....................................................................................... 30

    1.8 Structure of the Resettlement Policy Framework ....................................................................... 30 CHAPTER TWO: DESCRIPTION OF PROPOSED PROJECT ................................................................. 31

    2.1 Project Overview .................................................................................................................... 31 2.2 Project Components ............................................................................................................... 31 2.3 Project Location ..................................................................................................................... 36

    CHAPTER 3: THE PROCESS FOR PREPARING AND APPROVING RESETTLEMENT PLANS ................ 43 3.1 Introduction ........................................................................................................................... 43 3.2 The Land Selection Screening Process .................................................................................... 43 3.3 Socio-economic Study ............................................................................................................ 45 3.4 Preparation of Resettlement Plans .......................................................................................... 46 3.5 Approval Process ................................................................................................................... 46

    CHAPTER FOUR: LAND ACQUISITION AND LIKELY CATEGORIES OF PROJECT AFFECTED PERSONS ........................................................................................................................................................... 48

    4.1 Individuals and Households Potentially Affected............................................................................. 48 CHAPTER FIVE: CRITERIA AND ELIGIBILITY FOR COMPENSATION OF PROJECT AFFECTED PERSONS ........................................................................................................................................................... 50

    5.1 Introduction ............................................................................................................................... 50 5.2 Eligibility for Community Compensation ................................................................................... 51 5.3 The Cut off Date .................................................................................................................. 51

    5.3.1 Justification for Cut-off-date ............................................................................................. 51 5.3.2 Common complications in the Application of Cut off Date ................................................... 52 5.3.3 Establishing the Cut-off-date ............................................................................................ 52 5.3.4 Requirements for enforcing Cut-off Date ........................................................................... 52

    CHAPTER SIX: LEGAL/INSTITUTIONAL GUIDELINES, REQUIREMENTS AND SAFEGUARD POLICIES . 53 6.1 Land Ownership in Nigeria ...................................................................................................... 53 6.2 Nature of Land Rights in the Existing Schemes and Proposed Expansion Areas.......................... 55 6.3 Nigerian Legal/Institutional Guidelines and Requirements .......................................................... 56

  • 2

    6.3.1 Land Use Act of 1990 and Resettlement Procedures ......................................................... 56 6.4 International Guidelines .......................................................................................................... 58

    6.4.1 World Bank Policy on Involuntary Resettlement (OP.4.12) and TRIMING PROJECT ............ 58 6.5 Nigerian Law and World Bank OP 4.12 on Compensation A Comparison .................................. 59

    CHAPTER SEVEN: METHODS OF VALUING AFFECTED ASSETS. ....................................................... 62 7.1: Compensation Payments and Related Considerations. .................................................................. 62

    7.1.1 Compensation for Land ................................................................................................... 62 7.1.2: Compensation for Buildings and Structures. ........................................................................... 63

    Table 7.1: Compensation for Buildings and Structures ............................................................................. 64 7.1.3: Calculation of Crops Compensation Rate .............................................................................. 64 7.1.4: Compensation for Vegetable Gardens and Beehives ............................................................. 65 7.1.5: Compensation for Domestic Fruit and Shade Trees. .............................................................. 65 7.1.6: Compensation for Loss of Business/Employment .................................................................. 65

    CHAPTER EIGHT: ARRANGEMENTS FOR COMPENSATION ............................................................. 66 8.1 Introduction ........................................................................................................................... 66 8.2 Community Compensation Payments ..................................................................................... 67 8.3 Description of the Implementation Process .................................................................................. 67 8.4 Grievance Redress Mechanism .................................................................................................... 67

    8.4.1 Grievance redress process .............................................................................................. 68 8.4.2 Expectation When Grievances Arise ................................................................................. 69 8.4.3 Management of Reported Grievances .............................................................................. 70 8.4.4 Grievance Log ................................................................................................................ 70

    8.5 Resettlement, Cost Estimates and Contingencies ..................................................................... 71 8.6 Mechanism for Consultation and Participation of Displaced Persons .............................................. 71

    8.6.1 Identifying Stakeholders .................................................................................................. 72 8.6.2 Consultation Strategies ................................................................................................... 72 Level of Engagement .................................................................................................................... 72

    CHAPTER NINE: MONITORING AND EVALUATION ARRANGEMENTS ................................................. 74 9.1 Introduction ........................................................................................................................... 74 9.2 Monitoring Plan Procedure ...................................................................................................... 75 9.3 Evaluation ............................................................................................................................ 78

    Annex 1: Template For Preparing Resettlement Action/Compensation Plans (RAPS). .............................. 80 Annex 2. Indicative Resettlement Screening Form (Adapted from RAMP II) ............................................... 84 Annex 3: Calculation of Land and Crop Compensation Rate ..................................................................... 98 Annex 4. Sample Grievance Redress Form and Agreed Resolution Format ............................................. 101 Annex 5: The World Bank Operational Manual OP 4.12 - December 2001 ........................................... 103 Annex 6: Issues Emanating From the Consultation Visits ....................................................................... 110 Annex 7: List of Persons that attended the stakeholder consultation..112

  • 3

    LIST OF TABLES

    Table 3.1: Sample of possible sub projects that may be proposed under the NIWRMP that would trigger the involuntary resettlement policy with probable social impact Table 5.1 Eligibility Matrix Table 6.1: Comparison of Nigerian Law and World Bank OP4.12 Regarding Compensation Table 6.2: The Entitlement Matrix for Various Categories of PAPs Table 7.1: Compensation for Buildings and Structures Table 7.2: Example of method to be used to determine a monetary compensation rate for land* Table 8.1: Indicative budget for Resettlement and Compensation for NIWMRP Table 8.2: The Stakeholder Identification Matrix Table 8.3: Consultation Plan at Project Phases Table 9.1 Specific variables to monitor routinely in the course of implementation. Table 9.2 Indicators to monitor and evaluate the implementation of resettlement and compensation plans

    LIST OF FIGURES

    Figure 2.1: Map of Nigeria showing Zamfara and Katsina states Figure 3.1: Typical Process for Resettlement Plans (RAP/ARAP) Figure 8.1: Spectrum of Engagement Figure 9.1 Conceptual Model

  • 4

    LIST OF ACRONYMS & ABBREVIATIONS

    BP Bank Procedure DKIP Dadin Kowa Irrigation Project EAP Emergency Action Plans EMP Environmental Management Plan ESMF Environmental and Social Management Framework FGN Federal Government of Nigeria FMEnv Federal Ministry of Environment FMWR Federal Ministry of Water Resources HVIP Hajejia Valley Irrigation Project IBNET International Benchmarking Network IDA International Development Association IWRM Irrigation and water Resources Management JMP Joint Monitoring Programme KRIP Kano River Irrigation Project LUA Land Use Act M&E Monitoring & Evaluation NEWMAP Nigeria Erosion and Watershed Management Project NGO Non-Governmental Organization NIWRMC Nigeria Irrigation and Water Resources Management Commission NIWRMP Nigeria Irrigation and Water Resources Management Project O&M Operation and Maintenance OBA Output Based Aid OP Operational Policy PA Protected Areas PAP Project Affected Person PCU Project Coordination Unit PIM Project Implementation Manual PPP Public Private Partnership PSC Project Steering Committee PSP Private Sector Partner or Private Sector Participation RAMP Rural Access and Mobility Project RAP Resettlement Action Plan RBDA River Basin Development Authority RPF Resettlement Policy Framework TAC Technical Advisory Committee UNICEF United Nations International Childrens Emergency Fund WB World Bank WHO World Health Organization WUA Water User Associations

  • 5

    FOREWORD

    The Government of Nigeria (GoN) identified investments in the agriculture sector as effective means to reducing poverty. The GoN recognizes that higher levels of investments in agriculture, both by the public and private sector, can yield much better results if the reforms are undertaken to streamline not only the incentive structures for the farmers, but also the institutional framework in which agriculture and related activities take place. Seeds and irrigation are highlighted as priority assets, which can be catalysts for raising productivity on the supply side. The overall management of water resources (where agriculture is the largest consumer) is also highlighted as a challenge requiring attention. Solutions through greater efficiency in water use are recognized as critical with more focus given to better management of water in areas of large and medium irrigation projects. This also requires putting in place more holistic water resources management strategies. Finally, other key water management activities identified in the Twelfth Plan include: steps to greatly improve governance in water management through Water User Associations, a focus on on-farm works and the rehabilitation and physical modernization of existing major irrigation systems, and integration of these activities with existing surface reservoir based canal irrigation. In order to respond to the above challenges the GoN has requested the World Bank to support the preparation of a TRANSFORMING IRRIGATION MANAGEMENT IN NIGERIA (TRIMING) PROJECT. In addition to the policy and institutional focus, TRIMING intends to support on the ground Integrated Water Resources Management in the following three basins; Sokoto-Rima Basin, Upper Benue Basin, and the Hadejia-Jamaare-Komadugu-Yobe Basin (HYKYB). Also TRIMING will support dams operational and safety management improvement, particularly for the following dams and reservoirs; Bakolori, Zobe, Goronyo, Tiga, Challawa Gorge, Ruwan Kanya operational reservoir, Hadeija Barrage and Dadin Kowa and also Irrigation management through a particular focus on enhancing capacity of water users associations. From an Environmental and Social Safeguards point of view, the TRIMING project is rated as Category A. It triggers six World Bank safeguards policies (OPs), namely, Environmental Assessment (OP 4.01), Safety of Dams (OP 4.37), Natural Habitats (OP 4.04), Involuntary Resettlement (OP 4.12) mentioned above, Pest Management (OP 4.09), and Projects on International Waterways (OP 7.50). The following safeguards instruments have been prepared and subjected to public consultation and disclosure.

    1. Specific interventions will not be known in detail prior to appraisal and a Resettlement Policy Framework (RPF) is therefore the most appropriate instrument. This document spells out the key objectives and principles of the policy and gives guidance to the preparation of subsequent Resettlement Action Plan (RAP).

    2. Similarly, an Environmental and Social Management Framework (ESMF) describes in general terms the potential environmental and social impacts of the sub-projects to be financed by this project. The ESMF also provides guidance for preparation of ESIAs, ESMPs, and environmental audits.

    3. A Pest Management Plan (PMP) designed to minimize potential adverse impacts on human health and the environment and to advance ecologically based on integrated pest management.

    4. The Bakolori Irrigation Scheme has been submitted to a full Environmental and Social Impacts Assessment (ESIA), including consultation and disclosure, during project preparation. The other site-specific ESIAs will be prepared during project implementation along with the technical studies for the corresponding investments.

    The present document corresponds to the document No1 Above, [Resettlement Policy Framework (RPF)] for the TRIMING Project.

  • 6

    GABATARAWA Gwamnatin Tarayyar Nijeiya ta fahimci cewa zuba jaruka a sashen aiyukan gona ce kadai sahihiyar hanyar da za a bi domin saukaka talauci. Gwamnatin ta gane cewa zuba manya-manyan jaruka, daga sashen Hukumomin Gwamnati da kuma Kamfunnan alumma, a cikin aiyukan gona zai iya haifar da sakamako nagari idan manufar yinkurin gyara da ake yi, bata takaitu ga tallafa wa manoma da kayan aiki ba kurum, sai in ta hada da (samarda) ingantattun kafafen da zasu tallaba wa dukkan nauoin aiyukan gona. Samarda ingantaccen Iri da (filayen) noman-rani na daga cikin muhimman ababen da zasu sa a samu amfanin (gona) mai tarin yawa wanda kuma zaya wadatar da mabukata. Haka kuma, gabadayan alkinta albarkatun ruwa (inda aiyukan gona ke kwashe kaso mai yawa) wani babban Kalu Bale ne da ke bukatar a mayar da hankali a kansa. Yana daga muhimman matakan gyara, samarda amfani da wadataccen ruwan (noman-rani), ba tare da yin almubazzarancinsa ba, ga manya-manya da matsakaitan shirye-shiryen mona-rani. Wannan na bukatar kyawawan dabarun da tsare-tsaren alkinta albarkatun ruwa. A karshe, wasu daga tsare-tsaren adana ruwa da Shiri na Shabiyu ya tanada sun hada da: daukar kwararan matakai domin inganta gudanar tattalin ruwa ta hanyar amfani da Kungiyoyi Masu Taammuli da Ruwa, kula da aiyukan gyaran filayen gona da farfado dasu da kuma samarda tsari irin na zamani tare da gwamasu da ruwayen da ake ban ruwa da su a wurare daban-daban. Domin fuskantar wadannan Kalu Balance-balancen da aka ambata a sama, Gwamnatin Tarayyar Nijeriya ta nemi Bankin Duniya da ya bayar da goyon baya ga shirinta da ake wa lakabi da: SHIRIN SABON TSARIN GUDANAR DA NOMAN-RANI A NIJERIYA SHIRIN (TRIMING). Bugu da kari akan wadannan manufofi da mayar da hankali a kan (samarda) ingantattun kafafen gudanarwa, SHIRIN (TRIMING) ya kuduri aniyar tallafa wa tsarinda ke da akwaina Sarrafa Albarkatun Ruwa a hukumomin kula da noman-rani ire-irensu kogunan; Sokoto-Rima, Upper Benue, da kuma na kogunan Hadeja-Jamaare-Komadugu-Yobe (HJKYB). Haka kuma, SHIRIN (TRIMING) za ya tallafa wa tsarin gudanarwa da inganta madatsai na ruwa, musamman a madatsai da matattarar ruwa na; Bakolori, Zobe, Goronyo, Tiga, Challawa Gorje, Ruwan Kanya, da kuma na Hadejiya Barrage da Dadin Kowa, da inganta noman-rani ta hanyar bayar da karfin guiwa ga Kungiyoyin manoman damana da na rani.

    Ta fuskar Alkinta Muhalli da Tattalin Zamantakewa kuwa, an kimanta SHIRIN (TRIMING) a matakin A. Shirin na da manufofin ingantawa, kamar haka, Tantance Ingancin Muhalli (mai lamba OP 4.01), Kiblacewar Hadurra a Madatsun Ruwa (OP 4.37), Sake Matsugunnan (mazauna yankunan) da aka ambata a sama (OP 4.12) Dakile Kwarin da ke Barazana amfanin gona (O P 4.09), sai kuma Shirye-shiryen kyautata alaka akan amfani da hanyoyin ruwa na Kasa-da-kasa (O P 7.50). Wannan jerin bayanai ne na matakan kiyaye hadurra da aka tanada, wadanda sai an tuntubi jamaah masana kan cancantarsu kafin aiwatar da su.

    1. Ba za a san dalla-dallar tanade-tanaden da ke akwai ba sai bayanbisa manufaan baiyanar da Tsarin Sake Matsugunai (RPF); domin yin haka shine mafi dacewa. Wannan daftari ya zayyana muhimman manufofin wannan kuduri tare da shata yadda za a tsara sauran shirye-shirye tsugunnarwa da za su biyo baya. Ana kiran wannan Shiri da (RAP).

    2. Haka kuma, Ginshikin Gudanar da Alkinta Muhalli da Zamantakewar Alummah (ESMF) ya bayar da gundarn bayanai kan alfanun da ka iya samuwa a cikin kananan aiyukan da wannan babban shiri na (ESMF) za ya gudanar. Kana kuma Shirin zai bada haske a kan yadda za a gudanar da sauran tsare-tsare na ESIAs, ESMP, da kuma tsarin binciken muhalli.

    3. An kirkiro shirin dakile miyagun kwari masu barazana ga lafiyar Dan-Adam da muhalli ne domin samar da kubutaccen yanayi daga aibin kwarin.

  • 7

    4. Kafin kaddamar da shirin noman-rani a Bakolori sai da aka yi cikiakken nazari domin gane tasirin da ka iya samuwa musabbabin Shirin Alkinta Muhalli da Zamantakewar Alummaah (ESIA), an daddale (matsaya) ta hanyar daukar matakan tuntuba da fayyace bayanai (ga jamaah) kafin kaddamar da shirin. Irin wadannan matakai ne za a dauka kafin kaddamarwa da aiwatarwa tare da laakari da nazarce-nazarcen kwararru akan dukkan sassan (aiyukan noma) da za a zuba jaruka a kansu nan gaba.

    Wannan daftari na da muwafaka da daftarin na 1 (RPF) da aka zo da bayaninsa a sama.

  • 8

    DEFINITION OF KEY TERMS

    Word/Term Definition

    Asset Inventory A complete count and description of all property that will be acquired.

    Bank World Bank

    Census Official enumeration and collection of demographic information of people and individuals in the sub-project locations of the Transforming Irrigation Management in Nigeria (TRIMING) project.

    Cut - off Date A day beyond which any person who encroaches on the sub- project area will not be eligible for compensation or any form of resettlement assistance. Normally, the Cut-off Date is the day when the Census commences. The Cut-off Date could also be the date the project area was delineated, prior to the Census, provided that there has been an effective public dissemination of information on the area delineated, and systematic and continuous dissemination subsequent to the delineation to prevent further population influx

    Compensation Payment in cash or in kind of the full replacement cost of lost assets.

    Displacement Removal of people from their land, homes, farms, etc. as a result of a project's activities. Displacement occurs during the (1) involuntary taking of lands resulting in (i) relocation or loss of shelter (ii) loss of assets or access to assets (iii) loss of income sources or means of livelihood whether or not the affected persons must move to another location or (2) involuntary restriction of access to legally designated parks and protected areas resulting in adverse impacts on the livelihoods of PAPs.

    Entitlements Compensation and other forms of assistance to be provided to displaced persons in the respective eligibility category.

    Environmental and Social Management Framework (ESMF)

    An environmental assessment instrument (document) which establishes a mechanism to determine and assess future potential environmental and social impacts of productive investments under the proposed Transforming Irrigation Management in Nigeria (TRIMING) project, and then to set out mitigation, monitoring and institutional measures to be taken during design, implementation and operation of the project activities to eliminate adverse environmental and social impacts, offset them , or reduce them to acceptable levels. This instrument has been prepared as a separate and stand-alone document to be used in conjunction with this RPF.

    Grievance Procedures

    The processes established (a) under law, local regulations, or administrative decision to enable property owners and other displaced persons to redress issues related to acquisition, compensation, or other aspects of resettlement, as well as (b) specific grievance processes put in place as part of the design of a project.

    Host Communities

    Communities receiving resettled people as a result of involuntary resettlement activities

    Land Acquisition

    The process whereby a person is compelled by a public agency to alienate all or part of the land he/she owns or possesses, to the ownership and possession of that agency, for public purpose in return for a consideration.

    Market Rate Highest rate over the last five years based on commercial terms.

    Market Value The most probable selling price or the value most often sought by buyers and sellers. It assumes buyers and sellers have reasonable knowledge, act competitively and rationally are motivated by self interest to maximize satisfaction and both act independently and without collusion, fraud or misrepresentation.

  • 9

    Project Affected Person (s)

    A person that loses assets and/or usage rights and/or income generation capacities (e.g., land, structures, crops, businesses) because these assets/rights/capacities are located in land to be acquired or used, for needs of the project. Not all PAPs are displaced due to the Project, but all are potentially affected in the maintenance of their livelihood.

    Rehabilitation Assistance

    The provision of development assistance in addition to compensation such as land preparation, credit facilities, training, or job opportunities, needed to enable Project Affected Persons and Displaced Persons to improve their living standards, income earning capacity and production levels; or at least maintain them at pre-Project levels

    Replacement Cost

    Replacement cost" is the method of valuation of assets that helps determine the amount sufficient to replace lost assets and cover transaction costs. In applying this method of valuation, depreciation of structures and assets should not be taken into account. For losses that cannot easily be valued or compensated for in monetary terms (e.g., access to public services, customers, and suppliers; or to fishing, grazing, or forest areas), attempts are made to establish access to equivalent and culturally acceptable resources and earning opportunities. With regard to land and structures, "replacement cost" is defined as follows: For agricultural land, it is the pre-project or pre-displacement, whichever is higher, market value of land of equal productive potential or use located in the vicinity of the affected land, plus the cost of preparing the land to levels similar to those of the affected land, plus the cost of any registration and transfer taxes. For land in urban areas, it is the pre-displacement market value of land of equal size and use, with similar or improved public infrastructure facilities and services and located in the vicinity of the affected land, plus the cost of any registration and transfer taxes. For houses and other structures, it is the market cost of the materials to build a replacement structure with an area and quality similar to or better than those of the affected structure, or to repair a partially affected structure, plus the cost of transporting building materials to the construction site, plus the cost of any labor and contractors' fees, plus the cost of any registration and transfer taxes. In determining the replacement cost, depreciation of the asset and the value of salvage materials are not taken into account, nor is the value of benefits to be derived from the project deducted from the valuation of an affected asset.

    Resettlement Policy Framework (RPF)

    The present document which is the overall Policy Framework for Compensation, Resettlement and Rehabilitation of Project Affected Persons for theTRIMING Project. The Policy Framework describes the process and methods for carrying out resettlement under the Project, including compensation, relocation and rehabilitation of project affected persons.

    Resettlement Action Plan (RAP)

    The resettlement action plans prepared for specific sub-projects. It is a resettlement instrument to be prepared when project activities are identified, that require land acquisition that leads to physical displacement of persons, and/or loss of shelter, and /or loss of livelihoods and/or loss, denial or restriction of access to economic resources. The RAP is prepared by the party impacting people and livelihoods in this manner and contains specific and legal binding requirements to be taken by that party to resettle and compensate the affected party before project activities causing this adverse impact are implemented.

  • 10

    Right of Way Right to make a way over a piece of land, usually to and from another piece of land.

    Special assistance to vulnerable people

    This refers to special efforts provided to the vulnerable physically challenged persons such as those with blindness, paralysis, difficulties with locomotion, incapacity to work, etc who are ill prepared but displaced by the project. The special assistance must be given by qualified persons/relatives/agencies, for example an entity who can help care for an invalid, providing transitional support (e.g. moving expenses, temporary food supply, etc.).

    Vulnerable Groups:

    People who may by virtue of gender, ethnicity, age, physical or mental disability, economic disadvantage or social status be more adversely affected by resettlement than others; and who may have limited ability to claim or take advantage of resettlement assistance and related development benefits.

  • 11

    EXECUTIVE SUMMARY Irrigation is the application of water to the soil for the purpose of supplying moisture essential for plant growth. It is also undertaken to provide an insurance against droughts, for cooling the soil and atmosphere. It equally provides a more favorable environment for plant growth. Irrigation washes out or dilutes salts in the soil and reduces the hazards of piping and softening tillage pans. Given the abundant water resources in the country and its potential for increasing agricultural production in Nigeria, the Federal Government established the River Basin Development Authority (RBDA). The scheme became necessary because of the persistent too short rainy season in many states of the federation. It was against this background that the Bakolori and Middle Rima, the Kano River Irrigation, Hadejia Valley Irrigation and Dadin Kowa Irrigation Projects were established. However, because of the problems encountered in the project and the need for effective irrigation development, the Federal Government of Nigeria (FGN) has requested World Bank assistance to prepare the Transforming Irrigation Management in Nigeria (TRIMING) project. The proposed project seeks to improve performance of irrigated and water resources infrastructure and institutions for enhanced productivity in selected irrigation schemes. The proposed credit amount is US$ 400 million. Project Description Component 1: Water Resources Management and Dam Operations Improvements (100 million US$) This Component is part of the piloting support for the transformative water resources sector reform covering policies, enabling legislation, regulatory instruments and organizational restructuring currently being formulated for enactment by the FGN. It includes several subcomponents including Support to Integrated Water Resources Management (IWRM) and Dam Operations Improvement and Safety. The proposed Project supports the piloting of anticipated provisions for separation of government regulatory and operational powers and responsibilities for integrated water resources management (IWRM) of river basin-wide water allocation, river flow control and channel maintenance needed for sustainable bulk water supply & drainage for large public irrigation scheme planning, development and operational management. This Project has selected dams and irrigation schemes within: (i) the Sokoto-Rima river basin included in HA1 covering northwest Nigeria; (ii) the Hadejia-Jamaare river basin contained within the Hadejia-Jamaare-Komadugu-Yobe Basin of northeastern Nigerias HA 8; and (iii) the Gongola River Basin in the Upper Benue HA. Under the IWRM envisaged by the forthcoming water resources legislation and its implementing institutions, meeting the large consumptive water use and drainage water disposal of public irrigation schemes in a river basin requires the planned consideration of the water quantity and quality needs of all other non-irrigation water-using sub-sectors including the environmental water needed to sustain the biodiversity and productivity of diverse habitats. Component 2: Irrigation Development and Management (205 million US$) The poor condition and inefficient performance of irrigation canals and dilapidated drainage infrastructure are the major contributors to the poor water service delivery observed in most of the irrigation schemes in Nigeria. These schemes were developed more than 20 to 30 years ago and proposed for rehabilitation and expansion (new development) under TRIMING Project. These include Bakolori Irrigation Project (BIP) and Middle Rima Irrigation Valley (MRIV) in Sokoto-Rima River Basin Authority (SRRBA) and Kano River Project (KRIP) and Hadejia-Jamaare Valley Irrigation Project (HVIP) in Hadejia-Jama'are River Basin Authority (HJRBDA) in northern Nigeria. Combined with poor on-farm water management practices, inadequate agricultural services and market infrastructure as well as the prevailing gaps in the policy environment, these problems have

  • 12

    impeded the development of irrigated agriculture in the country. Moreover, some of the dams constructed during the same period and still in good condition with a potential for multi-purpose use are abandoned in various parts of the country. This is mainly attributed to incomplete construction of the irrigation system and instrumentation of the hydropower plant. Dadin Kowa dam in the Upper Benue River Basin Authority (UBRBA) in Gombe state of northeast Nigeria is among these dams. The sub components are Irrigation Infrastructure Investments and Improving Irrigation Management Component 3: Enhancing Agricultural Productivity and Supply Chains (40 million US$) This component will provide resources to support strategic issues of value chain development, complementing the programs of Agricultural Transformation Agenda of the FGN. This will include value chain management and capacity building for improved job opportunities to ensure inclusion of small and medium size local entrepreneurs. Promotion of e-extension services will be encouraged. Under this component technical assistance for value chain analysis and private sector development are foreseen: Matching grants for improvement of productive water use in agricultural processing and mechanization as well as support research and development. Technical assistance would be provided for farmer water schools, applied research such as monitoring of crop performance using remote sensing imagery, etc. Proposals will be invited from interested agencies to carry out such studies. Innovations from the project will be also identified and supported for technology transfer within and outside the country. Demonstrations and adaptive field trials will be carried out primarily focusing on direct water efficiency interventions and other water saving related technologies identified during the implementation of the project. Component 4: Institutional Development and Project Management (35 million US$) This component will enhance the efficiency of personnel through the provision of advanced IT based tools, performance-based systems for staff evaluation, modern survey and design techniques as well the overall management of the department through administrative and managerial skills enhancements and tools (e.g. management information systems). Through this business process re-engineering and strengthened governance approach a more flexible, accountable, and responsive Department can be nurtured. Moreover, a strengthened role for water users associations and the concomitant Department role in this agenda will be critical. Enhancing these reforms and building greater farmer participation in water management are crucial to achieving the development objective of improving agricultural productivity and water-use efficiency. There is on subcomponent for project management as well as monitoring and evaluation. This subcomponent will help strengthen the Ministrys capacity, incl. that of the PCU, to implement the project, including fiduciary aspects framework for Bank Projects (procurement, financial management, anti-corruption plan, environmental and social safeguards), M&E, computers, vehicles, Training on contract management, WUA, etc. A simple but effective monitoring and evaluation system will be put in place. There is another subcomponent on institutional development and governance where capacity building will be supported at all levels (FMWR, project, RBDA, scheme): (i) Under the capacity building part numerous activities will be undertaken including: capacity needs assessments for RBDAs, training in contract management, project management, quality assurance; study tours; specific studies and workshops; communications; generation of information and policy notes, etc.; partnerships between national educational centers (such as National Water Resources Institute in Kaduna) and universities (e.g. Wageningen); (ii) Under the advocacy line of activities the overall reform agenda will be promoted to make O&M sustainable. The subcomponent will support for the development of a communications strategy and its implementation; studies, TA, on appropriate fee setting and collection, downsizing of RBDAs, enhancing participation in decision-making, etc.

  • 13

    Need for RPF The Resettlement Policy Framework (RPF) is designed to provide procedures and guidelines that will be followed because the World Banks OP 4.12 is triggered by the project. The RPF provides a practical tool (e.g. screening checklist) to guide the preparation of Resettlement Action Plans (RAPs) for sub-projects during the implementation of the comprehensive Transforming Irrigation Management in Nigeria (TRIMING) project. The RPF sets out the policies, principles, institutional arrangements, schedules and indicative budgets that will take care of any anticipated resettlements. These arrangements shall also ensure that there is a systematic process (as against ad hoc one) for the different stages of the implementation of a framework that assures participation of affected persons, involvement of relevant institutions and stakeholders, adherence to both World Bank and Government procedures and requirements, and outline compensation for affected persons. The RPF provide the framework within which Resettlement Action Plans/Abbreviated Resettlement Action Plans will be developed and implemented when the project is certain of the locations, designs and specific impacts of the sub-projects. Project Location The coverage of the proposed interventions is shown in Table 1.

    Table 1: Overview of Coverage of Irrigation Schemes in the Coverage of TRIMING

    Basin (hydrological area)

    Sub-basin Irrigation Site Dam

    Niger North (HA-1) Sokoto Rima Bakolori Irrigation Scheme Bakolori dam

    Middle Rima Irrigation Valley Scheme

    Goronyo and Zobe dams

    Hadejia Jamaare Komadougou Yobe or Chad Basin (HA-8)

    Hadejia Jamaare Kano River Irrigation Scheme Tiga and Challawa Gorge dams

    Hadejia Valley Irrigation Scheme

    Hadeija barrage

    Upper Benue (HA-3) Gongola Dadin Kowa Irrigation Scheme

    Dadin Kowa dam

    Bakolori is the name of a rural community in Zamfara State in North Western Nigeria. The Bakolori Dam and Irrigation Scheme is located in Maradun LGA of which was carved out of the old Talata Mafara LGA. The irrigation scheme serves water users in the three LGAs of Talata Mafara, Bakura and Maradun LGAs in Zamfara State. The project area is located 110 km southeast from Sokoto City. The Middle Rima Irrigation Valley scheme is located in Sokoto State, north-west Nigeria. The Middle Rima Valley Irrigation Project is located downstream of Goronyo Dam (not far from Niger Republic border). The project area covers a total of 5,360hectares net divided into six different irrigable sectors on both sides of the Rima River. It is located between Goronyo Dam near the Village of Katsira to the north-east on one end and about 5km downstream of the village of Shinaka to the south-west on the other end.

  • 14

    The Kano River Irrigation Project (KRIP) began as far back as 1969 with the construction of Bagauda Dam which Started at Kadawa Irrigation Project Scheme, the precursor of the KRIP. The Government quickly followed the Bagauda Dam with a much bigger dam, the Tiga Dam between 1970 and 1973 with the primary purpose of boosting agricultural production through irrigation to enhance self reliance in food production. The control of the project was later shifted from the Kano State Government to the Federal Government of Nigeria as a project under Hadejia Jamaare River Basin Development Authority. The Hadejia valley irrigation project is one of the Federal Government Projects and is situated within Auyo, Kaugama, Miga and Kafin Hausa and Hadejia Local Government Area of Jigawa State, all in Hadejia Emirate. It is situated between Hadjia and Kafin Hausa Rivers. This Project was designed to utilize the water released from the upstream Challawa and Tiga dams, into the river system. The Dadin Kowa Irrigation Project is located in Dadin kowa village on the right bank of the Gongola River, near the Dadin kowa bridge on the Gombe to Biu Road, 5km downstream of the Dadin kowa Dam. It consists of 140ha gravity irrigation (phase I) and 160ha sprinkler (phase II). This scheme was started in 1979 and was used on a forerunner to the 25000ha Dadin kowa lot irrigation scheme under the Dadin kowa Dam Project. Categories of PAPs The likely displaced persons can be categorized into three groups, namely;

    Affected Individual An individual who suffers loss of assets or investments, land and property and/or access to natural and/or economical resources as a result of the subproject activities and to whom compensation is due.

    Affected Household A household is affected if one or more of its members is affected by sub project activities, either by loss of property, loss of access or otherwise affected in any way by project activities.

    Vulnerable Households This includes persons who by virtue of their gender, age, physical and/or economic disadvantage (or because they otherwise belong to a Vulnerable Group) may be worse off than others as a result of the partial or full demolition of structures or acquisition of landholding in the project area.

    Criteria for Eligibility for Compensation The Banks OP4.12 suggests the following three criteria for eligibility;

    a) Those who have formal rights to land (including customary land, traditional and religious rights, recognized under the Federal and/or State Laws of Nigeria)

    b) Those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets provided that such claims are recognized under the state, customary and/or federal laws of Nigeria or become recognized through a process identified in the resettlement plan

    c) Those who have no recognizable legal right or claim to the land they are occupying, using or getting their livelihood from.

    Legal Framework for Land Acquisition The legal framework for land acquisition in Nigeria is the land use Act of 1978, reviewed under Cap 202, 1990. The relevant World Bank operational policy (OP 4.12), which addresses land acquisition and involuntary resettlement was reviewed. The differences between the Land Use Act and the Banks OP 4.12 are mostly in rehabilitation measures, which are neither proscribed nor mandated in the Act. Thus it is noted in this RPF that

  • 15

    in the event of divergence between the two, the World Bank safeguard policy shall take precedence over Nigeria Land Use Act. Guiding Principles for Resettlement Planning Once the proposed intervention has been designed, which will require voluntary or involuntary taking of land or displacement, and before actual work begins, a resettlement action plan will be developed. This will involve a socioeconomic study and census (including complex households such as compounds) that will be carried out within the area directly affected by the project where land will be acquired. The socioeconomic study should focus on such issues as livelihoods, household and compound composition, clan and sub-clan organization, other forms of social organization, gender composition, ethnic groups, traditional and non-traditional leadership and other factors in the area, conflict and other issues relevant to the implementation of a resettlement plan. The census should include information on all income sources including remittances. All the above data shall be photographically documented. A sample household questionnaire has been prepared as an annex to this RPF. Concurrently, data will be collected on services available to households in the area such as educational institutions, health-care facilities, places of worship, extension agencies, shops and any other services normally used by household members. Transport facilities (roads, bus and van lines, etc.) should be registered. Distance from households to facilities should be noted. The valuation procedures of all assets that will be affected will be conducted by a qualified valuer/surveyor. Compensation for loss of income and assets will be at full replacement cost such that the PAPs will experience no net loss. Eligibility criteria have been defined. PAPs, communities, NGOs relevant stakeholders will participate in the resettlement/rehabilitation process. The specific plans/mechanisms for consultation and participation will be detailed in the RAP and will include resettlement / local resettlement committees for PAPs and communities and interagency committees for participating stakeholders. Summary on the GRM The grievance redress procedure will be simple, administered as far as possible at the local and State levels to facilitate access, flexible and open to various proofs taking into cognizance the fact most people are illiterate requiring a speedy, just and fair resolution of their grievances. All attempts would be made to settle grievances. Those seeking redress and wishing to state grievances would do so by notifying the Resettlement Committee. If the complainants claim is rejected, then the matter will be brought before the local courts for settlement. The decision of the state high courts would be final and all such decisions must be reached within a short period of time after the complaint is lodged. If a complaint pattern emerges, the PCU and the State Ministry of Environment and FMWR, with local community leaders will discuss possible remediation in close consultation with the PCU at FMEnV, who will only act as observers in this case. The local leaders will be required to give advice concerning the need for revisions to procedures. Once they agree on necessary and appropriate changes, then a written description of the changed process will be made. The municipal/township heads and other community leaders will be responsible for communicating any changes to future potential PAPs when the consultation process with them begins. Arrangements for Compensation Compensation (and resettlement) will be funded like any other activity eligible under the projects administrative and financial management rules and manuals. Funding would be processed and effected through the Transforming Irrigation Management in Nigeria (TRIMING) Project Coordinating Unit (PCU) and will comply with the financial arrangements agreed upon at project negotiations. The compensation process, which will involve several steps, would be in accordance with the Transforming Irrigation Management in Nigeria (TRIMING) project resettlement and compensation plans and will include public participation,

  • 16

    notification, documentation and preparation of contracts and compensation payments. The grievance redress mechanism as detailed in the document should be followed in case of complaints. Monitoring and Evaluation In order to successfully complete the resettlement management as per the implementation schedule and compliance with the policy and entitlement framework, there would be need for monitoring and evaluation of the RAP/ARAP implementation. Monitoring and evaluation will be a continuous process and will include internal and external monitoring. The safeguards officer shall play a key role in reporting the progress of implementation as well as compliance to the PCU, PSC, TAC and the World Bank. The RPF underscores the importance of monitoring and evaluation of the sub projects under the Transforming Irrigation Management in Nigeria (TRIMING) project. It also highlights mechanisms for internal and external monitoring and provides the indicators.

  • 17

    JAWABI A TAKAICE

    Noman rani shi ne zuba ruwa a cikin kasar noma da manufar samar da danshi da zai iya taimakawa tsirrai su

    fito kumahar su girma. Sannan kuma a na amfani da wannan domin samar daw ani mataki na magance

    barazanar fari, da kuma sanyaya kasa da ma yanayi baki daya. Haka zalika, yin hakan na samar daw ani

    kyakyawan yanayi day a dace da fitowar tsirrai. Wannan hanya kuma na wanke ko kuwa rage yawan sinadarin

    gishiri a cikin kasa da kuma rage matsanancin tsauri da bangori da kasa ked a shi. Ta laakari da yalwar

    kasar noma da kuma damar da ke akwai ta inganta yawan amfanin gona a kasar nan, ya sanya gwamnatin

    tarayya ta kafa hukumar raya koguna. Samar da wanna hukuma kuwa ya zamo wajibi ta laakari da takaitacen

    lokacin subar rowan damina da a ke fuskanta a wasu jahohin kasar nan wannan ne kuma a ka kakkafa shirye-

    shiryen noman rani na bakolori da Zobe da kano Hadeja gami da Dadin kowa.

    Sai dai kuma a sabili da matsalolin da a ka samu a cikin waddan shirye-shirye da kuma bukatar dake akwai ta

    bunkasa noman rani, gwamnatin tarayya ta roki bankin duniya don samun tallafi domin aiwatar da shirin tafi da

    noman rani a najeriya. Wannan shiri da za a gudanar na da kudurin habaka dukkanin fannonin noman rani da

    kyautata hukumomin dake kula da sho don samin skyakyawan sakamako a zababbun shirya-shiryen noman

    da abin ya shafa.

    BAYANI GAME DA SHIRIN

    Rashe na farko: Tattalin Albarkatun ruwa da inganta kariya ta fuskar amfani da madatsun ruwa. Wannan

    reshe na daga tallafi na gwaji da shirin ya kunsa domin sake fasalin amfani da albarkatun tuwa, da hakan yah

    ado da manufofi da tanajin doka da kuma kaidojin da aka gindaya. Wannan reshe kuma ya kunshi kananan

    rassa biyu: Tallafi gat sarin tattalin albarkatun ruwa da kuma ka kariya ta fuskar amfani da madatsun ruwa.

    Reshe na biyu (1): Tattali da kuma bunkasa Noman Rani

    Rashin Kyakyawan yanayi na kafofin ban ruwa da kuma lalacewa da wasu hanyoyin rowan suka yin a daga

    ikin-manyan ginshikan da suka haifar rashin kyakyawan tsari na ban ruwa da a ke fuskanta a mafi akasarin

    cibiyoyi noman rani a Najeriya. Wadannan cibiyoyin noman rani an kafa sun e tun kimanin shekaru ashirin ko

    talatin da suka gabata an kuma yi tanajin yi masu garambawul a karkashin shirin na TRIMING. Wadannan

    cibiyoyi sun hada shirin Noman Rani na Bakolori a hukumar raya kogunan Sokoto Rima da shirin Kogin Kano

    da shirin Noman rani na Tsibirin Hadeja-Jamaare a hukumar raya kogunan Hadejia Jamaare a yankin

    arewacin najeriya. Wadanna matsaloli sun e suka hadu gami da gurgunta cigaban ayyukan noman rani a

    kasar nan. Sannan kuma mafi akasarin madatsun rowan da aka giggina a wancan lokacin suka a cikin

    kyakyawan yanayi da kuma za a iya amfani da su domin abubuwa da dama an yi watsi das u a sassa daban-

  • 18

    daban na kasar nan. A kan danganta hakan ne rashin karasa shirin noman rani da kuma amfani da

    makamashin wutar lantarki ta ruwa. Madatsar ruwa ta dadin kowa dake cikin hukumar raya kogunnan Benue a

    jihar Gombe ta arewa maso gabashin Najriya, na daga cikin madatsu rowan da suka samu wannan matsala.

    Reshe na uku (2): kyautata aikace-aikacen gonad a tsarin samar da kayayyaki.

    Wannan reshe na shirin zai duba batutuwan bunkasa dukkan dukkanin matakan tallafawa shirye-shirye sake

    fasalin ayyuka gona na gwamna tin tarayya. Wannan kuwa zai kunshi inganta matakan samar da ayyukan yi

    da kuma tabbatar da shigo da masu kanana da matsakaitan sanoi dake a kananan matakai.

    Haka kuma shirin zai bad a karfi ga amfani da dubarun zamani. A karkashin wannan shiri akwai akanan rassa

    biyu.

    Karamin reshe na farko: Matakan Habaka amfani da ruwa ta hanyar da ta dace waje ayyukan gona.

    Wadannan matakai za su taimuka wajen aiwatar da tsarin bayar da tallafi na GES ga manoma da kuma isar

    da kumyya zamani ta fuskar adanawa da kulawa da abinda a ka noma a bangarorin shirin. Zai samar da

    kudade domin samun kayayya kayayyaki musamman da kulawa ga mata da matasa. Wannan karamin reshen

    zai kunshi adana abinda a ka samar da cibiyoyi kasuwancin, sad a samar da ruwa gami da bayanan

    kasuwanni da makamantan su.

    Karamin reshe na biyu: Bincke kan tallafi da bunkasa shirin za a samar da tallafin day a dace ga makarantun

    koyar da manoma da na gudanar da bincike ire-iren sub a sanya ido aka tasirin amfanin gona. Sannan za a

    nomi tayin bayanai daga hukumomi daban-daban domin gudanar da ayyukan bincike. Haka kuma za a gano

    sabbin abubawan da shirin ya kunsa gami da kyautata su domin yada kimiyyar a nan cikin gida da ma

    kasashen waje. Sannan kuma za a gudanar da gwaje-gwaje da manuniya a wurae da dama ta hanyar bayar

    da fifiko akan hanyoyin tattalin albarkatun ruwa a yayin gudanar da shirin

    Reshe na hudu (3): Bunkasa jamiai da kyautata kula da shirin.

    Wannan reshen zai inganta kwazon jaman shrin ta hanya samar da kayayyakin aiki na zamani da tsare-

    tsaren suna kwazon maaikatan da dubarun gudanar dasafiyo da tsartasaren shirin na zamani. Ta wannan

    hanya ne za a inganta sashen dake kula da wannan shiri don kyautata gudanar da aikin sa.

    Wannan kuma zai kara karfafa samun cigaba da sauye-sauye masalfanu ta fuskar amfani da albarkatun tuwa

    yadda ya kamat karamin reshen faroko a karkashin reshe na hudu: Sanya ido da kuma tantance shirin.

    Wannan karamin reshen zai taimaka, wajen karfafa kwazon ma aikatar da shirin ya shafa da kuma bangaren

    da ke kula da tsara aiwatar da shirin ciki kuma harda tsfiyar da aikace-aikace na banki (batutuwan kudade ken

    an). A takaice dai za a yi tanajin kyakyawan tsari na tantancewa da sanya ido a kan shirin.

  • 19

    Karamin reshe na biyu a karkashin reshe na hudu (4): Bunkasa hukumonin da shirin ya shafa:

    Za a karfafa dukkanin matakan bunkasawa a dukkanin fannonin shirin (wannan yah ado da maaikatar kula da

    albarkatun ruwa ta tarayya da hukumomin raya koguna). A karkashin wannan reshen za a fudanar da ayyuka

    daban-daban da suka hada da tantance abubuwan bunkasa aiki da ake bukata ga hukumomin raya koguna,

    bayar da hood a karawa juna sani da tattalin shirin da rangadin nazarin shirin da isar da sakonni da hanyoyin

    tattaro bayanai da kulla kawance da cibiyoyin ilmi na kasa

    BUKATAR SAMIR DA FASALIN BIYAN HAKKOKI

    An tsara faslin biyan hakkoki ne tsara kaidoje da matakai da za a bi a sabili da shigowar bankin duniya cikin

    gudanar da shirin. Wannan fasali kuma shi ne zai samar da wata shimfida da za ta zamo jagora wajen shirya

    hanyoyin biyan hakkoki a karkashin kananan rassa na shirin a lokacin aiwatar da babban shirin na TRIMING.

    Haka zalika wannan fasali ya fito da tsare-tsare da manufofi da za su kiyaye dukkanin shirin biyan hakkoki da

    a ka hasashe. Wajibi ne kuma wadannan tsare-tsare su tabbatar da cewa akwai wani kyakywar tanaji na

    shigowar hukumomin da abin ya shafe da sauran masu ruwa da tsaki gami da mutanen da shirin ya tabada

    kuma bin kaidojin gwamnati da bankin duniya da kuma batutuwan diyyar mutanen da shirin ya taba.

    Sannan kuma wannan fasali na manufofin biyan hakkoki zai samar da wata shimfida wadda daga cikin ta za a

    samar da tsare-tsare aiwatar da biyan hakkoki gami da aiwatar da shi idan shirin na TRIMING ya gamsu da

    tsarin da a ka yiwa aiwatar da kananan rassa na shirin.

    WARAREN DA SHIRIN YA SHAFA

    Jaddawali na farko: Dubi a kan wuraren da shirye-shiryen nomin rani ya hado da kuma yadda shirin na

    TRIMING ya shafe su.

    Yakin da kogi ya ke Hukuma Wajen shirin Noma Rani Madatsar ruwa

    yankin arewaa Niger Sokoto Rima SHIRIN Noman Rani na ts

    kolori/shirin Noman Rani na

    Tsibirin Rima

    Madatsar ruwa ta Bakolori.

    Madatsun ruwana Zobi da

    Goronyo.

    Kogin Hadeja-ja

    naare-komadom-jhou-

    yobe.

    Hadaja Jamaare Hirin noman rani na kogin

    kano

    Shirin noman rani na tsi

    Madatsun ruwa na tiga da

    challawa gorge

    Madatsar ruwa ta itaderia

    Kogin Benue Gangola Shirin nomin rani na dadin

    kowa

    Madatsar ruwa ta dadin

    kowa.

  • 20

    Bakolori dai wani suna ne na wani yankin karkara dake a cikin jihar Zamfara ta arewa maso yammacin

    Najeriya Madatsar ruwa da shirin noman ranin na Bakolori kuwa suna a cikin yankin karamar hukumar

    maradun wadda a ka ciro tsohuwar karamar hukumar Talate Mafara. Madatsar rowan dai na amfani har ga

    jamaa dake a yankunan kananan hukomomin Talat Mafarada Bakura da Maradun a jihar ta Zamfara. Wanna

    shirin dai ya na kimanin kilomita 110 a kudu maso gabas da birnin Sokoto.

    Shi kuwa shirin nomin rani na tsibirin Rama ya na a cikin jahar Sokotane daka a arewa maso yammacin

    Najeriya. Wannan aiki dai an yi samar das hi ne tattare da madatsar shrin nomin ranin kuma ya kunshi

    kimanin tsawon hekta dubu biyar da dari uku da sittin. An kafa shi ne a tsakanin madatsar ruwa ta Goronyo

    kusa da kauyen Katsina a bangaren arewa maso gabsa da kuma kilomita biyar da kauyan shinaka a bangaren

    kude maso yamma.

    Shirin Noman ranin kogin kano kuwa ya fare ne wajen shekare ta alif da sittin da tara a sakamakon gina

    madatsar ruwa ta Bagauda wanda ya fara daga shirin noma rani na kadawa. Daga nan ne kuma gwamnati ta

    hanzarta biyo bayan madatsar ruwa ta Bagauda da wata babbar madatsar ruwan wato madatsar ruwa ta

    Bagauda da Tiga a tsakanin shekara ta alif da dar tara da sabain zuwa shekara ta alif da dari tara da sabain

    da uku, da manufar bunkasa ayyukan gona ta hanyar noman rani don inganta dogaro da kai masamman ma

    ta fuskar samar eda abinci. Daga bisani hakkin kulawa da madatsar ruwan tashi daga hannan gwamntin jahar

    Katsina ya koma ga gwamnatin tarayya a matsayin wani shiri daka a karkashin hukumar raya kogunan

    Hadejia-jamaare.

    Sanna kuma shirin noman rani na tsibirin Hadejia na daya daga cikin ayyukan gwamnatin Auyo da kangama

    da Miga da Kafin Hausa da Masarautar Hidejia da kafin Hausa. Makasudin samar da shirin a shi ne a samu

    sukunin cin moriyar ruwn dake fitowa daga kwararon madatsun ruwa na Challawa da Tiga fitowa daga

    kwarorin madatsun ruwa na Challawa da Tiga ya zuwa ga Kogin.

    A bangare guda kuma, shrin noman rani na Dadin kowa an kafa shi ne kauyen Dadin kowa daga bangaren

    daman a Kogin Gongola kusa da gadar Dadin Kowa akan hanyar Zuwa Biu da kilomita biyar daga kwaroron

    madatsar ruwa da Dadin kowa. Wannan shirin dai ya fara ne a shekara ta alif da dari tara da sabain da tara.

    RUKUNNEN MATANEN DA SHIRIN YA SHAFA

    Za a iya rarraba mutanen da wanna shirin ya shafa ya zuwa rukunnai uku, kamar haka:

    Mutumin da shirin ya shafa- wato wanda ya rasa kayayyakin sa ko jarin sa ko fili a sakamakon aikace-

    aikace da shirin ya kunsa kuma ya cancanci a bas hi diyya.

  • 21

    Gidan da shirin ya shafa- gida zai iya zamowa shirin nan ya shafe shi ne idan daya ko fiya da haka

    daga mutanan day a kunsa ya samu tangarda a sakamakon aikace-aikacen da wannan shirin ya

    kunsa.

    Gidan masu larura- wannan kuwa ya kunshi mutanen daa sakamakon wata nakasa ko rashin tattalin

    arziki zai fuskanci Karin matsaloli idan a ka taba wani bangare ko kuwa dukkanin gine-ginen saa

    yarkin da saurin ya shafa.

    MATAKAN CENCENTA DA DIYYA

    Tsarin bankin duniya ya bijiro da wasu hanyoyi ukku na cancenta da diyya a cikin wannan shiri:

    a. Mutanen da suke da cikekken hakkin da mallakar fili ko kasa da tanajin dokokin kasa ko na gargajiya

    ma suka lamince da shi.

    b. Mutanen da basu da hakkin mallakar fili ya zuwa lokacin da a ka gudanar da kidaya, to amma su na

    ikirari yazo daidai da tanaje-tanajen dokokin kasa ko jiha ko kuwa gargaiya.

    c. Wadanda basu da cikakken hakkin mallaka ko ikirari dake da goyon bayan doka akan filayen da suke

    amfani da su don neman abinci.

    FASALIN DOKA A KAN MALLAKAR FILI

    Fasalin daya shafi mallakar fili a Najeriya shine daftarin dokar nan na amfani da fili ko kasa na shekara ta alif

    da dari tara da sabain da takwas da a ka yiwa gyara a karkashin babbar doka ta 202 ta shekara ta alif da dari

    tara da casain. Haka kuma anyi gyara akan tsarin gudanar da ayyuka na bankin duniya wanda ya shafi

    mallakar fili da biyan hakkoki. In da ke da banbancin tsakanin daftarin dokar amfani da fili da kuma tsarin

    gudanar da aiki na bankin shi ne wasu matakai na biyan hakkoki.

    HANYOYIN BI DOMIN TSARA BIYAN HAKKOKI

    Da zaran an tsara bangarorin da shirin zai shigo wanda zai kunshi karbar filaye da gonaki ko kuwa gidajedaga

    hannun Jamaa, to kafin a fara ainihin ayyukan da shirin ya kunsa zaa samar da tsarin aiwatar da biyan

    hakkoki. Wannan kuwa zai kunshi gudanar da nazari da kidaya na gidaje da gine-gine kai tsaye a yankin da

    shirin ya shafa. Kuma nazarin a kan yanayin zamantakewa jamaa zai dora fifiko ga akan batutuwa da suka

    hada da hanyoyin neman abinci da gidaje da gine-gine jinsi da rukuni-rukuni na jamaa da kabilu dake akwai

    da salsalon shugabanci da ma sauran bangarori da biyan hakkokin ya kunsa. Bayanin da zaa nema zasu

    hado da hanyoyin samun kudaden shiga, sannan kuma zaa adana dukkanin bayanin da a ka nemo gami da

    hotuna. Haka kuma nazarin zai kunshi wasu muhimman abubuwa da suka hada da makarantun ilmi da

    cibiyoyi kiwon lafiya da wuraren ibada da hukumomi da shagunan saya da sayarwa da sauran abubuwan

  • 22

    bukata na rayuwar yau da kullum. Haka kuma za duba hanyoyin sufuri da kuma tsarar dake akwai tsakanin

    jamaa da wadannan abubuwa.

    TAKAITACCEN BAYANI KAN HANYOYIN MAGAN RASHIN FAHINTA

    Za a dauki matakan warware rashin fahimta ko iwa kuwa damuwa masu sauki matuka a matakin jihad a

    kananan matakai ta hanyar bayar da cikakkun bayanai ma su gamsuwar, da la akari da cewar mafi akasarin

    mutanen na da karancin ilmi kuma sun a bukatar warware rashin fahimtar su a cikin sauri kuma a bias adalci.

    Don haka za a dauki dukkanin matakan da suka dace domin warware damuwa ko rashin fahimta a yayin da

    bukatar hakan ta taso. Wadanda ked a bukatar a duba damuwar su za su iya gabatar da bukatar su ga

    kwamitin kula da hakkoki. Idan ba a karbi koken da a ka gabatar ba, to sai amika batun ga kananan kotuna

    domin warware su. Sannan kuma matsayar da manyan kotuna na jihohi shi zai zamo karshe kuma wajibi ne a

    cimma wadannan matsayoyi a cikin takaitaccen lokaci daga sailin da aka gabatar da koken.

    SHIRYE SHIRYEN BAYAR DA DIYYA

    Za a iya diyya da sauran hakkoki a karkashin tsare-tsare da kaidoji na kudi da mulki na wannan sx=hiri. Za a

    tsara gami da samar da kudade a karkashin shirin na fasalin tafi da noman rani a Najeriya sannan kuma zai

    tafi kafada da kafada da yarjenjeniyar kasha kashen kudade da aka cimmawa a lokacin tsara shirin. Sannan

    kuma tsarin biyan diyyar wanda zai kasance a mataki-mataki, kuma za a gudanar da shi a daidai da tanaje

    tanajen biyan diyya da hakkoki na shirin na TRIMING.

    TANTANCEWA DA SANYA IDO

    Domin kamala biyan hakkoki baki daya. Matakin na tantancewa da sanya ido zai zamo wani alamari mai

    dorewa, kuma zai hado da cikin gida da kuma wanjen shrin.

  • 23

    CHAPTER ONE: INTRODUCTION

    1.1 Background Irrigation is the application of water to the soil for the purpose of supplying moisture essential for plant growth. It is also undertaken to provide an insurance against droughts, for cooling the soil and atmosphere. It equally provides a more favourable environment for plant growth. Irrigation washes out or dilutes salts in the soil and reduces the hazards of piping and softening tillage pans. Irrigation development has long been considered essential to the sustainable growth of agricultural production in Nigeria. Given the abundant water resources in the country and its potential for increasing agricultural production in Nigeria, the Federal Government established the River Basin Development Authorities (RBDA). The schemes became necessary because of the persistent too short rainy season in many states of the federation. It was against this background that the Bakolori and Zobe, the Kano River Irrigation, Hadejia Valley Irrigation and Dadin Kowa Irrigation Projects were established. However, because of the problems encountered in the projects and the need for effective irrigation development, the Federal Government of Nigeria (FGN) has requested World Bank assistance to prepare the Transforming Irrigation Management in Nigeria (TRIMING). The proposed project seeks to improve performance of irrigated and water resources infrastructure and institutions for enhanced productivity in selected irrigation schemes. The TRIMING Project will directly support key cross-cutting priorities in the water and agricultural sectors that are identified in the Country Partnership Strategy (CPS). These include increasing agricultural productivity, where the CPS places a strong emphasis on innovative approaches and on strengthening of systems. The proposed credit amount is US$ 400 million. The proposed project is classified as Category A for the purpose of the World Bank Safeguard Policies which means that it must be subjected to a full environmental assessment as required by the World Banks Operational Policy on Environmental Assessment (OP/BP4.01). The proposed project triggers a number of World Bank Safeguard Policies. The policies triggered are as follows:

    Environmental Assessment (OP/BP 4.01);

    Natural Habitats (OP/BP 4.04);

    Pest Management (OP/BP 4.09);

    Physical Cultural Resources (OP/BP 4.11);

    Involuntary Resettlement (OP/BP 4.12);

    Safety of Dams (OP/BP4.37);

    International Waterways (OP/BP 7.50). This Resettlement Policy Framework (RPF) is designed to provide procedures and guidelines that will be followed because the World Banks OP 4.12 is triggered by the sub-project activities. Considering that the details of the sub-projects under TRIMING (volume, scope, scale and/or actual nature of activities, etc.) are not known, it is therefore not possible in this situation to prepare a Resettlement Action Plan (RAP) or an Abbreviated Resettlement Plan (ARAP). The World Bank Operational Policy on Involuntary Resettlement (OP 4.12) therefore requires the development of a Resettlement Policy Framework (RPF) to guide the preparation of sub-project specific RAPs. This Resettlement Policy framework clarifies resettlement principles, organizational arrangements and design criteria to be applied during project implementation. Sub-project resettlement plans consistent with the RPF will subsequently be submitted to the Bank for approval after specific planning information becomes available. It should be noted that the policy is designed to mitigate harm caused by displacement or land acquisition

  • 24

    occurring in the process of the TRIMING project Implementation by setting out appropriate parameters for compensation and other assistance required by OP 4.12. The RPF shall serve as a practical tool (e.g. screening checklist) to guide the preparation of Resettlement Action Plans (RAPs) for sub-projects during the implementation of the comprehensive Transforming Irrigation Management in Nigeria (TRIMING).It is vital to note that for each subproject supported under the Project that involves land acquisition or relocation of people, a separate Resettlement Action Plan (RAP) satisfactory to the Bank is required prior to signing a work order. 1.2 Objectives for Consultancy The main objective of the consultancy is to prepare a Resettlement Policy Framework (RPF) applicable to the project over its time frame. The preparation of this RPF shall follow the requirements of the World Banks policy on Involuntary Resettlement, OP 4.12 and ESMF that has been prepared as a separate document for the project. The RPF shall also make reference to the Federal Government of Nigerias legal and institutional requirements. 1.3 Scope of Work The assignment by the Consultant shall cover the following key areas as described in the ToR. Other areas considered relevant by the Consultant should be included so far as they add value to the outlined areas below:

    i. The Resettlement policy framework shall clarify resettlement principles, organizational arrangements and design criteria to be applied to sub-projects to be prepared during project implementation. Sub-project resettlement plans (RAPs) consistent with the RPF will subsequently be submitted to the Bank for approval after specific planning information becomes available prior to disbursement for a specific subproject. .

    ii. The scope of work for the RPF assignment will cover the following elements, consistent with the provisions described in OP 4.12, paras. 2 and 4:

    iii. A brief description of the project and components for which land acquisition and resettlement are required, and an explanation of why a Resettlement Policy Framework;

    iv. Principles and objectives governing resettlement preparation and implementation, including a legal analysis and framework, reviewing the fit between borrower laws and regulations and Bank policy requirements and measures proposed to bridge any gaps between them;

    v. A clearly set out screening process for all subcomponents and a description of the process for preparing and approving Resettlement Action Plans (RAP), including outlining the process and content required for the preparation of such plans;

    vi. Estimated population displacement and likely categories of displaced persons, to the extent feasible; vii. Eligibility criteria for defining various categories of displaced persons; viii. A Methodology to identify precisely the affected population before the intervention; and to assure that

    this population will be the beneficiary of the relocation; this methodology will include a detailed census after which a cutoff date is declared;

    ix. A Methodology for valuing affected assets; Compensation and assistance are to be based on the overall principle that affected people shall not suffer net losses as a result of the project and that affected assets will be compensated at or above replacement cost;

    x. Definition of entitlements including, as appropriate, replacement housing, replacement farmland, cash compensation and other forms;

    xi. Organizational procedures for delivery of entitlements, including, for projects involving private sector intermediaries, the responsibilities of the financial intermediary, the government, and the private

  • 25

    developer; xii. A description of the implementation process, linking resettlement planning and implementation to both

    civil works and livelihood strategies; xiii. A description of grievance redress mechanisms to be supported or established; xiv. A description of the arrangements for funding resettlement including the preparation and review of

    cost estimates, the flow of funds, and the contingency arrangements xv. A description of mechanisms for consultations with, and participation of, displaced persons in

    planning, implementation, and monitoring; and xvi. Arrangements for monitoring by the implementing agency and, if required, by independent monitors. xvii. Template for the design of sub-project RAPs xviii. A description of the processes of monitoring, verification and evaluation required for effective

    implementation of the resettlement process. 1.4 Principles and Objectives of World Banks Resettlement Policy Generally, involuntary resettlement, unless properly managed, may result in long-term hardship and impoverishment for affected persons and communities, as well as environmental damage and social stress in areas to which they have been displaced. The impacts due to involuntary resettlement from development projects, if left unmitigated, often gives rise to severe economic, social and environmental risks resulting in production systems being dismantled; people facing impoverishment when their productive assets or income sources are lost; people being relocated to environment where their skills may be less applicable and the competition of resources greater; community institutions and social networks being weakened; kin/clan groups being dispersed; and cultural identity, traditional authority, and the potential for mutual help are diminished or lost. For these reasons, most projects, like the TRIMING supported by the Bank are designed to avoid involuntary resettlement. Where it is unavoidable to embark on involuntary resettlement assistance as a sustainable development initiative, appropriate measures to minimize, as much as possible, are chosen. For adverse impacts on displaced persons and host communities, carefully planned and implemented framework is ensured to mitigate the impact. The World Bank Resettlement Policy OP 4.12 could be triggered in instances where, project activities could result in loss of structures (houses, fences/ involuntary take of land etc.) and possibly incomes (rents for landlords, business premises, agricultural land). Therefore, people are in most cases compensated for their loss (of land, property or access) either in kind or in cash of which, in most cases the former is preferred. The failure to take into account potential involuntary resettlement in the rehabilitation of 11,200 ha of irrigated land and an expansion of the existing scheme of up to 22,400 ha., for example as will be carried out in TRIMING project can increase the risk of hardship and negatively impact poverty reduction objectives. It is generally recognized that the impacts due to involuntary resettlement from development projects give rise to severe economic, social and environmental risks if left unmitigated such as listed below: a. Landlessness

    Land expropriation removes the main foundation on which many people build productive systems, commercial activities and livelihoods.

    Often land is lost forever and sometimes it is partially replaced, seldom fully replaced or fully compensated. This is the main form of de-capitalization and pauperization of the people who are displaced, and both natural and man-made capital is lost.

    b. Homelessness

  • 26

    Loss of shelter may be only temporary for many people, but for some it remains a chronic condition and is also felt as loss of identity and cultural impoverishment.

    Loss of housing may have consequences on family cohesion and on mutual help networks if neighbouring households of the same kinship group get scattered.

    Group relocation of neighbours is therefore usually preferable over dispersed relocation. c. Joblessness

    Loss of salaried employment occurs both in rural and urban displacement. People losing jobs may be industrial or service workers, landless agricultural labourers, or artisans. Unemployment or under-employment among those who are resettled may linger long after physical

    relocation. Creating new jobs for them is difficult and requires substantial investments, new creative approaches,

    and reliance on sharing project benefits. d. Food Insecurity

    Destruction of crops diminishes self-sufficiency, dismantles local arrangements for food supply, and thus increases the risk of chronic food insecurity. This is defined as calorie-protein intake levels below the minimum necessary for normal growth and work.

    e. Increased Morbidity and Mortality Vulnerability of the poorest people to illness is increased by forced relocation, because it tends to be

    associated with increased stress, psychological traumas, or the outbreak of parasitic diseases. Decreases in health levels result from unsafe water supply and sewage systems that cause the

    spread of epidemic infections, diarrhoea, dysentery, etc. f. Educational Loss

    Involuntary displacement disrupts all public services at the departure sites, with heavy effects particularly on school programmes.

    Interruption of school attendance causes prolonged loss of access to education; some children do not return to school at all and are prematurely sent by their families to join the labour force.

    g. Social Displacement The dismantling of community structures and social organization, the dispersion of informal and formal

    networks, local associations, etc. is a massive loss of social capital. Such displacement undermines livelihoods in ways usually not recognized and not measured by planners, and is a cause of disempowerment and impoverishment.

    h. Marginalization This occurs when relocated families lose economic power and slide down towards lesser socio-

    economic positions. Middle-income households become small landholders while small shopkeepers and craftsmen lose

    business and fall below poverty thresholds. Economic marginalization tends to be accompanied by social and psychological marginalization.

    i. Loss of Access to Common Property Poor farmers, particularly those without assets, suffer loss of access to the common property goods

    belonging to communities that are relocated (e.g., loss of access to forests, water bodies, grazing lands, fishing areas, cemetery lands, etc.). This represents a form of income loss and livelihood deterioration that is typically overlooked by planners and therefore uncompensated.

    In line with the foregoing, this Resettlement Policy Framework has the following objectives: (i) Involuntary resettlement and land acquisition should be avoided where feasible, or minimized,

    exploring all viable alternative project designs; (ii) Where it is not feasible to avoid, resettlement and compensation activities should be conceived and

    executed as sustainable development programs, providing sufficient investment resources to enable

  • 27

    the persons displaced by the project the opportunity to share in project benefits. Displaced and compensated persons must be meaningfully consulted and have opportunities to participate in planning and implementing the programs linked to their resettlement.

    (iii) Displaced (economically or physically) and compensated persons should be assisted in their efforts to improve their livelihoods and standards of living , or at least restore them, in real terms, to pre-displacement levels or levels prevailing prior to the beginning of project implementation, whichever is higher.

    For the purposes of this framework, Affected Persons are defined as: All persons who, as a result of works carried out or to be carried out under the Project, would incur: (i) relocation or loss of shelter, such as houses; (ii) loss of assets or access to assets, such as land or crops; or (iii) loss of income sources or means of livelihood whether or not the affected persons must move to another location, such as stalls or productive activities on the land; or (iv) the involuntary restriction of access to legally designated parks or protected areas, which would result in adverse impacts on the livelihoods of displaced persons. Therefore, involuntary resettlement, as per the definition in OP 4.12 (Annex 1), means both physical displacement as well as economic displacement. The term involuntary means any taking or displacement, to which the project affected person cannot say no - that is an action that may take place without the displaced persons informed consent or power of choice, is involuntary and therefore the policy OP 4.12 applies. The policy applies to all displaced persons regardless of the total number affected, the severity of the impact and whether or not they have legal title to the land. Particular attention will be paid to the needs of vulnerable groups among those displaced; especially those below the poverty line; the landless, the elderly, women and children and the ethnic minorities or other displaced persons who may not be protected through Nigerian land compensation legislation. In particular for TRIMING Project, the policy also requires that the implementation of individual resettlement and compensation plans are a prerequisite for the commencement of project activities causing resettlement, such as land acquisition, to ensure that displacement or restriction to access does not occur before necessary measures for resettlement and compensation are in place. It is further required that these measures include provision of compensation and of other assistance required for relocation, prior to displacement, and preparation and provision of resettlement sites (if necessary) with adequate facilities, where required. In particular, the taking of land and related assets or the denial of access to assets may take place only after compensation has been paid and where applicable, resettlement sites, new homes, related infrastructure, public services and moving allowances have been provided to displaced persons. Furthermore, where relocation or loss of shelter occurs, the policy further requires that measures to assist the displaced persons are implemented in accordance with the resettlement action plan. 1.5 The Need for Transforming Irrigation Management in Nigeria (TRIMING) Project Resettlement

    Policy Framework (RPF)

    This Resettlement Policy Framework (RPF) is designed to provide procedures and guidelines that would be followed because the World Banks OP 4.12 is triggered by the project. The RPF provides a practical tool (e.g.

  • 28

    screening checklist) to guide the preparation of Resettlement Action Plans (RAPs) for sub-projects during the implementation of the comprehensive TRIMING project. The RPF sets out the policies, principles, institutional arrangements, schedules and indicative budgets that will take care of any anticipated resettlements. These arrangements shall also ensure that there is a systematic process (as against an hoc one) for the different stages of the implementation of a framework that assures participation of affected persons, involvement of relevant institutions and stakeholders, adherence to both World Bank and Government procedures and requirements, and outline compensation for affected persons. The RPF provide the framework within which Resettlement Action Plans/Abbreviated Resettlement Action Plans will be developed when the project is certain of the locations and specific impacts of the sub-projects.

    1.6 TRIMING Project and the Principle of Involuntary Resettlement Under the World Bank OP 4.12, those affected by resettlement are defined as those who are directly affected socially and economically by: (a) The involuntary taking of land and other assets resulting in:

    relocation or loss of shelter; loss of assets or access to assets; or loss of direct income sources or means of livelihood (i.e., income and livelihoods directly

    dependent on the affected areas), whether or not the affected persons must move to another location.

    (b) The involuntary restriction of access to legally designated parks and protected areas results in adverse impacts on the livelihood of the displaced persons. The Bank Safeguard Policy OP 4.12 applies to TRIMING Project in:

    1. All components under the project, whether or not they are directly funded in whole or in part by the Bank.

    2. All displaced persons due to the sub-projects regardless of the total number affected and the severity of the impact and whether or not they have legal title to the land.

    3. Squatters or other land occupiers who lack legal title or legal occupancy rights to the land they occupy who should be entitled to assistance in accordance with the objectives of the RPF.

    This RPF further applies to other activities resulting in involuntary resettlement that in the judgment of the Bank are:

    a) Directly and significantly related to TRIMING Project sub-projects during implementation b) Necessary to achieve its objectives as set forth in the project documents; and c) Carried out, or planned to be carried out, at the same time as the TRIMING Project sub-projects.

    Below, is an overview of what must be done to compensate those that will be displaced involuntarily (loss of land or prevention of access to normal means of livelihood) is given:

    Offer displaced persons choices among feasible resettlement options, including adequate replacement housing or cash compensation where appropriate.

    Provide relocation assistance suited to the needs of each group of displaced persons, with particular attention paid to the needs of the poor and the vulnerable.

    Make alternative housing and/or cash compensation available prior to relocation. Build new resettlement sites for displaced persons with improved living conditions.( where relocation

    to new site is the case

  • 29

    In the case of physically displaced persons with recognized or recognizable rights, the project will offer the choice of replacement property of equal or higher value, equivalent or better characteristics and advantages of location or cash compensation at full replacement value.

    For all displaced persons, including those without formal or recognizable rights to land, compensate them for the loss of assets other than land, such as dwellings and other improvements to the land, at full replacement cost.

    Offer compensation in kind in lieu of cash compensation where feasible. Based on consultation with such displaced persons, provide relocation assistance sufficient for them to restore their standards of living at an adequate alternative site. It is important to stress that the policy is not designed to address economic displacement in itself. Economic displacement could occur where people suffer losses or damage due to project activities that do not involve the taking of land. For example, if the water pipes to be replaced are located in a street where business shops are and disruption of economic activities may be caused temporary as people may be prevented for visiting nearby shops to make purchases. This is a purely economic displacement and not subject to OP4.12 because land was not taken from the business itself. In summary, this RPF reflects the fact that OP4.12 demands mitigation only


Recommended