+ All Categories
Home > Documents > Fidic Assignment Final

Fidic Assignment Final

Date post: 19-Feb-2018
Category:
Upload: asif-hameed
View: 223 times
Download: 1 times
Share this document with a friend

of 53

Transcript
  • 7/23/2019 Fidic Assignment Final

    1/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    Submitted To:

    Dr. Hadikusumo

    Submitted By:

    Suyog Krishna Shrestha (115573)

    Takehiko Yamaji (115663)

    Deeptara Luitel (115564)

    Muhammad Afzal (115659)

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK)

    1999 EDITION

    LEGAL & CONTRATUAL RISK MANAGEMNT

  • 7/23/2019 Fidic Assignment Final

    2/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    Table of Contents

    1.0 Introduction:.............................................................................................................................. 12.0 Management of the project risks by FIDIC:............................................................................. 1

    2.1 Project Time:......................................................................................................................... 1

    2.2 Project Cost:.......................................................................................................................... 6

    2.3 Project Quality:................................................................................................................... 10

    2.4 Project Safety:..................................................................................................................... 13

    3.0 Project Risks of OWNER (How he can manage them): ........................................................... 14

    4.0 Project Risks of CONTRACTOR (How he can manage them): ................................................. 18

    4.0 FIDIC Timeline: ........................................................................................................................ 30

    5.0 Claim, Suspension and Termination by the Contractor: ......................................................... 30

    5.0 Claim, Suspension and Termination by the Contractor: ......................................................... 35

    6.0 Clauses that can allow contractor to demand EOT/Additional Payment: .............................. 40

    7.0 Conclusion: .............................................................................................................................. 41

    Appendix I ..................................................................................................................................... 42

  • 7/23/2019 Fidic Assignment Final

    3/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    1

    1.0 Introduction:

    FIDIC (Fdration Internationale des Ingnieurs Conseils) is an international

    organization developed the brief and practical contract types for the international projects. FIDICRed book refers to the general conditions of contract for construction. In order to change/modify

    any of the condition in the general conditions of FIDIC based of the specific conditions of the

    project, we need to document that in the supplementary conditions of the contract.

    In the following part of this report, we have tried to analyze the project risks based on

    various perspective such as time, cost, owner, contractor as documented in the general conditions

    of the contract of FIDIC RED BOOK (1999 Edition) etc. The analysis is in form of Questions as

    stated below.

    2.0 Management of the project risks by FIDIC:

    FIDIC general conditions of contract provide the structure and guidelines to manage

    project risks from various perspectives. Below is the detail of the respective clauses and

    explanation of how the document is managing those particular risks.

    2.1 Project Time:

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    1 1.1 Definitions

    Most of the terms defined are related with time for

    example. The contract, commencement date should

    be taken into account to make it on specified time.

    2 1.2 InterpretationIt should be mentioned very clearly in the contract

    during providing conditions.

  • 7/23/2019 Fidic Assignment Final

    4/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    2

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    3 1.3 CommunicationsFor the approvals, certificates not to be delayed,

    communications must be made out by in writing or

    delivered by hand, or sent by email or courier

    4 1.4 Law and languageThe language for communications shall be that stated

    in the Appendix to Tender.

    5 1.5Priority of

    documents

    The documents should be in proper sequence i.e. The

    contract agreement, letter of acceptance, letter of

    tender ,the particular conditions, etc.

    6 1.6 Contract agreementThe parties should go for contract agreement within

    28 days after the Letter of acceptance is awarded.

    7 1.9Delayed drawings or

    Instructions

    The contractor should give notice to the engineer for

    the extension of time for any delays concerning the

    drawings and cost within the time

    8Permits, Licenses or

    Approvals

    And payment of any cost plus reasonable profit.

    2.2

    The contractor should be provided reasonable

    assistance in getting copies of Laws of the country

    relevant to the contract and also provided

    Permits, licenses or approvals for delivery of goods

    and export of contractorsequipment from site.

    9 3.5 Determination

    For variation that has been made, then the engineer

    will make the determination, whether to approve or

    disapprove, where the determination

    10 Site data Is binding, unless it is revised by DAB procedure.

  • 7/23/2019 Fidic Assignment Final

    5/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    3

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    4.1OThe contractor should inspect the site and collect thedata required before submitting the tender including

    all the form and nature of site

    Including sub-surface conditions, hydrological

    conditions, laws and labor practices of the country

    and other contractorsrequirements.

    11 4.16 Transport of goods The contractor should prepare material deliveryschedule and submit to the engineer so that he couldcheck the material delivery on site.

    12 4.17Contractor's

    Equipments

    For the mobilization of the equipment, the contractor

    needs the engineer's approval so that after use, it can

    be removed from the site.

    13 4.20Employers

    Equipment and

    Free Issue Material

    Any substandard material supplied for the work and

    made use of might negate the original design of theproject. This could lead to failure of the project on

    completion. So, standard materials as specified in the

    design must be purchased and applied.

    14 4.24 Fossils

    The artifacts should be removed by the owner

    through diplomatic arrangement with the community

    to remove them or otherwise to make way for the

    contract or to do his work. This done timely will go a

    long way to check delay in the execution of work.

  • 7/23/2019 Fidic Assignment Final

    6/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    4

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    15 7.3 Inspection

    Based on the specification of the designed project,

    the monitoring or time to time inspection of the work

    with guarantee the job or work being alone according

    to the designed standard.

    16 7.4 Testing

    Contractor should review testing method and

    standard in specification or in condition of contract if

    they fail to pass test on completion

    17 7.5 Rejection

    The Engineers duty amongst others is to ensure the

    contractor complies and carry out the project

    execution according to specification and schedule.

    18 7.6 Remedial Work

    There should be good relationship between the

    client/owner, the Contractor, the Sub-Contractor and

    the nominated Sub-contractor

    19 8.1Commencement of

    Works

    The owner in agreement with his Project Engineer on

    verification of claims by the Contractor should reach

    away forward on time so as to avoid delay in the

    work execution.

    20 8.3 Program

    Contractor should ask for time extension before the

    validity period expires. Providing detail explanation to

    engineer/owner.

    21 8.4Extension of Time

    for Completion

    Any Circumstances that could lead to extension of

    time must be notified within 28 days in writing to the

    Engineer who then act within a reasonable time. The

    extension of time must be avoided by owner to avoid

    the delay in completion.

  • 7/23/2019 Fidic Assignment Final

    7/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    5

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    If the access road Is the problem it should benegotiated and provided early enough by the owner

    before the commencement of the work; Natural

    occurrence is not the fault of either and should be

    integrated in the plan.

    Variation in design may cause extension of time if

    agreed upon by the contractor and the owner.

    22 8.7 Delay Damages

    Where there is friction, the work can suffer a setback

    time wise. This situation can be arrested by mutual

    understanding engendered by the Engineer or and

    23 8.8 Suspension of Work

    The owner as much as possible should avoid a

    situation such as this. The consequence of this act

    leads to extension of time to which the contractor

    can claim.

    24 8.9Consequences of

    Suspension

    The project owner being conscious of the

    consequences of acts that could lead to termination

    of contract is to avoid it. An amicable resolution of

    any issue in the contract terms can be a way out of

    the situation. The cost of termination of contract can

    be more costly than retendering for completion of

    the project.

    25 8.10

    Payment for Plant

    and Materials in

    Event of Suspension

    The payment issue is sensitive and therefore theproject owner should employ every possible means

    to ensure that the contractor is settled so as not to

    degenerate to suspension

  • 7/23/2019 Fidic Assignment Final

    8/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    6

    MANAGEMENT OF PROJECT RISK BY FIDIC

    TIME

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    26 8.11Prolonged

    Suspension

    The project owner, with a good understanding can

    settle this claim amicably with the contractor. He may

    not allow it out of hand. The two parties could

    negotiate unless otherwise, there will be more

    dispute and delay.

    27 10.1Taking Over of the

    Works and Sections

    Taking over by the employer is a critical phase as

    defect notification period starts and responsibility of

    the facility is being transferred to the employer bythis certificate. It is a critical point of potential claims

    if could not handle properly. Fiddich entails this

    clause with specific procedure, dates and deadlines

    to manage the risks.

    2.2 Project Cost:

    MANAGEMENT OF PROJECT RISK BY FIDIC

    Cost

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    1 1.1 Definitions

    Few terms related with cost for example, tendering, bill

    of quantities, variation, money and payment should be

    taken into consideration.

    2 1.7 Assignment Either party may, as security in favor of a bank orfinancial institution, assign its right to any moneys due,

    or to become due, under contract.

  • 7/23/2019 Fidic Assignment Final

    9/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    7

    MANAGEMENT OF PROJECT RISK BY FIDIC

    Cost

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    3 1.1OEmployer's Use of

    Contractor's

    Documents

    The contractor should give the employer a non-

    terminable transferable non-exclusive royalty-free

    license to copy, use and communicate the

    4 1.12 Confidential details

    Contractorsdocuments including modifications.

    The contractor should disclose all confidential to verify

    the compliance with the contract.

    5 1.13Compliance with

    laws

    The contractor should give the notice regarding allpayments of taxes, duties and fees and obtain all

    permits, licenses and approvals

    As required by the laws in relation to the execution and

    completion of the works and remedying of the any

    defects.

    6 1.14Joint and Several

    liabilityIf partner cannot finish, then engineer should be able

    to take the responsibility in case of joint venture.

    7 2.1 Right of Access toSite

    Before contractor enters the site, he must submit

    performance bond about 10% to prevent the delay of

    the works.

    8 2.4Employer's financial

    arrangementReasonable evidence regarding financial arrangements

    should be made out to pay contract price and should

    be submitted within 28 days.

    9 2.5 Employer's claims

    After receiving any request from the contractor and

    contractor should always be aware of the financial

    status of his contract.

    The contractor should be informed by the employer

    after he finds any even and any circumstances so that

    engineer could make determination.

  • 7/23/2019 Fidic Assignment Final

    10/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    8

    MANAGEMENT OF PROJECT RISK BY FIDIC

    Cost

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    And the notice is related with the extension of the

    Defects Notification Period that is made before expiry

    of such period.

    10 3.2Delegation by the

    EngineerContractor should clarify with the engineer in some

    communications about the claim and the Interim

    payment certificate.

    11 4.2Performance

    SecurityContractor need to buy this bond as insurance to make

    sure for the commitment by the contractor to the

    works.

    12 4.5

    Assignment of

    benefits of

    subcontract

    Once the benefit gets transferred to owner, then

    responsibility directly goes to owner for material

    supply equipment operation.

    13 4.6 Cooperation Contractor must identify the price of cooperation orcan be taken as an instruction if not mentioned in the

    contract.

    14 4.12Unforeseeable

    physical conditions

    The experienced contractor, during the period of

    tender, should consider these unforeseeable

    conditions and should notify the engineer within 28

    days.

    15 4.13Rights of way and

    facilitiesContractor should find additional ways to access to the

    site and use the other areas not provided and specified

    by owner.

    16 4.24 Fossils

    When fossils, coins, antiquity or archeological artifacts

    are found, the owner, on report by the contractor, acts

    immediately to avoid delay.

  • 7/23/2019 Fidic Assignment Final

    11/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    9

    MANAGEMENT OF PROJECT RISK BY FIDIC

    Cost

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    17 7.3 Inspection

    To ensure quality work, the ownersstaff shall at all

    reasonable times have full access to the site for which

    the Project is going on. The contractor shall give the

    owners personnel full opportunity to carry out their

    assigned duties without hindrance.

    18 7.4 Testing

    Review testing method and standard in specification or

    in condition of contract.

    19 7.5 Rejection

    The contractor has to establish the quality insurance

    system in his company to control the quality of work.

    20 8.7 Delay Damages

    The system monitored shall assist in the desired quality

    work and should be audited from time to time.

    21 8.9Consequences of

    Suspension

    Conduct site visit before tendering to gather as much

    information as possible about site condition.

    Contractor should incorporate such conditions in

    contract and to have good comparison later when such

    conditions are encountered.

    22 8.10

    Payment for Plant

    and Materials in

    Event of Suspension

    The detail report on why the payment is delayed

    should be given to contractor.eg.it is because of the

    unsatisfactory work and part of payment is delayed

    until rework is carried out

    23 9.4Failure to Pass Tests

    on Completion

    The failure of test has additional cost and delay risk,

    folic managed the risk as to specify the party

    (contractor, if under his responsibility) liable of

    repeating the test until successful or the contract price

    can be reduced to cover reduced value to the

    employer.

  • 7/23/2019 Fidic Assignment Final

    12/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    10

    MANAGEMENT OF PROJECT RISK BY FIDIC

    Cost

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    24 12.3 EvaluationThere is a risk for the deciding the quantity and price

    for the item of work, folic guides to decide those.

    Moreover, it guides on the items of work not specified

    in the contract.

    2.3 Project Quality:

    MANAGEMENT OF PROJECT RISK BY FIDIC

    QUALITY

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    1 1.1 DefinitionsTerm related with quality egotist after completion is

    carried out according to the particulate conditions.

    2 1.8Care and Supply of

    documents

    The contractor shall keep the copy of contract

    documents on the site, named Specification and the

    drawings and the specifications should be in custody

    and care of the employer.

    3 1.11

    Contractor's use of

    Employer's

    Documents

    The employers shall retain the copyright and the

    intellectual property rights in the Specification, the

    drawings and other documents made by the

    Employer.

    4 3.1Engineer's Duties and

    Authority

    The engineer has the right to issue variations which

    may include omissions i.e. Cancellation of the works.

    5 3.3Instructions of the

    Engineer

    If the contractor should solve the matter regarding

    the additional costs due to instruction with the

    engineer and if not possible, then the contractor

    should send a claim notice, and the instruction should

    not be given directly to the contractor or

    subcontractor.

  • 7/23/2019 Fidic Assignment Final

    13/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    11

    MANAGEMENT OF PROJECT RISK BY FIDIC

    QUALITY

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    6 3.4Replacement of the

    engineer

    To replace the engineer, not less than 42 days,employer should give the notice to the contractor,

    with supporting particulars.

    7 4.3Contractor's

    representative

    Contractor should appoint the representative on site

    who is fluent in the language mentioned in the

    contract.

    8 4.4 SubcontractorsThe contractor and the subcontractor should transfer

    their benefits to the owner.

    9 4.7 Setting out

    Contractor is responsible for setting out work like

    positioning, dimensioning of all parts of the works ND

    also should rectify them and if errors occurs, then

    should notify to the engineers so that he may ask for

    the additional payment and time.

    10 4.9 Quality assurance

    The contractor must develop quality manual and plan

    and Audit should be carried out by engineer or should

    be mentioned in particular conditions.

    11 4.11

    Sufficiency of the

    accepted contract

    amount

    The contactor must fulfil all the requirements so that

    the correctness and the sufficiency of the accepted

    contract amount can be easily met.

    12 4.20

    Employers

    Equipment and Free

    Issue Material

    Quality of materials and equipment supplied must be

    gauged each by the unit cost (Price) and agreed by

    the engineer. The BOQ is used as part of quality

    performance Qualitative and cost effective material

    are pointer to the quality of work.

    13 4.21 Progress ReportsThe monthly report properly guided would help in the

    desired quality control for greater performance.

    14 6.8Contractor's

    Superintendence

    Implement method statement and quality insurance

    system very strictly.

  • 7/23/2019 Fidic Assignment Final

    14/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    12

    MANAGEMENT OF PROJECT RISK BY FIDIC

    QUALITY

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    15 6.9Contractors

    Personnel

    Having experienced and committed team members.Having work method statement for each work and

    executing work under supervisor.

    16 7.2 Samples

    The Engineer shall instruct the Contractor submit

    Testing Plan for all project. The Contractor has to

    submit Testing document that including testing

    method/ procedure, standard, form for the Engineer

    consideration before testing. The Engineer has to

    check progress of work.

    17 7.3 Inspection

    It is suggested that the quality of work being done is

    being gauged through inspection beginning from

    materials used and the skills employed. The

    inspection report should guide the contractor and

    sub-contractor.

    18 7.4 Testing

    Contractor should review testing method and

    standard in specification or in condition of contract if

    they fail to pass test on completion

    19 7.5 Rejection

    The Engineer has to instruct the Contractor submit

    shop drawing by compare drawing with survey data

    of construction site for approval before starting.

    20 11.1

    Completion of

    Outstanding Work

    and Remedying

    Defects

    This clause clearly makes contractor liable for the

    works remaining and the repair of the works of poor

    quality. So, the risks of re-work will make the

    contractor to maintain his quality during the

    execution of the work.

  • 7/23/2019 Fidic Assignment Final

    15/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    13

    2.4 Project Safety:

    MANAGEMENT OF PROJECT RISK BY FIDIC

    SAFETY

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    1 2.3 Employer's PersonnelSafety procedures and Protection of the environment

    is required.

    2 4.1 Contractor's Obligations

    The contractor should be responsible for all

    contactors documents, temporary works and design

    of each plant and materials to be accordance within

    the contract and should be able to take responsibilityfor adequacy, stability and safety of all Site

    operations.

    3 4.8 Safety proceduresThe contractor should be responsible for all

    contactors documents, temporary works and design

    of each plant and materials to be accordance

    temporary works like fencing, guarding etc. So, need

    to make safety manual and safety plan.

    5 4.15 Access Routes

    As government has restrictions for allowance of size

    of vehicles passing the roads and the bridges, so the

    contractor must consider these things in tendering

    and if in case, any damages occurs, then contractor

    himself has to handle these problems related with the

    local authority.

    6 4.21 Progress Reports

    Investigation productive in project. Revise scheduling

    of project. Make details planning of critical works.

  • 7/23/2019 Fidic Assignment Final

    16/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    14

    MANAGEMENT OF PROJECT RISK BY FIDIC

    SAFETY

    S.No. CLAUSE No. CLAUSE RISK MANAGEMENT

    7 6.7 Health and safety

    The Engineer shall instruct the Contractor submit

    Safety Plan for all project. The Contractor has to

    submit Safety document that including Safety

    method/ procedure, standard, form for the Engineer

    consideration. The Engineer has to check progress of

    work for consideration whether the Contractor can

    Safety Plan is efficient or not. Arrange site meeting to

    monitoring status of Safety and construction

    progress.

    8 7.3 Inspection Making testing plan and submit to the Engineer.

    Review testing method and standard in specification

    or in condition of contract

    3.0 Project Risks of OWNER (How he can manage them):

    The Following table shows the risks borne by the owner according to FIDIC and

    suggestions to manage these risks.

    RISK ON PARTIES (FOR OWNER)

    S.No. CLAUSE No. CLAUSE RISK FOR OWNER RISK CONTROL

    1 1.1 DefinitionsRisk related with contract

    price, site ,etc.

    These terms should be

    clearly stated in the

    contract as the

    responsibility for running

    works on site and the cost

    related to owner.

  • 7/23/2019 Fidic Assignment Final

    17/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    15

    RISK ON PARTIES (FOR OWNER)

    S.No. CLAUSE No. CLAUSE RISK FOR OWNER RISK CONTROL

    2 1.2 Interpretation

    Risk related with different

    terms like 'Agreement,

    Written or in writing etc.

    The marginal words and

    other headings shall not be

    taken into consideration in

    the interpretation of these

    conditions.

    3 1.6Contract

    agreement

    Risk related with the time,

    cost ,quality and safety

    The contract agreement

    should be done within 28

    days after contractor

    receives the LOA and the

    contract agreement shall

    be based upon the form

    annexed to the particular

    conditions.

    4 2.1Right of access to

    the siteRisk of delay

    The owner shall give the

    contractor right of access

    to the site stated in

    appendix to tender.

    5 2.2Permits, licenses

    or approvalsRisk of compliance

    The employers shall

    provide assistance to

    contractor by obtaining

    copies of laws of country

    for delivery of good s and

    export of contractors

    equipment when removed

    from the site.

    6 2.3Employer's

    Personnel

    Risk related with safety

    procedures and protection

    of environment

    The employer should

    ensure the personnel and

    other contractors on the

    site (cooperation).

    7 2.4

    Employer's

    Financial

    arrangement

    Risk of suspension and

    termination

    The employer should

    submit within 28 days after

    receiving any request from

    the contractor with

    detailed particulars.

    8 4.5

    Assignment of

    benefits of

    subcontract

    Risk of risk transfer

    Once the benefit gets

    transferred to owner, all

    the responsibility goes to

    the owner.

  • 7/23/2019 Fidic Assignment Final

    18/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    16

    RISK ON PARTIES (FOR OWNER)

    S.No. CLAUSE No. CLAUSE RISK FOR OWNER RISK CONTROL

    9 4.7 Setting out Risk of claim by contractor

    Because of delay of

    specified items, the

    contractor will claim andafter getting the notice,

    engineer should go

    through sub clause

    3.5(determination) to

    agree or determine.

    10 4.12

    unforeseeable

    physical

    conditions

    Risk of claim by contractor

    The owner should set out

    the reasons why

    contractors considers them

    to be unforeseeable

    11 4.17Contractor's

    equipmentRisk of claim by contractor

    For the mobilization of

    equipment after use, theconsent is needed from

    engineer and if delay

    occurs in providing

    consent, then contractor

    will claim.

    12 4.20

    Employers

    Equipment and

    Free Issue

    Material

    The Employer shall, at his

    risk and cost provide these

    materials at the time and

    place specified in the

    Contract

    Enforcing the engineers

    to get all the necessary

    permits approved before

    the work commence at

    the site.

    13 4.24 Fossils

    Contractors Claims (a) anextension of time for

    completion (b) payment of

    any such Cost plus

    reasonable profit

    Detail survey of the site to

    check if such ground

    condition exists all over or

    just in a single spot.

    14 7.4 Testing

    Contractors Claims (a) an

    extension of time for

    completion (b) payment of

    any such Cost plus

    reasonable profit

    Define clearly the liability

    of Test on Completion in

    contract.

    15 7.6 Remedial Work

    The Employer shall be

    entitled to employ and payother persons to carry out

    the work

    Conduct a check list of

    all the activities to beperformed before the

    signing the contract.

    16 8.4Extension of Time

    for Completion

    Contractors Claims for an

    extension of time for

    completion

    Enforcing contractor to

    prepare shop-drawing and

    getting approved before

    every construction

  • 7/23/2019 Fidic Assignment Final

    19/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    17

    RISK ON PARTIES (FOR OWNER)

    S.No. CLAUSE No. CLAUSE RISK FOR OWNER RISK CONTROL

    Having good relation and

    regular communication

    with the consultant is vital.Work as per the

    specification and approved

    drawings

    17 8.8Suspension of

    Work

    Contractors Claims (a) an

    extension of time for

    completion (b) payment of

    any such Cost plus

    reasonable profit

    Owners Should have

    evidence like pictures, test

    report before suspending

    the work.

    18 8.9

    Consequences of

    Suspension

    Contractors Claims (a) an

    extension of time for

    completion (b) payment ofany such Cost plus

    reasonable profit

    Owners Should have

    evidence like pictures, test

    report before suspendingthe work.

    19 14.11

    Application for

    Final Payment

    Certificate

    After the application, owner

    has to take the responsibility

    of the product in spite of the

    detection of deterioration.

    Owner should force the

    engineer to confirm the

    value of all work done in

    accordance with the

    contract.

    20 14.15Currencies of

    Payment

    If the exchange rate

    negatively changes, actual

    payment become bigger

    than contract price

    Using bank consulting,

    appropriate insurance

    should be applied.

    21 17.3 Employer's Risks

    In the stated particular

    conditions, owner has to

    care the damage from the

    issue.

    Appropriate insurance is

    necessary. Additionally, if

    the foretaste is found,

    owner should make the

    decision how to treat the

    issue as soon as possible.

    22 18.2

    Insurance for

    Works and

    Contractor's

    Equipment

    Insurance has the exclusion

    statement. If the causing loss

    or damage is classified

    exclusion, owner has to

    discuss with contractor whoshould indemnify.

    By using particular

    condition, how to

    indemnify should be

    decided in the contract.

    23 19.4Consequences of

    Force Majeure

    In the stated particular

    conditions, owner has to

    care the damage from the

    issue.

    Appropriate insurance is

    necessary. Additionally, if

    the foretaste is found,

    owner should make the

    decision how to treat the

    issue as soon as possible.

  • 7/23/2019 Fidic Assignment Final

    20/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    18

    RISK ON PARTIES (FOR OWNER)

    S.No. CLAUSE No. CLAUSE RISK FOR OWNER RISK CONTROL

    24 20.6 Arbitration

    If dispute is judged by

    arbitration, owner must

    receive any result. And it

    becomes the final result.

    At first, owner should

    mitigate the predictable

    risk in the contract. Andafter contracting, owner

    should monitor the project

    risk. And once problems

    and risks causing, owner

    should make decision

    quickly with

    communicating with

    stakeholders.

    4.0 Project Risks of CONTRACTOR (How he can manage them):

    The Following table shows the risks borne by the contractor according to FIDIC and suggestions

    to manage these risks.

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    1 1.1 Definitions

    Risk related with the variation,

    materials, temporary

    worksheet.

    The contractor

    should carry out

    these works so

    clearly mentioned

    in the contract.

    2 1.2 Interpretation

    Risk related with different

    terms like 'Agreement,

    Written or in writing' etc.

    The marginal

    words and other

    headings shall not

    be taken into

    consideration in

    the interpretation

    of theseconditions.

    3 1.3 Communication

    Risk related with issuing

    approval, certificates,

    consents and determination.

    The notice should

    be sent by email or

    delivered by hand,

    courier or other

    reliable medium to

    prevent delay.

  • 7/23/2019 Fidic Assignment Final

    21/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    19

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    4 1.4 Law and languageRisk related with thecommunication

    It should be

    according to whathas been stated in

    the Appendix to

    the tender.

    5 1.5 Priority of documents Risk related with the delay

    To avoid delay, the

    documents should

    be in the proper

    sequence for the

    purpose of

    interpretation and

    if any ambiguity or

    difference found,

    then instruction

    should be issued

    by the engineer.

    6 1.6 contract agreementRisk related with the time,

    cost ,quality and safety

    The contract

    agreement should

    be done within 28

    days after

    contractor

    receives the LOA

    and the contract

    agreement shall

    be based upon theform annexed to

    the particular

    conditions.

    7 1.7 Assignment Risk related with bankruptcy

    If both parties

    agree, then

    another

    subcontractor can

    be assigned.

    8 1.8Care and supply of

    documentsRisk with the specification

    The contractor

    shall keep on the

    site the copy ofdocuments so that

    employer's

    personnel can see

    these documents

    at all reasonable

    times and check

    the variations and

    specifications.

  • 7/23/2019 Fidic Assignment Final

    22/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    20

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    9 1.9Delayed Drawings or

    Instructions

    Risk with the delay of works

    or disruption

    The contractor

    should give noticeto engineer if any

    necessary drawing

    or instructions is

    not issued.

    10 1.12 Confidential DetailsRisk with the compliance of

    contractor with contract

    The contractor

    shall disclose all

    such confidential

    and other

    information as the

    engineer.

    11 1.13 Compliance with the lawsRisk in performing the

    contract

    The contractor

    should comply

    with applicable

    laws otherwise

    contractor shall

    give notice, pay all

    taxes, duties and

    obtain license and

    approvals for

    execution and

    completion of the

    works.

    12 1.14 joint and several liability Risk with legal status

    The contractorshall not alter his

    composition or

    legal status

    without prior

    consent of the

    employer.

    13 2.5 Employer's Claim Risk of claim

    The contractor will

    be noticed by the

    employer after any

    circumstances or

    event is found.

  • 7/23/2019 Fidic Assignment Final

    23/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    21

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    14 4.1 Contractor's obligations Risk related with works

    The contract must

    follow what has beenstated in contract,

    responsibility of

    adequacy, stability and

    safety of all site

    operations should

    submit all details of all

    arrangements and

    method of execution.

    15 4.2 Performance security Risk of claim

    Performance

    security is

    required by owner

    as a risk control to

    ensure contractor

    will perform the

    contract.

    16 4.4 SubcontractorRisk of termination by

    employer

    The contractor is

    required to obtain

    prior consent of

    the engineer to

    subcontract parts

    of the works.

    17 4.6 Cooperation Risk of price variation

    The Contractor

    must identify the

    price ofcooperation.

    18 4.8 Safety proceduresRisk of obtaining taking over

    certificate

    The contractor

    needs to make

    safety manual and

    project safety plan

    that comply with

    govt. safety

    regulation.

    19 4.1O Site data Risk of claim

    The contractor

    should provide all

    the datasrequiredwhile executing

    site works, also

    mention site

    conditions

    ,geography etc.

  • 7/23/2019 Fidic Assignment Final

    24/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    22

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    20 4.14 Avoidance of interference Risk for damages and losses

    The contractor

    should not disturbthe convenience of

    public and must

    negotiate with

    local authority.

    21 4.16 transport of goodRisk of claims arising from the

    transport

    The contractor

    should prepare

    and update

    material delivery

    schedule and that

    schedule must be

    submitted to the

    engineer.

    22 4.19 Electricity, Water and Gas

    The Contractor shall, at his

    risk and cost, provide any

    apparatus necessary for his

    use of these services and for

    measuring the quantities

    consumed.

    Conduct site visit

    before tendering

    to gather as much

    information as

    possible about site

    condition.

    Contractor should

    incorporate such

    conditions in

    contract and to

    have goodcomparison later

    when such

    conditions are

    encountered.

    23 4.20

    Employers Equipment and

    Free Issue Material

    The Contractor shall be

    responsible for each item of

    Employer's Equipment whilst

    any of the Contractor'sPersonnel is operating it,

    driving it, directing it or in

    possession or control of it

    Owner/Engineer

    should provide

    details inspection

    report if

    contractor fail to

    remedy defect.

    Contractor shouldcheck again to

    make sure it is a

    fault of contractor

    or some external

    factors like

    environment.

  • 7/23/2019 Fidic Assignment Final

    25/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    23

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    24 6.9 Contractors Personnel

    If appropriate, the

    Contractor shall then appoint

    (or cause to be appointed) a

    suitable replacement person.

    Having

    experienced andcommitted team

    members. Having

    work method

    statement for each

    work and

    executing work

    under supervisor.

    25

    7.3 Inspection

    If the Contractor fails togive the notice, he shall if

    and when required by the

    Engineer, uncover the work

    and thereafter reinstate and

    make good, all at the

    Contractor's cost.

    Contractor should

    review testing

    method and

    standard in

    specification or in

    condition of

    contract if they fail

    to pass test on

    completion

    26

    Implement

    method statement

    and quality

    insurance system

    very strictly.

    27 7.4 Testing

    The cost of carrying out this

    Variation shall be borne by

    the Contractor,

    notwithstanding other

    provisions of the Contract.

    Making testing

    plan and submit tothe Engineer.

    Review testing

    method and

    standard in

    specification or in

    condition of

    contract.

    Inform the

    Engineer about

    incur cost and

    extra time toextend the

    contract if he want

    additional test

    which does not

    follow standard in

    specification.

  • 7/23/2019 Fidic Assignment Final

    26/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    24

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    Submission Plant,

    Material andWorkmanship to

    the Engineer for

    approval before

    working.

    28 7.5 Rejection

    If the Engineer requires thisPlant, Materials or

    workmanship to be retested,

    the tests shall be repeated

    under the same terms and

    condition. If .the rejection

    and retesting cause the

    Employer to incur additional

    costs, the Contractor shall

    subject to Sub-Clause 2.5

    [Employer's Claims] pay

    these costs to the Employer.

    Making testing

    plan and submit to

    the Engineer.

    Review testing

    method and

    standard in

    specification or in

    condition of

    contract.

    Inform the

    Engineer about

    incur cost and

    extra time to

    extend the

    contract if he want

    additional test

    which does not

    follow standard in

    specification.Submission Plant,

    Material and

    Workmanship to

    the Engineer for

    approval before

    working.

    29 7.6 Remedial Work

    The Contractor shall comply

    with the instruction within a

    reasonable time, which shall

    be the time (if any) specified

    in the instruction, or

    immediately if urgency is

    specified under subparagraph

    (c).

    Making testing

    plan and submit to

    the Engineer.

    Review testing

    method andstandard in

    specification or in

    condition of

    contract.

  • 7/23/2019 Fidic Assignment Final

    27/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    25

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    Inform the

    Engineer aboutincur cost and

    extra time to

    extend the

    contract if he want

    additional test

    which does not

    follow standard in

    specification.

    Submission Plant,

    Material and

    Workmanship to

    the Engineer for

    approval before

    working.

    30 8.4Extension of Time for

    Completion

    Contractors Claims for an

    extension of time for

    completion

    Having good

    relation and

    regular

    communication

    with the

    consultant is vital.

    Work as per the

    specification and

    approveddrawings

    31 8.6 Rate of Progress

    Unless the Engineer notifies

    otherwise, the Contractor

    shall adopt these revised

    methods, which may require

    increases in the working

    hours and/or in the numbers

    of Contractors Personnel

    and/or Goods, at the risk and

    cost of the Contractor

    Investigation

    productive in

    project.

    Revise scheduling

    of project.

    Make details

    planning of critical

    works.

    32 8.7 Delay Damages

    Damages to the Employer.These delay damages shall be

    the sum states in the

    Appendix to Tender, which

    shall be paid for every day.

    However, the total amount

    shall not exceed the maximum

    amount of delay damages

    stated in the Appendix to

    Investigationproductive in

    project.

    Revise scheduling

    of project.

    Make details

    planning of critical

    works.

  • 7/23/2019 Fidic Assignment Final

    28/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    26

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    Tender.

    33 8.8 Suspension of Work

    The Engineer may also notify

    the cause foe the suspension.

    If and to the extent that the

    cause is notified and is the

    responsibility of the

    Contractor

    Investigation

    productive in

    project.

    Revise scheduling

    of project.

    Make details

    planning of critical

    works.

    34 8.9Consequences of

    Suspension

    The Contractor shall not be

    entitled to an extension of

    time for, or to payment ofthe Cost incurred in, making

    good the consequences of

    the Contractors faulty

    design, workmanship or

    materials or of the

    Contractors failure to

    protect, store or secure in

    accordance with Sub-Clause

    8.8 [Suspension of Work]

    Investigation

    productive in

    project.Revise scheduling

    of project.

    Make details

    planning of critical

    works.

    35 8.10

    Payment for Plant and

    Materials in Event of

    Suspension

    The Contractor shall be

    entitled to payment of the

    value

    Investigation

    productive in

    project.

    Revise scheduling

    of project.

    Make details

    planning of critical

    works.

    36 8.11 Prolonged Suspension

    The suspension under sub-

    clause 8.8, the Contractor can

    request the Engineers

    permission to proceed if the

    suspension has continued formore than 84 days.

    Investigation

    productive in

    project.

    Revise scheduling

    of project.

    Make detailsplanning of critical

    works.

  • 7/23/2019 Fidic Assignment Final

    29/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    27

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    37 9.2 Delayed Tests

    There is a risk of failure of the

    contractor to carry out thetests in time or within 21 days

    of the notice of the engineer.

    If he fails, he has to bear two

    consequences:

    1. Bear the cost of the test

    carried out by someone else

    on discretion of the engineer.

    2. He has to accept the results

    of the test.

    The contractor cancontrol the

    delayed test risks

    as: 1.

    Preparing proper

    Testing Schedule.

    2. Notifying and

    Conducting Tests

    at Proper time.

    38 11.2Cost of Remedying

    Defects

    According to the FIDIC,

    contractor is liable to

    complete outstanding and

    remedying defects (Sub-clause

    11.1). So, the risk and cost is

    to be incurred by the

    contractor for the repair and

    remedying of the works.

    Contractor need to

    improve its

    productivity, so

    that the

    outstanding works

    can be completed

    in time as well as

    his workmanship

    to avoid re-work

    of the defects.

    39 11.3Extension of Defects

    Notification PeriodA risk of Employer's Claim.

    Contractor should

    carefully see if the

    extension is due to

    the suspension ofthe works by the

    employer then the

    liability is not on

    contractor for the

    delay. Contractor

    need to correct

    the defects within

    time and at most

    within defect

    liability period.

    40 11.4 Failure to Remedy DefectsA risk of Cost claim by the

    Employer

    The Contractorshould carry out

    the work by

    himself and if he

    sense he cannot

    then he should

    subcontract the

    work by the

    approval of the

  • 7/23/2019 Fidic Assignment Final

    30/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    28

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    Employer to avoid

    the claim. (A cost-efficient option

    41 14.11 Application for FinalPayment Certificate

    If contractor cannot receive

    the final payment certification

    because of his lack, taking-

    over date will be delayed. Andin the worst case, the

    contractor cannot receive the

    performance security.

    Contractor must

    prepare the

    taking-over

    procedure, Or if

    contractor find

    seriousdeterioration, as

    soon as possible

    they have to treat

    it before taking

    over.

    42 14.15 Currencies of Payment

    If the exchange rate

    negatively changes, actual

    payment become smaller than

    contract price

    Using bank

    consulting,

    appropriate

    insurance should

    be applied.

    43 15.2 Termination by Employer

    In the stated particular

    conditions, contractor has the

    probability of termination of

    the contract.

    The contractorshould understand

    the clause's

    particular

    conditions of

    termination. And

    they must avoid

    causing these

    conditions. Good

    communication

    will help to get the

    support of

    engineer.

    44 17.1 Indemnities

    Before the TOC, contractor

    has the responsibility of the

    property. And they also have

    the responsibility of the

    damage of staffs.

    The practice of

    proper project

    management

    (safety

    management,

    construction

    management and

  • 7/23/2019 Fidic Assignment Final

    31/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    29

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    so on) will prevent

    the propertydamage and

    human resource

    damage.

    45 17.2Contractor's Care of the

    Works

    From the project's

    commencement to TOC,

    contractor has the

    responsibility of thedamage/loss of works and

    goods.

    The practice of

    proper project

    management

    (safety

    management,

    construction

    management andso on) will prevent

    the property

    damage and

    human resource

    damage.

    46 18.2Insurance for Works and

    Contractor's Equipment

    Insurance has the exclusion

    statement. If the causing loss

    or damage is classified

    exclusion, contractor has to

    discuss with owner who

    should indemnify.

    By using particular

    condition, how to

    indemnify should

    be decided in the

    contract.

    47 19.5Force Majeure Affecting

    Subcontractor

    Applying force majeure to

    subcontractor, constructor

    must take the responsibility of

    the damage/loss.

    If the foretaste is

    found, contractor

    should make the

    decision how to

    treat the issue as

    soon as possible.

    48 20.6 Arbitration

    If dispute is judged byarbitration, contractor must

    receive any result. And it

    becomes the final result.

    At first, contractor

    should mitigate

    the predictable

    risk in the

    contract. And after

    contracting,

    contractor should

    monitor the

    project risk. And

    once problems

    and risks causing,

    contractor should

    make decision

  • 7/23/2019 Fidic Assignment Final

    32/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    30

    RISK ON PARTIES (CONTRACTOR)

    S.No.CLAUSE

    No.CLAUSE RISK FOR CONTRACTOR RISK CONTROL

    quickly with

    communicatingwith owner and

    engineer.

    4.0 FIDIC Timeline:

    Kindly refer to the Attached diagram on the proceeding page.

    5.0 Claim, Suspension and Termination by the Contractor:

    This portion of the document elaborates the clauses of FIDIC that can favor the

    contractor to put claim, or to suspend or terminate the contract because of the action or lack of

    action of the employer. The employer is in sensitive condition in these clauses and he needs to

    consider these carefully. The clauses are:

  • 7/23/2019 Fidic Assignment Final

    33/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    31

    CLAIM, SUSPENSION AND TERMINATION

    CONTRACTOR

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY CONTRACTOR

    WHAT NEED TO BE DONE BY PROJECT

    OWNER

    1 1.9

    Delayed

    drawings or

    Instructions

    Claim by a contractor. The contractor

    should give notice to engineer if works

    likely to be delayed if any necessary

    drawings and instructions get delayed.

    Itsbecause of the failure of engineer to

    provide notified drawings. So,

    contractor will claim for extension of

    time plus additional amount of

    contractor will claim for extension of

    time plus additional amount of

    reasonable profit.Subclause-20.1

    After receiving the notice, these matters

    should be determined and agreed.

    2 2.1Right of

    access to site

    Claim by contractor The employer shall

    give right of access to the site to

    contractor to proceed in accordance

    with the programme. But if contractor

    suffer or incurs cost, then contractor will

    claim for EOT plus additional amount of

    reasonable profit.

    After receiving the notice, it must be

    preceded in accordance with Sub clause

    (determination) to agree or to determin

    these matters.

    3 4.7 Setting out

    Claim by contractor for the extension of

    time for any kind of delay plus

    additional amount of reasonable profit

    that one should be included in the

    contract price.

    After receiving this notice, it should be

    preceded in accordance with sub clause

    (determination) to agree or to determinthese matters.

    4 4.12

    Unforeseeable

    physical

    conditions

    Claim by contractor after the contractor

    encounters adverse physical conditions,

    obstructions etc. Claim is for EOT plus

    additional payment.

    The engineer shall set out the reasons

    why the contractor considers it as

    unfired seeable.

    5 8.4Extension of

    Time for

    Completion

    Claim for additional pay mint

    Error in design may entitle

    Contractor to claim time/money

    Extension of time (EOT) available

    for a variation, delay or impediment

    of the Employer, exceptionally, adverseweather conditions, shortages of goods

    or personnel.

    On a project-financed deal, the

    Employer and Funder/Sponsor usually

    require the deletion of these EOT rights.

  • 7/23/2019 Fidic Assignment Final

    34/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    32

    CLAIM, SUSPENSION AND TERMINATION

    CONTRACTOR

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY CONTRACTOR

    WHAT NEED TO BE DONE BY PROJECT

    OWNER

    6 8.5Delay Caused

    by AuthoritiesClaim for extension of time

    Extension of time (EOT) available fora variation, delay or impediment of

    the Employer, exceptionally, adverse

    weather conditions, shortages of goods

    or personnel.

    7 8.8Suspension of

    WorkClaim for additional payment

    If the contractor suffers delay and /o

    incurs Cost from complying with the

    Engineers instructions under sub-Clause

    8.8[Suspension of Work] and/or from

    resuming the work, The Contractor hall

    give notice to the Engineer and shall be

    entitled subject to Sub-Clause 20.1[Contractors Claims] to:

    (a) An extension of time for any such

    delay, if completion is or will be delayed

    Under sub-clause 8.4 [Extension of Time

    for Completion], and

    (b) Payment of any such Cost which sha

    be included in the Contract Price.

    8 8.9Consequences

    of SuspensionClaim for additional payment

    If the Contractor suffers delay and/or

    incurs Cost from complying with the

    Engineers instructions under Sub-Clause8.8[Suspension of wok] and h/or from

    resuming the work, the Contractor shall

    give notice to the Engineer and shall be

    entitled subject to Sub-Clause 20.1

    [Contractors Claims] to claim for time

    extension and payment of any such Cost

    9 8.10

    Payment for

    Plant and

    Materials in

    Event ofSuspension

    Claim for extension of time and

    additional payment

    The Contractor shall be entitled to

    payment of the value (as at the date of

    suspension) of Plant and/or Materials

    which have not been delivered to site.

    10 10.2

    Taking Over of

    Parts of the

    Works

    There is a possibility that, after taking

    over, the contractor may bear extra cost

    in completing the works due to the

    partial use of the facility by the

    employer.

    The employer should be much careful in

    using the partially completed facility as

    this might pose a claim against him. If no

    other option, then taking over should be

    much specified and employer need to be

    careful that it might not interfere with

    the on-going contractor works.

  • 7/23/2019 Fidic Assignment Final

    35/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    33

    CLAIM, SUSPENSION AND TERMINATION

    CONTRACTOR

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY CONTRACTOR

    WHAT NEED TO BE DONE BY PROJECT

    OWNER

    11 10.8

    Interference

    with Tests on

    Completion

    It is obvious that the contractor has a

    tight schedule and any delay in the

    works by the actions of the employer

    will lead in extra cost borne by the

    contractor and ultimately claims from

    the Employer.

    The employer should be in proper

    communication with the engineer and

    contractor to inform his availability on

    the test on completion date, to avoid

    Contractor claims.

    12 11.8Contractor to

    Search

    Any job requested to the contractor

    beyond the scope of the contract shall

    be claimed by the contractor as he

    incurs extra cost for that.

    It is duty of the contractor to remedy the

    defects (Sub-clause 11.3) in defects

    notification period. The engineer should

    be competent in the preliminary and

    final inspection to highlight the defectsbefore taking over certificate.

    13 12.4 Omissions

    The omissions are considered as

    variations in the tender. The contractor

    will claim the cost he incurs as a result

    of the omission beside his profit.

    The employer should try to make the

    scope of the project very clear and fidic

    contract clauses (General condition)

    should be further refined according to

    the project situation in the particular

    conditions to avoid any major omission

    that can result in potential claim by the

    employer.

    14 13.2Value

    Engineering

    This clause refers to the proposal of the

    efficient design or construction by thecontractor in the benefit of the

    employer. As the contractor is working

    for the cost efficiency of the project at

    his own cost so, if the proposal results in

    cost saving then contractor should be

    given benefit of the saving.

    The employer should encourage the

    value engineering aspect of the

    contractor, but the proposal should be

    carefully analyzed before approval to

    avoid future dispute.

    15 13.7

    Adjustments

    for Changes in

    Legislation

    The change in the government rules and

    regulation can affect the contractor

    directly (change in construction laws) or

    indirectly (material price change). Such

    changes will affect the cash flow n

    performance of the contractor.

    To avoid such claims, the employer

    should mention a range in the particular

    conditions for keeping him flexible of

    price escalations. If the escalations go

    beyond that, he should compensate the

    contractor for the increased risk.

  • 7/23/2019 Fidic Assignment Final

    36/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    34

    CLAIM, SUSPENSION AND TERMINATION

    CONTRACTOR

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY CONTRACTOR

    WHAT NEED TO BE DONE BY PROJECT

    OWNER

    16 14.8Delayed

    Payment

    Delay in the payment clearly hinders the

    contractor from performance of his

    work and he will be entitle to claim the

    financing charges (interest) on the loans

    he took from bank to maintain his cash

    flow to execute the project.

    The employer should decide a practical

    payment plan in the contract agreed by

    both the parties and abide by that durin

    the execution of the project.

    17 16.1

    Contractor's

    Entitlement to

    Suspend Work

    Lack of the engineer's issuing

    certifications or others which are

    allowed as engineer's right to ask

    engineer in the contract causes the

    contractor's claim (EOT, additionalpayment).

    Owner and engineer should response

    the contractual contractor's request

    properly.

    18 16.4Payment on

    Termination

    If termination of contract happens,

    owner has to pay contractor's finished

    work. Contractor will claim the

    maximum amount of payment by

    according to the contract.

    Owner has to decide this condition

    carefully with the consideration of

    predictable termination cases.

    19 17.1 Indemnities

    If contractor's personnel receive the

    damage or loss by thee employer,

    contractor becomes to be entitle to

    claim indemnity.

    Owner should manage his/her personne

    to prevent causing those issues.

    20 17.4

    Consequences

    of Employer's

    Risks

    Delay of response against the

    contractor's request coming from clause

    "employer's risk" causes EOT

    Owner and engineer should response

    the contractual contractor's request

    properly.

    21 17.5

    Intellectual

    and Industrial

    Property

    Rights

    If engineer doesn't give notice against

    contractor's claim within 28 days,

    contractor becomes to get the right to

    take any goods and work in the site. And

    no notice finally causes

    ambition/litigation.

    Proper response to the contractor's

    claim and request is necessary.

    Additionally, if there is important

    goods/works in site, owner should

    protect this property by using particular

    condition.

    22 18.1General

    Requirements

    for Insurances

    If owner/owner's personnel/engineer

    don't follow insurance policy and cause

    damage/loss, contractor can claim

    owner to indemnify them.

    Owner side should understand and keep

    the insurance policy.

  • 7/23/2019 Fidic Assignment Final

    37/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    35

    CLAIM, SUSPENSION AND TERMINATION

    CONTRACTOR

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY CONTRACTOR

    WHAT NEED TO BE DONE BY PROJECT

    OWNER

    23 19.4

    Consequences

    of Force

    Majeure

    If the external force causes the

    damage/loss, contractor will try to apply

    this clause as much as possible to claim

    the indemnity.

    To making contract, owner shouldreview the condition of clause. And if

    there are predictable issues (for

    example: flood in Thailand), using

    particular condition, owner should

    mitigate these risk.

    24 19.6

    Optional

    Termination,

    Payment and

    Release

    If termination of contract happens,

    owner has to pay contractor's finished

    work. Contractor will claim the

    maximum amount of payment by

    according to the contract.

    Owner has to decide this condition

    carefully with the consideration of

    predictable termination cases.

    Additionally, owner should exclude

    predictable issue from force majeure.

    25 19.7

    Release from

    Performance

    under the Law

    When owner applies this clause to

    adjust the payment appropriately,

    contractor will claim and try to secure

    their benefit.

    Engineer should estimate the

    performance by confirming contractor's

    submissions and existing property. And

    engineer must make accurate

    estimation.

    26 20.1Contractor's

    Claims

    According to this condition, contractor

    becomes to be entitled to claim.

    Engineer has to inform these condition

    to owner correctly to prevent future

    owner's misunderstanding. And owner's

    understanding will help project

    controlling to avoid contractor's claim.

    5.0 Claim, Suspension and Termination by the Contractor:

    This portion of the document elaborates the clauses of FIDIC that can favor the employer

    to put claim against the contractor (multiple reasons), or to suspend or terminate the contract

    because of the non-performance of the contractor. The contractor is in sensitive condition in

    these clauses and he needs to consider these carefully. The clauses are:

    CLAIM, SUSPENSION AND TERMINATION

    OWNER

  • 7/23/2019 Fidic Assignment Final

    38/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    36

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY OWNER

    WHAT NEED TO BE DONE BY

    PROJECT CONTRACTOR

    1 2.5 Employer'sclaims

    If the employer considers himself

    to be entitled to any payment

    under any of the conditions or

    connected with the contract or anyextension of defect notification

    period, then employer should give

    notice and particulars to the

    contractors.

    The amount may be included in thecontract price and price certificates

    2 3.5 Determination

    If the agreement end

    inconclusively, then the engineer

    must give notice to both parties of

    determination and each party shall

    give the determination and unless

    and until revised under clause20

    (Claims, disputes andarbitration).This determination is

    binding unless revised by DAB

    procedure.

    Contractor need to follow clause

    20.1if he considers himself entitled

    for the additional payment and time

    3 4.2Performance

    security

    The employers will not make a

    claim under the performance

    security, except for amount to

    which the employer is entitled

    under the contract if failure by the

    contractor to extend validity of

    performance security and the

    failure by the contractor to pay the

    performance security and the

    failure by the contractor to pay the

    employer an amount due, or the

    circumstances which entitle the

    employer to termination under

    sub clause15.2(termination by

    employer) i.e. mistake by

    contractor occurs then employer

    will take the bond after

    termination of contract.

    Contractor should deliver the

    performance security to the

    employer within 28 days after

    receiving the letter of acceptance.

    4 4.19Electricity,

    Water and GasClaim for damage

    The Contractor shall, at his risk

    and cost, provide any apparatusnecessary for his use of these

    services and for measuring the

    quantities consumed.

    5 4.20

    Employers

    Equipment and

    Free Issue

    Material

    Claim for damage

    The Contractor shall be responsibl

    for each item of Employer's

    Equipment whilst any of the

    Contractor's Personnel is operating

    it, driving it, directing it or in

  • 7/23/2019 Fidic Assignment Final

    39/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    37

    CLAIM, SUSPENSION AND TERMINATION

    OWNER

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY OWNER

    WHAT NEED TO BE DONE BY

    PROJECT CONTRACTOR

    possession or control of it

    6 4.4 Subcontractors

    Each subcontract should include

    provisions that would entitle

    employer to require the

    subcontract to be assigned to the

    employer under sub clause 4.5 or

    in the event of termination under

    sub clause 15.2(termination of

    employer).

    The contractor and the

    subcontractor should transfer their

    benefit to the owner.

    7 6.9Contractors

    Personnelclaim for change the personnel

    If appropriate, the Contractor shal

    then appoint (or cause to be

    appointed) a suitable replacement

    person.

    8 7.3 Inspection Claim for damage , re-do of works

    If the Contractor fails to give the

    notice, he shall if and when

    required by the Engineer, uncover

    the work and thereafter reinstate

    and make good, all at the

    Contractor's cost.

    9 7.4 Testing Claim for damage , re-do of works

    The cost of carrying out thisVariation shall be borne by the

    Contractor, notwithstanding other

    provisions of the Contract.

    10 7.5 Rejection Claim for damage

    If the Engineer requires this Plant,

    Materials or workmanship to be

    retested, the tests shall be

    repeated under the same terms

    and condition. If .the rejection and

    retesting cause the Employer to

    incur additional costs, the

    Contractor shall subject to Sub-

    Clause 2.5 [Employer's Claims] pay

    these costs to the Employer.

    11 7.6 Remedial Work Claim for damage

    The Contractor shall comply with th

    instruction within a reasonable time

    which shall be the time (if any)

    specified in the instruction, or

    immediately if urgency is specified

    under subparagraph (c).

  • 7/23/2019 Fidic Assignment Final

    40/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    38

    CLAIM, SUSPENSION AND TERMINATION

    OWNER

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY OWNER

    WHAT NEED TO BE DONE BY

    PROJECT CONTRACTOR

    12 Retention amount and performancebond to be used for the test

    13 8.6 Rate of Progress Claim for damage

    Unless the Engineer notifies

    otherwise, the Contractor shall

    adopt these revised methods,

    which may require increases in the

    working hours and/or in the

    numbers of Contractors Personne

    and/or Goods, at the risk and cost o

    the Contractor

    14 8.8Suspension of

    WorkClaim for damage

    Unless the Engineer notifies

    otherwise, the Contractor shalladopt these revised methods,

    which may require increases in the

    working hours and/or in the

    numbers of Contractors Personne

    and/or Goods, at the risk and cost o

    the Contractor

    15 8.9 Consequences ofSuspension Claim for damage

    The Contractor shall not be

    entitled to an extension of time

    for, or to payment of the Cost

    incurred in, making good the

    consequences of the Contractorsfaulty design, workmanship or

    materials or of the Contractors

    failure to protect, store or secure

    in accordance with Sub-Clause 8.8

    [Suspension of Work]

    16 8.10

    Payment for

    Plant and

    Materials in

    Event of

    Suspension

    Claim for damageThe Contractor shall be entitled to

    payment of the value

    17 9.4

    Failure to Pass

    Tests on

    Completion

    Failing to pass the tests can havecritical consequences if the

    employer needs to put the facility

    in operation. Before

    commissioning, he could not do

    that and it might affect his plan of

    bringing facility in service. Or if the

    test fails and owner has to accept

    the reduced value facility.

    The contractor needs to clearly

    understand the project

    specifications and work with

    acceptable quality in order to

    prevent himself from the risk and

    claim of failure of facility at test.

  • 7/23/2019 Fidic Assignment Final

    41/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    39

    CLAIM, SUSPENSION AND TERMINATION

    OWNER

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY OWNER

    WHAT NEED TO BE DONE BY

    PROJECT CONTRACTOR

    18 11.4Failure to

    Remedy Defects

    Failure of the contractor to repairthe defect will result in the hiring

    of another contractor by the

    employer for remedying the

    defects. This will incur extra cost

    which employer will claim from

    the contractor.

    The contractor should do the workcorrect in first the first time. And fo

    specialized works, he should

    subcontract to a competent sub-

    contractor to avoid defects in

    specialized works that are complex

    to rectify.

    19 15.2Termination by

    Employer

    There is the probability of addition

    of particular condition about this

    clause for mitigate owner's risk.

    And owner will terminate the

    contract in particular condition.

    Contractor should confirm the all

    conditions of termination. And if

    there is unfair condition, contractor

    has to negotiate the correction of

    condition.

    20 15.3

    Valuation at

    Date of

    Termination

    If termination is applied, engineer

    start to estimate the contractors

    achieving works, property and

    delay from master schedule. And it

    strongly affects payment after

    termination.

    Contractor manages the project

    properly. And they have to eliminat

    the difference b/w actual progress

    and reporting progress.

    21 15.4Payment after

    Termination

    Using this clause, owner decides

    the payment for the work after

    termination. Therefore, if there is

    particular condition which cancels

    owner's payment after

    termination, contractor has to

    cover the site recovery cost.

    Contractor had to confirm whether

    particular condition mitigate owner

    payment.

    22 17.1 Indemnities

    If owner's personnel receive the

    damage or loss by the contractor

    side, owner becomes to be

    entitled to claim indemnity.

    Contractor should manage his/her

    personnel to prevent causing those

    issues.

    23 17.5

    Intellectual and

    Industrial

    Property Rights

    Delay of response against the

    owner's/engineersrequest

    coming from clause "owner's risk"

    causes litigation/arbitration in theworst case.

    Contractor should response the

    contractual contractor's request

    properly.

    24 18.1

    General

    Requirements

    for Insurances

    If contractor doesn't use

    appropriate insurance, it will cause

    the owner's/engineer's claim. And

    if the case is serious, owner will

    use termination of contract.

    Contractor should understand the

    condition of insurance correctly. An

    they must get correct type of

    insurance.

  • 7/23/2019 Fidic Assignment Final

    42/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    40

    CLAIM, SUSPENSION AND TERMINATION

    OWNER

    S.No.CLAUSE

    No.CLAUSE CONSEQUENCES BEAR BY OWNER

    WHAT NEED TO BE DONE BY

    PROJECT CONTRACTOR

    25 18.2

    Insurance for

    Works and

    Contractor's

    Equipment

    If contractor doesn't use

    appropriate insurance, it will cause

    the owner's/engineer's claim. And

    if the case is serious, owner will

    use termination of contract.

    Contractor should understand the

    condition of insurance correctly. An

    they must get correct type of

    insurance.

    26 19.6

    Optional

    Termination,

    Payment and

    Release

    If termination of contract happens,

    owner has to pay contractor's

    finished work. So owner will claim

    the minimum amount of payment

    by according to the contract.

    Contractor has to decide this

    condition carefully with the

    consideration of predictable

    termination cases.

    Additionally, contractor should

    negotiate the clause's condition to

    remove serious risk.

    27 19.7

    Release from

    Performance

    under the Law

    When owner applies this clause to

    adjust the payment, owner will try

    to minimize the payment.

    Contractor should confirm

    engineersestimation. And if they

    find underestimation of payment,

    contractor should claim correct pric

    with evidence.

    6.0 Clauses that can allow contractor to demand EOT/Additional

    Payment:

    EOT / ADDITIONAL PAYMENT

    S.No. CLAUSE No. CLAUSE

    1 1.9 Delayed drawings or Instructions

    2 2.1 Right of Access to the Site

    3 4.7 Setting out

    4 4.12 Unforeseeable Physical Conditions

    5 8.4 Extension of Time for Completion

    6 8.5 Delay Caused by Authorities

    7 10.2 Taking Over of Parts of the Works

  • 7/23/2019 Fidic Assignment Final

    43/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    41

    EOT / ADDITIONAL PAYMENT

    S.No. CLAUSE No. CLAUSE

    8 10.3 Interference with Tests on Completion

    9 11.8 Contractor to Search

    10 12.4 Omissions

    11 13.2 Value Engineering

    12 13.7 Adjustments for Changes in Legislation

    13 14.8 Delayed Payment

    14 19.4 Consequences of Force Majeure

    15 19.6Optional Termination, Payment and

    Release

    16 20.1 Contractor's Claims

    7.0 Conclusion:

    This report has been developed by a profound study of the FIDIC general conditions of

    contract (1999 Edition). By study of the document we go to know that, FIDIC unequivocally

    elaborates the project risks considering multiple practical scenarios and assumptions. One

    interesting thing worth mentioning here is that though the contract conditions clearly highlight

    project risks with respect to the employer and the contractor perspectives. But the clauses that

    pose the risk on the contractor are much more than those of the contractor. So, Contractor needs

    to much careful while working in the FIDIC Arrangement.

  • 7/23/2019 Fidic Assignment Final

    44/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    42

    Appendix I

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    1 GENERAL PROVISION

    1 1 Definitions

    1 2 Interpretation1 3 Communications

    1 4 Law and Language

    1 5 Priority if Documents

    1 6 Contract Agreement

    1 7 Assignment

    1 8Care and Supply of

    Documents

    1 9Delayed Drawings or

    Instructions

    1 10Employer's Use ofContractor's

    Documents

    1 11Contractor's Use of

    Employer's Documents

    1 12 Confidential Details

    1 13 Compliance with Laws

    1 14Joint and Several

    Liability

    2 THE EMPLOYER

    2 1 Right of Access to theSite

    2 2Permits, Licences or

    Approvals

    2 3 Employer's Personnel

    2 4Employer's Financial

    Arrangements

    2 5 Employer's Claims

  • 7/23/2019 Fidic Assignment Final

    45/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    43

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    3 THE ENGINEER

    3 1Engineer's Duties and

    Authority

    3 2Delegation by the

    Engineer

    3 3

    Instructions of the

    Engineer

    3 4Replacement of the

    Engineer

    3 5 Deteminations

    4 THE CONTRACTOR

    4 1Contractor's General

    Obligations

    4 2 Performance Security

    4 3Contractor's

    Representative

    4 4 Subcontractors

    4 5Assignment of Benefit

    of Subcontract

    4 6 Co-operation

    4 7 Setting Out

    4 8 Safety Procedures

    4 9 Quality Assurance

    4 10 Site Data

    4 11

    Sufficiency of the

    Accepted Contract

    Amount

    4 12Unforeseeable Physical

    Conditions

    4 13Rights of Way and

    Facilities

    4 14Avoidance of

    Interference

  • 7/23/2019 Fidic Assignment Final

    46/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    44

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    4 15 Access Route

    4 16 Transport of Goods

    4 17Contractor's

    Equipment

    4 18Protection of the

    Environment

    4 19Electricity, Water and

    Gas

    4 20

    Employer's Equipment

    and Free-Issue

    Material

    4 21 Progress Reports

    4 22 Security of the site

    4 23Contractor's

    Operations on Site

    4 24 Fossils

    5NOMINATED

    SUBCONTRACTORS

    5 1

    Definition of

    "nominated

    Subcontractor"

    5 2Objection to

    Nomination

    5 3

    Payments to

    nominated

    Subcontractors

    5 4 Evidence of Payments6 STAFF AND LABOUR

    6 1Engagement of Staff

    and Labour

    6 2Rates of Wages and

    Conditions of Labour

    6 3Persons in the Service

    of Employer

  • 7/23/2019 Fidic Assignment Final

    47/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    45

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    6 4 Labour Laws

    6 5 Working Hours

    6 6Facilities for Staff and

    Labour

    6 7 Health and Safety

    6 8Contractor's

    Superintendence

    6 9 Contractor's Personnel

    6 10

    Records of Contractor's

    Personnel and

    Equipment

    6 11 Disorderly Conduct

    7PLANT, MATERIALS

    AND WORKMANSHIP

    7 1 Manner of Execution

    7 2 Samples

    7 3 Inspection

    7 4 Testing

    7 5 Rejection

    7 6 Remedial Work

    7 7Ownership of Plant and

    Materials

    7 8 Royalties

    8

    COMMENCEMENT,

    DELAYS AND

    SUSPENSION8 1

    Commencement of

    Work

    8 2 Time for Completion

    8 3 Programme

    8 4Extension of Time for

    Completion

    8 5 Delays Caused by

  • 7/23/2019 Fidic Assignment Final

    48/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    46

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    Authorities

    8 6 Rate of Progress

    8 7 Delay Damages

    8 8 Suspension of Work

    8 9Consequences of

    Suspension

    8 10

    Payment for Plant and

    Materials in Event of

    Suspension

    8 11 Prolonged Suspension

    8 12 Resumption of Work

    9TESTS ON

    COMPLETION

    9 1Contractor's

    Obligations

    9 2 Delayed Tests

    9 3 Retesting

    9 4Failure to Pass Tests on

    Completion

    10EMPLOYER'S TAKING

    OVER

    10 1Taking Over of the

    Works and Sections

    10 2Taking Over of Parts of

    the Works

    10 3

    Interference with Tests

    on Completion

    10 4Surfaces Requiring

    Reinstatement

    11 DEFECTS LIABILITY

    11 1

    Completion of

    Outstanding Work and

    Remedying Defects

  • 7/23/2019 Fidic Assignment Final

    49/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    47

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    11 2Cost of Remedying

    Defects

    11 3Extension of Defects

    Notification Period

    11 4Failure to Remedy

    Defects

    11 5 Removal of DefectiveWork

    11 6 Further Tests

    11 7 Right to Access

    11 8 Contractor to Search

    11 9Performance

    Certificate

    11 10 Unfulfilled Obligations

    11 11 Clearance of Site

    12

    MEASUREMENT AND

    EVALUATION

    12 1 Works to be Measured

    12 2Method of

    Measurement

    12 3 Evaluation

    12 4 Omissions

    13VARIATIONS AND

    ADJUSTMENTS

    13 1 Right to Vary

    13 2 Value Engineering

    13 3 Variation Procedure

    13 4Payment in Applicable

    Currencies

    13 5 Provisional Sums

    13 6 Daywork

    13 7Adjustments for

    Changes in Legislation

  • 7/23/2019 Fidic Assignment Final

    50/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    48

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    13 8Adjustments for

    Changes in Cost

    14CONTRACT PRICE AND

    PAYMENT

    14 1 The Contract Price

    14 2 Advance Payment

    14 3Application for Interim

    Payment Certificates

    14 4 Schedule of Payment

    14 5Plant and Materials

    intended for the Works

    14 6Issue of Interim

    Payment Certificates

    14 7 Payment

    14 8 Delayed Payment

    14 9

    Payment of Retention

    Money

    14 10Statement at

    Completion

    14 11Application for Final

    Certificate

    14 12 Discharge

    14 13Issue of Final Payment

    Certificate

    14 14Cessation of

    Employer's Liability

    14 15 Currencies of Payment

    15TERMINATION BY

    EMPLOYER

    15 1 Notice to Correct

    15 2Termination by

    Employer

    15 3Valuation at Date of

    Termination

  • 7/23/2019 Fidic Assignment Final

    51/53

    ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION

    49

    No Title

    Project Risks Management Project RisksClaim, Suspension&

    Termination

    EOT/Additio

    Payment

    Time Cost Quality Safety Owner Contractor Contractor Owner

    15 4Payment after


Recommended