Date post: | 03-Nov-2014 |
Category: |
Documents |
Upload: | dvbhavanna-rao |
View: | 117 times |
Download: | 7 times |
National Cyclone Risk Mitigation Project(NCRMP)
Revenue (DM) DepartmentGovernment of Andhra Pradesh
THIRD PARTY QUALITY AUDIT (TPQA)
in JointVenture with
INDEXS. NO. CONTENT PAGE NO.
I List of Abbreviations 1
1 Introduction 2
2 Objectives of Third Party Quality Audit 2
3 Project Area 2
4 Components & Implementation 3
5 Project Implementation Arrangements 3-4
6 Project Progress at a Glance 4-5
7 Approach of the Assignment by TPQA, Environment & Social Team 6-7
8 Site visits by the Field Team 7
9 Environment & Social issues identified, Action taken by the Environment& Social Team (TPQA) and Action taken by the Line Department
7-9
10 Environment & Social Team, Lessons learned from the above work 10-11
11 Suggestions 11
12 Saline Embankments in Kruthivennu & Kona Mandals of Krishna District 11-13
12.1 Environmental & Social Specification- Main focus on 11-12
12.2 Some observations from Kruthivennu Saline Embankment 12
12.3 Some observations from Kona Saline Embankment 12-13
13 Grama Sabhas for Community based Cyclone Shelter Management,Maintenance Welfare Committees (CSMMWC)
13-14
14 Summary of advantages in conducting the Grama Sabhas 14-15
15 District wise photos of site visits by the Environment & Social Team,TPQA
16-43
16 Photos of Grama Sabhas for Community based Cyclone ShelterManagement, Maintenance Welfare Committees (CSMMWC) Coordinatedby the field staff (Social), TPQA
44-45
17 Photos of Inspection of the Environment & Social Team of TPQA and thevisit by the World Bank Social Expert to the Saline Embankments in Kona& Kruthivennu Mandals of Krishna District
46-52
LIST OF ABBREVIATION
ASI: Archaeological Survey of IndiaCD: Cross DrainageCES: Consulting Engineering ServicesCITES: Convention of International Trade on Wildlife Flora and FaunaCRZ: Coastal Regulation zoneCS: Cyclone SheltersCSMMC: Cyclone Shelter Management & Maintenance CommitteeEA: Environmental AssessmentEAC: Expert Appraisal CommitteeEC: Environmental ClearanceEIA: Environmental Impact AssessmentEMP: Environmental Management PlanESMF: Environmental and Social Management FrameworkFLC: Fish Landing CentreGoI; Government of IndiaGPS: Global Positioning SystemHTL: High Tide LineIIT: Indian Institute of TechnologyIRC: Indian Road CongressLA: Land AcquisitionLTL: Low Tide LineMCS: Multipurpose Cyclone SheltersMOEF: Ministry of Environment & ForestNCRMP: National Cyclone Risk Mitigation ProjectProject: Environmental & Social Screening from National Cyclone Risk Mitigation ProjectDocument: 2009105/EC/Screening Report Date: July 2010 Environment & Ecology
Department Page - vNDMA: National Disaster Management AuthorityORSAC: Orissa Remote Sensing Application CentreOSDMA: Orissa State Disaster Management AuthorityPAP: Project Affected PersonsPCM: Public Consultation MeetingPF: Protected ForestPMGSY: Pradhan Mantri Gram Sadak YojanaRAP: Resettlement Action PlanRCC: Reinforced Cement ConcreteRF: Reserved ForestRFP: Request for ProposalRI: Revenue InspectorRoW: Right of WaySEAC: State Expert Appraisal CommitteeTOR: Terms of Reference
Page 1 of 52
1 Introduction
The National Cyclone Risk Mitigation Project (NCRMP), a World Bank funded project, had
identified 13 cyclone prone States and Union Territories (‘UT’s) for implementation. These
States & Union Territories have been classified into High and Low vulnerability categories based
on the frequency of occurrence of cyclones, size of population and the existing institutional
mechanism for disaster management. A.P. comes under high vulnerability states. Andhra
Pradesh and Orissa are the first two states for implementation of the project. The Third Party
Quality Audit (TPQA) is a part of the project. For this in Andhra Pradesh, The Egis International
SA France and Egis India consulting Engineers Pvt. Ltd. have entered into a contract with
Commissioner for Disaster Management & Project Director, PIU, NCRMP, Revenue (DM)
Department, A.P. Secretariat-22 on 31st May, 2011. The assessment of Environment and Social
Management by the implementing agency is one of the major components of TPQA.
As a part of the Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project
(NCRMP) and social management, the following approach has been followed during the last
more than one year. After analysing several practices, a revised methodology has been devised
for applicability of social audit for the present projects. In summary, this document will deals with
the operational guidelines for institutionalization of environment & social audit carried out during
the project Period up to February, 2013.
2 Objectives of the Third Party Quality Audit
2.1 The objectives of the assignment:
a) Assist the PIU in maintaining the quality standards of the civil works by
independent assessment/audit of quality of works at various stages of
construction of multipurpose cyclone shelters, roads, bridges and culverts etc.
being implemented by P.R. Departments, for bridges and roads R & B Dept.,
b) Assess and report on the compliance with the requirements of Environmental and
Social Frame work (ESMF), including the management measures provided in the
Environmental Management Plans and the Resettlement Action Plans, wherever
required.
3 PROJECT AREA
The works are spread over 9 coastal districts in Srikakulam, Vizianagaram, Visakhapatnam,
East Godavari, West Godavari, Krishna, Guntur, Prakasam and Nellore.
Page 2 of 52
4 COMPONENTS & IMPLEMENTATION
The Project envisages implementation of following components:
ImplementingAgency Components Total number of
unitsImplementation status,
Phase – I,(year-1)
Panchayat Raj(PR) Department,A.P.
a) MultipurposeCyclone Sheltersb) Roads tohabitationc) Roads to Cycloneshelters
148 Nos.
273 Nos.( 477.51km)205 Nos.(281.56 km)
55 Nos.
102 Nos. (198.82 km)81 Nos. ( 95.86 km)
Roads & BuildingDepartment
Connectinga) Bridgesb) Roads
22 Nos.2 Nos. (19.5 km)
9 Nos.2 Nos.(19.5 km)
IrrigationDepartment
SalineEmbankments 2 Nos. (33.6 km). Nil
NOTE: The present consultancy does not cover saline embankments.
The following departments were reasonable for implementation:
Panchayat Raj Department:
a. Construction of multipurpose Cyclone Shelters.
b. Construction of Roads to Cyclone Shelters
c. Construction of Roads to habitations
Roads & Buildings (R & B) Department:
a. Construction of Roads & Bridges
5 Project Implementation Arrangements
1. A Project Implementing Unit (‘PIU’) in the State of Andhra Pradesh has been set
up. The Addl. Commissioner for Disaster Management, Revenue (DM)
Department, A.P. Secretariat, Hyderabad heads the PIU as Project Director. The
Page 3 of 52
PIU is responsible for coordinating and monitoring the implementation of the
Project by the respective implementation agencies. The line departments are the
implementation agencies on ground, and are responsible to ensure timely
completion of the works at desired quality levels.
2. A review of literature along with agreement was made available to the consultant
for this project
3. After reviewing the literature & field data a revised approach has been prepared
for the audit in completion of work in proper time frame.
4. A Project Implementing Unit (‘PIU’) in the State of Andhra Pradesh has been set
up. The Addl. Commissioner for Disaster Management, Revenue (DM)
Department, A.P. Secretariat, Hyderabad heads the PIU as Project Director. The
PIU is responsible for coordinating and monitoring the implementation of the
Project by the respective implementation agencies. The line departments are the
implementation agencies on ground, and are responsible to ensure timely
completion of the works at desired quality levels.
5. A review of literature along with agreement was made available to the consultant
for this project
6. After reviewing the literature & field data a revised approach has been prepared
for the audit in completion of work in proper time frame.
6 Project Progress at a Glance
1. The total number of works with concluded agreements were 143
2. The total number of works completed were 122
3. One work at D.Musalayyapeta in East Godavari district was deleted due to
site problem.
4. At Tikkavanipalem in Visakhapatnam, the site was not finalized to construct
cyclone shelter.
The details of NCRMP Project Progress is summarized in the following table
Page 4 of 52
Project progress at a Glance
District
No. of works(Under ConcludedAgreements) No. of works Completed No. of works in progress Works
Deleted
Worksnotstarted
RHB RCS MPCS
Bridges
Roads
(R&B)
Total RHB RCS MPCS
Bridges
Roads
(R&B)
RHB RCS MPCS
Bridges RCS MPCS
Srikakulam 6 8 2 4 1 21 3 8 - 3 1 3 - 2 1 - -
Vizianagaram - - - 2 1 3 - - - 2 1 - - - - - -
Visakhapatnam 8 6 7 - - 21 8 6 - - - - - 6 - - 1
EastGodavari 2 8 3 - - 13 2 7 - - - - - 3 - 1 -
WestGodavari 10 - - - - 10 10 - - - - - - - - - -
Krishna 5 3 - - - 8 5 3 - - - - - - - - -
Guntur 3 12 - 2 - 17 3 11 - 1 - - 1 - 1 - -
Prakasham 14 7 2 1 - 24 14 7 2 1 - - - - - - -
Nellore 17 9 - - - 26 17 7 - - - - 2 - - - -
GrandTotal 65 53 14 9 2 143 62 49 2 7 2 3 3 11 2 1 1
Page 5 of 52
7 Approach of the Assignment by TPQA, Environment & Social Team
In order to assist the PIU to carry out the tasks, the entire Field Support Team of TPQA
Consultant has been stationed in the project area. The following action plan has been
adopted during the Project Period by the Social & Environment Team:
Coordinated with the project staff (Technical) at the field level
Planned the Social & Environment Audit based on construction of identified/sampled
projects within the region
Anticipated various possible issues that are likely to come up during the project
implementation and informed the line department about them
Updated the Team Leader about the project progress and bottlenecks in the work
region
Established suitable measures for the anticipated issues
Reviewed and prepared all progress reports and submitted the reports
Coordinated with the line departmental officers of respective districts
Coordinated in identifying solutions for Environment & Social issues with the line
department
Provided training to the project staff on Environment & Social issues and measures
to be taken to resolve them
The community participation approach and social inclusion has been adopted in this
project. To fulfil the objectives of the Project, the task force of TPQA Consultant
posted and stationed in the project area for establishing close contact with the Local
People by paying frequent visit to them and disseminating all project related
information. One to one meeting followed by small group meeting was the main key
to gain confidence of the Locals.
After establishing close bonds with Project People, the Environment & Social team
has also identified the elite persons and Volunteers of the area. Additional efforts had
been made to make Project People aware of the adverse impacts and mitigation
measures.
District level meetings with revenue staff as well as other district level functionaries
have been regularly carried out to brief them about the project and the need for
seeking their support.
Page 6 of 52
Along with the above, Focus Group Discussions were carried out frequently with the
people, line department & people to establish mutual cooperation and to resolve the
Environment & social issues.
Transect walk in the sites with line department, people and the staff of the Contractor
for physical verification and identification of issues.
Semi structured check list with the points agreed by the line department and
contractor to know how far they were compiled and issues where intervention is
needed.
The community based approach has helped the Environment & Social Team in Reaching out to the affected persons
Assessing the magnitude of adverse impacts
Resolving some issues with participation of people
8 Site Visits by the Field Team
As a part of the project work, the Environment & Social Team visited the sites and
submitted (No.) reports up to 28th February, 2013. A team approach is followed and the
technical team in the sites also helped the Environment & Social Team in making a follow
up of the issues by contacting the line department and the contractors. The district wise
frequency of the visits made by the Environment & Social Team is as follows.
DISTRICT WISE FREQUENCY OF SITE VISITS BY ENVIRONMENT & SOCIALTEAM (TPQA, NCRMP)
S. No. Name of the DistrictFrequency of Site Visits
TotalThrice Four times Five times Six times
1 Guntur 14 1 2 - 172 Srikakulam 7 12 1 1 213 Vizianagaram 1 1 1 - 34 Visakhapatnam 18 1 1 1 215 Prakasam 23 1 - - 246 Nellore 24 2 - - 267 East Godavari 8 3 1 - 128 West Godavari - 2 6 2 109 Krishna 2 6 - - 8
Total 96 30 12 4 142
Page 7 of 52
9 Environment & Social issues identified, Action taken by the Environment &Social Team (TPQA) & Action taken by the Line department
S.No.
Environment & SocialIssues Identified
Action taken by theEnvironment & Social Team
Action taken by theLine Department
1 Contractors have notsubmitted the Work Plan forEMP implementation
The Social & Environment Teamexplained the contractors andthe line department on variousitems of EMP. They don’t haveany clarity about the EMP in thebeginning. NCRs were alsoissued to the Contractors ofCyclone Shelters at EastGodavari for the PersonalSafety Equipment to theworkers and first aid kit to beprovided in the cyclone shelters
The line departmenttaking the guidancefrom The Environment& Social Team tookmeasures likeproviding helmets andshoes to the workersworking in CycloneShelters, providingfirst aid boxes,sprinkling of water onthe constructing roadsetc. by theContractors
2 PUC was not obtained for allthe vehicles/equipment usedfor/ during construction
The Environment & Social Teammade a continuous follow upand made the contractors torealize the importance of thePUC
Following themotivation from theEnvironment & SocialTeam, the Linedepartment hascompleted this taskwith the contractors
3 Permission/Consent of theDistrict Administration/MiningDepartment/other agenciesfor quarrying and/orborrowing operations formaterials like sand and earthwas not obtained by theContractors
The Environment & Social Teamexplained the necessity of thispermission to the LineDepartment. The Contractorswere unable to realize thenecessity in the beginning butunderstood it with repeatedpersuasion from theEnvironment & Social Team
The Line departmentprovided properguidance to thecontractors inobtaining thepermission fromconcerned authority
4 Permission of waterextraction from the local areais not obtained by theContractors
The Environment & Social Teamguided the procedure to getpermission and model inobtaining the permission
The Line departmentand the Contractorstogether madenecessaryarrangements toobtain the permission
5 No consent was obtainedfrom the land owner forborrow areas by theContractors
The Environment & Social Teamexplained the contractors theprocedure involved in it
The Line departmenttook appropriate stepsin resolving this issue
6 No consent was obtainedfrom the land owner fordisposal of debris and otherwaste material by theContractors
The Environment & Social Teamstopped the improper disposalof the debris and suggested theLine department to give properguidance to the Contractors
The line departmentand the Contractorsworked together inresolving the issue
Page 8 of 52
7 The Contractors have notobtained a copy of theapproval by StateGovernment from theQuarries where they haveprocured material
The Environment & Social Teamexplained the Line Departmentand the contractors thatprocuring the material fromapproved sources is notadequate and shall besupported by proper approvalcertificate
The Line Departmenthelped the Contractorin obtaining theapproval letter
8 The Contractor has notobtained written approvalfrom the Engineer for borrowareas
The Environment & Social Teamclarified the issue both to theLine Department and Contractor
The line departmentresolved the issue byproviding writtenapproval from theEngineers
9 Written permission for waterextraction was not obtainedby the Contractor from theowners of water source
The Environment & Social Teamdiscussed with the villagersabout this issue in the meetingsand helped the Contractors
The Line Departmentand the Contractorsmet the owners andobtained thepermission letters
10 Traffic safety arrangementswere not made by theContractors
The Environment & Social Teamexplained the Line Departmentand Contractors the locationsand type of safety arrangementsrequired in those locations
The Line departmentguided the contractorsand took appropriatesteps in providingthese safetymeasures at sites
11 Proper barricading was notdone for the construction siteby the Contractors
The Environment & Social Teamgave NCRs also for somecontractors especially forconstruction of Cyclone Shelters
The Line departmenttook action and thecontractors madeproper barricading atthe site
12 Personal protection materialwas not supplied by theContractor to the workers
Environment & Social Teamgave NCRs also for somecontractors especially forconstruction of Cyclone Shelters
The Line departmentmade the contractorsto provide personalprotection material tothe workers
13 Proper care was not taken forthe Public Taps by theContractor to avoidstagnation of water on Roads
The Environment & Social Teamshowed the locations to the linedepartment where there isproblem
The Line departmenthelped the contractorin resolving the issue
14 Painting was not done to thetrees by the Contractors toavoid accidents
The Environment & Social Teammade a continuous follow up fora necessary action
The Line departmentmade the Contractorsto paint on the treesto avoid accidents
15 No attention was paid by theContractors for the ElectricalPoles and Electrical lines inobstruction for theconstruction
The issue was basically raisedby the Environment & SocialTeam and persuaded the linedepartment
The line departmentcontacted TRANSCO.Some poles incarriage way werealready shifted andthe process is goingon to shift theremaining poles in theshoulders which areclose to the road edge
Page 9 of 52
The Environment & Social Team as a part of its activity coordinated the stakeholders of the
project. By making frequent Focus Group Meetings awareness was created among the people
on various issues. In land acquisition and voluntary donation also it has played a significant role.
Issues like land acquisition near Pocahmma Temple for the road in West Godavari District is
one the example for land acquisition to Road. Regarding the shifting of electrical poles, it was
not included in the DPR for Year I works. The attention by the line department was also less in
the beginning of the project. Now, for year II works, shifting of electrical poles was included in
the DPR by the line department due to persuasion by the TPQA Consultant.
Suggestions from World Bank during Site inspections and follow up
The Environment & Social Team also made a follow up for the suggestions made by the World
Bank Team and the Line department has taken necessary action with the guidance of TPQA
Consultant to resolve the issues which is as follows:
Patnavanipeta Bridge: As per the request of the farmers to the World Bank ISR team, a pipe
culvert was constructed. The villagers wanted steps for washing clothes in the tank and the
SE(R&B) promised that they will be taken up after the water level in the tank is reduced. Now
they are constructed.
Surampeta Bridge: For the bridge approaches where the height is more than 2m, necessary
protective revetment work was sanctioned and entrusted by calling for tenders. It will commence
shortly.
Avulamanda MPCS: The World Bank ISR team wanted to explore the feasibility of providing a
drainage system to prevent water entering the MPCS. As per the line departmental officers,
suitable action will be taken in this regard.
10 Environment & Social Team Lessons Learnt from the above work
Proper awareness is not there for villagers about the project.
Local people are not involving or showing interest in construction activities
The EMP is not properly understood by the Line department and the Contractor
Orientation to Contractors on contract agreements is not adequate
Page 10 of 52
Issues like electrical poles shall be resolved much before starting work
Awareness about protection of the assets created is lacking among people
Motivation is not adequate for voluntary donation of land by the people
Projecting the voluntary donation by people is not adequate
11 Suggestions
Team approach shall be strengthened in identifying and resolving issues
Local people shall be encouraged and motivated for asset maintenance
Joint survey of the sites once by the line department and the consultants will bring
accuracy in identifying the number of obstructions and possible measures.
12 Saline Embankments in Kruthivennu & Kona Mandals of Krishna District
The Environment & Social Team visited these sites once in the month of November, 2012
and February, 2013 along with World Bank Social Expert in Krishna District. The
Environment & Social Team suggested some specifications and observations which were
as follows:
12.1 Environmental & Social Specifications-Main focus on
Construction Camp & workers camp
Establishing Construction of camp office with concrete mixture and quality control lab
etc.
Quarry operations
Borrowing earth
Soil erosion and sedimentation control
Monitoring Water, Air & Noise quality
Flora and Fauna
Environmental enhancement
Management of waste material
Conservation of religious structures/preservation of Archeological Assets
Encroachments
Labour
Legislative permits and approvals
Page 11 of 52
Any unauthorized construction debris and or Municipal solid waste deposited either
by the contractor or Public within the Road Reserve Corridor, particularly just on the
outskirts of the urban areas, shall be disposed of in the location approved by the
engineer.
Generally neither LA nor R&R issues are being considered under these Contracts.
However
If any structure (private or public), is to be demolished during the time of
construction, the modified Resettlement & Rehabilitation policy (Vide G.O. Rt. No.
1059, T R&B (R.IV), Dept., Dt: 20.11.2010) will apply.
If any built up area is identified with large gathering of people along the road, road
safety awareness camps have to be organized to them.
12.2 Some observations for Kruthivennu Saline Embankment
It is noted that 10 lakhs cubic meters of the earth is required. Necessary permission
from the concerned authorities shall be taken to use the earth.
Since it is observed that the project stretch is high embankment area, necessary
safety arrangements like provision of RCC Guard Posts with reflective stickers,
reflective cautionary sign boards shall be included in the DPR for the safety of road
users.
Since the project is coming under CRZ III, necessary clearance shall be taken before
the commencement of the work
The villagers expressed their willingness to cooperate with the line department.
The villagers during interaction mentioned that they are also trying to locate land for
CH Soils
The villagers will take necessary precautions in the village while the construction is
going on and transportation of material is done through the village.
12.3 Some observations for Kona Saline Embankment
It is noted that 12.4 lakhs cubic metres of the earth is required. Necessary
permission from the concerned authorities shall be taken to use the earth.
Since it is observed that the project stretch is high embankment area, necessary
safety arrangements like provision of RCC Guard Posts with reflective stickers,
reflective cautionary sign boards shall be included in the DPR for the safety of road
users.
Page 12 of 52
Since the project is coming under CRZ I CRZ II CRZ III, necessary clearance shall
be taken before the commencement of the work
A clear statistics & location of number of temporary houses constructed in the entire
stretch shall be collected by the line department
While discussing with the villagers at Kona, they said that 12 temporary houses are
there in the stretch of the bank
There are 5 electrical poles near the bank on the RHS from Km. 7.500 to Km.8.00.
Necessary action shall be taken to shift these poles.
13 Grama Sabhas for Community based Cyclone Shelter Management,Maintenance Welfare Committees (CSMMWC)
As per the instruction from the Client, the field staff (Social) of TPQA Consultant involved in
organizing the Grama Sabhas to form committees for the cyclone shelters from 30-1-2013. So
far, the field staff (Social) coordinated Grama Sabhas in Srikakulam, Nellore & Prakasam
districts and will be continued in the remaining districts of the project area.
The details of Grama Sabhas coordinated by the field staff (Social) of TPQA Consultant were
as follows:
GRAMASABHAS FOR CSMMWC IN SRIKAKULAM Dist.,
Date Mandal Gramasabhas
31.01.2013 Sompeta (2) 1.Gollavuru2.Ramayyapattanam
01.02.2013 Kaviti (2) 1. Idduvanipalem2. Ch.Karrivaripalem
GRAMASABHAS FOR CSMMWC IN NELLORE Dist.,
Date Mandal 1.Gramasabhas
11.02.2013 Muthukur 1.Epurupattepupalem
12.02.2013 Indukurpeta 1.West Pattepupalem2.Korutu Pattepupupalem
13.02.2013 Vidavaluru 1.Idduvanipalem2.Ch.Karrivaripalem
Page 13 of 52
GRAMASABHAS FOR CSMMWC IN PRAKASAM Dist.,Date Mandal Gramasabhas
17.02.2013 Ulavapadu
1. Chakicherla2. Alagayyapalem of Karedu3. Kothapallipalem of Karedu4. Pedapallipalem of Karedu
18.02.2013 Gudlur 1. Mondivaripalem20.02.2013 N.G.Padu 1. Thopulapalem of Kanuparthy20.02.2013 Chirala 1. Odarevu
21.02.2013 Kothapatnam
1. K.Pallipalem2. Motumala3. Padarthy4. Rangaih Palem5. Gamalla Palem6. Madanur
14 Summary of advantages in conducting the Grama Sabhas
Secretary election is unanimous in around 70% of the Grama Sabhas
Now people are more aware of the approach of World Bank and the Government
in constructing the Cyclone Shelters
The orientation helped the people to understand various components and
management of the committee
Many issues like site problem if any is coming out in the meeting and brought to
the notice of the MROs
Since the committees are formed before construction of many cyclone shelters, the
feeling of belongingness is developing among the people and they are preparing to
protect the material before the construction and the asset after construction
People are getting more awareness about voluntary donation for alternative site if
they are not satisfied with the present selection of land
Many of the social issues will be resolved much before starting the work as the
committees are getting registration within a short time
People are also thinking about the multiple uses of the Cyclone Shelters
As Mandal level officials are also part of the committee under the leadership of
MRO, people are getting confidence for the service by the committee
Page 14 of 52
The concept Multipurpose is leading to Multi benefit by the people. The people
have already started thinking on those lines.
To finally conclude with, the experience during the entire project shows the need for better
involvement of people through frequent meetings, coordination of consultants and Line
department, Joint surveys and frequent of sharing experiences between the consultants will
enhance the quality of the works in the project.
Page 15 of 52
Page 16 of 52
Page 17 of 52
Page 18 of 52
Page 19 of 52
Page 20 of 52
Page 21 of 52
Page 22 of 52
Page 23 of 52
Page 24 of 52
Page 25 of 52
Page 26 of 52
Page 27 of 52
Page 28 of 52
Page 29 of 52
Page 30 of 52
Page 31 of 52
Page 32 of 52
Page 33 of 52
Page 34 of 52
Page 35 of 52
Page 36 of 52
Page 37 of 52
Page 38 of 52
Page 39 of 52
Page 40 of 52
Page 41 of 52
Page 42 of 52
Page 43 of 52
Page 44 of 52
Page 45 of 52
Page 46 of 52
Page 47 of 52
Page 48 of 52
Page 49 of 52
Page 50 of 52
Page 51 of 52
Page 52 of 52