Television Tower and Equipment Building at Slidell, LA Proposal By Edgar Company Document Version: Version 1.0 Date: 12/07/2009 Prepared by: ProjectM Team Lauren Artz Carlton Dennis Nzekwe (Pat) Ibe Robert King Proprietary Information
Transcript
Page 1: Final_Project_ProjectM_DE

Television Tower and

Equipment Building

at Slidell, LA

ProposalBy

Edgar CompanyDocument Version: Version 1.0

Date: 12/07/2009

Prepared by: ProjectM Team

Lauren Artz

Carlton Dennis

Nzekwe (Pat) Ibe

Robert King

Proprietary Information

Page 2: Final_Project_ProjectM_DE

TABLE OF CONTENTS

TABLE OF CONTENTS........................................................................................2

PROJECT MANAGEMENT PLAN........................................................................3

EXECUTIVE SUMMARY AND OBJECTIVES......................................................9

WORK BREAKDOWN STRUCTURE.................................................................10

PROJECT ORGANIZATION & LINEAR RESPONSIBILITY CHART.................12

ACTIVITY ON NODE WITH CRITICAL PATH....................................................14

EARLY START SCHEDULE...............................................................................16

LABOR RESOURSES HISTOGRAM.................................................................17

CASH FLOW.......................................................................................................18

PROPOSAL COST BREAKDOWN....................................................................26

ASSUMPTIONS..................................................................................................26

Proprietary Information

Page 3: Final_Project_ProjectM_DE

Laborers Laborers

Laborers LaborersLaborers

Laborers

Carpenters

Painters

PlumberCrane Operator

Estimator Contract Specialist

Senior Management

Project Manager (John Harris)

EC General Foreman

Rod men

Land Surveyor

Brick layers

Electricians Iron Worker

Laborers Laborers

Equipment Operator

PROJECT MANAGEMENT PLAN

PROJECT OVERVIEW

1.1 Project title: Construction of television station facilities at Slidell, Louisiana

1.2 Contract price: $1,584,735.08

1.3 Contract period: Firm period of 46 weeks effective from contract signature date

1.4 Contract commencement date/contract signature date: 5 May 2008

1.5 Project completion date: 20 March 2009

1.6 Project Team (Management Structure) is listed below it shows you the level of communication between Edgar Employees and contractors.

Proprietary Information

Page 4: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

1.7 Milestones

(i) Contract signature date/contract commencement

(ii) Site Survey

(iii) Site Clearing

(iv) Completion of tower erection

(v) Completion of facilities building

(vi) Commissioning of electrical equipment/other equipments and tower

(vii) Job acceptance and project hand over

2. PROJECT SCOPE

2.1 Survey

2.2 Site Clearing and site layout

2.3 Procurement

2.3.1 Structural steel and guys for tower

2.3.2 Electrical equipment for tower and connecting underground cable

2.4 Construction

2.4.1 Building2.4.1.1 Excavation of basement

2.4.1.2 Casting of footings

2.4.1.3 Casting of basement slabs and fuel tank slab

2.4.1.4 Casting of outside basement wall

2.4.1.5 Casting of walls for basement rooms

2.4.1.6 Castings of floor beams

2.4.1.7 Casting of main floor slabs and concrete block walls

2.4.1.8 Casting of floor slabs

2.4.1.9 Interior training and utilities

2.4.1.10 Roofing

2.4.1.11 Painting, installation of facilities, clean up.

Proprietary Information

Page 5: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

2.4.2 Tower

2.4.2.1 Casting of tower footings and anchor

2.4.2.2 Erection of tower and installation of electrical equipment

2.4.2.3 Cable connection in tower site

2.4.2.4 Installation of drains and storm drain in tower site

2.4.3 External Works

2.4.3.1 Backfill and grade tower

2.4.3.2 Backfill around building grade surface with crashed stone

2.4.3.3 Installation of main cable between tower site and building

2.4.3.4 Installation fuel tank

2.4.3.5 Installation of building septic tank

2.4.3.6 Installation of drain tile and storm drain in building site

2.4.3.7 Lay base for connecting road between tower and building

2.4.3.8 Complete grading and surface connecting road

2.4.3.9 Clean up site

2.5 Testing and commissioning: Testing and commissioning of electrical equipment, tower, other equipment.

2.6 Obtain Job acceptance and handover

3. PROJECT OBJECTIVE: To deliver, by 20 March 2009 a 340-foot high television antenna and other facilities including building to specified quality; and to the full scope described above. It is estimated that Edgar Company will be making a profit of $94,351.75 at the completion of the works. Efforts will be made to improve on this profit, which is estimated at the company’s average by effective monitoring and control during project execution.

4. GENERAL APPROACH:

4.1 Subcontractors: The client will supply, through another source, electrical equipment and other equipment to be housed in the building

4.1.2 The following equipment will be rented from specialist subcontractors

- Earthmoving equipment

Proprietary Information

Page 6: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

- Concrete mixer

- Crane

- Road equipment

4.2 Work procedure: All works, except 4.1.1 & 4.1.2 above will be executed by the project team in house

5. CONTRACTOR ADMINISTRATION

5.1 COMMUNICATION PLAN – This communication plan diagram below allows you to view the different type of communication on this project and the center of all communication is the project manager.

5.2 Change Order/Scope Creep: Change in scope will only be initiated, and authorized through a change order by the TV management.

6. RISK MANAGEMENT PLAN

Risk Factors: The factors that will give rise to uncertainties are basically the following.

6.1 The probable incompleteness of the activities as reconciled by Edgar’s estimator and the foreman.

6.2 The coordination of activities relevant to the project, but not within the scope of Edgar company

6.3 The appointment of subcontractors and the coordination of their activities

6.4 The authorization of the project management plan, comprising the cash flow, the personnel histogram, among others; by Edgar Senior Management.

Proprietary Information

Page 7: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

6.5 The continuous monitoring and control of the cost performance, schedule performance, and technical performance of the project; to ensure they meet the project objectives, and are to the client’s satisfaction

Risks: The following risks have been identified.

The incompleteness of the activities/project requirements as reconciled by the estimator and general foreman resulting in the following not being considered, in terms of cost and schedule

Schedule: The times for accomplishing the following tasks.

- procurement of materials for building (cement, lumbers, tiles)

- procurement of base materials for road

- procurement of the fuel tank

- procurement of the septic tank

- testing and commissioning of installed electrical/other equipment

- excavation for underground cable

- excavation for septic tank

- leasing of earthmoving equipment, concrete mixer, crane, road equipment

Cost: The following labor costs.

- excavation for underground cable

- excavation for septic tank

- testing and commissioning of electrical/other equipment

- procurement of materials for the building

- procurement of base materials for the road

- procurement of septic tank

- procurement of fuel tank

Proprietary Information

Page 8: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

6.6 The coordination of the provision on site, at the required time, of the specified electrical / other equipment for the building by the client

6.7 The appointment of competent equipment leasing company to ensure that the project schedule is not disrupted

6.8 Authorization of the project plan by Edgar company senior management

6.9 he monitoring and control of the project performance parameters, to ensure project success

Risk Analysis: All the risks identified have a high probability of occurring

7. Contingency Plan: This will comprise the following.

7.1 A revision of the project schedule, within the contract delivery period, to accommodate durations for all the activities listed

7.2 A revision of the project cost to accommodate the Labor cost for excavation of underground costs, excavation of septic tanks, testing/commissioning of electrical/other equipment

7.3 A revision of the labor resource histogram to accommodate listed activities in 2.1b

7.4 A revision of equipment resource histogram to accommodate excavation for underground cable

7.5 A revision of indirect cost to accommodate the procurement of materials for the road, septic tank, fuel tank

7.6 The project manager is to liaise with the client, as regards the delivery of electrical/other equipment for the building. It is suggested that he, along with the client, review the production and delivery schedule of the supplier of the materials to ensure it is in line with the project schedule. It is further recommended that the client formerly authorizes the project manager to progress and expedite the procurement to ensure compliance with quality and project schedule

7.7 Competent equipment leasing companies will be appointment to reduce downtime, which will effect project delivery. In addition, alternative companies will be appointed on call-up basis to immediately fill any gap that may be created by equipment breakdown

7.8 Starting from project inception, the Earned Value Analysis will be deployed to monitor and control the project performance in terms of schedule, cost and quality. This way, negative trends will be detected, and corrective measures taken to reverse them. In addition, any changes in specification will be approved by the client as a change other, which may affect the schedule and/or cost of the project

7.9 This risk analysis and contingency plan, being part of the project management plan, will be approved by Edgar company senior management.

Proprietary Information

Page 9: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

7.10 The approved project management plan, along with the risk plan, will be communicated to all project team members. It is the project manager’s responsibilities to ensure that members are part of the plan formulation, to ensure they will be commitment to the effective implementation to ensure project success.

8. Responsibility Matrix (enclosed)

9. PROJECT SCHEDULE and cash flow (enclosed): Management approval required.

10. LABOR RESOURCE HISTOGRAM (enclosed)

11. PROJECT PERFORMANCE EVALUATION: The monitoring and evaluation method to be adopted will be the earned value analysis. With the project schedule and Cost schedule, the cost variance/cost performance index and the schedule performance index, will continuously be monitored to achieve the following.

Determine the performance of the project in terms of cost and schedule Note any negative trend and analysis the causes of the trend Proffer solution to reverse the negative trend Anticipate any future negative trend, mitigate against it. Estimate, on a continuous basis, the estimated time of completion, and the estimated cost to

completion, for the project.

11. The project plan is submitted to management for review and approval.

EXECUTIVE SUMMARY AND OBJECTIVES

Executive Summary

Introduction

Edgar Company was founded in 1998 as a construction company that builds a variety of facilities across the nation.

We have a proven track record of the most viable construction life cycle. We have helped several hundred businesses complete their commercial business requirements.

We are focused on improving the positions all businesses, ultimately, helping them to reach the success that they are working on for their company.

Edgar Company Inc. is a leader in new building construction

Product/Service

Edgar Company is a California based, full service commercial development and Construction Company. The Edgar Company’s is a comprehensive organization with a reputation for competitive, quality-driven construction and development projects.

Proprietary Information

Page 10: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Target Market

Our customer base includes new business construction and we handle small to large business contracts.

Competitive Position

Edgar Inc’s portfolio consists of a diverse range of client-owned properties. Throughout its history, we have developed numerous relationships in the construction and financing communities; as a result the company's abilities have grown and expanded.

Those relationships have helped to secure the company a unique position within the development and construction communities, earning the company a distinct advantage of premium pricing, unmatched financial strength and a competitive edge unsurpassed in our field.

Goals and Objectives

The company’s key objectives for each project are:

Meeting our client’s requirements by completing their project on time and on budget. Employing motivated staff and providing them with the opportunities to further their skill base. Having quality assurance and management systems that can measure product consistency and financial

performance. Complying with all health & safety and environmental legislation. Adopting an honest and fair approach to all dealings and relationships.

In order to achieve the above objectives our company is controlled on a day to day basis by its senior management team. Every project comes under the direct control of a Project Manager who is ultimately responsible for the setting up of the contract, administration, attending site meetings, discussing and agreeing methodology and resources required.

Because new business for the company is obtained through its relationships and client referrals, the company values these relationships above all else, and they continue to strive for excellence through communication and a true understanding of the changing corporate cultures needs. It is to that end that the company continues to be committed to the one thing that has made them unique, our clients -- It is their vision that becomes Edgar Company's signature for success.

WORK BREAKDOWN STRUCTURE

1. Project Management1.1 Review plans and blueprint for the project1.2 Prepare cost estimates for all activities1.3 Prepare time estimates for all activities1.4 Prepare schedule for the project1.5 Sum all direct cost for the project1.6 Include indirect and overhead costs based on company standards

Proprietary Information

Page 11: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

1.7 Allow 15% of the total estimated cost for contingencies1.8 Prepare final Bid Proposal for the project1.9 Submit Bid proposal to the client1.10 Negotiate contract with TV station, sign contract with TV station1.11 Define the project goals 1.12 Form the project team and draw up Responsibilities Matrix1.13 Build up the right team culture, and set up team processes to ensure effective team1.14 Prepare risk management plan 1.15 Review the schedule for the project1.16 Review labor resources histogram for the project1.17 Review equipment resources histogram for the project1.18 Review materials resources histogram for the project1.19 Review indirect cost histogram for the project1.20 Prepare a cash flow for the project1.21 Get management approval for the schedule and cash flow1.22 Prepare monitoring and control plan for the execution of the project1.23 Manage project construction, performance evaluation, coordination, and control1.24 Liaise with client, progress and expedite their supplier for electrical equipment/other equipment for

the building1.25 Appoint and coordinate the activities of equipment leasing companies and other subcontractors1.26 Draw up communication plan for the project.

2. Survey Site3. Procurement

3.1 Procure structural steel and guys for tower3.2 Procure electrical equipment for tower and connecting underground cable.

4. Construction4.1 Building

4.1.1 Grade building site and excavate for basement4.1.2 Pour building footings4.1.3 Pour basement slabs and fuel tank slab4.1.4 Pour outside basement wall4.1.5 Pour walls for basement rooms4.1.6 Pour concrete floor beams4.1.7 Pour main floor slabs and lay concrete block walls4.1.8 Pour roof floor slabs4.1.9 Complete interior framing and utilities 4.1.10 Lay roofing4.1.11 Paint building interior, install fixture, and clean up

4.2 Tower4.2.1 Grade tower site

Proprietary Information

Page 12: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

4.2.2 Pour concrete for tower footings and anchor4.2.3 Erect tower and install electrical equipment4.2.4 Install connecting cable in tower site4.2.5 Install drains and storm drain in tower site

4.3 External Works4.3.1 Backfill and grade tower site4.3.2 Backfill around building, grade surface with crushed stone4.3.3 Install main cable between tower site and building4.3.4 Install fuel tank4.3.5 Install building septic tank4.3.6 Install drain tile and storm drain in building site4.3.7 Lay base for connecting road between tower and building4.3.8 Complete grading and surface connecting road4.3.9 Clean up sites

PROJECT ORGANIZATION & LINEAR RESPONSIBILITY CHART

Project Organization – The chart shown below is the organization of Edgar Company and its advisors who communicate to management at the Television Station.

Proprietary Information

Laborers Laborers Laborers LaborersLaborers Laborers

Carpenters Painters PlumberCrane Operator

Brick layers

Electricians Iron Worker

Laborers Laborers

Equipment Operator

Estimator Contract Specialist

EC General Foreman

Rod men

Land Surveyor

Senior Management

Television Station Management

Project Manager (John Harris)

Page 13: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Linear Responsibility Chart – The chart below shows the WBS item and the responsible person and their duty per tasks. The legend is at the bottom of the chart

Team project: Television Tower and Building Project: PROJECTM-Edgar Company (EC)

Proprietary Information

Page 14: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

ACTIVITY ON NODE WITH CRITICAL PATH

The AON chart below is the project tasks and how they relate to each other. The diagram also shows the early start, early finish, duration, last start, slack and late finish. The legend is in the upper right corner of the first chart.

Proprietary Information

Page 15: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 16: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

EARLY START SCHEDULE

The early start schedule Gantt chart shown below lists all the project tasks, durations, start, and finish.

Proprietary Information

Page 17: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

LABOR RESOURSES HISTOGRAM

The chart below shows by date the different resources working on the project and their hours of work.

5/5/2

008

5/17/2

008

5/29/2

008

6/10/2

008

6/22/2

008

7/4/2

008

7/16/2

008

7/28/2

008

8/9/2

008

8/21/2

008

9/2/2

008

9/14/2

008

9/26/2

008

10/8/2

008

10/20/2

008

11/1/2

008

11/13/2

008

11/25/2

008

12/7/2

008

12/19/2

008

12/31/2

008

1/12/2

009

1/24/2

009

2/5/2

009

2/17/2

009

3/1/2

009

3/13/2

009

0

1

2

3

4

5

6

7

8

Land SurveyorContract SpecialistRodmanBricklayerPainterCrane OperatorPlumberIronworkerCarpenterElectricianLaborerEquipment OperatorProject Manager

Proprietary Information

Page 18: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

CASH FLOW

The cash flow diagram listed on the next eight pages shows the costs of each item broken down by week and a total on the last slide.

Proprietary Information

Page 19: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 20: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 21: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 22: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 23: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 24: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 25: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

Proprietary Information

Page 26: Final_Project_ProjectM_DE

Document Title: System Design Document Date: 11/30/09

PROPOSAL COST BREAKDOWN

Materials $156,480.50 Labor $1,238,688.00 Equipment $189,566.58 Total $1,584,735.08

ASSUMPTIONS

Concrete Mixer does not require an Equipment Operator All work will meet appropriate standards (structural, electrical, plumbing) Each Equipment Operator requires either an Earth Mover or Road Equipment

o Activity H requires a Crane Operator not an Equipment Operator A sufficient number of workers, of appropriate type, will be available at all times. A sufficient amount of equipment, of appropriate type, will be available at all times. All materials will be available on site, on time, as required by the schedule. Working Times

o 8 hour work dayso 5 day work weekso Schedule excludes all holidays.

Cash Flow Charto Contingency Fee is not included in the Cash Flow charto Profit is not included in the Cash Flow chart

Proposal Cost Breakdowno Materials Cost includes: Actual Cost, Contingency Fee, Profito Labor Cost includes: Actual Cost, Overhead Cost, General Administrative Cost, Contingency Fee, Profito Equipment Cost includes: Actual Cost, Overhead Cost, Contingency Fee, Profit