+ All Categories
Home > Documents > Financial Appraisal Part I Project Cost and Its Financing

Financial Appraisal Part I Project Cost and Its Financing

Date post: 14-Apr-2018
Category:
Upload: ravi-gupta
View: 252 times
Download: 1 times
Share this document with a friend

of 90

Transcript
  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    1/90

    Prof. A. G. Mendhi

    5. PROJECT MANAGEMENT

    FINANCIAL APPRAISAL

    PART I

    PROJECT COST

    ANDITS FINANCING

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    2/90

    Prof. A. G. Mendhi

    INTRODUCTION

    Basic questions raised (by Financial Institutions /stake holders) during any project appraisal exerciseare:

    1. Can we sell the goods / services ?2. Can you produce the goods / render the services ?

    3. Can we earn a decent (satisfactory) return on theinvestment made in the project?

    ANSWER TO THE LAST QUESTION LIES INFINANCIAL APPRAISAL

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    3/90

    Prof. A. G. Mendhi

    IN THIS SESSION:

    Elements of project cost

    Means of financing

    Profitability Projections (Financial Institution

    Guidelines)

    Project financing Institutions, other means of financing

    Projecting Cash Flows

    Projecting Balance Sheet Break-even analysis

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    4/90

    Prof. A. G. Mendhi

    ESTIMATING PROJECT COSTS

    Two Methods of building project budget

    or project cost:

    1. Top Down approach: Quick and economicalmethod. Also called analogous method. Reliability

    depends on the degree of similarity between the

    projects, scalability of parameters and expertise of

    the estimating team in given field.2. Bottom up approach: Time consuming and

    costly but more accurate technique.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    5/90

    Prof. A. G. Mendhi

    ELEMENTS OF PROJECT COST

    Land & site development

    Buildings & civil works

    Plant and machinery

    Technical know-how & engg. Fees, expenses onforeign technicians & training of project personnelabroad

    Miscellaneous fixed assets

    Preliminary & Pre-operative expenses Margin money for working capital

    Initial cash losses, if applicable

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    6/90

    Prof. A. G. Mendhi

    LAND & SITE DEVELOPMENT

    Cost of acquisition of land (basic cost, cost of

    conveyance, stamp duty, etc.) (Extra land

    acquired but not meant for the project is not

    considered)

    Premium paid on leasehold land & conveyance

    charges paid. (Lease Rent?)

    Cost of site development: Leveling, Approachroads, Internal Roads, Fencing, Gates, etc.

    Cost of tube wells.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    7/90

    Prof. A. G. Mendhi

    COST OF BUILDINGS &

    CIVIL WORKS

    Factory building

    Administrative building

    Auxiliary buildings housing utilities equipment, warehousing/ storage house, etc.

    Non-factory buildings: Residential buildings / staff quarters,canteen, guest house, watch & ward, time office, etc.

    Places of prayer,

    Silos, tanks, garages, etc.

    Drainage, sewerage system, etc.

    Any other civil work including special foundations, podiums,etc.

    Architects fees

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    8/90

    Prof. A. G. Mendhi

    PLANT AND MACHINERY

    Cost of indigenous machinery (FOR value + sales tax,Octroi, other taxes and transportation cost to the site)

    Cost of imported machinery (FOB value, shippingcharges, cost of insurance, clearing, loading &

    unloading, import duty and local transportation costs) Cost of stores & spares

    Foundation and installation charges

    For financial appraisal, FIs normally insist on three latest

    quotes and allow for a provision for inflation, foreigncurrency rate fluctuation, etc. if not separately provided in

    provision for contingencies.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    9/90

    Prof. A. G. Mendhi

    TECHNICAL KNOW-HOW AND

    ENGINEERING FEES

    Fees of consultants, collaborators, etc. for:

    Assistance on technical matters e.g. Project Report,

    selection of process / technology, plant and machinery,

    detailed project engineering, supervision duringinstallation and commissioning, etc.

    Expenses on foreign technicians and on training of

    Indian technicians abroad (all expenses).

    Recurring payment of royalty does not form a part of the

    project cost; it is treated as operating expense.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    10/90

    Prof. A. G. Mendhi

    MISCELLANEOUS FIXED ASSETS

    Assets, which are not a direct part of themanufacturing process.

    - Furniture and fixtures,

    - Office equipment and machines,- Vehicles,

    - D.G. sets, Transformers, Switchgear, boilers, pipingsystems, workshop and quality control / laboratoryequipment,

    - Investment in effluent treatment plants,

    - Payments for trade marks, licences, copyrights,deposits paid to Electricity Boards, etc.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    11/90

    Prof. A. G. Mendhi

    PRELIMINARY EXPENSES

    Expenses incurred on identification of the project,

    market survey, Techno-Economic Feasibility Report,

    drafting of Memorandum and Articles of Association

    for the company, Incorporating and registering of thecompany, Legal charges, etc..

    Expenses incurred on capital issues by the company

    such as underwriting commission, brokerage, fees to

    registrars of issue, managers to the issue, printing,publishing, advertising, listing fees, stamp duty, etc.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    12/90

    Prof. A. G. Mendhi

    PRE-OPERATIVE EXPENSES

    Expenses incurred on the following till the start of the commercialproduction:

    Interest on borrowed funds during the implementation period,

    commitment charges, etc.

    Establishment expenses e.g. rent paid, traveling expenses, insurance

    charges, mortgage expenses, etc.

    Trial production or start up expenses.

    Miscellaneous expenses

    Pre-operative expenses can be apportioned to fixedassets on some acceptable basis. The firm may also treat them

    as deferrred revenue expenditure and write them off over a

    period of time.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    13/90

    Prof. A. G. Mendhi

    PROVISION FOR CONTINGENCIES

    This is a provision for unforeseen expenses:

    Inflation,

    Exchange Rate risks, Delay in execution and hence

    escalation of costs

    Any other miscellaneous costs / liabilities that may

    arise.

    Normal provision is 5% of firm costs and 10%

    for non-firm costs.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    14/90

    Prof. A. G. Mendhi

    MARGIN MONEY FOR WORKING

    CAPITAL

    Banks normally provide finance / credit facilities for

    meeting requirements of working capital. A part of this

    is to be brought in by the promoters basically from

    long term sources of finance. This is a critical element of project cost particularly if

    there are over-runs in the cost. FIs normally block an

    amount equivalent of the margin money from the term

    loans till the project is complete.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    15/90

    Prof. A. G. Mendhi

    INITIAL LOSSES

    Most of the promoters do not show

    these as a part of the project cost.

    Prudence however calls for makingsuch a provision if there are any

    initial losses since they could affect

    the liquidity position of the company.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    16/90

    Prof. A. G. Mendhi

    PROJECT FINANCING

    Types of Projects Manufacturing Projects

    Infrastructure Projects

    Scientific Research Projects

    Innovative, experimental, developmental System development Projects

    Systems / software development & implementation

    Management Projects

    Managing change within organization

    All Projects could be: Greenfield Projects Expansion / Relocation Projects

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    17/90

    Prof. A. G. Mendhi

    PROJECT FINANCING

    Project financing is a special case of financing in whichlenders have to rely on repayment from the net cash flowgenerated by the project.

    Project finance is usually provided against assets of and the

    rights in a particular project rather than against theborrowers balance sheet, though Net worth of thepromoters is also important.

    Financers are therefore concerned with the analysis of therisks associated with the project before they accept the

    investment opportunity which it represents. The cost and terms of financing therefore reflect thefinanciers view about the risks involved in implementingthe project.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    18/90

    Prof. A. G. Mendhi

    NEED FOR PROJECT FINANCING

    Project financing is required in a number ofsituations:

    For companies in general, to enhance their investment limits.

    To spread the risk among several parties to lessen adversefinancial impact if any, and to increase their capacity toundertake more projects.

    For multinational corporations to protect their corporatebalance sheets from the impact of large projects

    For governments to share the costs and risks of exploitingnatural resources

    For governments to increase foreign capital investment in thecountry at no cost to the country.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    19/90

    Prof. A. G. Mendhi

    FINANCING STRATEGY

    The project will fail, no matter what is its technical merit,unless enough finance is made available to complete it.

    The design, implementation and management of projectfinancing demands the same level of commitment from the

    promoters as the rest of the project management activities.

    Financial planning should begin at the same time, or insome cases even earlier than the technical project planning.

    While financing package is likely to reflect the complexity

    of the project, finance has some inherent characteristics,which themselves add to the complexity of undertaking.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    20/90

    Prof. A. G. Mendhi

    SOURCES OF FINANCE

    Identifying sources of finance

    Identifying suitable sources of finance is the first stepin planning finance for a project.

    Finance for projects falls into two major categories: Debt:Borrower has the obligation to repay. Debt also

    usually carries obligation to pay interest and to adhere to aprearranged repayment schedule. The lender has priorityclaim if borrower goes into liquidation.

    Equity:Funds subscribed by the shareholders from their own

    resources. There is no guarantee that the dividend will bepaid and investors tend to loose their money if the projectfails to perform. Equity shareholders have the last claim ifthe project goes into liquidation.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    21/90

    Prof. A. G. Mendhi

    PROJECT FINANCING

    Share Capital (Equity & Preference)- (dividend, claim, control,tax)

    Term Loans (Secured Borrowings)major source of finance

    Rupee or Foreign Currency Term Loan

    Incentives (Capital subsidy or seed capital, tax deferment orexemption)

    Debenture Capital (Debt instruments: convertible or non-convertible, more flexible than term loans)

    Deferred Credit (usually offered by suppliers of plant andmachineryinterest and phased payment conditions varybankguarantees are required)

    Other sources (unsecured loans by promoters, lease or hire-purchase programs, Public deposits, etc.)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    22/90

    Prof. A. G. Mendhi

    SOURCES OF FINANCE

    The main sources of debt finance are:

    Commercial banks

    Multilateral lending institutions

    Suppliers of equipment & services for the project

    Suppliers of raw materials to the project

    Buyers of output from the project The main sources of equity finance are:

    Internal: Corporate cash flow generated by existing businessoperations

    Public: Corporate or individual investors, or funds raised throughstock markets

    Joint venture partners Government subscriptions & aids

    Multilateral investment institutions

    *Venture capitalists

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    23/90

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    24/90

    Prof. A. G. Mendhi

    RAISING CAPITAL IN

    INTERNATIONAL MARKETS:

    Global Depository Receipts: Indirect equityinvestment - Shares issued by a firm are held by aDepository (International Bank), which receivesdividends, reports, etc. and issues claims.

    1. Each receipt is a claim on specific number of shares.

    2. GDRs are denominated in a convertible currency

    3. GDRs may be listed on major stock exchanges

    4. Issuer firm pays dividends in home currency.5. Issuer firm can thus avoid listing procedures,

    disclosures, etc.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    25/90

    Prof. A. G. Mendhi

    UNCONVENTIONAL SOURCES OF

    PROJECT FINANCING:

    Leasing & Hire Purchase: Use of project assets through

    off-balance sheet financing.

    Forfaiting: Sale of financial instruments due to mature in

    future.

    Counter-Trade: Seller accepts goods or services in lieu of

    cash payments.

    Switch Trading: Making use, via a third party, of un-cleared

    credit surpluses arising from bilateral trade agreements.

    Offset: Exporter of technically advanced project incorporatesan agreed value of materials, equipment & services supplied

    by the buyer.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    26/90

    Prof. A. G. Mendhi

    UNCONVENTIONAL SOURCES OF

    PROJECT FINANCING:

    Franchise Financing: Engineering, Procurement &Construction (EPC) contractors become equity holding jointventure partners for the project they design & build.

    Debt/Equity Swapping: Multinational technology ownerbuys host country debt at a discount. The debt is redeemed inlocal currency at favorable rate of exchange for setting up alocal company. The local company uses transferredtechnology to earn foreign exchange, replace imports &generate local employment.

    Build Own - Operate Transfer (BOOT): Government

    grants concession to a project company (SPV) to build afacility and operate it on commercial basis. Facility istransferred to the government at the end of the concession.This type of finance arrangement is usually used forinfrastructure projects.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    27/90

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    28/90

    Prof. A. G. Mendhi

    EQUITY V/S DEBT

    Shareholders have a residual

    claim over the income and

    assets of the firm.

    Dividend paid to equity

    holders is not a tax

    deductible payment.

    Equity ordinarily has

    indefinite life.

    Equity investors have aprerogative to control the

    affairs of the company.

    Creditors have a fixed claim

    equivalent to principal and

    interest outstanding.

    Interest paid to creditors is a

    tax deductible payment.

    Debt has a fixed maturity.

    Creditors play a passive role

    in the affairs of the company

    though they may imposecertain restrictions to protect

    their interest.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    29/90

    Prof. A. G. Mendhi

    LEADING FINANCIAL INSTITUTIONS

    / BANKS IN INDIA

    Industrial Finance Corporation (IFC),

    Industrial Bank of India (IDBI),

    Industrial Credit and Investment Corporation of India(ICICI),

    Infrastructure Development Finance Corporation Ltd,(IDFC)

    State Industrial & Investment Corporations (SICOM,PICUP, RIICO, IPICOL, etc.)

    State Finance Corporations (SFCs like MSFC, GSFC,etc.)

    Banks like SBI, BoB, others

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    30/90

    Prof. A. G. Mendhi

    LEADING FINANCIAL INSTITUTIONS

    / BANKS IN INDIA (Contd.)

    Export Credit Guarantee Corporation of India (ECGC).

    Export-Import (EXIM) Bank of India

    General Insurance Corporation of India (GIC)

    Life Insurance Corporation of India (LIC)

    National Bank for Agriculture And Rural Development

    (NABARD)

    National Housing Bank (NHBC) Small Industries Development Bank of India (SIDBI)

    Unit Trust of India (UTI)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    31/90

    Prof. A. G. Mendhi

    TERM LOANS

    Primary sources for term loans are Financial

    Institutions.

    Term Loans are normally payable in less than ten

    years. Usually there is a moratorium of two years andrepayment is made in five to seven years.

    Repayment of principal is in terms of equated semi-

    annual or quarterly installments.

    Term loans are used to finance purchase of fixed assets

    and margin money only.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    32/90

    Prof. A. G. Mendhi

    TERMS AND CONDITIONS OF TERM

    LOANS

    Currency: Rupee as also Foreign currency loans arepossible

    Processing fee charged: usually one percent of loan

    amount sanctioned Security:

    First equitable mortgage of immovable properties/ fixed assets

    Hypothecation of all movable properties subjectto prior charges in favor of commercial banks forworking capital loans

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    33/90

    Prof. A. G. Mendhi

    TERMS AND CONDITIONS OF TERM

    LOANS

    Interest Payment & Principal repayment:

    Payable irrespective of the financial

    position of the borrower. Penalty imposed by FIs in case of

    default on interest and 2% p.a. for

    liquidated charges in case of default onprincipal repayment.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    34/90

    Prof. A. G. Mendhi

    TERMS AND CONDITIONS OF TERM

    LOANS

    Restrictive clauses:

    Nomination on Board of Directors. Management setup to be finalized in consultation with the FIs.

    Insist on making arrangements for additional funds ifrequired through unsecured loans / deposits frompromoters.

    Refrain from taking additional projects / financialcommitments not related to the project without prior

    approval from FIs. Obtain various licences / permissions / clearances etc.from relevant Govt. Authorities.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    35/90

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    36/90

    Prof. A. G. Mendhi

    TERM LOAN PROCEDURES

    Submission of loan application:

    Promoters background

    Particulars of the industrial concern (Annual reports andbalance sheets)

    Particulars of the project (Project Report: Capacity,process, technical arrangements, manpower, utilities,implementation schedule, project cost, financing pattern,marketing arrangements, etc.)

    Profitability and cash flow statements, Economic considerations, social cost benefit analysis,EIA study if necessary

    Government consents / permissions.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    37/90

    Prof. A. G. Mendhi

    TERM LOAN PROCEDURES (contd.)

    Initial processing of loan application (Flash Report).

    Appraisal of the proposed project.

    Issue of the letter of sanction.

    Acceptance of terms and conditions by the applicant

    unit.

    Execution of loan agreement.

    Creation of security. Disbursement of loans.

    Monitoring.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    38/90

    Prof. A. G. Mendhi

    FINANCIAL APPRAISAL BY

    FINANCIAL INSTITUTIONS:

    Justification of estimate of cost of capital

    Justification for estimate of working capital

    Adequacy of Rate of Return:

    IRR: should be 3 to 5 % more than WACC and not less than 15%

    DSCR: 1.5 to 2.0 or more

    ROI: should be ideally 15% or more

    Justification of Debt:Equity Ratio

    Should be 1.5:1

    Debt should be adequately covered by investment in immovablefixed assets

    Stock Exchange regulations are to be met in case of listing. Promoters should contribute a certain minimum percentage of the

    project cost

    Means and capacity of the promoters to contribute to a reasonableshare of the project cost

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    39/90

    Prof. A. G. Mendhi

    FINANCIAL ESTIMATES AND

    PROJECTIONS

    Estimates of production and sales

    Assume progressive increase in effective capacityutilization (50%, 60%, 75% and 90% in 1st, 2nd, 3rd and fourthyear of operationconstant thereafter).

    Assume production equal to sales or make a provision forstocks.

    Assume realistic x-factory selling price. Each product to betreated separately.

    Selling price is net of excise and if selling commission is

    included, it should also be shown as item of expense (partof selling expenses)

    Changes in selling price should be considered only withcorresponding changes in costs of production.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    40/90

    Prof. A. G. Mendhi

    ESTIMAATES OF

    COST OF PRODUCTION

    Cost of raw materials

    Cost of consumables

    Cost of utilities

    Cost of labor

    Cost of Factory overhead

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    41/90

    Prof. A. G. Mendhi

    ESTIMATED REQUIREMENTS OF

    RAW MATERIALS & CONSUMABLES

    (At 70% Capacity Utilisation, for Year I)

    S

    r.

    N

    o.

    Raw

    Material

    Requirement per

    1000 litres of

    Biodiesel

    Unit

    Approx.

    CIF

    Price

    Per unit

    (Rs.)

    Annual

    Requirement

    Quantity

    Cost

    (Rs.

    Lakh)

    1. JatrophaSeeds 3.42 Tonne 5.00 7,187 359.33

    2. Methanol 150 Litre 22.00 3,15,000 69.30

    3.Caustic

    Potash3.8 Kg 42.00 7,980 3.35

    4.Liquid

    Catalyst 6.00 Litre 10.00 12,600 1.26

    5.Solid

    Catalyst6.00 Kg 20.00 12,600 2.52

    6. TOTAL 435.76

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    42/90

    Prof. A. G. Mendhi

    ESTIMATED REQUIREMENTS OF

    UTILITIES

    Norms of consumption given by consultants or

    technical collaborators. Else, go by the standards

    established in existing units. Make a higher

    provision. Power: Connected load X loading factor X No. Of

    hours in a day X No. of working days in a year X

    prevailing tariff+ provision for other requirements.

    Fuel: Annual consumption X Price

    Water: Annual consumption X Price

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    43/90

    Prof. A. G. Mendhi

    LABOR

    All manpower employed in the factory to be

    considered

    Salaries and wages assumed on the basis of prevailing

    rates in the industry. Remuneration to include basic salaries, allowances

    (DA, HRA, LTA, Medical, etc.), statutory provisions

    like PF, gratuity, insurance, bonus, etc.

    Normally (basic + fixed percentage) provided. Annual

    rise of 5% is usually assumed for annual increments.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    44/90

    Prof. A. G. Mendhi

    FACTORY OVERHEADS

    These would normally include

    Cost of repairs and maintenance (Generally 2 to

    3% on plant & machinery and 1.5% on

    Buildings/civil construction and MFA). Costswould increase with the age of machinery.

    Insurance (o.5% on all factory assets)

    Rents, taxes to be guided by prevailing rates. Provision for miscellaneous factory expenses

    ESTIMATES OF WORKING CAPITAL

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    45/90

    Prof. A. G. Mendhi

    ESTIMATES OF WORKING CAPITAL

    & ITS FINANCING

    Working capital is required mainly for maintaining adequate stocksof raw materials (both indigenous and imported), Work in progress,finished goods and provision for accounts receivables (i.e. creditgiven to customers) and cash on hand required for meeting day today expenses.

    Usually Tandon Committee norms are followed by Banks.Accordingly at least 25% of the requirements of working capital areto be financed by the promoters and to be brought in as long termfinance. Banks normally insist that Cash-on-hand be financedentirely by the promoters.

    Promoters can follow the format given in the application formprepared by all India Financial Institutes.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    46/90

    Prof. A. G. Mendhi

    WORKING CAPITAL (CONTD.)

    ITEM NO. OFMONTHS

    FINANCIAL YEAR OF OPERATIONI II

    (A) Current

    AssetsRaw Material &

    Packaging

    Work in progress1.50

    0.1Finished goods 1.50Outstanding

    Debtors / Accounts

    receivable 1.00

    Sub-total (A)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    47/90

    Prof. A. G. Mendhi

    (B) Minimum cash

    on handNO. OFMONTHS

    YEAR I YEAR II

    Salaries and wages 1.00

    Utilities 1.00

    Others (Rent, Tax,

    packing and selling

    expenses, Repairs

    & maintenance,

    Insurance, etc.)

    1.00

    Sub-total (B)

    (to be funded 100%

    by promoters)

    WORKING CAPITAL (CONTD.)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    48/90

    Prof. A. G. Mendhi

    WORKING CAPITAL (CONTD.)

    (C) Current

    Liabilities

    N0. of

    months

    YEAR I YEAR II

    Trade credit on raw

    materials0.5

    Trade credit onconsumables 0.5

    Other credits 1.0

    Sub-total (C)

    NET W. Capital

    N=(A+B-C)

    M= Margin @ 25% of

    (A-C) + B

    Working capital loan

    availed= N-M

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    49/90

    Prof. A. G. Mendhi

    ESTIMATES OF WORKING RESULTS

    / PROFITABILITY STATEMENTS

    A= Cost of production

    B=Total Administrative expenses (2 to 3% of sales)

    C= Total Selling expenses (5 to 10% of sales)

    D= Royalty payable (2 to 5% of sales)

    E=Total cost of production

    (A+B+C+D)

    F= Sales revenue

    G= Gross profit before interest= F-E

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    50/90

    Prof. A. G. Mendhi

    ESTIMATES OF WORKING RESULTS /

    PROFITABILITY STATEMENTS (contd.)

    H= Total financial expenses (Interest payable

    on both long and short term loans)

    I=Depreciation

    J= Operating profit (G-H-I)

    K= Other income

    L= Preliminary expenses written off

    M= Profit or (Loss) before taxation (J+K-L)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    51/90

    Prof. A. G. Mendhi

    ESTIMATES OF WORKING RESULTS /

    PROFITABILITY STATEMENTS (contd.)

    N= Provision for tax

    O= Profit after Tax (PAT=M-N)

    P= retained profit= (O- Dividend declared on

    Equity & preference shares)

    Q= Net cash accrual = (P+I+L)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    52/90

    Prof. A. G. Mendhi

    DEPRECIATION

    Straight Line

    Depr.Rate (%)

    Non Factory Building 1.63% Factory Building 3.34%

    *Plant and

    Machinery 10.34%

    Miscellaneous

    Fixed Assets 6.33%

    WDV Method

    (Taxation purpose)

    Non Factory Building 5.0% Factory Building 10.0%

    *Plant and

    Machinery 25.0%

    Miscellaneous

    Fixed Assets 10.0%

    *Three shifts per day basis

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    53/90

    Prof. A. G. Mendhi

    DEPRECIATION CALCULATIONS

    Provision for contingency and pre-operative expensesestimated in project cost are added proportionately tothe cost of fixed assets to arrive at the depreciablevalue of fixed assets.

    Preliminary expenses in excess of 2.5 % of the projectcost (excluding margin money) should also be added tothe cost of the fixed assets to arrive at the depreciable

    value of fixed assets.

    St.Line

    Valu FINANCIAL YEAR OF OPERATION

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    54/90

    Prof. A. G. Mendhi

    ITEM LineDepr.Rate

    (%)e

    at

    Cost I II III IV V VIVI

    I VIII IX X

    Land - 14 - - - - - - - - - -

    Building 1.63 78 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2

    Plant and Machinery 10.34 124 13 13 13 13 13 13 13 13 13 7

    Miscellaneous Fixed

    Assets6.33 14 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8

    TOTAL BOOK

    WDVFINANCIAL YEAR OF OPERATION

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    55/90

    Prof. A. G. Mendhi

    ITEM Depr.Rate

    (%)Value

    at Cost I II III IV V

    Land - 14 - - - - -

    Building 10.00 78.26 7.83 7.04 6.34 5.70 5.13

    Plant and Machinery 25.00 124.21 31.05 23.29 17.47 13.10 9.83

    Miscellaneous Fixed

    Assets15.00 13.94 2.09 1.78 1.51 1.28 1.09

    TOTAL TAX

    DEPRECIATION 40.97 32.11 25.32 20.09 16.05

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    56/90

    Prof. A. G. Mendhi

    INTEREST CALCULATIONS

    Interest on Long Term loans is taken as the present rate

    of interest charged by the Financial Institutions. The

    interest burden will decrease with the repayment of the

    loan by the borrower. For simplicity, Interest is calculated on the average of

    the balances at the beginning and at the end of the year.

    For short term loans / credit facilities, the rate of

    interest would be equal to the rate of interest chargedby commercial banks. No repayment is assumed.

    TYPE OFFINANCIAL YEAR OF OPERATION

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    57/90

    Prof. A. G. Mendhi

    Table 7.6: LOAN REPAYMENT AND INTEREST SCHEDULE (Figures in Rs. Lakh)

    TYPE OF

    LOANI II III IV V VI VII VIII

    Short-termloan13% InterestLoan at the end of

    the year 65.91 79.12 93.53 109.19 114.60 120.28 126.24 132.49 1Interest 8.57 10.29 12.16 14.19 14.90 15.64 16.41 17.22Long-term

    loan@ 13%

    Loan at the

    beginning 142.90 142.90 142.90 122.49 108.20 93.91 79.62 65.33Repayment - - 20.41 14.29 14.29 14.29 14.29 14.29Loan at the end of

    the year 142.90 142.90 122.49 108.20 93.91 79.62 65.33 51.04Interest 18.58 18.58 17.25 14.99 13.14 11.28 9.42 7.56

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    58/90

    Prof. A. G. Mendhi

    PART IIMARCH 5, 2006

    ESTIMATES OF WORKING RESULTS /

    PROFITABILITY STATEMENTS (contd.)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    59/90

    Prof. A. G. Mendhi

    ESTIMATING CASH FLOWS

    It is important to estimate the cash flows for aproject to make a proper investment evaluation.

    All care and precautions need to be taken to

    ensure that the implementation of the projectdoes not get hampered as a result of lack ofadequate cash or finance in time.

    Correct estimate of cash flows is thus a keyelement in the process of successful financialplanning.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    60/90

    Prof. A. G. Mendhi

    ELEMENTS OF CASH FLOWS

    There are three phases in the life of any project:

    1. Setting up or investment phase.

    2. Operational phase

    3. Terminal phase / Winding up phase

    Accordingly the cash flows would also be categorized

    in three classes.

    1. Initial investment,2. Operational cash flows and

    3. Terminal cash inflow

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    61/90

    Prof. A. G. Mendhi

    LIFE OF A PROJECT

    How is the life of a project determined and whatshould be the normal period / horizon for estimatingcash flows?

    Life of a project is usually minimum of the following:

    1. Physical life of the plant (wear and tear, depreciation,ask the supplier).

    2. Technological life of the plant (chips manufacturing -Manual to automatic operations)

    3. Product life of the plant (computers / chips)

    4. Investment Planning Horizon of the Firm

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    62/90

    Prof. A. G. Mendhi

    BASIC PRINCIPLES OF CASH FLOW

    ESTIMATION

    1. Separation principle

    2. Incremental principle

    3. Post tax principle and

    4. Consistency principle

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    63/90

    Prof. A. G. Mendhi

    SEPARATION PRINCIPLE

    Two sides viz. investment side and financing side should be

    treated separately.Cost of capital is used as a hurdle rate againstwhich rate of return on investment side is compared.

    TIME

    CASH FLOW TIME

    CASH FLOW

    0 +100 0 -100

    1 - 115 1 +120

    COST OF CAPITAL 15% RATE OF RETURN 20%

    PROJECT

    FINANCING SIDE INVESTMENT SIDE

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    64/90

    Prof. A. G. Mendhi

    SEPARATION PRINCIPLE

    Operationally this means that in cash flows on

    investment side, interest on debt is ignored

    while computing profits & Taxes.

    Hence, Profit before interest and tax (1-tax rate) =

    (profit before tax +interest) * (1-tax rate)

    = (profit before tax) (1-tax rate) +interest (1-tax

    rate)= Profit after tax + interest (1-tax rate)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    65/90

    Prof. A. G. Mendhi

    INCREMENTAL PRINCIPLE

    Cash flows of a firm should be measured in incremental terms.

    = -

    To ascertain the cash flows following principles should be followed:

    1. Consider all incidental effects (positive and negative effects such as productcannibalization).

    2. Ignore sunk costs,

    3. Include opportunity costs (Is there any alternative use of existing resource with thefirm if the project is not undertaken?),

    4. Check allocation of overhead costs and

    5. Estimate Working capital systematically.

    Project cash flowsFor the year t

    Cash flows for firmwith the project for t

    Cash flows for firmWithout project for t

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    66/90

    Prof. A. G. Mendhi

    POST TAX PRINCIPLE

    Cash flows are measured on a after tax basis.

    1. What tax rate should be used for project cash

    flows? Average tax rate or the marginal tax

    rate that would be applicable to projects

    income?

    2. Treatment of losses

    3. Effect of non-cash charges (depreciation)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    67/90

    Prof. A. G. Mendhi

    CONSISTENCY PRINCIPLE

    Cash flows and discount rates applied to them

    must be consistent with respect to investor

    group and inflation.

    Investor group: cash flow to be estimated from

    the point of view of all investors (equity

    holders as also the lending agencies)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    68/90

    Prof. A. G. Mendhi

    CASH FLOW FOR ALL INVESTORS

    PBIT (1-tax rate)

    +Depreciation

    - Capital Expenditure- Change in working capital

    CASH FLOW FOR EQUITY

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    69/90

    Prof. A. G. Mendhi

    CASH FLOW FOR EQUITY

    SHAREHOLDERS

    Profit after tax (PAT)

    +Depreciation

    - preference dividend

    - Capital Expenditure

    - Change in working capital- repayment of debt

    + proceeds from debt issues

    - Redemption of preference capital

    + proceeds from preference issue

    You can discount the cash flows at WACC for all investors while for the

    equity holders, you can discount using cost of equity

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    70/90

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    71/90

    Prof. A. G. Mendhi

    PROJECTED CASH FLOW STATEMENTS

    (B) Uses / disposition of Funds:1. Capital Expenditure for the project.

    2. Other normal capital expenditure.

    3. Increase in working capital

    4. Decrease in secured long term loans.5. Decrease in other medium / long term loans.

    6. Decrease in unsecured loans or deposits.

    7. Decrease in short term loans for working capital

    8. Increase in investments in other companies.

    9. Interest on both long and short term loans.10. Taxes paid

    11. Dividends paid during the year.

    12. Other expenditure

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    72/90

    Prof. A. G. Mendhi

    PROJECTED CASH FLOW STATEMENTS

    C. Opening Balance of cash in hand and

    at bank.

    D. Net Surplus / Deficit (A-B)E. Closing Balance of cash in hand and

    at bank

    (C + AB)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    73/90

    Prof. A. G. Mendhi

    PROJECTED BALANCE SHEET

    LIABILITIES

    1. Share Capital

    Equity

    Preference

    2. Reserves & Surplus

    3. Secured Loans

    4. Unsecured Loans5. Current Liabilities &

    Provisions

    ASSETS

    1. Fixed Assets

    2. Investments

    3. Current Assets, Loans& Advances given

    4. Miscellaneous

    Expenditures & Losses

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    74/90

    Prof. A. G. Mendhi

    BREAK-EVEN ANALYSIS

    Also called Cost, Volume, Profit (CVP) Analysis.

    Studies relationship between costs, revenues and

    profits.

    Break-even indicates the level of sales at which thecosts and revenues are in equilibrium i.e. there is no-

    loss and no-profit situation. This equilibrium point is

    called break-even point.

    In other words, break even point is that level / point ofsales at which the total revenue is equal to total costs.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    75/90

    Prof. A. G. Mendhi

    BREAK-EVEN ANALYSIS

    Pre-requisite of break-even point calculation

    or using CVP analysis is that total costs can

    be divided into fixed costs and variable costs.

    Variable costs are those that change in direct

    proportion to change in volume of production.

    Fixed costs remain fixed / constant

    irrespective of the volume of operation.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    76/90

    Prof. A. G. Mendhi

    FIXED COSTS

    Salaries

    Fixed Selling Expenses

    Depreciation

    Administrative overheads

    Repairs and maintenance

    Insurance

    Interest on long term loans Amortization of expenses

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    77/90

    Prof. A. G. Mendhi

    VARIABLE COSTS

    Raw Materials

    Consumables

    Utilities

    Wages

    Variable Selling Expenses / commissions /

    royalty linked to sales

    Interest on short term loans

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    78/90

    Prof. A. G. Mendhi

    DETERMINING BREAK-EVEN POINT

    Two methods are usually adopted:

    1. Mathematical Formula

    2. Graphic approach

    Mathematically, Break Even Point (BEP) can be calculated in

    terms of units, sales or percentage capacity utilization.

    Each unit sold will cover its part of the variable cost andleave remainder (called contribution) to cover a part of thefixed costs.

    Break even will occur when sufficient units are sold so thattotal contribution is just equal to total fixed costs.

    Contribution per unit is the difference between selling priceper unit and variable cost per unit.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    79/90

    Prof. A. G. Mendhi

    DETERMINING BREAK-EVEN POINT

    1. Mathematical Formula:

    sv = c (selling price - variable cost = contribution)perunit

    c . Q = C (Q = Total sales in units,

    C= Total contribution)

    S = s.Q (S= Total Sales in value terms)

    CF = Profit (Total contribution less total fixed costs)

    For break even, C - F = 0 F

    c.Qb = F Hence, Qb = ----------(sv). Qb = F (sv)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    80/90

    Prof. A. G. Mendhi

    DETERMINING BREAK-EVEN POINT

    Mathematical Formula:

    F

    Qb = ----------

    (sv)

    Total fixed costs

    = ---------------------------------------------selling pricevariable cost per unit

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    81/90

    Prof. A. G. Mendhi

    2. Mathematical Formula in Rupee terms:F.s F

    Qb.s = ---------- = ------------(s v) 1 v/s

    Total fixed costsRb = ---------------------------------

    1- variable cost ratio

    Total fixed costsRb = ---------------------------------

    Contribution ratio

    Contribution Ratio is also called P/V ratio

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    82/90

    Prof. A. G. Mendhi

    BREAK EVEN CHART

    Value

    Output

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    83/90

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    84/90

    Prof. A. G. Mendhi

    LIMITATIONS OF BEP This is only a supply side (i.e.: costs only) analysis.

    It tells you nothing about what sales are actually likely to be for theproduct at various prices.

    It assumes that total costs can be separated into two components viz.fixed and variable costs

    It assumes that fixed costs (F) are constant It assumes average variable costs are constant per unit of output, at

    least in the range of sales (both prices and likely quantities) ofinterest.

    The selling price per unit remains the same i.e. it does not changewith volume or other factors.

    The firm manufactures only one product or in case of multipleproducts, the product mix remains the same.

    Production and sales are synchronized i.e. inventories remain thesame!!

    DEBT SERVICE COVERAGE RATIO

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    85/90

    Prof. A. G. Mendhi

    DEBT SERVICE COVERAGE RATIO

    (DSCR)

    It shows to FIs the capacity of the company to

    pay back the principal as well as the interest on

    the term loans given by them.

    PAT + DEPR. + Intr. On LT Debt + Amortized Exp.

    DSCR = -------------------------------------------------------------------

    Repayment of LT Debt + Interest on LT Debt

    Total cash accrual over ten year period

    = ----------------------------------------------------------

    Total Debt service burden over ten years

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    86/90

    Prof. A. G. Mendhi

    SENSITIVITY ANALYSIS

    FIs normally carry out sensitivity analysis onprojected working results to assess the impact ofadverse changes in following parameters of the

    project:

    1. Increase in raw material prices,

    2. Decrease in selling prices,

    3. Increase in operating costs

    Impact on IRR, BEP & DSCR of 5% to 10% variationin above parameters is usually assessed to know howwell the project can sustain these changes.

    CONCEPT OF AVERAGE COST OF

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    87/90

    Prof. A. G. Mendhi

    CONCEPT OF AVERAGE COST OF

    CAPITAL

    A firms cost of capital is the weighted average cost ofvarious sources of finance used by it viz. Equity,Preference shares, Long Term Debt and short termdebt.

    Many firms do not take into account the short termdebt while calculating WACC.

    WACC is used as the hurdle rate in capital budgeting /project financing (why?)

    WACC = Pi X riWhere,Pi is the proportion of the ith source of financeand ri is the cost of this source of finance.

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    88/90

    Prof. A. G. Mendhi

    QUESTIONS

    1. What is Long Term Funds principle for evaluation of

    project cash flows? Why is it necessary to exclude

    Financing costs when the long-term funds principle is

    accepted? (2002)

    2. What are the relative merits of building a project

    budget from bottom-up and from the top-down

    methods?

    How does the assignment of costs to individual projectactivities help in effective cost & schedule control?

    (2003)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    89/90

    Prof. A. G. Mendhi

    QUESTIONS

    3. Following information is available about a proposed expansion project: Initial project outlay is Rs.50.0 crores consisting of Rs.40.0 crores fixed

    assets & Rs.10.0 crores current assets. The financing pattern: Equity Rs.15.0 crores, Term loans Rs.30.0 crores,

    Working Capital advances Rs.4.0 crores & Trade Credits Rs.1.0 crores. Term loan repayable in ten equal six monthly instalments, the first

    instalment due 18 months after starting of production. Interest on termloan will be @ 12.0% p.a. applicable on opening balance at thebeginning of the year.

    The levels of working capital and trade credit remain unchanged till end.The interest on working capital advance will be @ 15.0% p.a.

    Sales revenues are Rs.65.0 crores p.a. while operating costs excludingdepreciation & interest are Rs.45.0 crores. Depreciation on fixed assetsis charged @ 25.0% p.a. on Written down value (W.D.V.) basis.

    Project life being 7 years, the salvage value will be Rs.5.34 crores forfixed assets. Current assets recovery will be at cost. Average corporate Income Tax rate is 40.0%Work out the project cash flows during its life from long term fundspoint of view. (2002)

  • 7/30/2019 Financial Appraisal Part I Project Cost and Its Financing

    90/90

    QUESTIONS

    4. What are the various ways of financing a project

    along with the relative merits or demerits of each of

    them? Your answer should include all traditional as

    well as non-traditional means of financing. The

    sources should cover both domestic as well as

    foreign sources of financing.

    5. What is the criterion used for determining Life of

    the project for determining time span of cash flowprojections? (2003)


Recommended