Finance Tools for Project Advancement Florida Department of TRANSPORTATION Leon Corbett Project Finance Manager NCSL Southern States Fiscal Leaders September 23, 2016
Transcript
Page 1: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Finance Tools for Project Advancement

Florida Department of

TRANSPORTATION

Leon Corbett

Project Finance Manager

NCSL Southern States Fiscal LeadersSeptember 23, 2016

Page 2: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Discussion Topics

• Public-Private Partnerships (P3s)

• New Transportation Finance Corporation

Florida Department of Transportation2

Page 3: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

FDOT’s P3 Program - $6.8B in Projects

Florida Department of Transportation3

COMPLETE

I-95 at Pineda - $199M (DBF)

COMPLETE

US 1/SR 5 - $114M (DBF)

COMPLETE

I-75 (IROX) - $458M (DBF)

COMPLETE

I-95 Express Lanes - $139M (DBF)

COMPLETE

Palmetto Section 2 - $191M (DBF)

UNDER CONSTRUCTION

US 19 - $125M (BF)

UNDER CONSTRUCTION

SR 79 - $98M (DBF)

UNDER CONSTRUCTION

Palmetto Section 5 - $567M (DBF)

IN OPERATIONS

PortMiami Tunnel - $667M* (DBFOM)

IN OPERATIONS

I-595 - $1.2B* (DBFOM)

UNDER CONSTRUCTION

I-4 Ultimate - $2.3B* (DBFOM)

COMPLETE

I-4 Connector - $438M (BF)

*construction portion

BF – Build FinanceDBF – Design Build FinanceDBFOM – Design Build Finance Operate Maintain

COMPLETE

I-75 N of SR 80 to S of SR78 - $72M (DBF)

IN PROCUREMENT - FEB. 2016

I-395 - $626M (DBF)

COMPLETE

9B - $95M (DBF)

COMPLETE

I-95 - $130M (DBF)

Page 4: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Two Methods for P3 Delivery

Procured under s.334.30, F.S., two categories:

Florida Department of Transportation4

Design-Build Finance (DBF) or Build Finance (BF)

• Traditional agreement• Construction only • Cash Availability Schedule • Terms around 7 years • Short-term financing • $100 M - $600 M• Project typically advanced 2-

3 years

Design-Build-Finance-Operate-Maintain (DBFOM)

• Concession Agreement• Add Operations and Maintenance • Construction period and

Availability Payments• Terms of 35 to 40 years• Long-term financing • More than $500 M• Project advanced 15 years or

more

Page 5: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Legal Framework Ensures Creditworthiness

Florida Department of Transportation5

• Authority for availability payment deals introduced in 2007 statutes

• 15% of federal and state funding cap, cost effectiveness analysis

• Availability payments prioritized ahead of new capacity projects

• Further controls introduced in 2012

• Approval by Governor following Legislature review

• Inclusion in State Transportation Trust Fund debt assessment

• Additionally, portions of P3 payments are included in the Division of Bond Finance Debt Affordability Report

Page 6: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Why has FDOT pursued P3s?

• Both DBF and DBFOM:

– Advance priority projects that add capacity,

enhance safety and reduce congestion

– Additional sources of capital via private sector

• DBFOM procurement method further

incentivizes private sector innovation

• DBFOM contract transfers appropriate risks

through construction and operations

• Toll revenue risk has not been transferred

with FDOT’s P3s

Florida Department of Transportation6

Page 7: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

PortMiami Tunnel DBFOM

Financing:

• $341M federal TIFIA loan, $341.5M bank loans, and $80.3M in private equity

• Milestone, final acceptance and availability payments

Benefits:

• Direct access from I-395 to PortMiami

• Concessionaire has 30-year O&M period following construction

• Construction complete in 2014

Key Decisions:

• No tolls

• Shared geotechnical risk

Construction Cost: $667M

PortofMiamiTunnel.com

Florida Department of Transportation7

Page 8: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

I-595 DBFOM

Financing:

• $603.4M federal TIFIA loan, $781.1M bank loans, and $207.7M in private equity

• Final acceptance and availability payments

Benefits:

• Adds 3 at-grade reversible tolled express lanes and full corridor improvements

• Concessionaire has 30-year O&M period following construction

• Estimated 15 year advancement

Key Decisions:

• Tolls set and retained by FDOT

• Provisions for sharing refinancing gain

Construction Cost: $1.2B

595express.info

Florida Department of Transportation8

Page 9: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

I-4 Ultimate DBFOM

Financing:

• $949M TIFIA loans, $486M bank loans, and $104M private equity

• Construction period, final acceptance, and availability payments

Benefits:

• Major interchanges and bridge reconstruction

• Addition of express lanes provides congestion relief and improves safety

• Estimated 20-year advancement

Key Decisions:

• 21 miles at one time, size and complexity of project

• 40-year concession agreement

9

Construction Cost: $2.3B

I4Ultimate.com

Florida Department of Transportation

Page 10: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Transportation Financing Corporation

Created under s. 339.0809, Florida Statutes

Nonprofit corporation that can finance

projects for FDOT

Adds another tool to our toolbox

Florida Department of Transportation10

Page 11: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Who oversees the TFC?

Florida Department of Transportation

Director of the Office of Policy and Budget within the Executive Office of the Governor

Director of the Division of Bond Finance

Secretary of the Florida Department of Transportation

BOARD OF DIRECTORS

11

Page 12: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

How does the TFC work?

Florida Department of Transportation

Transportation Financing

Corporation

Florida Department of Transportation

Contractor

Contractual Relationship #1

Contractual Relationship #2

Debt Proceeds

Service Payments

Contractor Payments

12

Page 13: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

How does the TFC benefit Floridians?

Florida Department of Transportation

ADDITIONAL

FINANCING TOOL

LOWER INTEREST

RATES

PROJECT

ADVANCEMENT

13

Page 14: Florida Department of TRANSPORTATIONDBF – Design Build Finance DBFOM – Design Build Finance Operate Maintain COMPLETE I-75 N of SR 80 to S of SR78 - $72M (DBF) IN PROCUREMENT -

Questions and Contact Information

Leon Corbett

Project Finance Manager

Office of Comptroller

850-414-4421

[email protected]

www.dot.state.fl.us/officeofcomptroller/pfo.shtm

Florida Department of Transportation14