+ All Categories
Home > Documents > FP7 ABSOLUTE Deliverable Template - CORDIS · Global Positioning System ... This deliverable...

FP7 ABSOLUTE Deliverable Template - CORDIS · Global Positioning System ... This deliverable...

Date post: 14-Jun-2018
Category:
Upload: lamdieu
View: 221 times
Download: 0 times
Share this document with a friend
33
Integrated Project ABSOLUTE - Aerial Base Stations with Opportunistic Links for Unexpected & Temporary Events Contract No.318632 Deliverable FP7-ICT-2011-8-318632-ABSOLUTE/D5.7 Qualification and Certification Framework Report Contractual date: 26/03/2015 Actual date: 31/03/2015 Authors/Editors: Romain Hermenier, Macià Mut, Vincent Boussemart (TGS) Philippe Charpentier (TCS) Sandy Allsopp (HLK) Participants: TGS, TCS, HLK Work package: WP5 T5.7 Security: PU Nature: Report Version: V1.0 Total number of pages: 33 Abstract This deliverable aims at providing a first insight into the qualification and certification framework within the ABSOLUTE project. First this report will present the qualification and certification procedures of the aerial platform used for the final demonstration. Then, although it is not foreseen to have qualified and certified avionics components for the proof-of-concept, this deliverable will touch upon the certification procedures within Europe that could be relevant for a future exploitation of the ABSOLUTE system. Finally a section highlighting some guidance for public and worker protection against antenna radiation will close the document. Keywords Qualification, certification, aerial platform, launch system, EASA, airworthiness, UAV, ETSO certification, guidance, antenna radiation, worker protection, satellite, terrestrial Ref. Ares(2015)1739245 - 24/04/2015
Transcript

Integrated Project

ABSOLUTE - Aerial Base Stations with Opportunistic Links for

Unexpected & Temporary Events

Contract No.318632

Deliverable

FP7-ICT-2011-8-318632-ABSOLUTE/D5.7

Qualification and Certification Framework Report

Contractual date: 26/03/2015

Actual date: 31/03/2015

Authors/Editors: Romain Hermenier, Macià Mut, Vincent Boussemart (TGS)

Philippe Charpentier (TCS)

Sandy Allsopp (HLK)

Participants: TGS, TCS, HLK

Work package: WP5 – T5.7

Security: PU

Nature: Report

Version: V1.0

Total number of pages: 33

Abstract

This deliverable aims at providing a first insight into the qualification and certification framework

within the ABSOLUTE project. First this report will present the qualification and certification

procedures of the aerial platform used for the final demonstration. Then, although it is not foreseen to

have qualified and certified avionics components for the proof-of-concept, this deliverable will touch

upon the certification procedures within Europe that could be relevant for a future exploitation of the

ABSOLUTE system. Finally a section highlighting some guidance for public and worker protection

against antenna radiation will close the document.

Keywords

Qualification, certification, aerial platform, launch system, EASA, airworthiness, UAV, ETSO

certification, guidance, antenna radiation, worker protection, satellite, terrestrial

Ref. Ares(2015)1739245 - 24/04/2015

ABSOLUTE D5.7

Dissemination Level PU Page 2

Table of Contents

List of Figures ......................................................................................................................................... 3

List of Tables ........................................................................................................................................... 4

Abbreviations .......................................................................................................................................... 5

Executive Summary ................................................................................................................................ 6

1 Introduction .......................................................................................................................................... 7

2 Qualification and Certification for Aerial Platform ............................................................................. 8

2.1 Qualification .................................................................................................................................. 8

2.1.1 Will the Helikite: ........................................................................................................................ 8

2.1.2 Will the launch system: .............................................................................................................. 9

2.2 Certification ................................................................................................................................. 10

2.2.1 Helikite ..................................................................................................................................... 10

2.2.2 Launch System: ........................................................................................................................ 11

3 Aerial and Avionics Components Certifications ................................................................................ 13

3.1 Introduction ................................................................................................................................. 13

3.2 Initiation towards the EASA airworthiness certification procedure ............................................ 13

3.3 The Unmanned Aircraft Systems (UAV) case ............................................................................ 14

3.4 Equipment approval : EASA ETSO certification ........................................................................ 15

4 Guidance for Public/Worker Protection against antenna radiation .................................................... 17

4.1 Introduction ................................................................................................................................. 17

4.2 Ka-band dish antenna .................................................................................................................. 19

4.3 Helix antenna ............................................................................................................................... 21

4.4 Dipole antenna array ................................................................................................................... 22

5 Conclusion .......................................................................................................................................... 23

Appendix – 1 ......................................................................................................................................... 24

Appendix – 2 ......................................................................................................................................... 25

References ............................................................................................................................................. 33

Acknowledgement ................................................................................................................................. 33

ABSOLUTE D5.7

Dissemination Level PU Page 3

List of Figures

Figure 1: Example of an ADOA to achieve an EASA ETSO authorization ......................................... 16

Figure 2: Exposure Limits for worker and general public ..................................................................... 18

Figure 3: Deployable Ka-band satellite terminal ................................................................................... 19

Figure 4: Safety computed zone for the satellite Ka-band terminal ...................................................... 20

Figure 5: Antenna installation recommendations on LAP .................................................................... 21

Figure 6: Safety computed zone for the LAP antenna ........................................................................... 21

Figure 7: Antenna installation recommendations on a tripod ................................................................ 22

Figure 8: Safety computed zone for the tripod antenna ......................................................................... 22

ABSOLUTE D5.7

Dissemination Level PU Page 4

List of Tables

Table 1: Exposure Limits for worker and general public ...................................................................... 17

Table 2: Ka band antenna characteristics .............................................................................................. 19

Table 3: Calculated limits for the satellite dish in distances and energy fields for general public and

workers ......................................................................................................................................... 19

Table 4: Calculated limits for the LAP antenna in distances and energy fields for general public and

workers ......................................................................................................................................... 21

Table 5: Calculated limits for the tripod antenna in distances and energy fields for general public and

workers ......................................................................................................................................... 22

ABSOLUTE D5.7

Dissemination Level PU Page 5

Abbreviations

ABSOLUTE Aerial Base Stations with Opportunistic Links For Unexpected & Temporary Events

ADOA

CAA

Alternative Procedures to Design Organization Approvals

Civil Aviation Authority

DDP Declaration of Design and Performance

EASA

EC

European Aviation Safety Agency

European Commission

ETSO

EU

GPS

HLK

ICNIRP

LAP

European Technical Standard Orders

European Union

Global Positioning System

Helikite

International Commission on Non-Ionizing Radiation Protection

Low Altitude Platform

NAA National Aviation Authority

PLMU

POA

Portable Land Mobile Unit

Production Organization Approval

QTP

QTR

TCS

Qualification Test Plan

Qualification Test Results

Thales Communication & Security

TGS TriaGnoSys GmbH

UAV

UK

Unmanned Aircraft Systems

United Kingdom

ABSOLUTE D5.7

Dissemination Level PU Page 6

Executive Summary

This deliverable corresponds to deliverable D5.7 “Qualification and Certification framework Report”,

due Month 30. The objective of this deliverable is to provide a first overview report of the expected

regulatory, qualification and certification framework for a future implementation of the ABSOLUTE

system. Although it is not foreseen to have qualified and certified avionics components for the proof-

of-concept, it is of paramount importance for a later exploitation of the ABSOLUTE concept to know

what the regulations in effect are in terms of airworthiness.

To this end, Chapter 2 first presents the qualification and certification procedures applying to the aerial

platform to be used for the final demonstration. It does not only focus on the flying platform itself, but

also includes the regulatory processes applying to the launch system of the aerial platform. Some

regulatory aspects about the system deployment, the material used and the electronic devices on board

are also discussed.

Chapter 3 then concentrates on providing a brief introduction into the world of airworthiness

qualification and certification within Europe by presenting the certification procedures that could be

relevant for a future exploitation of the ABSOLUTE proof-of-concept. The overall EASA

airworthiness regulatory process is touched upon as well as the current procedures towards Unmanned

Aircraft Systems (UAV). A last subsection about how the equipment manufacturer can obtain an

ETSO authorization when aeronautical equipment is not certified as part of the product closes this

chapter.

Finally Chapter 4 exposes some guidance related to public and worker protection against antenna

radiation. Based on some recommendations and directives provided by the European Commission, it

gives the reader some insights on how to compute the minimum distance required between

workers/public and a working antenna to avoid strong radiations. This analysis considers all the

antenna types used in the ABSOLUTE project, namely a satellite Ka-Band dish antenna, an Helix

antenna and an dipole antenna array.

Chapter 5 concludes the document.

ABSOLUTE D5.7

Dissemination Level PU Page 7

1 Introduction

The use of flying platform containing electronic equipments within the ABSOLUTE project addresses

the issues of understanding on the one hand the regulatory procedures of flying objects and on the

other hand the qualification and certification processes to be applied to the avionics equipment. While

the project’s design and development work does not have the ambition to come up with qualified and

certified avionics components for the proof-of-concept, it is still meaningful to understand and be

aware of all related implications and requirements of any applicable processes and standards for a later

exploitation.

As an already certified product, the Helikite aerial platform used for the ABSOLUTE demonstration

already fulfils the safety and regulatory requirements. The later encompass procedures for the platform

itself (such as materials used, visible safety features, deployment phase...) but also for the personal

using the platform. It is also worth mentioning that some requirements are also necessary for the

launch system of the platform.

As to the avionic equipment, the European Aviation Safety Agency (EASA [1]) requires the product

manufacturer to obtain the appropriate European Technical Standard Orders (ETSO) authorization in

order for this equipment to be certified as part of the overall product. It is therefore of interest for a

later implementation of the ABSOLUTE system to understand how an ETSO authorization works and

what the requested document for such authorization are.

Furthermore, deploying a system such as ABSOLUTE could easily raise the issue of the worker safety

towards antenna radiation. Indeed the ABSOLUTE system use a bunch of satellite and terrestrial

antennas with different antenna patterns and transmitting power. Here again, understanding the

European regulations about antenna exposure limits is of paramount importance for the public and

worker safety.

The deliverable is thus structured as follows. Chapter 2 will present and highlight the existing

qualification and certification procedures of the aerial platform as well as its launch system. The main

airworthiness certification processes will then be discussed in Chapter 3, with a focus on the UAV

case and the ETSO authorization. Some guidance for public and worker protection against antenna

radiation is described in Chapter 4. Finally Chapter 5 concludes the document.

ABSOLUTE D5.7

Dissemination Level PU Page 8

2 Qualification and Certification for Aerial Platform

For sake of clarity towards the qualification and certification procedures of the aerial platform and its

dedicated launch system used in ABSOLUTE, this section has been written using a “question/answer”

approach.

2.1 Qualification

2.1.1 Will the Helikite:

1) Fly steadily in the proscribed weather conditions for long enough?

The 34m3 Desert Star Helikite has been extensively tested in winds between 0 and 50mph, which are

the wind speeds required by the ABSOLUTE project. The Helikite flew well in these winds for long

periods. It also flew in rain, snow and high temperatures with no problems.

2) Have enough lifting capability to lift the payload to the proscribed altitude correctly in all

these conditions?

The ABSOLUTE payload is expected to be 10Kg or less. The 34m3 Desert Star Helikite has a pure

helium lift of 14Kg in no wind which is enough to lift the payload plus flying line up to the proscribed

1,000ft altitude for the trials. In a 15 mph wind it was tested to lift 30Kg. In higher winds it lifts even

more. If it happens that the payload ends up being a heavier weight than 10Kg, then a larger 40m3

Desert Star Helikite can be supplied instead that uses the same ground handling equipment as the

34m3.

3) Will the electronics function correctly while on the Helikite?

This is only possible to test when the electronics are finished, which has not happened yet.

4) Accommodate the radio/electronics + Antennas + Batteries + Fibre-Optic in the correct way?

Representative models plus actual batteries of the electrical components have been fitted to the

Helikite with no problems. However, until the electronics are finished it is not possible to fit them.

5) Be easy and quick to operate?

For the ABSOLUTE project, the Helikite requires to be operated with a minimum of two people in all

designated weather conditions, night and day. This has been extensively tested over many months in

different weather conditions night and day, both from the dedicated Helikite Trailer and the ground-

based launch Helibase system. The deployment has always been trouble-free and in fact perfectly

possible for only one person even in high winds.

6) Be transported easily enough?

The Ground-Based Helikite Launch System can be packed up into a number of Pelicases and hold-alls.

These can quickly be placed in the back of a van or pick-up truck and driven wherever required. The

helium cylinders can be secured to the pick-up truck or van internal structural wall for safe transport.

This was successfully tested.

The dedicated ABSOLUTE Helikite Trailer combines the functions of helium cylinder handling,

helium transport, Helikite transport and Helikite launch - all into one unit. This has been extensively

tested both on and off road, and has been in almost constant use launching Helikites for many months.

It has performed flawlessly.

7) Be stored well enough for long periods?

There are two types of storage:

a) Long-term storage in the depot of the Helikite system ready for deployment.

ABSOLUTE D5.7

Dissemination Level PU Page 9

This has been tested since the beginning of the ABSOLUTE project two years ago. The Helikite

polyurethane balloon materials, which are the most likely to deteriorate in long-term storage, have

been kept in cool, dry, dark conditions as proscribed. The materials have shown no sign of

deterioration. Allsopp Helikites Ltd has in fact kept similar materials for 20 years in such conditions

with very little deterioration. However, it is recommended that the Helikite balloons are replaced every

4 years as a routine precaution.

The other possible storage problem will be the helium in the cylinders, as it is possible it might leak

out over many years. This possibility can be eliminated by testing the cylinders every 3 months when

in storage. By law, the helium cylinders need to be strength-tested by their manufacturers every 4

years.

b) Inflated storage on the Helibase or the Trailer during times when the Helikite has been

deployed but is not required to be flying for some reason.

It is essential that an inflated Helikite has somewhere safe to rest in all weather conditions when not in

flight. The most common form of damage to aerostats is due to incorrect ground storage.

The ABSOLUTE Helikite was tested for inflated storage both on the ground-based, air-inflated

Helibase and on the Helikite Trailer over many months outside in all weathers, winter and summer.

Both systems performed very well. Even in the severest gales there was no damage to the Helikite.

The balloon materials did not rot or wear due to damp or long-term vibration. Polyurethane balloon

material can quickly rot if left in damp, warm conditions is an enclosed place such as when placed wet

into a sealed storage box. However, the polyurethane balloons do not seem to rot if they are kept

inflated outside. This is probably due to the good air circulation that kills any offending fungus.

2.1.2 Will the launch system:

1) Be easy to transport to site?

The ground based Helikite launch system fits easily into a van or pick-up truck. These were tested and

proved to be suitable to be driven on or off-road to any suitable site.

The Helikite trailer was tested on and off road and is capable of being trailed to the centre of a field or

anywhere in urban areas for rapid launch. The trailer is more versatile than the ground launch system,

because setting up on areas of concrete such as car-parks is straightforward.

2) Fast enough to set up in time? During tests at Allsopp Helikites flying facility, set-up time for the ground launched system was under

one hour, and for the trailer it was under 30 minutes. Both these times are within the ABSOLUTE

criterior.

3) Launch the Helikite correctly and safely?

During tests at Allsopp Helikites flying facility, launching took place numerous times from both the

ground-based system and the trailer. At all times launch occurred correctly and safely with no

particular problems.

4) Transport the helium safely?

The transport of helium in the pick-up truck can be done by fastening the helium to be firmly to the

floor of the truck using the strong tie-down points provided. Helium can also be attached vertically to

the bars at the front of the flatbed.

In the van the cylinders were at times secured either vertically or horizontally using suitable strong-

points. Either method was fine. It is important to ensure that there is a bulkhead between the driver and

the helium cylinders so that if gas escapes it cannot reach the driver.

ABSOLUTE D5.7

Dissemination Level PU Page 10

5) Pack up correctly?

The ground based launch system was packed into cases or bags. The Helibase was deflated, rolled up

and then pushed into its soft, breathable, bag. The Helikite was deflated, rolled up and put into a sail

bag temporarily for the journey to the depot. The Helikite spars were inspected and put into their

plastic storage tubes. The winch was put into its Pelicase. The ground anchors and tools and handling

rope were put into another Pelicase. The electronic equipment will have its own Pelicases. All this

took about 45 minutes.

The Trailer Based system only takes about 20 minutes to pack up. Essentially, it just involves deflating

the Helikite and rolling it up to be stored in its sail-bag for the journey to the depot. Then the trailer

arms are folded up and the trailer cover put on.

6) Return the equipment to the storage area safely?

During a representative trial, the ground based Helikite system was placed into a van and driven to the

storage depot with no problems.

The Helikite trailer was towed off the launch site and driven to the storage depot, then reversed into

the depot.

7) Be stored well enough for long periods?

The Helikite needed to be dried perfectly before long-term storage. So, immediately after arriving at

the storage depot it was removed from its sail bag and placed onto a perfectly clean carpeted area to be

inflated with blown air. This facilitates full inspection of the balloon, the kite sail and the balloon

cover for faults or dirt. Any cleaning or repairs can be done immediately. The inflated Helikite is then

left until perfectly dry. A fan heater on low heat, or no heat, will speed up drying. However, normally

the Helikite is simply left overnight to dry. Leaving it inflated overnight also allows the operators to

detect any loss of gas due to a leak.

After the Helikite is perfectly dry and assured to be in perfect condition it can be carefully rolled up

and put back into its Pelicase for long-term storage. Every three months the Helikite should be

carefully taken from the Pelicase, unrolled on the clean floor and inspected for signs of damp, vermin,

etc before being put back in its case.

2.2 Certification

2.2.1 Helikite

1) Does the Helikite have the correct safety features required by law such as Auto-Cut-Down-

Device, flags, lighting, etc.?

Yes. The Helikite has a GPS Operated Auto-Cut-Down Device made by Allsopp Helikites Ltd that

automatically makes a hole in the balloon if the Helikite strays more than 1 mile from its launch pad.

This small hole in the balloon slowly releases helium from the balloon in a controlled manner thus

allowing the Helikite to gently return to earth. Flags and lighting adhering to the CAA Air Navigation

Order are supplied.

2) Is the Auto-Cut-Down-Device able to be proven that it is working?

Yes. An important part of the Auto-Cut-Down Device is its self-checking procedure that it initiates

upon being turned on. It automatically checks that the battery has enough power, that the electrical

wires are sound and that it has correctly established its position via GPS, before it signals that it is

ready and working correctly.

ABSOLUTE D5.7

Dissemination Level PU Page 11

3) Are the materials of the Helikite suitable for purpose?

Yes. The kite part of the Helikite is made from rip-stop nylon resistant to UV and and a well known

kite and sail making material. The balloon is pure polyurethane which is the best quality balloon

material available. The balloon does not endure structural stresses as it is contained within the outer

balloon cover. This outer cover is made from Allsopp Helikites` 'Ultra' material which is a lightweight

composite of woven polyethylene and polyester that is UV resistant and very strong.

4) Are the materials strong enough for purpose? What is their strength?

The materials have been proven over many years of Helikite flying hours to be exceptionally strong

and suitable for all normal conditions. See also in Appendix – 1, the table of Helikite Material

Strengths.

5) Are there safety lines to the payload components?

Yes. These go from the payload component to the main body of the Helikite.

6) Has a Health and Safety Assessment been completed for the Helikite structure and handling?

Yes. Please refer to appendix – 2.

2.2.2 Launch System:

1) Are the ground anchorage points strong enough and strength rated?

The 'Grabba' ground anchor has a structural steel ring rated to 1,500Kg which give it a 3X safety

margin for strength.

2) Is the Helikite allowed to operate from the launch site?

The vast majority of places in Europe are legal for Helikites to operate from without a licence or even

air-traffic permission up to certain altitudes. Above 200ft permission may be needed in some areas

such as the UK. Above 400ft air-traffic permission is always needed almost everywhere, but this is

generally easy enough to obtain quite quickly. The only places generally prohibited without air-traffic

control permission are the air-traffic-zones of registered airfields and emergency helicopter landing

pads. It is important to investigate the legal requirements of each site regarding Helikite flight.

3) Is the tether line strong enough with adequate margin of safety?

The flying line is 1,900 Kg breaking strain Dyna 1 Dyneema. As the expected line load is expected to

be no more than 500Kg in the 50mph top recommended wind speed, there is a 3.8X safety margin.

4) Has a Health and Safety Assessment been completed for the launch and operation of the

Helikite?

Yes. Please refer to appendix – 2.

5) Are the personnel involved proven to be adequately trained in Helikite operations?

Yes. They have long experience in Helikite operations in multiple different countries and have a 100%

safety record.

6) Is the trailer of correct design and have the correct warning signs etc?

The trailer is designed with all the relevant health and safety features in mind. It has a massively

strong chassis construction of galvanised steel. It has twin axles but can function with only one axle if

required thus providing redundancy in case of a tyre puncturing. It is highly stable at the legal speed

limit on tarmac roads and it is also a capable off-road trailer with a high enough ground clearance. The

ABSOLUTE D5.7

Dissemination Level PU Page 12

helium is stored in steel cylinders firmly strapped down to the trailer. The cylinders are protected from

knocks and there is a special ramp provided allowing the cylinders to be easily and safely pulled onto

the trailer. The Helikite is very easily and safely inflated and flown from the trailer in all weathers. The

trailer has the designated warning sign relating to the carriage of stored helium in pressurised

cylinders.

ABSOLUTE D5.7

Dissemination Level PU Page 13

3 Aerial and Avionics Components Certifications

3.1 Introduction

This chapter aims at providing a brief introduction into the world of airworthiness qualification

and certification within Europe. Due to the complexity of this process, the following information just

touches upon the certification procedures that could be relevant for a future exploitation of the

ABSOLUTE proof-of-concept. The reader is invited to refer to the provided references for more

detailed insights on this topic.

3.2 Initiation towards the EASA airworthiness certification procedure

The European Aviation Safety Agency (EASA [1]) corresponds to the civil aviation authority in

Europe and is responsible for determining all aviation policy Europe-wide. Created by EC Regulation

1592/2002, the main goal of the agency is to establish and maintain a high uniform level of civil

aviation safety in Europe. To achieve it, basic regulations have been instituted and apply to the design,

production, maintenance and operation of aeronautical products, parts and appliances, as well as

personnel and organisations involved not only in the design, production and maintenance of such

products, parts and appliances but also in the operation of aircraft [2]. Each of these regulations

focuses on an aspect of civil aviation safety (such as initial airworthiness, continuing airworthiness, air

crew, air operations, etc...) and contains implementing rules to ensure that all products meet the level

of safety required by the basic regulation. Additionally EASA issues certification specifications, which

contains guidance material and acceptable means of compliance, to assist in the understanding and

also demonstrate compliance with the implementing rules.

Any aircraft which is subject to the EASA regulation and implementing rules will be required to

have an EASA airworthiness certificate. In order to obtain a standardised aeronautical product, a

specific procedure within EASA has to be followed [3]. The applicant must first submit a type

certificate whose eligibility will be assessed by EASA. If accepted, technical investigation will be

further processed by a team of experts either from EASA or from a National Aviation Authority

(NAA). Once a certification team established, the EASA type certification process can generally be

divided in four different phases1:

- Phase I – Technical Familiarization and establishment of the Type Certification Basis

Once a sufficient degree of maturity is considered reached, the aircraft manufacturer

presents the project to EASA. The objective of this phase is to provide technical information

about the project to the Team experts to enable the definition of and the agreement on the

initial EASA Type Certification Basis.

- Phase II – Agreement of the Certification Program

EASA and the manufacturer need to define and agree on the means to demonstrate

compliance of the aircraft type with each requirement of the Certification Basis.

1 This process is valid for EU products. For non EU products, please refer to [3] for the certification procedure

ABSOLUTE D5.7

Dissemination Level PU Page 14

- Phase III – Compliance determinations

The objective of this phase is the demonstration of compliance with the Certification Basis

and the acceptance of the compliance demonstration.

- Phase IV- Final Report and issue of a Type Certificate

The objective of this phase is the establishment of a project final report recording details

of the type investigation and, based on approval of the final report by the responsible

certification manager, the issue of the EASA Type Certificate.

During the certification process, a co-ordination with a number of other activities is also required.

These activities include:

- Aircraft/Engine/Propeller interactions

The applicant is responsible for the installation of the engine/propeller within the aircraft

and has to show compliance with installation requirements that apply to over and above those

required for the separate type certification of the engine/propeller.

- Environmental protection

The applicant has to show compliance with the applicable aircraft noise and fuel venting

requirements as well as with the applicable engine emissions requirements.

- Maintenance and Operation interactions

- Design and Production Organization approval

- Equipment approval

For the approval of equipment to be certified as part of the Product, the applicant is

responsible for the approval of the equipment and its installation. An acceptable mean of

providing compliance data in support of the equipment and its installation is to show that the

equipment meets the appropriate European Technical Standard Orders (ETSO) standard.

- Continuing Airworthiness

- Approval of Flight Conditions

- Reporting System

3.3 The Unmanned Aircraft Systems (UAV) case

The basic regulations and its implementing rules do not apply to aircraft engaged in military,

customs, police or similar services (State aircraft), although EU Member States must, however, ensure

that such services fulfil similar requirements to the objectives of the EASA Regulation. Furthermore

some categories of civil aircraft are also not required to meet the EASA requirements:

- aircraft specifically designed or modified for research, experimental or scientific purposes and

likely to be produced in very limited numbers;

- aircraft whose initial design was intended for military purposes only;

- and unmanned aircraft with an operating mass of less than 150 kg.

ABSOLUTE D5.7

Dissemination Level PU Page 15

It must be noted that aircrafts which are exempt of EASA regulation (such as an unmanned aircraft

less than 150 kg) remains anyway subject to national regulation about airworthiness certification and

continuing certification.

As to unmanned aircraft requiring an airworthiness certification (more than 150 kg), the applicant

must follow the procedure described in section 3.2 by submitting a type certificate and demonstrate

compliance with a defined type certification basis. Once the compliance with the approved type design

has been proved, a certificate of airworthiness is issued to an individual unmanned aircraft. More

insights on the certification procedure for unmanned aircraft can be found in [4] and [5].

3.4 Equipment approval : EASA ETSO certification

When aeronautical equipment is not certified as part of the product, the equipment manufacturer is

responsible for obtaining ETSO Authorization. The ETSO Authorization provides means of

compliance for the equipment and its installation and is the recognition by EASA that the equipment

meets predefined qualification and performance criteria.

The ETSO certification procedure follows closely the one for a type certificate as described in

section 3.2. It consists of the following steps:

- The applicant must first prepare the draft Declaration of Design and Performance (DDP) of his

equipment and the Alternative Procedures to Design Organization Approvals (ADOA) design

plan with the certification program. Together with the specifications and the application form

for ETSO [6], these documents describe the intended design and functions of the equipment

and must be submitted to EASA for first review. Corrections might be required by EASA at

this stage.

- The design phase will then produce a prototype of the hardware equipment to be used in the

subsequent qualification tests. During this phase, more exhaustive information must be

provided, including all design data (such as detailed drawings, software and hardware

versions, etc…), a draft production manual and the Qualification Test Plan (QTP), which

entails the qualification test procedures.

- Once the design phase concluded, qualification tests will be performed following the QTP in

various laboratories. Test results must be stored and documented in the Qualification Test

Results (QTR).

- Finally, all final versions of documents must be submitted to EASA for final verification. It

includes, among others, the final DDP, a statement of compliance, the QTR, the Production

Organization Approval (POA) manual for manufacturing, etc… ETSO authorization is granted

after the approval of all those documents.

Once the ETSO authorization achieved, the applicant as POA is entitled to produce his equipment

following the production manual and certify compliance to the DDP by issuing an EASA form 1.

Figure 1 summarizes the steps to follow to achieve an EASA ETSO authorization and displays an

example of ADOA.

ABSOLUTE D5.7

Dissemination Level PU Page 16

Figure 1: Example of an ADOA to achieve an EASA ETSO authorization

ABSOLUTE D5.7

Dissemination Level PU Page 17

4 Guidance for Public/Worker Protection against antenna

radiation

4.1 Introduction

Exposure limits for electromagnetic fields was determined by the International Commission on Non-

Ionizing Radiation Protection (ICNIRP). Based on these values, the European Community drafts

recommendations and directives regarding the exposure of the public and of workers from the risks

arising from electromagnetic fields:

- Recommendation 1999/519/EC for the general public

- Directive 2004/40/EC for workers

These texts define limits on exposure which “are based directly on established health effects and

biological considerations. Compliance with these limits will ensure that people exposed to

electromagnetic fields are protected against all known adverse health effects”.

The main difference between workers and general public is that workers “who are exposed to risks

from electromagnetic fields at work and/or their representatives shall have received any necessary

information and training” relating to the outcome of the risk assessment provided, concerning in

particular “the values and concepts of the exposure limit values and the associated potential risks” and

“safe working practices to minimize risks from exposure”.

Exposure limit and action values for electric fields are exposed in tables below and represented on

below curves.

Frequency range Exposure limit for worker regarding

electric field strength, E (V/m)

0 - 25 Hz 20000

0,025 - 0,82 kHz 500/f

0,82 - 1000 kHz 610

1 - 10 MHz 610/f

10 - 400 MHz 61

400 - 2000 MHz 3f^1/2

2 - 300 GHz 137

Frequency range Exposure limit of the general public regarding

electric field strength, E (V/m)

0 - 25 Hz 10000

0,025 - 3 kHz 250/f

3 - 1000 kHz 87

1 - 10 MHz 87/(f^1/2)

10 - 400 MHz 28

400 - 2000 MHz 1,375f^1/2

2 - 300 GHz 61

Table 1: Exposure Limits for worker and general public

ABSOLUTE D5.7

Dissemination Level PU Page 18

Figure 2: Exposure Limits for worker and general public

The following paragraphs provide guidance concerning the protection of the public and workers

concerning some ABSOLUTE emitting pieces of equipment.

The calculation is done using following formula. The electrical field (E) at the distance (d) of the

emitter is given by:

Where:

- E, is the electrical field expressed in V/m

- K, is a multiplicative factor between 2 and 4 used in case of reflective surfaces

- P, is the emitting power expressed in W

- G, is the antenna gain (linear value)

- D, is the distance between the emitter and the public expressed in m

Note: This formula is applicable if the following conditions are fulfilled (far field condition). d shall be

greater than D expressed depending on the wavelength λ:

1

10

100

1000

10000

100000

1,E+00 1,E+01 1,E+02 1,E+03 1,E+04 1,E+05 1,E+06 1,E+07 1,E+08 1,E+09 1,E+10 1,E+11 1,E+12

Ch

am

p E

(V

/m)

Frequency (Hz)

Electromagnetic Exposure limit values - Directive 2004/40/CE (Workers) - Recommendation 1999/519/CE (public)

E Workers

E Public

20000

137

61

610

28

87

d

GPkE

...30

2D

ABSOLUTE D5.7

Dissemination Level PU Page 19

4.2 Ka-band dish antenna

ABSOLUTE uses a deployable Ka-band satellite terminal to establish backhauling communications

via satellite.

Figure 3: Deployable Ka-band satellite terminal

The main specifications of the antenna retained for the calculation of the exposure limits are:

Table 2: Ka band antenna characteristics

The calculated limits are:

Personnel category General Public Workers

Maximum field, E (V/m) 61 137

Minimal distances, d (m) 33 15

Table 3: Calculated limits for the satellite dish in distances and energy fields for general public and

workers

One shall take also the radiated pattern into consideration. At the high frequency of the Ka band, the

antenna dish produces a very directive beam, width of which is around 1°.

So the protection actions shall be taken as follows for the general public:

- in front of the dish, the recommended safety distance is 33 m.

- side to the dish (considering side lobes of the radiating patterns), the recommended safety

distance is 1 m

Considering the tilt of the antenna which is expected in our region (33° at Paris latitude), this could be

further reduced to 5 m as shown in following picture.

As the antenna is on the ground, visible limits shall be used to materialize the excluding zone.

ABSOLUTE D5.7

Dissemination Level PU Page 20

Figure 4: Safety computed zone for the satellite Ka-band terminal

-33,1

6

-29,8

5

-26,5

3

-23,2

1

-19,9

0

-16,5

8

-13,2

7

-9,9

5

-6,6

3

-3,3

2

0 3,3

2

6,6

3

9,9

5

13,2

7

16,5

8

19,9

0

23,2

1

26,5

3

29,8

5

33,1

6

-15,0061,00137,00 -16,58

-13,27

-9,95

-6,63

-3,32

0,00

3,32

6,63

9,95

13,27

16,58

137,00-147,00

61,00-137,00

-15,00-61,00

emitter

Horizintal distance (m)

Vertic

al d

ista

nce (m

)

-5,0

0

-4,5

0

-4,0

0

-3,5

0

-3,0

0

-2,5

0

-2,0

0

-1,5

0

-1,0

0

-0,5

0

0 0,5

0

1,0

0

1,5

0

2,0

0

2,5

0

3,0

0

3,5

0

4,0

0

4,5

0

5,0

0

-15,0061,00137,00 -2,50

-2,00

-1,50

-1,00

-0,50

0,00

0,50

1,00

1,50

2,00

2,50

137,00-147,00

61,00-137,00

-15,00-61,00

emitter

Horizintal distance (m)

Ve

rtical d

ista

nc

e (m

)

5m

> 2,5 m

33°

ABSOLUTE D5.7

Dissemination Level PU Page 21

4.3 Helix antenna

The ABSOLUTE designed helix antenna is to be used on the aerial platform. Its characteristics are:

band 7, gain: ~5 dBi, circular polarization.

The following picture gives an insight of the installation recommendations on LAP together with the

antenna description.

Figure 5: Antenna installation recommendations on LAP

The calculated limits are (taking into account antenna max gain and emitter max power of 30 dBm):

Personnel category General Public Workers

Maximum field, E (V/m) 61 137

Minimal distances, d (m) 0,22 0,10

Table 4: Calculated limits for the LAP antenna in distances and energy fields for general public and

workers

So the distances corresponding to the exposure limits are very small (10 cm for the workers). As the

antenna is on the rear of the balloon at a certain height taking into account the size of the balloon, no

particular action is foreseen except advertising workers of the risk, which is not being very near of the

antenna when emitting (at the take-off of the balloon).

Figure 6: Safety computed zone for the LAP antenna

LAP

Antenna

Feeding circuit

QHA

Plastic radome

-0,2

8

-0,2

5

-0,2

2

-0,2

0

-0,1

7

-0,1

4

-0,1

1

-0,0

8

-0,0

6

-0,0

3

0 0,0

3

0,0

6

0,0

8

0,1

1

0,1

4

0,1

7

0,2

0

0,2

2

0,2

5

0,2

8

-15,0061,00137,00 -0,14

-0,11

-0,08

-0,06

-0,03

0,00

0,03

0,06

0,08

0,11

0,14

137,00-147,00

61,00-137,00

-15,00-61,00

emitter

Horizintal distance (m)

Vertic

al d

ista

nce (m

)

ABSOLUTE D5.7

Dissemination Level PU Page 22

4.4 Dipole antenna array

The ABSOLUTE designed collinear antenna is to be used on a mast or a tripod at the PLMU

subsystem. Its main characteristics are: Band 7, max gain: 9 dBi, aperture: omni x 15°.

Figure 7: Antenna installation recommendations on a tripod

The calculated limits are (taking into account antenna max gain and emitter max power of 30 dBm):

Personnel category General Public Workers

Maximum field, E (V/m) 61 137

Minimal distances, d (m) 0.40 0,18

Table 5: Calculated limits for the tripod antenna in distances and energy fields for general public and

workers

No particular action is to be taken on a mast (see picture below with a 8 m mast) but if a tripod is used,

access to near vicinity of the tripod should be restricted (40 cm).

Figure 8: Safety computed zone for the tripod antenna

TeNB

Collinear antenna

PLMU

-0,5

0

-0,4

5

-0,4

0

-0,3

5

-0,3

0

-0,2

5

-0,2

0

-0,1

5

-0,1

0

-0,0

5

0 0,0

5

0,1

0

0,1

5

0,2

0

0,2

5

0,3

0

0,3

5

0,4

0

0,4

5

0,5

0

-15,0061,00137,00 7,75

7,80

7,85

7,90

7,95

8,00

8,05

8,10

8,15

8,20

8,25

137,00-147,00

61,00-137,00

-15,00-61,00

emitter

Horizintal distance (m)

Vertic

al d

ista

nce (m

)

ABSOLUTE D5.7

Dissemination Level PU Page 23

5 Conclusion

This deliverable has provided a brief overview of the qualification and certifications procedures for a

latter exploitation of the ABSOLUTE system.

As has been seen in Chapter 2, the Helikite aerial platform to be used for the demonstration also fulfils

some specific qualification and certification procedures in terms of materials, deployment, safety

regulations, personal training... Those procedures also apply to the launch system of the platform.

Furthermore a brief overview of the EASA airworthiness processes has been presented in Chapter 3 so

as to provide a general idea of what would be required to certify avionics equipment, such as an ETSO

authorization.

Finally Chapter 4 provided some guidance for public and worker safety towards antenna radiation. The

metric computed here was the maximum exposure distance of the workers and public for the different

antennas that will be used within ABSOLUTE. Particular care is required for using the satellite dish

antenna, as a recommended safety distance of 33 m is necessary in front of the dish and 1m on the side

(considering side lobes of the radiating patterns).

ABSOLUTE D5.7

Dissemination Level PU Page 24

Appendix – 1

CONSTRUCTION AND STRUCTURAL MATERIAL STRENGTHS FOR 34 CUBIC METRE DESERT

STAR HELIKITE

ABSOLUTE D5.7

Dissemination Level PU Page 25

Appendix – 2

ABSOLUTE HELIKITE OPERATIONS RISK ASSESSMENT

ABSOLUTE D5.7

Dissemination Level PU Page 27

ABSOLUTE HELIKITE OPERATIONS RISK ASSESSMENT

COMPANY NAME: Allsopp Helikites Ltd ASSESSMENT CARRIED OUT BY: Sandy Allsopp DATE: 10/12/2014 HAZAR

D SEVERITY 1 Insignificant 2 Minor 3 Moderate 4 Serious injury or Death

HAZARD LIKELIHOOD 1 Rare 2 Unlikely 3 Possible 4 Likely

HAZARD RISK 1-2 Very Low 3-4 Low

5-6 Medium 7-8 High

Operation What are the hazards?

Who might be harmed and

how?

Hazard Severity

1 - 4

Hazard Likelih

ood 1 - 4

Hazard Combin

ed Score 2 - 8

Hazard Reduction Strategies

Surveying launch site before deployment

Uneven terrain. Wildlife. Snake

bites. Insect and scorpion stings.

Operators. Site surveyors.

Tripping up. Falling down.

Attack by wildlife.

2 1 3 Study terrain on map first. Look out. Be aware of wildlife. Have safe vehicle refuge. Have anti-venom and first aid kit available.

Do not operate alone if possible.

Hammering in ground anchors

Hammer injuries Operators, by hammering

mistakes

2 1 3 Hammering tuition and practice. Wear safety gloves and safety goggles. Inspect the

ground. Deploying air-inflatable Lifting injuries Operators, by 1 1 2 Use proper lifting techniques. Wear safety

ABSOLUTE D5.7

Dissemination Level PU Page 28

Helibase launch pad lifting. gloves.

Lifting Helikite onto Helibase

Lifting injuries Operators, by lifting.

1 1 2 Use proper lifting techniques. Wear safety gloves.

Moving helium cylinders Lifting injuries. Crush injuries.

Operators, by lifting and dropping cylinders.

1 2 3 Use proper lifting techniques and equipment, wearing safety gloves and steel capped boots. Have first aid kit easily available.

Moving winch Lifting injuries. Crush injuries.

Operators, by lifting small winches or

positioning large trailed winches.

2 1 3 Use proper lifting techniques and equipment, wearing steel capped boots and safety

gloves. Obeying winch deployment instructions. Winch to have proper lifting

eyes, wheels if required, and handles. Have first aid kit easily available.

Fitting and operating the gas regulator valve

Gas regulator valve faulty or not

suitable for the operation.

Operators. Gas regulator valve

may shear off the cylinder when gas is released from

cylinder into valve.

3 1 4 Ensure regulator valve is suitable for the climate and helium cylinder. Ensure the valve

is properly secured onto the cylinder. Hold head away from the valve when releasing gas

from cylinder.

Filling the Helikite balloon with helium gas.

Gas hose may split. Gas may leak

from balloon or cylinder or hose.

Operators. Gas hose splitting

may cause injury.

4 1 5 Ensure hose is suitable to withstand expected gas pressures. Do not exceed

correct hose gas pressure.

Filling Helikite in an enclosed place

Helium gas may escape from Helikite, or

cylinder, or filling hose and displace

the air in the enclosed space.

Operators. Inhaling helium gas may cause

asfixiation.

4 1 5 Ensure that any enclosed space has good ventilation when filling or storing Helikites.

Do not inhale helium gas.

ABSOLUTE D5.7

Dissemination Level PU Page 29

Tying down Helikite onto ground anchors and

adjusting as it fills with gas.

Rope handling hazards

Operators. Fingers trapped

in rope.

1 1 2 Ensure the supplied Helikite handling ropes are present. Wear gloves. Ensure fingers do

not get trapped. Operating Winch Winch drum

moving. Rope moving. Engine

hot.

Operators. Body parts trapped in winch or rope.

Burns.

3 2 5 Wear gloves. Ensure fingers do not get trapped in rope. Ensure no body parts can

contact winch drum. Ensure winch drum has adequate safety cage. Avoid hot engine

parts. Read and obey all winch operating instructions.

Launching Helikite Helikite moving. Flying cable

tightening on sheave block.

Operators. Contacting

moving Helikite. Trapping body parts in sheave

block.

2 2 4 Use the air-inflatable "Helibase" launch pad whenever possible. Observe wind strength

and direction. Predict likely Helikite movement. Keep a look out to ensure the Helikite cannot contact operators when launching. Keep body parts away from

sheave block. Wear safety gloves.Train and practice in low wind conditions before

operating in high winds. Flying Helikite Helikite or flying

line contacting overhead wires.

Operators. Public. Risk of

electrocution. Risk of damage to

overhead lines and Helikite and

flying line.

4 2 6 During site survey, ensure that there are no power lines, telephone lines or other

overhead lines anywhere near when the Helikite will fly.

Flying Helikite Aircraft contacting Helikite when

Helikite in normal flight

Aircraft pilots and passengers.

Public. Operators. Aircraft

contacting a flying Helikite

may be damaged and crash. The

4 1 5 Operators should always follow the local tethered balloon flying regulations regarding allowed height and allowed flight position.

Correct flags, banners etc should be displayed on the flying line. The Helikite

should be brightly coloured if possible, or coloured the correct legally designated colours if required. At night the correct

ABSOLUTE D5.7

Dissemination Level PU Page 30

public or operators may be

harmed by crashing aircraft

lighting regulations for moored tethered balloons must be followed. Air traffic control permission must be sought if flying above an altitude where it is required. Also, in certain countries, aerostats above certain masses

and volumes need air traffic control permission to fly at any height at all.

Flying Helikite Helikite breaking away from tether

and flying off.

Public. Operators. Aircraft pilots and

passengers. Aircraft

contacting a free flying Helikite

may be damaged and crash. The

public or operators may be

harmed by crashing aircraft

2 1 3 Ensure the flying line has a manufacturers rated breaking strain at least 5 time greater

than the expected pull from the Helikite. Ensure that a certified, legal and functioning Emergency Balloon Cut-Down-Device is on

the Helikite balloon. If Helikite flies off, note altitude, speed and heading and contact the

local Air Traffic Control Authorities immediately and have their phone number

easily available.

Flying Helikite Flying line breaking

Operators. Broken end of

flying line whipping back

down onto operator.

1 2 3 Ensure the flying line has a manufacturers rated breaking strain at least 5 time greater

than the expected pull from the Helikite. Always ensure Dyneema® or Spectra® flying

line is use, because they have very little stretch and so do not rebound back if cut

(unlike nylon or steel). Ensure Helikite is not flown in winds that will cause too much

strain on the line. Measure strain on line with a suitable cable strain gauge.

Carrying Equipment Equipment falling off.

Public. Operators. Items falling on

them.

4 1 5 Ensure equipment is well secured to Helikite. Ensure equipment has safety line attached. Ensure nobody goes under Helikite when

flying.

ABSOLUTE D5.7

Dissemination Level PU Page 31

Landing Helikite Rope handling hazards. Contact

hazards.

Operators. Body parts, especially fingers may get

trapped in handling lines.

Helikite may hit somebody when

close to the ground.

2 2 4 Observe wind strength and direction. Predict likely Helikite movement. Keep a look out to ensure the Helikite cannot contact operators

when landing. Keep body parts away from sheave block. Ensure body parts do not get

trapped in handling ropes. Wear safety gloves. Train and practice in low wind

conditions before operating in high winds.

Deflating Helikite Gas inhalation hazards.

Operators. Inhaling helium gas may cause

asfixiation.

4 1 5 Ensure this occurs in a very well ventilated environment. Preferably outside. Do not

inhale helium gas for any reason. Do not hold mouth or nose near venting gas exit plugs.

Packing up Helikite and equipment

Lifing injuries. Crush injuries. Trip

hazards.

Operators, by lifting and dropping cylinders.

Operators, by lifting small winches or

positioning large trailed winches.

Operators by tripping over equipment,

especially packing up in the dark

evenings.

2 3 5 Use proper lifting techniques and equipment, wearing safety gloves and steel capped

boots. Obeying winch deployment instructions. Be aware of trip hazards. Have

suitable storage equipment for all equipment. Take note of the position of equipment during the day, ready for the nightime. Provide good lighting for the

operating area. Avoid operating when too tired.

ABSOLUTE D5.7

Dissemination Level PU Page 33

References

[1] EASA – Europe Aviation Safety Agency: https://www.easa.europa.eu/

[2] Regulation (EC) No 1592/2002 “on common rules in the field of civil aviation and

establishing a European Aviation Safety Agency”, https://www.easa.europa.eu/document-

library/regulations/regulation-ec-no-15922002

[3] EASA – Aircraft Certification: https://www.easa.europa.eu/easa-and-you/key-topics/aircraft-

certification

[4] EASA – Unmanned Aircraft Systems (UAS) and Remotely Piloted Aircraft Systems

(RPAS): https://www.easa.europa.eu/unmanned-aircraft-systems-uas-and-remotely-piloted-

aircraft-systems-rpas

[5] EASA – E.Y013-01, “Airworthiness Certification of Unmanned Aircraft Systems (UAS)”,

https://www.easa.europa.eu/document-library/policy-statements/ey013-01

[6] EASA – FO.ETSOA.00034, “Application form for European Technical Standard Order”,

https://www.easa.europa.eu/document-library/application-forms/foetsoa00034

Acknowledgement

(Mandatory Text) This document has been produced in the context of the ABSOLUTE project.

ABSOLUTE consortium would like to acknowledge that the research leading to these results has

received funding from the European Commission’s Seventh Framework Programme (FP7-2011-8)

under the Grant Agreement FP7-ICT-318632.


Recommended