1 Welcome to our Clients and Cooperation Partner From the Steinmüller Team
Transcript
Page 1: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

1

Welcome to our Clients and Cooperation Partner

From the Steinmüller Team

Page 2: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

2

AGENDA FOR THE 3rd STEINMÜLLER CONFERENCE09:45 Welcome address by the Managing Directors Dr. Hans-Ulrich Thierbach & Shinichi Takano10:10 Welcome address by the First Deputy Mayor and

Treasurer of the City of GummersbachRaoul Halding-Hoppenheit

10:20 The Engineers Company - your solution provider Lutz Brandau, (SE)10:45 Coffee break11:15 PS Matla LNB design - challenges and extraordinary

boundary conditionsDr. Zajac, (SE)

11:45 PS Weisweiler Unit G - modifi cation of a lignite combustion system to meet challenging BREF regulations

Rainer Hesse, RWE Power AG, Anojan Santhirasegaran, (SE)

12:15 Lunch break13:30 PS Schkopau - mercury reduction measures –

experiences and resultsSylvio Sauer, Power Station Schkopau, Uniper, Dr. Dorian Rasche, (SE)

14:00 GKM Unit 8 - Steinmüller tray installation-a proper solution for improvement of atwo-loop absorber performance

Andreas Geier, Grosskraftwerk Mann-heim AG, Dr. Stefan Binkowski, (SE)

14:30 Coffee break15:00 Application of CFD for optimization of waste heat boilers Waldemar Hoffmann, (SE)15:30 Challenges and solutions on a revamp of a refi nery boiler Sina Partoshoar, (SE)16:00 Coffee break16:30 PS Duvha unit 3 – rehabilitation of a 600 MW coal-fired

unitArmin Martz, (SE)

17:00 High temperature storage systems as contribution to the „Energiewende“

Dr. Thomas Bauer, Deutsches Zentrum für Luft- und Raumfahrt e.V., Benedikt Tressner, (SE)

17:30 Summary Tetsuya Iwasaki17:45 Steinmüller Engineering awards 2019 - the winners Prof. Bartz-Beielstein, TH Köln18:15 Closing words and Invitation for Dinner Dr. Sigfrid Michelfelder

Page 3: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

Steinmüller Engineeringan IHI Group Company

Yesterday – Today – Tomorrow

Speaker: Dr. Hans-Ulrich ThierbachShinichi Takano

Rely on good experience with

The Engineers Company

Page 4: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

4

Table of Contents

1 Company History

2 Facts about the Status Today

3 Strategy for the Future

4 Cooperation as IHI Group Company

5 Challenges for the next 3 years

Nice Picture

Page 5: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

5

History – Steinmüller Engineering Based on History of L. & C. Steinmüller as Boiler Supplier

1872L&C SteinmüllerGmbH was legallyfounded byLebrecht andCarl Steinmüller

1997

L&C Steinmüller‘smost successfulyear with 5,650 staff, sales of 1.74 billion and net income before tax of 79.2 million Deutsche Mark

1995

Steam Boiler construction (Boiler Height 160m; Steam Temp 580°C; Pressure 285 atm; Steam Quantity 2428 t/h

2002

Babcock insolvent, consequently the fall of L&C Steinmüller GmbH. Successorcompanies arose,

1999

Acquisition of L&C SteinmüllerGmbH byDeutsche Babcock AG.

2003 - 1st Contract: Engineering Services for Iskenderun, Turkey

2004 - 1st

Bituminous coal SMV - LNB for Altbach CHP2

2005 - 1st Lignite RSM - LNB for Jänschwalde PS

200960% shares acquired by Siemens AG.

2012Remaining 40% shares acquired by Siemens AG.

2015 - Maritsa 3 – EPC Lignite Low-NOx-Firing Retrofit2017 - Paroseni - FGD retrofit 2016 - Stanari – consultancy for a power plant to be realised by the customer2009 - Albbruck - 1st EPC for Low-NOx-Firing System 2009 - Hemweg – 1st FGD revamp2013 - Chalampe first new heat exchanger supplied

2014100% shares acquired by

IHI Corporation

1874

L&C SteinmüllerGmbH built the firststeam boiler.

1.5 meters high and max. steampressure of 3 atm

2003Establishment of Steinmüller Engineering First Owner Great Grandsons of Carl SteinmüllerNot the legal successor ofL&C Steinmüller, but theSteinmüller name continued.

2006 - first EscomContract Review activities for Medupi & Kusile

2014 - 1st LowNOX-Burner retrofit with Eskom in Camden PS

2016 – Boiler-Reengineering of a 600 Mwel Unit in Duvha

1. Company History - General Information

2018

15th

Anniversary of SteinmüllerEngineering

1st 2nd 3rd

Since 2016Development of New Busenss areas

Thermal applications for Industrial processes

Application driven by `Energiewend´ConsultingStorage solutions

SE-Conference

Page 6: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

6

1. Company History – Steinmüller Conferences

Conclusion: Next SE-Conference in three or four years

First SE Conference Wiehl 201357 international Guests

Second SE Conference Gummersbach 201665 International Guests

Positive Feedback concerning Conference and Development of Steinmüller Engineering

Page 7: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

7

1. Company History-15thAnniversary Steinmüller Engineering

• Contribution of Donations for Kindergarten playground

Page 8: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

8

Business Development

After Sales

QA/QC

Control BoardIwasaki, Awano

Board of DirectorsTakano, Dr. Thierbach

Operations

Kriegeskotte

Project Management

Field Services

Finance & Controlling

IT

ConsultingMarketing &

ProposalsBrandau

Consulting(Owners Engineering)

Russian Representation

Process FC

Design FC

Process SG

Design SG

Steam Generation

Dr. Ernst

Commercial Administration

(CFO)Hohnschopp

Proposals FC

Proposals SG

Proposals CS

CFB-Systems

Process CS

Design CS

Combustion Systems

Dr. Hamel

Flue Gas Cleaning

Trautner

HR

Contract Management

Commercial Project Management &Procurement

SESABranch South

Africa

Technical CoordinationProcess

Will

Technical CoordinationDesign

Schadow

2. Steinmüller Engineering Organization

Page 9: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

9

With the short FY 2015/16 (Oct.15-March16) SE changed to IHI FY StandardFY 2016 is running from 1st April 2016 till 31st March 2017

0,0

5,0

10,0

15,0

20,0

25,0

30,0

35,0

40,0

FY2014 FY2015 FY2016 Short FY2016 FY2017 FY2018

Order EntryRevenueM

io. E

UR

Equivalent for 12 months period

2. Facts about Steinmüller Engineering Today

0

20

40

60

80

100

120

140

FY2014 FY2015 FY2016 Short FY2016 FY2017 FY2018

Total HCTotal FTEEngineers HCEngineers FTE

Num

bero

fEm

ploy

ees

Page 10: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

10

Brazil

Nigeria

Hungary

Bulgaria

Iran

Ecuador

France

India

Poland

Czech Republic

Kasachstan

Serbia

Indonesia

Japan Sri Lanka

Russia

South Africa

Tunesia

Pakistan

Kyrgyzstan

GermanyTurkey

Uzbekistan

Romania

2. Facts about the Status Today - 24 nationalities

Page 11: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

11

2. Global Activities and Markets with Focus on Europe & Africa

ESP-Projects- Govora # 7 (ROM)

LTSA-Jorf Lasfar 5;6TAQA Morocco

LNB*-Projects (bituminous)

- HKW II (GER)- Herne #4 (GER)- Astana (KAS)

SCR-Projects

- Shell unit 6 (GER)

Eskom Activities (RSA)- Hendrina LTE Studie- FGD engineering- DeNOx fleet assessment- DeSOx fleet assessment- LNB-burner engineering- Boiler rehabilitation Duvha- Medupi FGD engineering- Other professional services

LNB-Projects (Lignite)

- ME III (BLG)- Kostolac (SER)- Agios Dimitrios

(GR)

CPC*- Yara Trinidad

Consulting- Stanari (BOS)

CFBMartech / Vietnam

FGD- Paroseni (ROM)

Concept StudyWaiGaoQiao, China

*LNB: Low Nox Burner *CPC: Chemical Plant Components

Page 12: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

12

3. Strategy for the Future – What do we want to develop into?

Our Vision

Steinmüller Engineering GmbH is the unique technology partner for globally operating thermal processing industries and related OEM's. By providing our partners with advanced technologies and pioneering energy supply solutions, we jointly contribute to a more sustainable future.

– Thermal processing Industries• Power ( Biomass; Solar; Waste Fuels; Fossil Fuels )• Heat ( District; Waste; Solar; Storage; etc. )• Industrial thermal applications in

Refineries; Chemistry; Cement: Pulp Paper; GlassWaste Incineration; Metallurgical Industry; etc.

Page 13: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

13

IHI-Group company since 5 years (2014 -2018)After IHI has acquired SE, following developments were achieved

1. Integration of SE to IHI Group company has been completed.

All IHI Group policy has been applied to SE internal management manual All SE division managers have travel to IHI HQ to make direct relation ship SE has started human exchange program with IHI HQ from FY2018

(Ms. Blechmann internship in IHI HQ) SE has started networking activity between IHI affiliates company each other

(IHI Europe Ltd., Jurong Engineering, IHI E&C, IHI Plant Construction etc.)

IHI President Mr.Mitsuoka visited SESE Internship Ms.Blechmann in Tokyo

4. Cooperation as IHI Group Company

Page 14: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

14

News from IHI-Group since last conference in Energy sector

2016 May :Jointly established Nanatsujima Biomass Power Limited Liability Company for operating the woody biomass power plant with 8 partners.

2017 August :Orders Awarded for Construction of Thermal Power Plant (600MW x 2 Bituminous Coal fired boiler ) and Port in Bangladesh

2017 August :IHI and NEDO Completes World’s First 100kW Class Demonstration Test of Ocean Current Power Generation

2017 November IHI to Implement Pilot Scale Experiment of Algae Mass Cultivation for Biofuel in Thailand

2018 March : IHI conducted pilot scale Ammonia co-combustion test with coal at IHI’s combustion facility (10MWth)

2018 November :Expansion of solid biomass fuel business utilizing palm waste -Contributing to the Malaysian palm industry and promoting renewable energy .

4. Cooperation as IHI Group Company

Page 15: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

15

Source: https://www.ihi.co.jp/

Ocean Current Power Generation Demonstration testCapacity: 100kWWater Depth:100mCurrent velocity:1.5m/s

2017 August :IHI and NEDO Completes World’s First 100kW Class Demonstration Test of Ocean Current Power Generation

4. Cooperation as IHI Group Company

Page 16: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

16

Source: https://www.ihi.co.jp/

(Pilot Scale test for Bio jet fuel from micro algae)

(10,000m2)

2017 November IHI to Implement Pilot Scale Experiment of Algae Mass Cultivation for Biofuel in Thailand

4. Cooperation as IHI Group Company

Page 17: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

17

1kW Fuel Cell with Ammonia fuel2000kW Gas Turbine with Ammonia fuel

10MWth Coal co-firing with Ammonia fuel

Source: https://www.ihi.co.jp/

IHI try to establish green ammonia value chain under support of SIP program which financed by Japanese Government.

2018 March : IHI conducted pilot scale Ammonia co-combustion test with coal at IHI’s combustion facility (10MWth)

4. Cooperation as IHI Group Company

Page 18: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

18Source: https://www.ihi.co.jp/

IHI Solid Biomass Malaysia SDN.BHDNovember 2018

2018 November :Expansion of solid biomass fuel business utilizing palm waste -Contributing to the Malaysian palm industry and promoting renewable energy .

4. Cooperation as IHI Group Company

Page 19: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

19

Common activities between SE and IHI

Development New Burner\1) TBK (Pre dried Lignite) Burner development

Development New Burner2) IHI New Low Nox Burner development

Development New Burner and optimization with Furnace3) CFD analysis with IHI New Low Nox Burner at 1000MW Boiler with optimize side airport

4. Cooperation as IHI Group Company

Page 20: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

20

Common activities between SE and IHIExpand After Sales business 1) Trianel Luenen (TKL)

SE is acting as window to TKL for IHI’s boiler warranty work and maintenance support.

Expand After Sales business 2) Moroccan Market

IHI expects SE will expand our after sales business to Moroccan Market because of 4 IHI’s boiler were installed and needs OEM quality maintenance which SE can provide.

4. Cooperation as IHI Group Company

Page 21: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

21

Common activities between SE and IHIPiping Engineering New Boiler Project (Indonesia)July 2016- April 2017

Energy Storage Business developmentSE and IHI conducting co-work to develop European Client and partner for Thermal storage system.

CFB standard design developmentSE and IHI are working together to develop standard biomass firing CFB design.

4. Cooperation as IHI Group Company

Page 22: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

22

Developing after sales activity in Morocco starting for IHI’s boiler

To be a major player in mercury removal business in Europe

Increasing industrial application

Development of new product application

Developing new business opportunities in Digitalization application

In addition to keep current business field, SE would like to expand our business during coming 3 years by doing following activity.

5. Challenges for the next 3 years - plan FY2019 FY2020 FY2021

Page 23: From the Steinmüller Team · PS Duvha unit 3 – rehabilitation of a 600 MW coal -fired unit. Armin Martz, (SE) 17:00; High temperature storage systems as contribution to the

23

Thank you for your attention