FY 2017-2022 ROADWAYS CIPCITY COUNCIL BRIEFING
MARCH 8, 2016
I. Requested FY 2017-2022 CIP
II. Recent Accomplishments
III. HB 2
IV. CIP Project Detail Sheets Fully Funded Projects in CIP
V. Existing Projects with Balances to Complete (BTC)
VI. Requested – Not Funded Projects
OVERVIEW
2
I. REQUESTED FY 2017-2022 CIP
3
Summary▪ 38 CIP Projects and 10 Programs▪ 1 New Project; 2 New Phases of 2 Existing Projects▪ 6-Year Funding
City Funding - $336.0M* State Funding - $205.3M Federal Funding - $ 11.2M Total - $552.5M
*Light Rail City Funding (Buses, Shared-Use Path, Transit Extension) - $159.8M
▪ Total Project Cost - $1.3B▪ All Projects Previously Fully Funded are Still Fully Funded
REQUESTED FY 2017-2022 CIP
4
REQUESTED FY 2017-2022 CIP
5
29%
52%
7%5% 7%
Congestion Relief & CapacityImprovement Projects - $97.0M
Special Programs & Projects -$174.9M
Safety Improvement Programs -$24.4M
Bridge Projects - $17.9M
Maintenance Programs & Projects -$21.8M
Total City Funding in Years 1-6: $336.0M
REQUESTED FY 2017-2022 CIP
Major Programs in the CIP
▪ Street Reconstruction II▪ Major Bridge Rehabilitation II
6
New Projects in the FY 17 CIP
▪ Elbow Road Extended Phase II-B▪ Indian River Road Phase VII-A▪ Nimmo Parkway VII-B
REQUESTED FY 2017-2022 CIP2016 City Council Workshop Major Projects▪ Centerville Turnpike, Phases II and III▪ Burton Station▪ Seaboard Road Lighting▪ Wesleyan Drive Lighting▪ Princess Anne Road/Kempsville Road Intersection▪ Lesner Bridge▪ Indian River Road/Kempsville Road Intersection▪ Witchduck Road, Phase II▪ Lynnhaven Parkway, Phase XI▪ Holland Road, Phase VI▪ Shore Drive Corridor Improvements, Phase III▪ Greenwich Flyover▪ I-64/I-264, Phase I▪ Princess Anne Road, Phase VII▪ Laskin Road Bridge Replacement▪ Pacific Avenue Improvements
7
II. RECENT ACCOMPLISHMENTS
8
UNDER CONSTRUCTION
▪ Holland Road Phase VI▪ Lesner Bridge Replacement▪ Lynnhaven Parkway Phase XI▪ Pacific Avenue – Phase II▪ LED Streetlightso Nimmo Parkway Phase V-Ao Princess Anne Road/Kempsville Road Intersection
9
o Started Construction –November 2014
o Approximately 20% Complete
o Complete Construction –October 2017
o Total Project Cost –$59.6M
HOLLAND ROAD PHASE VICIP 2-158
10
o Started Construction –June 2014
o Approximately 53% Complete
o Complete Construction –August 2017
o Total Project Cost –$119.5M
LESNER BRIDGE REPLACEMENTCIP 2-168
11
o Started Construction –January 2014
o Approximately 50% Complete
o Complete Construction –December 2016
o Total Project Cost –$39.8M
LYNNHAVEN PARKWAY PHASE XICIP 2-167
12
o Started Construction –October 2014
o Complete Construction –April 2017
o Total Project Cost –$17.3M
PACIFIC AVENUE IMPROVEMENTS CIP 2-045
13
o Nimmo Parkway Phase V-A
o Princess Anne Road/Kempsville Road Intersection
LED STREETLIGHTS
14
III. HB 2
15
HB 2
▪ Passed by General Assembly in 2014
▪ Data-Driven Scoring Process
▪ Process Used for FY 17
▪ Projects Approved by CTB in June 2016
16
HB 2 SCORING SUMMARY
321 Applications Submitted Statewide 34 Screened Out 287 Applications Scored $7.0B Total Requested $883M HB2 Funding Available
City of Virginia Beach Submitted Centerville Turnpike Phase III Indian River Road Phase VII-A Laskin Road Bridge Replacement Elbow Road Extended Phase II-B
17
HB 2 HAMPTON ROADS
18
Project Applicant FundingGeneral Thomas Highway Signalization Project Southampton $650,000 Route 10/58 Godwin Boulevard Park and Ride Lot Suffolk $603,594 U.S. 58 Corridor Intersection Capacity & Safety Improvements City of Norfolk $2,336,605 Warwick Boulevard over Lake Maury Bridge Replacement City of Newport News $1,240,076 Coliseum Drive Extension City of Hampton $2,823,000 Norfolk Traffic Control System Platform Upgrade City of Norfolk $3,000,000 Centerville Turnpike - Phase III City of Virginia Beach $6,000,000 U.S. Route 17 at U.S. 258 Intersection Capacity Improvements County of Isle of Wight $4,270,000 Laskin Road Bridge Replacement City of Virginia Beach $10,000,000 Atkinson Boulevard City of Newport News $7,700,726 Little Back River Rd Reconstruction w/New Peak Alt-Dir Lane City of Hampton $9,270,000 Longhill Road Improvements - Route 199 to Olde Towne Road County of James City $18,029,136 US Route 17/Shoulders Hill Intersection (UPC 69050) Suffolk $14,662,049 Nike Park Road Extension from Reynolds Drive to US Route 17 County of Isle of Wight $11,658,000 I-64/Northampton Boulevard Interchange Modifications City of Norfolk $9,300,000 Route 602 Lee Street/Cemetery Road- Accomack County County of Accomack $3,198,323 Deep Creek Atlantic Intracoastal Waterway Bridge Replacement City of Chesapeake $20,000,000 U.S. Route 58 Corridor Improvement Project Suffolk $39,588,000 Indian River Road Phase VII-A City of Virginia Beach $20,000,000
HB 2 TIMELINE▪ July 2015 – Early coordination with VDOT/DRPT on Candidate
Projects ▪ August 2015 to September 2015 – Solicit Candidate Projects ▪ September 30, 2015 – Deadline for Submitting Project Applications ▪ October 2015 to January 2016 – Screen and Evaluate Projects ▪ January 19, 2016
Project scores released and presented to CTB HB2 Recommended Base Funding Scenario presented to CTB
▪ February to April 2016 – CTB to consider evaluated projects for inclusion in SYIP
▪ April 20, 2016 – CTB to release Draft SYIP ▪ April to May 2016 – Public hearings on Draft SYIP ▪ June 2016 – CTB to adopt Final SYIP
19
IV. CIP PROJECT DETAIL SHEET
20
FULLY FUNDED PROJECTS IN CIP
BUS STOP INFRASTRUCTURE AND ACCESSIBILITY IMPROVEMENTSCIP 2-094 • Shelters• Benches• Sidewalks• Trashcans• ADA Access Ramps• Increase Accessibility and
Connectivity• Improve Safety
21
Average $311K/year
BUSES FOR VIRGINIA BEACH TRANSIT EXTENSIONCIP 2-093
• 12 Transit Buses • Feeds “the Tide” Light Rail
System• Improved Weekend Service• Longer Spans of Service• New Feeder Bus Route
Between Witchduck Road and the Greenbrier Area
22
Total Project Cost: $3.6M
CENTERVILLE TURNPIKE – PHASE IICIP 2-409
• 4-Lane Divided Highway from Indian River Road to Kempsville Road
• Design Underway; 90% Complete
• Utility Relocations –Overhead
• Potential Noise Barriers• Start Construction –
July 2018• Complete Construction –
November 2020
23
Total Project Cost: $38.2M
CENTERVILLE TURNPIKE –PHASE IIICIP 2-419
• 4-Lane Divided Highway from Kempsville Road to the Chesapeake City Line
• HB2 Funding –$6M Requested
• Start Construction –July 2021
• Complete Construction –August 2023
24
Total Project Cost: $30.1M
ELBOW ROAD EXTENDED –PHASE II-BNew Project
• 2 Through Lanes on Ultimate 4-Lane Right of Way from Meadow Crest Way/Margaret Drive to the Chesapeake City Line
• Approximately 1.2 miles• 8-ft Sidewalk• 4-ft On-Road Bike Lanes• Noise Barriers• New 2-Lane Bridge• HB2 Candidate Project• Start Construction –
September 2018• Complete Construction –
December 2020
25
Total Project Cost: $37.6M
FERRELL PARKWAY CIP 2-054
• 6-Lane Divided Roadway from Indian Lakes Blvd to Indian River Road
• Ranks #3 in Volume/Capacity• Turn Lanes• New Mast Arm Signal• Bike/Pedestrian
Accommodations• Start Design –
July 2017• Start Construction –
July 2020
26
Total Project Cost: $3.5M
FIRST COLONIAL RD / LASKIN ROAD INTERSECTION IMPROVEMENTSCIP 2-030
• Additional Westbound Left Turn Lane
• Mast Arm Signals• Ranks #6 for Over-Capacity
intersections• Start Construction –
July 2022• Complete Construction –
July 2023
27
Total Project Cost: $1M
FIRST COLONIAL RD / VIRGINIA BEACH BLVDINTERSECTION IMPROVEMENTSCIP 2-072
• Improvement of Intersection Including Turn Lanes and Signalization Upgrades
• Currently in Site Acquisition; Approximately 60% Complete
• Utility Relocations –Overhead; Underground at Intersection
• Start Construction –May 2017
• Complete Construction –May 2020
28
Total Project Cost: $29.9M
GREENWICH ROAD CROSSOVER &CLEVELAND STREET IMPROVEMENTS –PHASES I & II, CIP 2-401 • Component of VDOT’s
I-64/I-264 Interstate Project• Phase IA
• Pipe Existing Open Channel• New BMP• Construct Access Road• Expand Parking Lots for Impacted
Properties• Construction Complete
• Phase IB & II• Relocate Cleveland St/Clearfield
Ave Intersection; New Signal• Expand Parking Lot for Impacted
Property• Design Underway; 90% Complete• Start Construction – October 2016• Complete Construction –
March 2017
Total Project Cost: $11.4M
29
I-264/WITCHDUCK INTERCHANGE • VDOT Interstate Project• 2nd Phase of I-64/I-264 Interstate
Project• CD Road Will Access Newtown
Road Interchange• New Flyover to Connect
Greenwich Road and Cleveland Street
30
• Widened Ramps at Newtown Road and Witchduck Road Interchanges
• Start Construction –June 2017
• Complete Construction –June 2021
Total Project Cost: $190M
HOLLAND ROAD –PHASE VICIP 2-158
• 4-Lane Divided Highway from Dam Neck Road to Nimmo Parkway
• Currently in Construction• Utility Relocations –
Overhead• VDOT Administered• Started Construction –
November 2014• Complete Construction –
October 2017
31
Total Project Cost: $59.6M
INDIAN RIVER ROAD / KEMPSVILLE ROADINTERSECTION IMPROVEMENTS CIP 2-418 • Indirect Left Turns on
Kempsville Road• Median U-Turn Lefts on
Indian River Road• Currently in Site Acquisition;
approximately 30% complete• Utility Relocations –
Overhead• Start Construction –
August 2016• Complete Construction –
February 2018
32
Total Project Cost: $19.6M
INDIAN RIVER RD –PHASE VII-ANew Project
• 2 Through Lanes on Ultimate 4-Lane Right of Way from Lynnhaven Parkway to Elbow Road
• Approximately 2.6 miles• Currently in Site Acquisition;
Approximately 5% Complete• HB2 Funding - $20M
Requested• Start Construction –
November 2019• Complete Construction –
July 2022
33
Total Project Cost: $48M
LANDSTOWN ROAD IMPROVEMENTS –PHASE ICIP 2-050
• Widen Landstown Road to 4-Lane Undivided, from Sportsplex Drive to the Bend
• Approximately 0.6 Miles• Bike Accommodations• Asphalt Path• Provide Access to the
Proposed Baseball Complex• Utility Relocation –
Underground Distribution Line• 60% Design• Start Construction –
August 2017• Complete Construction –
August 2018
34
Total Project Cost: $7.3M
LASKIN ROAD BRIDGE REPLACEMENTCIP 2-040 • VDOT-Managed project• Built in 1938• Structure has exceeded
useful life• Sufficiency rating – 40.3• Deck and Beam Deterioration• HB2 Funding - $10M
Requested• Design 90% Complete• Start Construction –
August 2018• Complete Construction –
February 2021
35
Total Project Cost: $21.2M
LESNER BRIDGE REPLACEMENTCIP 2-168
• Start Construction –June 2014
• Complete Construction –August 2017
36
Total Project Cost: $119.5M
LIGHT RAIL CORRIDOR SHARED-USE PATH CIP 2-108
• Along Norfolk-Southern R/W in Conjunction with Light Rail Extension Project
• Approximately 3 miles• 12-ft Wide• Start Construction –
July 2017• Complete Construction –
December 2019
37
Total Project Cost: $17.7M
LYNNHAVEN PARKWAY PHASE XICIP 2-167
• 4-Lane Divided Highway from Indian River Road to Centerville Turnpike
• VDOT Administered• Utility Relocations –
Underground• Construction –
Approximately 50% Complete• Complete Construction –
December 2016
38
Total Project Cost: $39.8M
NEWTOWN ROAD / BAKER ROADINTERSECTION IMPROVEMENTSCIP 2-037
• Improve Safety• Reduce Congestion• Additional Turn Lanes• Intersection Reconfiguration• Start Design – July 2020
39
Total Project Cost: $1M
PACIFIC AVENUE IMPROVEMENTS –CIP 2-045
• Improvements Between 15th Street to 23rd Street
• New Sidewalk, Curb and Gutter, and LED Streetlights
• Currently Under Construction (Season 2) – Private Utility Companies
• Complete Construction (Season 3) – April 2017
40
Total Project Cost: $17.3M
PLEASURE HOUSE ROAD STREET IMPROVEMENTS –PHASE ICIP 2-056
• Street and Safety Improvements from Northampton Blvd to Shore Drive
• New Curb and Gutter• Pavement Rehabilitation• Storm Drainage• Bike Accommodations• Concrete Sidewalk• Start Design – July 2020
41
Total Project Cost: $1.2M
PLEASURE HOUSE ROAD STREET IMPROVEMENTS –PHASE IICIP 2-057
• Street and Safety Improvements from Shore Drive to Lookout Road
• Pavement Rehabilitation• Storm Drainage• Bike Accommodations• Concrete Sidewalk• Start Design – July 2019
42
Total Project Cost: $2.9M
PRINCESS ANNE ROAD – PHASE VII CIP 2-195
• 4-Lane Divided Roadway from General Booth Blvd to Fisher Arch
• Improvements at the Intersections of General Booth Blvd, Elson Green Ave, and Upton Drive/Sandbridge Road
• Design is 95% complete• Currently in Site Acquisition;
Approximately 50% Complete
• Utility Relocations –Overhead
• Start Construction –July 2017
• Complete Construction –July 2019
43
Total Project Cost: $40.1M
PROVIDENCE ROAD SIDEWALKCIP 2-058
• Street and Pedestrian Improvements from Kempsville Road to the Intersection of Indian Lakes Blvd and Churchill Drive
• New Curb and Gutter• 5-ft Concrete Sidewalk• Start Design – July 2020
44
Total Project Cost: $1.1M
ROSEMONT ROAD –PHASE VCIP 2-038
• 4-Lane Divided Roadway Between Lynnhaven Parkway and Dam Neck Road
• Reduce Congestion• 60% Design• Utility Relocations –
Existing Underground• Start Construction –
September 2017• Complete Construction –
September 2019
45
Total Project Cost: $15.8M
SANDBRIDGE ROAD BRIDGE REPLACEMENTCIP 2-416
• New Bridge Over Hells Point Creek
• Sufficiency rating – 35.2• Rated as “FAIR” Due to Deck
and Beam Deterioration• 60% Design• Start Construction –
July 2018• Complete Construction –
June 2020
46
Total Project Cost: $8M
SHIPPS CORNER ROADCIP 2-414
• Improvements from Skylark Drive to Approximately 900-ft from London Bridge Road
• Left Turn Lane• Geometric Improvements• Pedestrian Improvements• Design – 100% Complete• Start Construction –
January 2017• Complete Construction –
September 2017
47
Total Project Cost: $2.3M
SHORE DRIVE CORRIDORIMPROVEMENTS –PHASE III CIP 2-117
• No Capacity Expansion –Retains 4 Lanes from Vista Circle to North Great Neck Road
• Includes Safety Improvements, Edge Treatments, and Shared-Use Paths
• Currently at 60% Design• Utility Relocations –
Overhead; Undergrounding at Signalized Intersections
• Start Construction –May 2018
• Complete Construction –May 2020
48
Total Project Cost: $16.6M
STREET RECONSTRUCTION II CIP 2-026
• Design and Reconstruction of 1 to 3 Streets Per Year
• As Funding Allows• Streets Have Reached the
End of Their Service Life• Maintenance is No Longer
Effective
49
Average Funding: $1.8M/year
Accomplishments• VB Blvd & Thalia Road• Indian River Road & Reon Drive • Indian River Rd. & Princess
Anne Road• Northampton Blvd.• Indian River Road & N. Landing
Scheduled/Underway• Shore Drive• Kempsville Rd. & Centerville
Turnpike • Witchduck Rd. Underpass• Independence Blvd. &
Pembroke Blvd.
VB/Thalia
Indian River/Reon
Indian River/N. Landing
▪ This program provides for modification of existing roadways by constructing turn lanes and bypass lanes, realignment of existing roadways, installing traffic signals, installing guardrails, installing sidewalks, removing visual obstructions, and various other traffic safety improvements.
▪ Active projects in the program:
TRAFFIC SAFETY IMPROVEMENTS
50
Average Funding: $2.6M
Cypress Avenue Sidewalk Mediterranean Avenue Sidewalk Wolfsnare Road Sidewalk Phase I Dam Neck Road/General Booth
Blvd Intersection Improvements
Kendall Street Sidewalk Greenwell Road Sidewalk Shore Drive Bike Facility Eaglewood Drive Sidewalk Buckner Blvd Shared-Use Path
UPTON DRIVE EXTENSION/DAM NECK STATION IMPROVEMENTS CIP 2-047
• Left Turn Lane on SB General Booth Blvd
• Left Turn Lane on Dam Neck Station Road at General Booth Blvd
• New Traffic Signal at General Booth Blvd/Dam Neck Station Road Intersection
• Upgrade Existing Traffic Signal at Upton Drive/Dam Neck Road Intersection
• Supports the Dam Neck Station Development
• Cost Participation with Developer
• Construction Start – July 2016
• Construction Complete –March 2017
51
Total Project Cost: $1.3M
VIRGINIA BEACH TRANSIT EXTENSION PROJECT CIP 2-092• Design-Build Project• Extend “The Tide” from the
Newtown Station/Norfolk Virginia Beach City Line to Town Center
• Start Construction –July 2017
• Complete Construction –December 2019
52
Total Project Cost: $310M
WEST NECK ROAD –PHASE IVCIP 2-088
• 2-Lane Un-Divided Parkway From Kellam High School to King’s Landing Development Entrance
• 4,850 linear feet• On-Road Bicycle
Accommodations• Shared-Use Path• Cost-Participation Agreement
being Developed• Construction Start –
August 2018• Construction Complete –
August 2019
53
Total Project Cost: $12M
WITCHDUCK RD –PHASE IICIP 2-025
• 6-Lane Divided Highway from I-264 to Virginia Beach Boulevard
• Currently in Site Acquisition; Approximately 95% Complete
• Utility Relocations –Underground Duct Bank
• Start Construction –August 2016
• Complete Construction –December 2018
54
Total Project Cost: $60.6M
Title CIP Number Budget
Citywide Street Lighting Improvements 2.160 $60K/yearRural Road Improvements 2.024 $200K/yearSoutheastern Parkway & Greenbelt 2.089 $23.5M TPCTraffic Signal Rehabilitation 2.410 Average $217K/yearTransportation Network Modeling and Analysis Projects 2.176 Average $150K/year
Various Cost Participation Projects 2.027 $25K/yearWetlands Mitigation Banking 2.028 $100k/year
OTHERS
55
V. EXISTING PROJECTS WITH BALANCES TO COMPLETE (BTC)
56
Projects in CIP with a BTC
EXISTING PROJECTS WITH BTC
57
Project Unfunded Amount1. Greenwich Road Crossover/Cleveland Street Improvements Phase III $ 4,565,000 2. Indian River Rd/Princess Anne Rd Intersection Improvements $ 6,521,937 3. Laskin Road Phase I $ 66,929,678 4. Laskin Road Phase II $ 10,231,642 6. Nimmo Parkway Phase II $ 33,961,739 7. Nimmo Parkway VII-B $ 26,817,620 8. Princess Anne Road Phase VII-A $ 7,678,702 9. Sandbridge Road - Nimmo VII-A $ 17,729,684
Total $174,436,002
GREENWICH RD CROSSOVER &CLEVELAND ST IMPROVEMENTS PHASE IIICIP 2-401
• Improve Cleveland Street from Clearfield Avenue Intersection to Witchduck Road Intersection
• Improvements Include:
Re-Striping
Sidewalk
Shared-Use Path
58
Total Project Cost: $4.9M
INDIAN RIVER RD /PRINCESS ANNE RD INTERSECTION IMPROVEMENTSCIP 2-422• Intersection Improvements at
the Princess Anne Road/ Indian River Road Intersection
• Increase Capacity
59
Total Project Cost: $6.8M
LASKIN ROAD –PHASE ICIP 2-156
• 8-Lane Divided Highway With Continuous Right Turn Lanes from Republic Road to Winwood Drive and 6-Lane Divided Highway to Oriole Drive
• VDOT Administered (Last Legacy Project)
• Site Acquisition is Complete• Utility Relocation (Overhead)
Underway, Scheduled Completion –December 2016
60
Total Project Cost: $103.2M
LASKIN ROAD –PHASE IICIP 2-165
• 6-Lane Divided Highway from Oriole Drive to the 31st/30th Street Split
• Conceptual Design Complete
61
Total Project Cost: $11.6M
MAJOR BRIDGE REHABILITATION II CIP 2-022
• Rehabilitation of Bridges, Culverts and Overpasses
• Average Annual Funding -$1.6M/year
• 14 Bridges Functionally Obsolete
• 3 Bridges Structurally Deficient
• Short Term Maintenance Needs Long Creek Bridge Rehab -
$1M
Pungo Ferry Bridge Rehab -$3.5M
62
After
Before
Elbow Road Bridge Superstructure Replacement
Pungo Ferry Bridge Fender Repairs
NIMMO PARKWAY PHASE IINew Project
• New Roadway Connecting Nimmo Pkwy from West Neck Road to Future Landstown Road – Phase III
• Approximately 1.3 miles• 4-Lane Divided Parkway• On-Road Bike Lanes• Shared-Use Path
63
Total Project Cost: $34.2M
NIMMO PARKWAY PHASE VII-BNew Project
• New Roadway Connecting Nimmo Pkwy to Sandbridge Road
• 2-Lane Undivided Roadway from Albuquerque Drive to Western Terminus of SB Road-Nimmo Parkway Phase VII-A
• Paved Shoulders• On-Road Bike Lanes• Shared-Use Path
64
Total Project Cost: $27.8M
PRINCESS ANNE ROAD PHASE VII-A CIP 2-033
• Safety Improvements from Sandbridge Road to Seaboard Road
• Design underway –15% complete
65
Total Project Cost: $8.0M
SANDBRIDGE RD –NIMMO VII-ACIP 2-078
• Construction of Ultimate Sandbridge Road – Nimmo VII-A from Sandpiper Road to Approximately 1-mile West of Sandpiper Road
• 2 Lane Roadway with Shoulders
• On-Road Bike Lanes• Shared-Use Paths• Design – 30% Complete• Environmental Permit
Application Submitted
66
Total Project Cost: $19.5M
VI. REQUESTED – NOT FUNDED PROJECTS
67
Others
REQUESTED – NOT FUNDED PROJECTS
68
Project Unfunded Amount1. Atlantic Avenue Traffic Signal Pole Replacements $ 1,750,000 2. Dam Neck Road - Phase I $ 30,680,978 3. Dam Neck Road - Phase II $ 25,388,801 4. Drakesmile Road Extended $ 15,335,020 5. Elbow Road Extended Phase II-C $ 24,834,140 6. Elbow Road Extended Phase II-D $ 27,273,630 7. Holland Road/Rosemont Road Intersection Improvements $ 56,585,0008. Shore Drive Corridor Improvements-Phase IV $ 12,758,721 9. Landstown Road Phase II $ 18,886,000 10. Landstown Road Phase III $ 12,817,000 11. Landstown Road Phase IV $ 18,000,00012. Nimmo Parkway Phases II & III $ 56,205,000 13. Salem Road Extended $ 35,614,000 14. West Tournament Drive $ 3,349,000
Total $339,477,290
DISCUSSION
69
ATLANTIC AVE TRAFFIC SIGNAL POLE REPLACEMENTS• Replacement of Deteriorating
Traffic Signal Poles and Mast Arms at 7 Intersections on Atlantic Avenueo 31st Streeto 22nd Streeto 21st Streeto 19th Streeto 17th Streeto 9th Streeto 5th Street
70
Total Project Cost: $1.75M
DAM NECK ROAD –PHASE I
• 6-Lane Divided Highway from Princess Anne Road to Holland Road
• Reduce Congestion• Existing Volume 44,800 vpd• Ranks #8 in Volume/Capacity
71
Total Project Cost: $30.7M
DAM NECK ROAD –PHASE II
• 6-Lane Divided Highway from Holland Road to Drakesmile Road
• Reduce Congestion• Existing Volume 42,100 vpd• Ranks #21 in
Volume/Capacity
72
Total Project Cost: $25.4M
DRAKESMILE ROAD EXTENDED
• New Road from Dam Neck to Holland Road
• 3,050 feet• 4-Lane Divided Roadway
73
Total Project Cost: $15.3M
ELBOW ROAD EXTENDED –PHASE II-C
• 2 Westbound Lanes of Phase IIB Project from Meadow Crest Way/Margaret Drive to the Chesapeake City Line
• 4 Lane Section from Meadow Crest Way/Margaret Drive to Salem Road
• Approximately 1.5 miles• 8-ft Sidewalk• 4-ft On-Road Bike Lanes• New 2-Lane Bridge
74
Total Project Cost: $24.8M
ELBOW ROAD EXTENDED –PHASE II-D
• 2 Westbound Lanes from Salem Road to VB Amphitheater
• Approximately 1.2 Miles• 8-ft Sidewalk• 4-ft On-Road Bike Lanes
75
Total Project Cost: $27.3M
HOLLAND ROAD / ROSEMONT ROADINTERSECTION IMPROVEMENTS• Reconstruct the Holland
Road/Rosemont Road Intersection
• Increase Capacity• Improve Safety and Traffic
Flow• Intersection Ranks #1 in
Hampton Roads in Crashes and Severity of Crashes
76
Total Project Cost: $56.6M
SHORE DRIVE CORRIDOR IMPROVEMENTS –PHASE IV CIP 2-118 • No Capacity Expansion –
Retains 4 Lanes from Marlin Bay Drive to East Stratford Road
• Includes Safety Improvements, Edge Treatments, and Shared-Use Paths
• Currently at 30% Design
77
Total Project Cost: $12.8M
ITA PROJECTSLandstown Road Phase II BTC: $18.9M
Landstown Road Phase IIIBTC: $12.8M
Landstown Road Phase IVBTC: $18.0M
Nimmo Parkway Phase IIBTC: $34.0M
Nimmo Parkway Phase IIIBTC: $22.0M
Salem Road ExtendedBTC: $35.6M
West Tournament Drive BTC: $3.3M
Total BTC: $144.6M
78
LANDSTOWN ROAD –PHASE II
• 4-Lane Divided Parkway from the 90° Bend South 4,200 Linear Feet
• On-Road Bicycle Accommodations
• Shared-Use Path
79
Total Project Cost: $18.9M
LANDSTOWN ROAD –PHASE III
• 4-Lane Divided Parkway from the Terminus of Landstown Road Phase II to North Landing Road
• 2,850 Linear Feet• On-Road Bicycle
Accommodations• Shared-Use Path
80
Total Project Cost: $12.8M
LANDSTOWN ROAD –PHASE IV
• 4-Lane Divided Parkway from North Landing Road to Indian River Road
• 4,000 linear feet• On-Road Bicycle
Accommodations• Shared-Use Path
81
Total Project Cost: $18M
NIMMO PARKWAY PHASES II & III
• 4-Lane Divided Parkway from West Neck Road to the Intersection of North Landing Road at Indian River Road
• 11,500 Linear Feet• On-Road Bicycle
Accommodations• Shared-Use Path
82
Total Project Cost: $56.2M
SALEM ROAD EXTENDED
• 4-Lane Divided Parkway that Extends Southeast from Existing Intersection at Landstown Road to Future Landstown Road Phase II
• 7,920 Linear Feet• Provide Access to Proposed
Sustainability Park• On-Road Bicycle
Accommodations• Shared-Use Path
83
Total Project Cost: $35.6M
WEST TOURNAMENT DRIVE
• 2-Lane Un-Divided Parkway That Extends East from Landstown Centre Way 1,200 Linear Feet
• Provide Access to Future Development Within Princess Anne Commons
• On-Road Bicycle Accommodations
• Shared-Use Path
84
Total Project Cost: $3.3M