Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX ® Robotics Systems Gateway Testbed Build Instructions Version 31 MATERIALS QUANTITY MATERIALS QUANTITY 1 1 8 11 2 4 15 1 1 1 1 5 BASEPLATE VEX CORTEX SCREW, 8-32 x 3/4” LONG SCREW, 8-32 x 1/2” LONG SCREW, 6-32 x 3/4” LONG SCREW, 6-32 x 1/2” LONG NUT, 8-32 BUMP SWITCH LIMIT SWITCH LINE TRACKER POTENTIOMETER 2” DRIVE SHAFT 36 TOOTH GEAR 1 6 1 1 3 3 2 2 2 1 1 2 SHAFT COLLAR BATTERY STRAP SLOTTED ANGLE DELRIN BEARING 2 WIRE MOTOR(393) SPACER 2.75” WHEEL 2” STANDOFF BATTERY GREEN LED LIGHT MOTOR CONTROLLER CLAW KIT 1 PARTS LIST
Transcript
Page 1: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 1

MATERIALS QUANTITY MATERIALS QUANTITY 1 1

8112 4

15 1 1 1 1 5

BASEPLATE VEX CORTEX SCREW, 8-32 x 3/4” LONG SCREW, 8-32 x 1/2” LONG SCREW, 6-32 x 3/4” LONG SCREW, 6-32 x 1/2” LONG NUT, 8-32 BUMP SWITCH LIMIT SWITCH LINE TRACKER POTENTIOMETER 2” DRIVE SHAFT 36 TOOTH GEAR 1

6 1 1 3 3 2 2 2 1 1 2

SHAFT COLLAR BATTERY STRAP SLOTTED ANGLE DELRIN BEARING 2 WIRE MOTOR(393) SPACER 2.75” WHEEL 2” STANDOFF BATTERY GREEN LED LIGHT MOTOR CONTROLLER CLAW KIT 1

PARTS LIST

Page 2: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 2

x4 x4

3/4”

Base Plate Cortex

x2x2

1/2”

Bump Switch

Note: Unless otherwise stated, the screw size is 8/32”

Page 3: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 3

x2 x2

1/2”

Limit Switch

x1 x1

1/2”

Line Tracker

Page 4: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 4

x2 x2

3/4”

Potentiometer

x1 x1x136 Tooth Gear 2” Drive Shaft Shaft Collar

Page 5: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 5

x2x2

1/2”

Battery Strap

x2 x2x2

3/4”

Slotted Angle Delrin Bearing

Page 6: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 6

x2 x2x2 x2 x2 x22-Wire Motor (393) 2” Drive Shaft Small Spacer Shaft Collar

x2 x22.75” Wheel Shaft Collar

6-32 x 1/2” 6-32 x 3/4”

Page 7: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 7

x2 x2x1 x1 x2 x1Shaft Collar2-Wire Motor (393) 2” Drive Shaft 12 Tooth Gear

Note: Items (except Motor)included in the Claw Kit.

6-32 x 1/2”

Page 8: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 8

x2

1/2”

x2x2

1/2”

2” Standoff

Page 9: Gateway Testbed Build Instructions Version · 2017. 6. 16. · Gateway Testbed Build Instructions Version 3 Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use

Gateway Testbed Build Instructions Version 3

Project Lead The Way © and Carnegie Mellon Robotics Academy © / For use with VEX® Robotics Systems Gateway Testbed Build Instructions Version 3• 9

Line FollowerPotentiometer

Limit SwitchBump Switch

Green LED

Left MotorRight Motor

Battery

Green LED

Claw

Motor Controller (x2)

This side will connect to

motor.

This side will connect to

Cortex