Date post: | 06-May-2015 |
Category: |
Software |
Upload: | monica-di-bratto |
View: | 1,551 times |
Download: | 3 times |
Getting started with Microsoft Project 2010
Madou, 07th of March 2014
European
Commission
Contents
Introduction
The MS Project interface
Basic steps to create a
project
Let's practice!
Recommendations
Getting started with Microsoft Project 2010
European
Commission
MS Project overview: Strengths
Microsoft Project is a project management software program,
developed and sold by Microsoft, which is designed to assist a
project manager in developing a plan, assigning resources to tasks,
tracking progress, managing the budget, and analysing workloads.
The first commercial version of Project was released for DOS in 1984
The most widely used PM program because:
It is fairly generic in its approach
Highly automated once configured. Requires relatively low amount of user manipulation
Scalable – can be used for small to enormous projects
Balances visual approach (charts, graphs, etc) with logical structured approach (task and resources lists)
Getting started with Microsoft Project 2010
European
Commission
Initiating
• Set the project goal
• Identify the necessary start or finish date limitations
• Identify the project manager
• Identify budget and quality considerations
• Enter project tasks, duration and relationships
• Identify project milestones
• Define available resources and costs
• Assign resources to tasks
• Producing work results
• Requesting changes
• Recommending improvements
• Creating project records, reports, and presentations
• Updating project
• Managing resources and tasks
• Meet management timing, resource, and cost objectives
• Identify budget and quality considerations
• Review and analyze performance of the project
• Create a Closure Report
• Archive records
Planning
Executing
Controlling
Closing
Project
Management: process of initiating,
planning, executing,
controlling, and
closing a project
MS Project overview: PM steps
Getting started with Microsoft Project 2010
European
Commission
Contents
Introduction
The MS Project interface
Basic steps to create a
project
Let's practice!
Recommendations
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
The Quick Access Toolbar (File, Task, Resource,
Project, View, Developer, Format)
The Ribbon (tabs, buttons and drop-down list)
Main Screen components Indicators column with message icons
Status bar with messages
Screen divider, to separate spreadsheet from timescale
View buttons
Zoom slider
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
Single view versus combination view (example)
European
Commission
The MS Project interface
Getting started with Microsoft Project 2010
Change the timescale in a view 1. In the View
group select
Timescale
2. In the
Timescale
dialog box,
click the Top
Tier, Middle
Tier, or
Bottom Tier
tab.
3. In the Units box,
select the time unit that
you want to use. (e.g.
Years)
4. In the Label list, select
the label format that
you want to use to
display the time unit.
5. In the Count box,
type or select a
number to specify the
frequency of unit
labels on the
timescale tier.
To focus on a specific time period or group of tasks, use the zoom slider in the
status bar at the bottom of the screen.
European
Commission
Contents
Introduction
The MS Project interface
Basic steps to create a
project
Let's practice!
Recommendations
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Find critical path
Close Project
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Start a new project: Start or Finish date
By default, the new project file is scheduled from a
Project Start Date
All tasks are scheduled to begin as soon as possible
Project 2010 calculates the project’s Finish date based on Tasks, Durations, Dependencies.
When a project is scheduled from a Finish date, such as
a conference, all tasks are scheduled to begin as late as
possible
To schedule from a Finish Date, apply this setting as soon as the project is created
Getting started with Microsoft Project 2010
European
Commission
Start a new project: from a Start date
Getting started with Microsoft Project 2010
1. Click on Project
Information
button
2. Enter the start
date of your
project
This is a description
of the costraint on
this project
This allows you to
choose between
forward scheduling
(Project Start date)
and backward
scheduling (Project
Finish date)
European
Commission
Start a new project: from a Finish date
Getting started with Microsoft Project 2010
European
Commission
Create a project: Customize standard calendar
By default, the entire project, each task, and each resource is
scheduled according to the Standard calendar.
The Standard calendar specifies that Monday through Friday
are working days with 8 hours of work completed each
day. Saturday and Sunday are designated as nonworking
days.
The Calendar can be modified to identify holidays or other
nonworking days or times in which work should not be
scheduled.
You can also create unique calendars for tasks and resources
that do not follow the working and nonworking times specified
by the Standard calendar.
Getting started with Microsoft Project 2010
European
Commission
Create a project: Customize standard calendar
Getting started with Microsoft Project 2010
Select
Exceptions Tab
Add Holiday as
exceptions Nonworking holiday
will be showed on
the Calendar
To customize the standard calendar click on Change
Working Time on the Ribbon Project.
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: Entering tasks and durations
Entering tasks and durations is probably the single
most important effort in developing a useful project file.
If tasks are omitted or durations underestimated, the
value of the project’s scheduling and cost information is
compromised.
Often you will need to change an existing task or insert,
delete, split or move a task. Project 2010 offers a
variety of tools that you can use to accomplish these
common tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: insert, delete, inactivate tasks
Getting started with Microsoft Project 2010
Right‐click
shortcut
menus task
European
Commission
Create a project: entering recurring tasks
A recurring task is a task that repeats at a regular
interval (i.e. status meeting )
In Project 2010, you can define a recurring task one
time using the Recurring Task Information dialog box
from the task menu.
Project 2010 then handles the details of scheduling
the task at specified interval for the entire project or
for the time period you specify.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering recurring tasks
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering milestones
A milestone is a task that marks a significant point in
time or a progress checkpoint.
It has a zero duration and is therefore a symbolic task
that is used mainly to communicate progress or to
mark the end of a significant phase of the project.
Examples include the signing of a contract or the
announcement of a new product.
Milestones can also be used to motivate project
participants by recognizing accomplishments.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering milestones
Getting started with Microsoft Project 2010
European
Commission
Create a project: attaching documents to tasks
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. In the Notes tab, click
on Insert Object
button
3. Select Create from
File, then Browse and
locate your file and
Insert
4. Turn on Link check box, if you want
that the icon will be linked to the file. In
this way changes to the attached file
will be reflected in your project.
European
Commission
Create a project: display information about tasks
Getting started with Microsoft Project 2010
2. Select
Indicators
1. Click on Add
New Column
3. Drag the
column to a
new location
Useful information and alerts related to tasks and resources can be displayed
showing the Indicators Column.
European
Commission
Create a project: display information about tasks
Getting started with Microsoft Project 2010
4. Indicators column displays:
• Miscellaneous indicators
• Constraint indicators
• Task type indicators
• Dependency indicators
European
Commission
Create a project: add a deadline
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. In the Advanced tab,
click on Deadline
Menu and define date
If you know that your task has a deadline one common mistake is to put inflexible
constraint -> must finish on Why? Because you are telling MS PROJECT that this
task MUST finish on that date and NOT BEFORE!
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
A very important strategy for managing projects well is
to organize the work that needs to be done in a logical
manner, a Work Breakdown Structure (WBS) can be
an example.
In order to use a WBS in Project 2010, you must
organize tasks into Summary tasks (groups of tasks
that logically belong together).
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
When developing a new, large project, some project
managers prefer to start with broad groupings of summary
tasks and then break them down into smaller tasks. This is
called the top‐down method of creating a WBS.
Other project managers prefer to list all of the individual
tasks, and then collect them into logical groupings using
the bottom‐up method.
Once you have identified your summary tasks, you use
Outdenting and Indenting in Project 2010 to create the
summary tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: WBS with Summary Tasks
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering tasks dependencies
Create relationships between tasks: task dependencies.
Four task dependencies define the relationships
between tasks in MS Project.
Getting started with Microsoft Project 2010
European
Commission
Create a project: entering tasks dependencies
Getting started with Microsoft Project 2010
1. Double click on the
task name to open the
Task Information
Dialog Box
2. Click on the
Predecessors tab
3. Chose the
Predecessor and the
Constrain type
4. In the Lag field, type
the Lag time (positive
or negative)
Lag time is a delay between two tasks that are linked by a dependency.
European
Commission
Create a project: entering tasks dependencies
Getting started with Microsoft Project 2010
Create task dependencies using the predecessors column.
2. Select
Predecessors
1. Click on Add
New Column
3. Digit the ID of the
task you want to
link.
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Assign resources to tasks
One of the most important but often overlooked parts of the
project management process is allocating resources properly.
In 4 steps you can allocate resources in Microsoft Project and
keep you in control of your project from start to finish.
1. Consider resource availability when estimating task
duration.
2. Create and organize a resource pool for the project
3. Assign each work task to a resource
4. Check the resource allocation in the resource graph view
Getting started with Microsoft Project 2010
European
Commission
1. Consider resource availability when estimating task duration
This step is crucial but often overlooked. Resources
must be considered during the construction of the
schedule, not just afterwards.
Pay special attention to concurrent tasks (those that
happen at the same time) that use the same
resources
Focus on man-hours rather than total workdays, to
take into account how many resources will be needed
Getting started with Microsoft Project 2010
European
Commission
2. Create and organize a resource pool for the project
On the View menu, click Resource
Sheet
On the Resource menu, click Add
Resources
Define which kind of resource you
need:
• "Work" resources are the most
useful, and should be used to
categorize
• "Material" resources should refer
to materials that get used up
during work,
• "Cost" resources are time
independent resources (like
Airplane tickets)
Getting started with Microsoft Project 2010
European
Commission
3. Assign a resource to each work task
Find the task's line in the left panel, and click the cell in the
"Resource" column. A drop-down menu will appear listing all the
resources you have created. Select the appropriate resource.
Getting started with Microsoft Project 2010
European
Commission
4. Check the resource allocation in the resource graph view
After creating your schedule and assigning resources, you
can check for over-allocation (click on "View" and select
"Resource Graph")
Any point at which a resource exceeds 100 percent usage
represents an over-allocation (meaning the resource can't
possibly perform all the tasks assigned to it in the given
time). Over-allocation is represented in red.
To remedy this, increase the task durations, assign more
resources to the tasks, or shift concurrent tasks to create
less overlap.
Getting started with Microsoft Project 2010
European
Commission
4. Check the resource allocation in the resource graph view
On the contrary, any point at which the resource is being used
very little may point to inefficient under-allocation. Consider
decreasing the task durations or using fewer total resources.
The Resource Graph shows
allocation over time, resource
by resource.
When the vertical bar is higher
than the horizontal line and
part of the bar is bright red, the
resource is overallocated.
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Find critical path
Critical path: the series of critical tasks that dictates the
calculated finish date of the project in Project path.
Critical tasks: the tasks that cannot be delayed without
affecting the project finish date. A task becomes critical
when it meets any one of the following conditions:
It has no slack.
It has a Must Start On (MSO) or Must Finish On (MFO) date
constraint.
It has an As Late As Possible (ALAP) constraint in a project
scheduled from a start date.
It has an As Soon As Possible (ASAP) constraint in a project
scheduled from a finish date.
Getting started with Microsoft Project 2010
European
Commission
Find critical path: viewing the slack
Inserting the columns Total Slack, Free Slack and Critical you'll be able to see the
reason why a task is considered critical or not.
The critical path calculation is also being influenced by relationships, constraints,
deadlines, resource assignments, and task, resource and project calendars.
Only you can determine if the critical path is correct!!
Total Slack
The amount of time a task's finish
date can be delayed without
delaying the project's finish date.
Free Slack
The amount of time than a task
can be delayed without delaying
any successor tasks.
If the task has no successors Free
Slack is the amount of time a task
can be delayed without delaying
the entire project's finish date.
Critical
When you apply the Critical
filter this column shows tasks
on critical path.
Getting started with Microsoft Project 2010
European
Commission
Find critical path: crash your project
If you want to bring in the project finish date, you need to bring in the
dates of your critical path tasks. This is also known as crashing a
project.
Crash: To decrease a project's overall duration without changing
task relationships. Crashing a project typically requires assigning
additional resources to tasks.
To crash a project you can:
Shorten the duration or work on a task on the critical path.
Change a task constraint to allow for more scheduling flexibility.
Break a critical task into smaller tasks that can be worked on simultaneously by different
resources.
Revise task dependencies to allow more scheduling flexibility.
Set lead time between dependent tasks where applicable.
Schedule overtime.
Assign additional resources to work on critical path tasks.
Getting started with Microsoft Project 2010
European
Commission
Create a project: basic steps
Start a new project from a Start or Finish date
Add tasks, recurring tasks and milestones
Creating WBS with Summary Tasks
Create dependencies
Assign resources
Close Project
Find critical path
Getting started with Microsoft Project 2010
European
Commission
Close a project: key elements
Identify Lesson learnt
• The end of a project is a great time to sit back and reflect on achievements and identify and prepare to share what’s been learnt. Adopting an aura of constructive feedback, this can be done in a ‘lessons learnt session’ with resources, stakeholders and management involved.
Review the project
• There are several elements of the project that can be reviewed, but at least a Project Closure Report should be created. This report will provide confirmation that the project has met success criteria and can be used to request a sign-off from the sponsor to close the project.
Archive project records
• At least the following records should be archived:
Project Plan
Management Control Documents (Correspondence, Relevant meeting notes, Status reports)
Technical documents
Project Closure Report
Getting started with Microsoft Project 2010
European
Commission
Close a project: Print a view
Getting started with Microsoft Project 2010
European
Commission
Contents
Introduction
The MS Project interface
Basic steps to create a
project
Let's practise!
Recommendations
Getting started with Microsoft Project 2010
European
Commission
Excercise 1/2
1. DRAFTING NEW REGULATION
1. 1 Assess new regulation
1.1.1 Create questionnaires
1.1.2 Send questionnaires (task starts when 1.1.1 finish)
1.1.3 Receive feedbacks (task starts when 1.1.2 finish)
1.1.4 Analyse questionnaires (task starts when 1.1.3 finish)
1.2 Verify impacts of new regulation (task starts when 1.1 finish)
1.3 Analyse impacts (task starts when 1.2 finish)
1.4 Create Report (task starts when 1.3 finish)
1.5 Propose Report to Parliament and Council (Task starts when 1.4
finish, and finishes 1/04/2016. Set as a deadline!)
Getting started with Microsoft Project 2010
Create a project starting the 1st of February 2014 and ending on
the 1st of April 2016
Add "Commission Easter holidays" to the Calendar (17th and 18th
of April)
Create the following tasks and subtasks. Add dependencies.
European
Commission
Add a "Weekly Team meeting"
recurring every Wednesday
until the end of the project
Attach a document to the first
meeting
Create a resource pool with
your names
Assign resources to tasks
Set the timescale to view the
entire project in the Gantt
Chart
Excercise 2/2
Getting started with Microsoft Project 2010
European
Commission
Contents
Introduction
The MS Project interface
Basic steps to create a
project
Let's practice!
Recommendations
Getting started with Microsoft Project 2010
European
Commission
Recommendations
Know the project goal before beginning
Know the required tasks before beginning
Identify resources before beginning
Identify task relationships before beginning
Refer to the tutorial as often as needed
Refer to help section as often as needed
Keep the configuration as simple as possible
Avoid losing touch with the project
Getting started with Microsoft Project 2010
European
Commission
Recommendations
MS Project is only a tool – it does not create or
“own” the project – it reflects the data provided
The simpler the configuration, the easier the
data will be to understand, for all involved
If the plan doesn’t look right, it probably isn’t!
Check resource and task assignments/relationships
Check constraints and dependencies
Look for what has changed in the plan and follow the clues -
a small unintentional change can compromise the entire
project
Getting started with Microsoft Project 2010
European
Commission
Useful links
Getting started with Project 2010
(Microsoft Office online training
video)
Support on Project 2010
(Microsoft Office Support page)
Finding answers, sharing ideas
and solving problems related to
Project 2010 (Microsoft
Community)
Microsoft Project 2010 – 1
(Course material from Georgia
Technology Authority)
Getting started with Microsoft Project 2010
Monica Di Bratto