Flaring Data Reporting ToolFlaring Data Reporting Tool Why develop the Data Tool ?Why develop the Data Tool ?
Good quality data reporting is a part of the Standard. Therefore, there was a need to:
• better understand vented and flared gas volumes on country specific basis to manage it
• gather consistent data with flexibility• track flaring reduction versus projected
forecasts• Include oil production to put flaring level in
context
Information Information
FlowFlowcountry producing assets matrix
Country Administrato
r (CA)
General Public
Government
Oil and Gas
Industry
Users
LocalPlayer
sIOCs NOC
flaring data input
Operators
Country Owned Database
flaring data releasedSubject to
CAapproval
Input Coordinator (INC)
Operator Assurance (OAC)
country producing assets matrix
Country Administrato
r (CA)
General Public
Government
Oil and Gas
Industry
Users
LocalPlayer
sIOCs NOC
flaring data input
Operators
Country Owned Database
flaring data released
Country CA located in
Algeria SONATRACH
Cameroon SNH
Nigeria Presidential Advisor
Qatar HSE Regulation
Operator Assurance Coordinator(one representative from each Operator)
Responsible for defining:- the Sub-Assets (within each operated Asset) that will
each report flare and vent volumes- the ‘Input Coordinators’ for the Operator
Country Administrator (one representative from the Regulatory Authority or NOC)
Responsible for defining:- The parameters of the Data Tool (reporting frequency etc) - Each Asset that will report flare and vent volumes- The Operator associated with each Asset- The ‘Operator Assurance Coordinator’ for each Operator
Input Coordinator(one or more representative from each Operator)
Responsible for inputting the data for each Sub-Asset
Operator Assurance Coordinator(one representative from each Operator)
Responsible for defining:- the Sub-Assets (within each operated Asset) that will
each report flare and vent volumes- the ‘Input Coordinators’ for the Operator
Country Administrator (one representative from the Regulatory Authority or NOC)
Responsible for defining:- The parameters of the Data Tool (reporting frequency etc) - Each Asset that will report flare and vent volumes- The Operator associated with each Asset- The ‘Operator Assurance Coordinator’ for each Operator
Input Coordinator(one or more representative from each Operator)
Responsible for inputting the data for each Sub-Asset
Ministry/NOC
Operators (located incountry or in HQ)
Flaring Data Reporting ToolFlaring Data Reporting Tool
Country
Sub-asset 1
Sub-asset 3
Sub-asset 4
Sub- asset 5
Sub-asset 6
Sub-asset 1
Sub- asset 2
CA
INC C2
Operator 1 Operator 2
INC C1
Flaring Data Reporting ToolFlaring Data Reporting Tool
Asset A Asset B Asset C
Sub- asset 2
OAC OAC
INC A1
INC A8
INC A9
INC A1
GGFR Data Tool GGFR Data Tool “Granularity””“Granularity””
Well Group of wells
Major cluster of Wells or groupof platforms
ProdnBlock
Country
Monthly
Quarterly
Annually
Bi-annually Pointless Data
Data Tool area
No-Go Area
Typical current reporting level
Data Tool 2006 roll out Data Tool 2006 roll out scheduleschedule
Country Cameroon Nigeria Algeria EG
Roll out date
Q2 Sept Q4 2007
• Country Ownership: Country Administrator (CA). Will usually be a NOC or Ministry representative. Controls, accesses and publishes relevant data
• Data Input and validation: Input coordinator (INC) and approver (OAC). Will both be from the asset operators.
• Website Support: Data Base Administrator (DA). By the World Bank.
• Reporting: Web users (NGOs, Multilateral organizations, universities, press, general public…)
A useful tool to determine the baseline for gas flaring and venting and manage the reduction
Flaring Data Reporting ToolFlaring Data Reporting Tool
Muchas gracias!Muchas gracias!Para más información:
www.worldbank.org/ggfr
Visión de GGFR Visión de GGFR
GGFR Data Tool GGFR Data Tool
Back Up slidesBack Up slides
Country Administrator (CA) :
• Defines the hydrocarbon assets and their operators
• Defines the users, with login id and initial password
• Defines the data base rules (reporting timing & frequency, number of forecast years, sending of reminders, access rights to reports, …)
• Releases (final approval) of reports at the asset level. He/she may reject a data record and inform the OAC and INC by e-mail of the reason why
• Decides on release for public reporting at the country level
Flaring Data Reporting ToolFlaring Data Reporting Tool
Operator Assurance Coordinator (OAC) :
• Sole corporate responsibility for data quality and timing for all an operator’s assets vis-à-vis Country Administrator (CA)
• Defines list of sub assets in each asset
• Validates or rejects INC’s data input on sub-asset basis
• Cannot make any changes to the data. He/she may reject a data record and inform the INC by e-mail of the reason why
Flaring Data Reporting ToolFlaring Data Reporting Tool
Input Coordinator (INC):
Responsible for:
- Collecting actual and forecast data per agreed sub asset
- Inputting the data
- Correcting data records rejected by the OAC or CA
Flaring Data Reporting ToolFlaring Data Reporting Tool
Server Hardware/Site• Dedicated Server: 3mhz processor, 512mb RAM, 80gb
Raid 1 storage
• Unlimited bandwidth on redundant T-3 connections
• 72 hours back-up power supply w/21 days back-up generator
• Located in biometric entry controlled hardened site
• Nightly full rotating 10-day backup
• Weekly disaster recovery backups
Server Software• Window Advanced Server 2000
• IIS 5.x
• SQL Server 2000
Flaring Data Reporting ToolFlaring Data Reporting Tool
Security / ConfidentialitySecurity / Confidentiality• Web Server and Database Server reside in a Private
Network
• A Hardware Firewall separates Private Network from the Public Network (Internet)
• Public Network READ ONLY access to the website flows through public port in the Firewall (see next slide)
• Information stored on the Database Server is accessed by the Web Server on the Private Network
• Public Network access to the Database Server in not possible
Security / ConfidentialitySecurity / Confidentiality
• Virus/Spyware/Malware scanners run constantly on both the Web Server and Database Server to detect and block malicious intrusions
• Critical Operating System updates are applied immediately as published
• Each country’s data is stored in a separate database that is username/password controlled
• GGFR Tool Users may only access their own country’s website
• Country Administrator controls user access to asset data
Firewall Protected Private Firewall Protected Private NetworkNetwork