GODAE IGST meeting, 7-9 August 2007. Status of EUMETSAT services in respect to GODAE Francois Parisot Hans Bonekamp July 2007. METOP-A: Satellite and Instruments. GRAS. GOME-2. AVHRR-3. HIRS-4 Metop 1/2 only. IASI. ASCAT. AMSU-A1. MHS. AMSU-A2. METOP-A: Events. - PowerPoint PPT Presentation
16
Slide: 1 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007 GODAE IGST meeting, 7-9 August 2007 Status of EUMETSAT services in respect to GODAE Francois Parisot Hans Bonekamp July 2007
Transcript
Page 1: GODAE IGST meeting,  7-9 August 2007

Slide: 1 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

GODAE IGST meeting, 7-9 August 2007

Status of EUMETSAT services in respect to GODAE

Francois Parisot

Hans Bonekamp

July 2007

Page 2: GODAE IGST meeting,  7-9 August 2007

Slide: 2 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

METOP-A: Satellite and Instruments

IASI

HIRS-4Metop 1/2

only

AVHRR-3

AMSU-A1

AMSU-A2MHS

GOME-2GRAS

ASCAT

Page 3: GODAE IGST meeting,  7-9 August 2007

Slide: 3 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

METOP-A: Events

19 October 2006: Successful METOP-A Launch.

22 October 2006:Orbit 42, formal transfer of METOP-A operations from ESA to EUMETSAT

28 March 2007: Joint EUMETSAT/ESA Satellite In Orbit Verification Phase Review.

15 May 2007: Formally transfer of the EPS system and its services to the EUMETSAT Operation Department.

Page 4: GODAE IGST meeting,  7-9 August 2007

Slide: 4 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

METOP-A: Level 1 Products Status

Level 1Products

AMSU-A Operational

ASCAT Trial Dissemination

AVHRR Operational

GOME Trial Dissemination

GRAS Trial Dissemination

HIRS Operational

IASI Trial Dissemination

MHS Operational

WWW.EUMETSAT.INTHome > What We Do > Satellites > EUMETSAT Polar System > Metop-A Commissioning

METOP-A Commissioning is still ongoing

July 2007

Page 5: GODAE IGST meeting,  7-9 August 2007

Slide: 5 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

ASCAT Level 2: Surface Vector Winds

06 March 2007:• Start trial dissemination of the Ocean and Sea Ice Satellite Application Facility (OSI SAF) ASCAT wind product on 25km swath grid resolution. (Demonstrational status, but service as planned for operations.)

19 June 2007:• ASCAT data operationally used by ECMWF.

22 June 2007:• Winds Group in NOAA/ NESDIS: ASCAT winds became available to OPC forecasters

Page 6: GODAE IGST meeting,  7-9 August 2007

Slide: 6 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Ocean and Sea Ice Satellite Application Facility

The OSI-SAFroutinely produces and disseminates products characterising the ocean surface and the energy fluxes across the sea surface

The OSI-SAF Operationally produces information on the sea ice characteristics (extend, concentration, …)

Leading Entity is Météo-France in Lannion

The OSI SAFdistributes near real-time products based on e.g,MSG, METOP,NOAA, Seawinds, DMSP and GOES data

OSI SAF is in its Continued Development and Operation Phase (CDOP) since 1 February 2007. www.osi-saf.org

The OSI SAF is part of the

EUMETSAT SAF Network.

Page 7: GODAE IGST meeting,  7-9 August 2007

Slide: 7 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

OSI-SAF: Status of Services

WWW.OSI-SAF.ORG

SSI Sea Surface Irradiance

SST Sea Surface Temperature

DLI Downward Longwave Irradiance

HL High Latitude

LML Low and Mid Latitude (Atlantic)

MAP Gridded products

NAR North Atlantic Region

Page 8: GODAE IGST meeting,  7-9 August 2007

Slide: 8 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

OSTM/JASON-2: Altimetry

NASA/JPL

NOAA

CNES

EUMETSAT

EUMETSAT – Usingen, Germany

NOAA - Wallops/ Fairbanks - USA

Jason 2

AMR Reflector

AMR Electronics

GPSP Antenna

LRA

Poseidon 3 Altimeter

DORIS

Dedicated Delta II Launch Vehicle

NASA Instrument Ops

Operational product processing and Science Data archive & Distribution

Operational product processing & Distribution

Science data processing, archive & Distribution

NASA ElementsNOAA ElementsEUMETSAT ElementsCNES Elements

S/C Operations (Suitland, MD)

S/C Operations (Toulouse, France)

Page 9: GODAE IGST meeting,  7-9 August 2007

Slide: 9 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

STATUS OSTM/JASON-2

• System Interfaces Review has been held in Toulouse in December 2006.

• Services and Product Definitions are completed in March 2007.• Joint Announcement of Opportunity has been released in June

2007. Due date for proposals, 7 September 2007.• Spacecraft fully integrated in June 2007• Environmental and performance test up until end of 2007• Spacecraft preparation for launch site: Jan 21-Feb28, 2008.• Transportation and campaign: April 17-June15, 2008.• Launch: Planned for Mid-June 2008.

WWW.EUMETSAT.INTHome > What We Do > Satellites > Jason

Page 10: GODAE IGST meeting,  7-9 August 2007

Slide: 10 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Jason-3

Concept today proposed by EUMETSAT(After extensive discussions with CNES and NOAA and other partners)

Page 11: GODAE IGST meeting,  7-9 August 2007

Slide: 11 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Jason-3 : Driving factors

Ensure continuity of data availability after Jason-2Answer to priority one to fulfil the Marine Core Services serving

the needs of GMES downstream servicesContinuity of a very successful partnership between the Europe

and the USProgramme leaded by the operational agencies EUMETSAT and

NOAA but relying on support and expertise from the research agencies CNES and NASA

Minimize risk and cost

Develop in parallel with all potential partners an extensive thought on the future altimetry system

Page 12: GODAE IGST meeting,  7-9 August 2007

Slide: 12 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Jason-3 : Main features

Maximum of recurrence between Jason-2 and Jason Follow-on

Almost identical responsibilities sharing between partners

CNES will be the system prime for the operational agencies EUMETSAT and NOAA

Page 13: GODAE IGST meeting,  7-9 August 2007

Slide: 13 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Proposed Technical Partnership

US

Radiometer GPS receiver Laser retroreflector Launcher and launch services Ground segment elements Satellite operation in routine mode Near Real Time (3hrs) product processing and dissemination

EUROPE

Proteus Satellite bus Altimeter Doris receiver Satellite integration and test Ground segment elements Launch and Early Operation Phase and Initial Assessment phase operation Offline and Near Real Time product processing and dissemination

Page 14: GODAE IGST meeting,  7-9 August 2007

Slide: 14 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Funding hypothesis

Funding shared between the US and Europe, no exchange of funds

Funding shared in Europe between research and operational agencies and the European commission

Overall estimated cost for development and 5 years of operations 250 M€ (all cost in e.c. 2007)

This figure has to be compared with the 300 M€ e.c. 2001 (336 M€ e.c. 2007) of Jason-2

US part 100 M€ European part 150 M€

Deviation from a 50% sharing between the US and Europe mainly due to anticipated decrease of launcher cost

Page 15: GODAE IGST meeting,  7-9 August 2007

Slide: 15 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

Way Forward

EUMETSAT : Preparation at EUMETSAT of Preliminary Program proposal and Initiating Resolution to be submitted to Delegate Bodies fall 2007

All partners : By mid 2008, confirmation by Partners of their commitment to finance the program

EUMETSAT : At the same time, Programme declaration and definition and Enabling resolution at EUMETSAT

From mid 2008 to mid 2009, subscription period at EUMETSAT

All partners : Mid 2009, the funding of Jason follow on programme should be formally approved by each of the partners and the related agreements signed

In addition, EUMETSAT plans to organize later this year or early 2008 a workshop, in the frame of the CEOS ocean surface topography constellation activity, with the objective to initiate and foster discussions regarding the user needs and possible ways to fulfil them after Jason-3

Page 16: GODAE IGST meeting,  7-9 August 2007

Slide: 16 Status of EUMETSAT services, GODAE IGST meeting, 7-9 August 2007

STATUS POST-EPS

• Several Post-EPS Mission Experts Team (PMET) meetings were held in 2006 and 2007. • The Ocean Application Experts Group (AEG) Position Paper has been updated for the

inclusion of tables of priorities of geophysical variables. In summary, the highest Post EPS priority ranking is set for Ocean Topography, Surface Winds and SST. Ocean Currents and Ocean Colour are lower ranked in priority.

• The Initial version of the Post-EPS Mission Requirements Document (MRD) has been released. On the basis of the MRD, strong interactions between EUMETSAT and ESA for the start of Phase 0 studies are ongoing.

Some particularly relevant Post-EPS requirements:• Altimeter: MRD_ALT.090: The coverage requirement for the post-EPS ALT needs to be considered in

conjunction with the availability of other operational altimetry missions in the post-EPS time frame. The general coverage requirement for ocean topography requires two altimeters, one in a nonsunsynchronous repeat orbit, with a repeat period in the 10 to 35 day range to maximise coverage over the non-frozen ocean, the other in a sun-synchronous orbit to achieve coverage over the poles.

• Scatterometer: MRD_SCA.001: If a trade-off is necessary between swath width and horizontal resolution, the swath width shall have higher priority as long as the horizontal resolution is < 25 km (Breakthrough), < 50 km (Threshold).


Recommended