+ All Categories
Home > Documents > HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap...

HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap...

Date post: 11-Jul-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
18
Transcript
Page 1: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing
Page 2: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

HAMPTON ROADS BRIDGE TUNNEL

APPROACH TRESTLE REPAIRS

Andrew Zickler, PE

VDOT Structure and Bridge Division

Complex Structures and ABC Support Program Manager

CFRP Prestressed Beam Repairs

June 25, 2019

AASHTO Annual COBS Meeting

Page 3: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• Hampton Roads Bridge Tunnel (HRBT) carries I-64 across

Hampton Roads.

• All repair work was done to the two southern approach trestles

• HRBT trestles were opened 1957 (WB) and 1974 (EB).

Project Orientation

Virginia Department of Transportation

Page 4: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

Project Location

Virginia Department of Transportation

Page 5: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

Trestle

Virginia Department of Transportation

Approximately 9000LF of

trestle, each way

Clearance is near low tide

Page 6: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• The channel over the tunnel is major international cargo and

US Navy passage.

• Severe Deterioration was noted during routine inspections

• Additional issues were noted during patching operations;

• Line girder rating required posting.

• Grid analysis eliminated need for posting if deterioration stopped

• Several alternatives were evaluated for repairs.

• Due to lack of familiarity with

proposed repair approaches

and a wide range of loss of

section several approaches

were proposed

Critical Link with Critical Needs

Virginia Department of Transportation

Page 7: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

Serious deterioration

Virginia Department of Transportation

Worst examples of strand loss

The solution at this level was

not a wrap. This was repaired

with external PT.

Page 8: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• External PT was eventually designed for the worst conditions

where additional capacity was required to meet service and

strength level conditions.

• Wrap was designed for beams which passed service level

requirements but required additional capacity for strength

Repair Selection

Virginia Department of Transportation

Beams in 1957 were similar to Type 3 with Gr 250 7/16” dia. SR

strands,. In 1974 similar to Type 4 with Gr 270 ½” dia SR strands

Page 9: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• Mock ups were proposed for PT using beams which had been

stored on site since construction.

• 2 1957 beams and 2 1974 beams were retrieve for PT markup

• Contractor asked to retrieve an extra beam for CFRP (making total of 5

beams. A formal mockup was added for CFRP wrap during

construction

• Beams were salvaged from a nearby bridge to increase the testing

sample.

Virginia Department of Transportation

Mock up beams

Page 10: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• Anchor at ends of CFRP repair was difficult to install due to the sharp inside corner at

the web to flange transition.

• Contractor asked to build up epoxy; that was rejected due to thermal incompatibility.

• VDOT proposed an alternative wrap layout to reduce pullout when wet, contractor

rejected

Virginia Department of Transportation

Lessons from CFRP Mockup

Contractor and VDOT agreed to single piece covering horsetail anchors

Page 11: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• VDOT has several additional structures with similar exposures

for which these repair types are being considered

• Getting information related to the efficacy for restoration of

load was considered important enough to warrant follow up

testing (testing coming August 2019)

Lab testing

Virginia Department of Transportation

Page 12: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

• The patching was under a separate contract (using shotcrete)

• Drilled holes for the horsetail anchorages were made easier by use of pachometer to

determine rebar location

• Installation was fairly easy. It was complicated by an inside curve on both sides with

sharp corners

• A proposal was submitted for a build up to soften the radius with an epoxy build up. this was rejected

due to the change in the properties in thick epoxy layer. An alternative to lap multiple layers to avoid the

massive rework was approved.

CFRP Installation.

Virginia Department of Transportation

Shotcrete patching Surface prep for CFRP after patching

Page 13: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

CFRP Installation

Virginia Department of Transportation

Page 14: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

CFRP Installation

Virginia Department of Transportation

Page 15: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

CFRP Installation

Virginia Department of Transportation

Page 16: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

CFRP Installation

Virginia Department of Transportation

I was not able to get final step.

Last step is to seal beam and

CFRP wrap repair

Page 17: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

Closing thoughts

Virginia Department of Transportation

VDOT is very satisfied at the conclusion of the construction

process

Installation went very quickly and smoothly with no significant

hiccups during the wrap installation

We are waiting for confirmation from the Lab.

We have other major structure where this is potentially a

solution to extend the life of the superstructure

The trestles will be removed from service by 2024

Page 18: HAMPTON ROADS BRIDGE TUNNEL APPROACH TRESTLE REPAIRS · A formal mockup was added for CFRP wrap during construction • Beams were salvaged from a nearby bridge to increase the testing

Questions?

Virginia Department of Transportation

Contact Information:

Andy Zickler

Program Manager, Complex Bridge and ABC Support Section

VDOT Structure and Bridge Division.

[email protected]

Fort Wool,

@ South Island:

National Historic Site


Recommended