+ All Categories
Home > Documents > Heavy oil Extraction Project

Heavy oil Extraction Project

Date post: 08-Aug-2018
Category:
Upload: rohit-nair
View: 217 times
Download: 0 times
Share this document with a friend

of 26

Transcript
  • 8/22/2019 Heavy oil Extraction Project

    1/26

    06/12/2012

    NAIR, ROHIT CHANDRASEKHARAN | 51231896

    SON, CHANG HWAN | 51231722

    SURESH KUMAR, TILAK | 51232891

    GROUP17 PROJECTPEGASUS

  • 8/22/2019 Heavy oil Extraction Project

    2/26

    1 PENGUIN EPCM

    CAPITAL EXPENDITURE REQUEST

    PROJECT DATA

    CER Number: 1EPCM2012

    Title: Project Pegasus

    Cost: USD 123,050,000

    Expenditure Flow: USD 60,015,000(1st Year)USD 63,035,000(2nd Year)

    Project Category: Pilot Scale

    Date: 05/12/2012

    Location: Aberdeen

    Completion Date: 25/07/2014

    Business Team: Penguin Engineering

    Business Project: Engineering,Procurement &Construction

    Management (EPCM)

    SUMMARY PROJECT DESCRIPTION

    Project Pegasus is a pilot scale project for recovering the heavy oil from the block 25/11 ofGrane Field. The project shall involve engineering, procurement and construction managementof developing the facilities associated with the project. Statoil has awarded Project Pegasus toPenguin Engineering. Penguin Engineering is an engineering, procurement and constructioncompany operating predominantly with the offshore industry based in North Sea. The companyhas been contracted for developing a pilot scale facility in the view of extracting heavy oil fromGrane field in block 25/11 which is at 180km off Norwegian coast at water depth 127m in North

    Sea. Grane field has been developed with 31 production well and 4 injection wells, with aproduction rate of more than 200,000 bbl / day. The pilot facilities shall be tested in the well 36,which is scheduled to be drilled by the Statoil in 2013 such that the well is available for

    production of heavy oil using the pilot facilities. Business case had been developed based onevaluation of key factors schedule, feasibility, cost, risk, technology and applicability for heavyoil recovery enhancing.

    SUMMARY PROJECT BENEFIT

    Internal Rate of Return and Net Present Value have been evaluated for the period of 17 years.

    Internal Rate of Return: 22%

    Net Present Value: USD 38,113,092

    APPROVALS

    This project has complied with all the environmental and safety criterias in accordance with thecodes and standards of the company, regulation bodies, and the government policies.

    05/12/2012 Issued for Approval Project Team Project Manager CEO

    DATE DESCRIPTION PREPARED REVIEWED APPROVED

  • 8/22/2019 Heavy oil Extraction Project

    3/26

    2 PENGUIN EPCM

    CONTENTS

    1. BACKGROUND ..................................................................................................................... 5

    2. BUSINESS CASE .................................................................................................................... 6

    2.1. PROJECT SCOPE ................................................................................................................................................................... 6

    2.2. STRATEGIC CONTEXT ........................................................................................................................................................ 6

    2.3. COMMERCIAL CASE ............................................................................................................................................................ 6

    2.4. OPTIONS CONSIDERED ..................................................................................................................................................... 6

    2.5. CAPITAL COST ...................................................................................................................................................................... 6

    2.6. HIGH LEVEL PROGRAM MILESTONE ............................................................................................................................ 6

    2.7. HIGH LEVEL RISK ................................................................................................................................................................ 7

    2.8. HSE 7

    2.9. PROJECTS TARGETS ........................................................................................................................................................... 7

    2.10. PROJECT RISKS ..................... .................... ..................... ...................... .................... ..................... ..................... ................ 7

    2.11. CRITICAL SUCCESS FACTOR:......................................................................................................................................... 7

    3. OPTION GENERATIONS AND APPRAISAL .............................................................................. 8

    3.1. TECHNOLOGY APPRAISAL AND SELECTION .............................................................................................................. 8

    3.1.1. IN-LINE SUBSEA SEPARATION UNIT ......................................................................................................................... 8

    3.1.2. SUBSEA SEPARATOR UNIT ........................................................................................................................................... 8

    3.1.3. APPRAISAL AND SELECTION ....................................................................................................................................... 9

    3.2. FIELD SELECTION ............................................................................................................................................................. 10

    3.2.1. SEALION FIELD ROCKHOPER ................................................................................................................................ 10

    3.2.2. GRANE FIELD STATOIL ............................................................................................................................................ 10

    3.2.3. APPRAISAL AND SELECTION .................................................................................................................................... 11

    3.3. OPTION APPRAISAL ........................................................................................................................................................ 13

    4. STAKE HOLDERS ................................................................................................................. 14

  • 8/22/2019 Heavy oil Extraction Project

    4/26

    3 PENGUIN EPCM

    5. PROJECT EXECUTION PLAN ................................................................................................ 16

    5.1. PROJECT DESCRIPTION ................................................................................................................................................. 16

    5.2. PROJECT OBJECTIVES ..................................................................................................................................................... 16

    5.3. PROJECT SCOPE ................................................................................................................................................................ 16

    5.4. PROCUREMENT STRATEGY .......................................................................................................................................... 16

    5.5. SCHEDULING PLAN .......................................................................................................................................................... 16

    5.6. ORGANIZATIONAL CHART ............................................................................................................................................ 17

    5.7. QUALITY ASSURANCE MANAGEMENT ...................................................................................................................... 17

    5.8. HSE MANAGEMENT ......................................................................................................................................................... 17

    6. RISK MANAGEMENT STRATEGY ......................................................................................... 18

    6.1. RISK IDENTIFICATION ................................................................................................................................................... 18

    6.2. RISK ANALYSIS .................................................................................................................................................................. 18

    6.3. RISK MITIGATION ............................................................................................................................................................ 19

    6.4. RISK REVIEW ..................................................................................................................................................................... 19

    7.

    PROJECT WORK BREAKDOWN STRUCTURE......................................................................... 20

    8. PROJECT SCHEDULE ........................................................................................................... 21

    9. ESTIMATED BUDGET .......................................................................................................... 22

    10. RISK REGISTER ................................................................................................................. 24

    11. REFERENCE ...................................................................................................................... 25

  • 8/22/2019 Heavy oil Extraction Project

    5/26

    4 PENGUIN EPCM

    LIST OF FIGURES

    Figure 1: Total World Oil Reserves ..................................................................................................... 5Figure 2: Light Oil Production from North Sea ................................................................................... 5

    Figure 3: A Typical Inline Phase Splitter ............................................................................................. 8Figure 4: A Typical Subsea Separator ................................................................................................. 8Figure 5: Sealion Field ....................................................................................................................... 10Figure 6: Grane Field ......................................................................................................................... 11Figure 7: Probability Tree Diagram ................................................................................................... 12Figure 8: Stakeholders Matrix .......................................................................................................... 14Figure 9: Grane Field Development Organizational Chart ................................................................ 17Figure 10: Risk Matrix ....................................................................................................................... 19Figure 11: Mitigated Risk Matrix ...................................................................................................... 19Figure 12: Work Breakdown Structure .............................................................................................. 20

    Figure 13: Project Schedule ............................................................................................................... 21Figure 14: Estimated Budget.............................................................................................................. 22

    LIST OF TABLES

    Table 1: MVDM For In-Line Separation Units ................................................................................... 9Table 2: MVDM For Subsea Separator ............................................................................................... 9Table 3: Sealion Field Information .................................................................................................... 10

    Table 4: Grane Field Information ...................................................................................................... 10Table 5: Field Pros & Cons Evaluation ........................................................................................... 11Table 6: Development cost of projects .............................................................................................. 11Table 7: Decision Tree for Selected Options ..................................................................................... 12Table 8: Summary of Technology Evaluation ................................................................................... 13Table 9: Summary of Field Evaluation .............................................................................................. 13Table 10: Stakeholder Analysis ......................................................................................................... 15Table 11: Risk Identification.............................................................................................................. 18Table 12: Risk Probabilities ............................................................................................................... 18Table 13: Risk Impact ........................................................................................................................ 18Table 14: NPV & IRR Calculation .................................................................................................... 23Table 15: Risk Register ...................................................................................................................... 24

  • 8/22/2019 Heavy oil Extraction Project

    6/26

    5 PENGUIN EPCM

    1. BACKGROUNDLight crude oil resources are decreasing throughout the world, especially in North Sea and Gulf ofMexico, which were are developed in the early days. This causes operators to implement enhancedoil recovery techniques to maintain production rates of their respective fields. This has forced theoperators to explore other opportunities. Heavy oil and extra heavy oil constitute for 40% of the

    total world oil reserves. But extracting this heavy oil has always been a difficult task. Presentlythermal recovery techniques are being used successfully to recover heavy oil. But using thistechnology has its own disadvantages. Thermal recovery technique is not environmental friendly asit pollutes its surrounding environment and also it is difficult to implement this technology offshore,causing the operators to look for a better technology. The major problem the operators encounterwhile extracting heavy oil is that the viscosity of heavy oil is very high and it doesnt flow as easilyas the light crude oil does. Also the processing and separation of heavy oil is another difficult task.It requires high capacity separators topside, which is less feasible economically.

    Figure 1: Total World Oil Reserves

    Figure 2: Light Oil Production from North Sea

  • 8/22/2019 Heavy oil Extraction Project

    7/26

    6 PENGUIN EPCM

    2. BUSINESS CASE2.1.PROJECT SCOPEThe scope of our project is to identify the best technology available for recovering the vast reserves

    of heavy oil available. It also involves setting up the pilot scale facility at a feasible location to testthe efficiency of the technology being used as quickly as humanly possible.

    2.2.STRATEGIC CONTEXTThe global energy demand is on the rise and majority part of this energy demand is expected tocome from fossil fuels. The resources of heavy oil are twice that of conventional light crude oil.Penguin Engineering in tie up with FMC technologies have come with a new and innovativetechnology, which will be implemented to a pilot scale facility to establish the feasibility of heavyoil extraction

    2.3.COMMERCIAL CASEThe project has to make use of a new and innovative technology for heavy oil extraction inintegration with an already existing topside facility. The light crude oil resources are gettingdepleted and there is an increase in demand of heavy oil around the world. Using the technology,Penguin engineering expects to increase the oil production rate by 1000 bbl/day.

    2.4.OPTIONS CONSIDEREDThe project has considered technological and field options, which were thoroughly evaluated andthe best among them was selected for developing the pilot scale facility.

    The field options that were considered are:

    Sea Lion Field off the coast of Falkland Islands Grane Field in the Norwegian Continental Shelf.

    The technological options that were evaluated are:

    In-line Subsea Separation Unit Subsea Separator

    After detailed evaluation it was determined that Grane field fits the company strategy best and In-line Subsea separation technology was the best suited for the development of the project.

    2.5.CAPITAL COSTThe cost of the project has been estimated to be around USD 88,050,000 with a contingency of afurther 35,000,000.

    2.6.HIGH LEVEL PROGRAM MILESTONEKey completion dates should be maintained for achieving complete project in time.

    Completion of System Engineering 25/ 04/ 2013 Letter of Award for In-Line Separator 24/ 05/ 2013 Completion of System Integration Test 25/ 04/ 2014 Completion of Installation 04/ 07/ 2014 Hand-over 25/ 07/ 2014

  • 8/22/2019 Heavy oil Extraction Project

    8/26

    7 PENGUIN EPCM

    2.7.HIGH LEVEL RISKThe use of new technology for the recovery of Heavy oil is a critically important aspect of this

    project. As the evaluation of the recovery and profits associated with it is highly debatable due tolack of field proven data. The calculations are estimated on based on assumptions that the

    technology is highly reliable for the recovery of oil and the facilities commissioned would deliverexpected recovery.

    2.8.HSETo provide and maintain safe, healthy working conditions for delivering highly reliable, zero harm,operationally safe engineering solutions.

    2.9.PROJECTS TARGETS Set up the pilot scale facility within 20 months of sanctioning project Increase production 1,000 bbl/day Project CAPEX is maximum USD 123.05 New available technologies would be deployed to tackle problems experienced in previous

    projects.

    2.10. PROJECT RISKS CostLow: The accuracy of estimated costs are low as limited engineering data is available.

    This means that the total cost of the project has low percentage accuracy and therefore will bemore susceptible to variation in cost.

    Time High: Scope change and problems with technology acquirement and reaching aconclusive agreement among stakeholders. QualityHigh: Subsea project require for high level of quality due to huge cost in work over.

    2.11. CRITICAL SUCCESS FACTOR: The entire project to be carried out in environmental friendly manner and shall be a zero harm

    work area.

    Project execution to be as per the planned project schedule. Quality of the project and reliability of the product & equipments to be of high standards. Facilities to demonstrate a complete operational capability. Increase in the recovery of oil.

  • 8/22/2019 Heavy oil Extraction Project

    9/26

    8 PENGUIN EPCM

    3. OPTION GENERATIONS AND APPRAISAL3.1.TECHNOLOGY APPRAISAL AND SELECTIONVarious technological options were considered and after careful evaluation and analysis twotechnologies were selected. Various decision-making tools are being employed for selecting the

    best technology among them.

    3.1.1.IN-LINE SUBSEA SEPARATION UNITAn Inline subsea separation unit is considered because of its wide scale applicability and flexibility.It can be easily incorporated into an existing field. It is cost effective. Different in-line units are

    being used for the separation of water sand and gas from the oil. This considerably reduces theviscosity and increases the flow rate. Different inline separation units being used are- Inline Desanderit is used for removing the sand from the flow line. Sand removal reduces

    the viscosity to a great extent and thus helps in easier flow of hydrocarbons through theflowline.

    Inline Phase Splitter- it is used for separation gas from the hydrocarbon mixture. The gas thatis separated is then injected into the reservoir for increasing reservoir pressure and thusincreasing the flow rate. After all the oil has been recovered, all the gas injected can berecovered and then sold.

    In-line Electrocoalescer- Separates water from the oil mixture. The oil separated istransported for storage. Separated water is sent for water injection in the well reservoir.

    Figure 3: A Typical Inline Phase Splitter

    3.1.2.SUBSEA SEPARATOR UNITSubsea separator unit is another technology option that is considered. The main function of thesubsea separator unit is to separate the gas, sand, and water from the oil and pump it up to topsideunit. It is an all in one integrated unit and is a relatively new technology.

    Figure 4: A Typical Subsea Separator

  • 8/22/2019 Heavy oil Extraction Project

    10/26

    9 PENGUIN EPCM

    3.1.3.APPRAISAL AND SELECTIONMulti-variable decision-making tool is being employed for finding the best technological option for

    project PEGASUS.

    Table 1: MVDM For In-Line Separation Units

    Attributes Sub attributes Weights(a)

    Score (b) Score (b) OverallScore

    10 30 50 70 90

    Strategic Fit 0.5 60 30

    Programme 0.5 X 25

    Time 0.5 X 35

    Risk 0.1 60 6

    Cost 0.2 X 10

    Time 0.5 X 35

    Quality 0.3 X 15

    Cost ofDevelopment

    0.1 X 5 5

    Benefits 0.3 X 21 21

    Total 62

    Table 2: MVDM For Subsea Separator

    Attributes Sub attributes Weights(a)

    Score (b) Score(b)

    OverallScore

    10 30 50 70 90

    Strategic Fit 0.5 50 25Programme 0.5 X 15

    Time 0.5 X 35

    Risk 0.1 50 5

    Cost 0.2 X 14

    Time 0.5 X 15

    Quality 0.3 X 21

    Cost ofDevelopment

    0.1 X 3 3

    Benefits 0.3 X 21 21

    Total 54

  • 8/22/2019 Heavy oil Extraction Project

    11/26

    10 PENGUIN EPCM

    3.2.FIELD SELECTION3.2.1.SEALION FIELD ROCKHOPER

    Table 3: Sealion Field Information

    Location Off Falkland island coastBlock No. 14/10-2

    Water Depth 2700m

    Discovered Rockhopper in 2010

    Estimated Recovery 355.6 million barrels

    Cost for Developing USD 875,000,000

    Plateau Oil Production Rate Estimated up to 70,000bbl/d

    Peak Oil Production Rate -

    Participants Rockhopper (100%)

    Figure 5: Sealion Field

    3.2.2.GRANE FIELD STATOILTable 4: Grane Field Information

    Location 185 Km west of Haugesund

    Block No. Block 25/11

    Water Depth 350m

    Discovered By Hydro in 1991

    Estimated Recovery 700 million barrels of oil

    Cost for Developing 150 to 200 million

    Plateau Oil Production Rate 200,000bbl/d

    Peak Oil Production Rate 243,000bbl/d

    Participants Stat oil (36.67%) Petoro (28.94%),ExxonMobil Exploration & Production

    Norway (28.22%) ConocoPhillipsSkandinavia (6.17%)

  • 8/22/2019 Heavy oil Extraction Project

    12/26

    11 PENGUIN EPCM

    Figure 6: Grane Field

    3.2.3.APPRAISAL AND SELECTIONTwo field options were evaluated based on the pros & cons, cost of development and the profits

    based recovering the cost of development by the additional recovery of oil using the inlineseparation technology are as shown below.

    Table 5: Field Pros & Cons Evaluation

    Table 6: Development cost of projects

    GRANE FIELD SEALION FIELD

    PROs:

    Existing topside and subsea facilitiesLower logistic costsAvailability of field data for comparisonApplicability of EOR techniquesScheduleLow CAPEX

    PROs:

    Unlimited design specifications as it isa relative green field

    CONs:

    Production loss due to interventionDesign limitations

    CONs:

    Political tensionTopside and subsea facility needs to be

    constructed

    No data for establishing the benefit oftechnologyLonger schedulesHigher logistic costHigher CAPEXTechnical limitation due to water depth

    Project Development Cost Additional Recovery

    Grane Field USD 82,400,000 1,000 bbl/day

    Sealion Field USD 882,400,000 1,000 bbl/day

  • 8/22/2019 Heavy oil Extraction Project

    13/26

    12 PENGUIN EPCM

    Table 7: Decision Tree for Selected Options

    Project Best Case Base Case Worst Case

    Grane Field

    Income: (1,100 bbl/day x16 years x 365 x price

    per barrel)=US$ 655.2 million

    Probability:0.2

    Income: (1,000 bbl/day x16 years)=

    US$ 595.68 millionProbability:0.6

    Income: (900 bbl /day x16 years x 365 x price per

    barrel)=US$ 536.11 million

    Probability:0.2

    Sealion Field

    Income: (1,100 bbl/day x25 years x 365 x price

    per barrel)=US$ 1,023.82 million

    Probability:0.2

    Income: (1,000 bbl/day x25 years x 365 x price

    per barrel)=US$ 930.75 million

    Probability:0.6

    Income: (900 bbl/day x25 years x 365 x price per

    barrel)=US$ 837.67 million

    Probability:0.2

    Note: Oil production data for both Field is assumed due to lack of available data. Oil price is

    102 USD/bbl available inwww.oil-price.net

    Figure 7: Probability Tree Diagram

    The figure above shows the probability tree diagram and the comparative studies, which are beingused to determine the best field option for project development shows Grane field as the mostfeasible option among the two. Thus Penguin Engineering is planning to develop its pilot scalefacility at Grane Field.

    http://www.oil-price.net/http://www.oil-price.net/http://www.oil-price.net/http://www.oil-price.net/
  • 8/22/2019 Heavy oil Extraction Project

    14/26

    13 PENGUIN EPCM

    3.3.OPTION APPRAISALAfter employing various analysis tools for determining the best technological and field option forsetting up the pilot scale facility, the best among them was selected using the summary ofappraisals.

    Table 8: Summary of Technology Evaluation

    In-line separation unit Subsea separator unit

    Cost 40 million 90 million

    Efficiency10-15 % increase in reservoir

    output5-10 % increase in reservoir

    output

    Technological status Newly developed Relatively new technology

    Inspection and Maintenance ROV ROV

    Flexibility Highly FlexibleRelatively low on flexibility

    because of its bulky natureSafety issue No potential safety issue No potential safety issue

    Lead time 7 months 12 months

    Table 9: Summary of Field Evaluation

    Project Attribute Sealion Field Grane Field

    Estimated increase oil recovery 1000bbl/d 1000 bbl/d

    Estimated cost USD 923,050,000 USD 123,050,000

    Estimated schedule 21 months* 21 months

    Risk associated

    - Political Factor- Reservoir Data YESUNKNOWN NOKNOWN

    3rd party involvement Yes Yes

    Estimated value $ 930.75 million $ 595.68 million

    Benefit to company

    - Increase production- Generate profit YesYes YesYes

    Does it fit for Companys

    strategies Yes Yes

    * align with field development schedule in 2016.

  • 8/22/2019 Heavy oil Extraction Project

    15/26

    14 PENGUIN EPCM

    4. STAKE HOLDERSThe important stakeholders who influence the project were identified in the matrix given below.The stakeholders position in the matrix shows the importance and the influence they have in the

    project.

    Strategy for each group also included. Key player group should be involved with project andmonthly meeting with each party will be held. Shareholders in the project field are categorized withactive consultation group due to their importance in the project. They should be included in theinformation loop and their feedback will be clarified or rectified as much as possible. Projectmanagement team will maintain interest in subcontractors. Their work progress will be monitoredregularly; package lead and inspector will report any commercial / technical issue. Norwegiangovernment and local community will be informed when it is required

    Figure 8: Stakeholders Matrix

    Maintain Interest1. Umbilical Manufacturer

    2. Pipeline Manufacturer3. Installation Vessel Contractor4. Insurance Company

    5. Subcontractors

    Key Players1. Stat oil2. Penguin Engineering

    3. FMC4. Verification AgencyActive Consultations1. Mitchel Thevor2. Conoco Phillips3. Petoro4. Exxon Mobil

    Keep Informed1. Norwegian Fisherman

    Federation2. Coastguard3. Norwegian Government4. Media/Technical Societies

    ImportanceLOW HIGH

    HIGH

    Impact

  • 8/22/2019 Heavy oil Extraction Project

    16/26

    15 PENGUIN EPCM

    The table below shows what each stakeholder expect from the project and how it is going to beaddressed by PENGUIN Engineering.

    Table 10: Stakeholder Analysis

    STAKEHOLDER % OWNERSHIP NEED EXPECTATION

    Statoil 60% Highly reliabletechnical solutionswith goal zero practicein project execution.

    Effective planning andscheduling of projectmanagement.

    Commercially viableevaluation of thetechnology for future

    project.

    Recovery of Heavy Oilefficiently, timely &environmentallyfriendly

    Michel Thevor 20% Recovery of Heavy Oilefficiently, timely &environmentallyfriendly

    Conoco Philips 10% Recovery of Heavy Oilefficiently, timely &

    environmentallyfriendly

    Exxon Mobil 10% Recovery of Heavy Oilefficiently, timely &environmentallyfriendly

    Penguin Engineering NA Highly reliable andtimely projectexecution.

    Complete projectwithin time and budget

    FMC NA Dispatch project teamto site

    Delivery the product intime

    NorwegianGovernment

    NA Field developmentplan will be submittedfor approval

    Develop the projectwithin regulation

    NorwegianEnvironmentalProtection Agency

    NA All safety standardswill be adhered to.

    No Environmentalpollution

    NorwegianFishermens

    Federation

    NA Related issue(EnvironmentalImpact) will be sharedand discussed

    Minimize impact intheir industry

    Coastguard NA Required information

    (offshore workschedule) will beshared and discussed

    Prevent any kind of

    offshore accident

    Installation Contractor NA Work progress to bemonitored closely

    Complete the work intime

    Subcontractors NA Work progress to bemonitored closely

    Delivery the product intime

    Verification Agency NA Any feedback to beclarified

    Verify engineeringwork

    Insurance Company NA Required information

    to be shared

    Project information to

    be sharedMedia/TechnicalSocieties

    NA Required informationto be shared

    Project information tobe shared occasionally

  • 8/22/2019 Heavy oil Extraction Project

    17/26

    16 PENGUIN EPCM

    5. PROJECT EXECUTION PLAN5.1.PROJECT DESCRIPTIONThe reserves of untapped heavy oil reserves are huge and our project aims at evaluating the best

    possible technique to extract heavy oil using the most advanced technology options available in themarket and to conduct a feasibility study for future expansion of the field. Our project is a pilotscale facility in the Grane field 185km from the city of Haugesund, Norway. The project will beable to demonstrate the benefit of using the proposed technology and also the scope of futureexpansion of a field. For this project an existing topside facility of the contracting company will beused and the subsea technology proposed will be integrated into an already existing field.

    5.2.PROJECT OBJECTIVESThe principal objectives of the project team are hiring unproven technology and incorporating intoexisting facilities for enhancing the production in mature fields. Key objectives are addressed as

    below.

    Building a pilot scale facility for extraction of heavy oil Using new and innovative technology incorporating with an existing topside facility. Integrating the technology to an already existing subsea facility Commissioning of project with maximum CAPEX $ 123.05 million Completing the project as fast as humanly possible Increasing the production by 1000 bbl/d

    5.3.PROJECT SCOPEThe principal scope of the project team is to engineering, procurement, test, installationmanagement, commissioning and provide for assistance in start-up and maintenance for the pilot-facilities. Key activities of project scope are addressed as bellows;

    Evaluating the field options available for building the pilot scale facility Selecting the best possible technology option for pilot scale facility development Procurement of technology and other essential requites (Umbilicals, risers, pumps) Installing pilot scale facility Modifying topside as per requirement Commissioning the project

    5.4.PROCUREMENT STRATEGYProcurement activities for Project PEGASUS shall be handled by Project group. They will performthe requisition, budding and commercial evaluations. Technical evaluations will be performed byengineering group. All activities are supported by the QA/QC and HSE group. The Long Lead-Equipments will be tracked to complete in time. The subcontract requirements will be defined bythe Project team in early stage and will be included as activities in the project schedule. Especially,in-line separator package, pipeline and umbilical will be closely monitored and managed by the siterepresentative together with the QA / QC group and respective engineering group.

    5.5.SCHEDULING PLANThe Long Lead-Equipment will be scheduled depends on progress monitoring so that criticalactivity could be completed in time. Due to the challenging delivery schedule, it is important forPenguin Engineering to ensure key milestones on the agreed dates. A tendering schedule is

    described in section 7.0. It is important to forecast milestone activities and ensure they arecompleted on time.

  • 8/22/2019 Heavy oil Extraction Project

    18/26

    17 PENGUIN EPCM

    5.6.ORGANIZATIONAL CHARTThe project organizational chart for Project FEGASUS is portrayed in figure below. The chart helpsto understand each groups role and decision structure. The project directorensures that the projectlink to corporate management, ensure project key resources to be allocated to achieve the projectobjectives. The project management team will consist of a Project Manager, Project Deputy

    Manager, QA/QC Manager, HSE Manager and Installation Manager. They will maintain the overallproject control and resolving internal / external conflicts. Commissioning team will be involvedearly stage of the project to minimize production downtime.

    Figure 9: Grane Field Development Organizational Chart

    5.7.QUALITY ASSURANCE MANAGEMENTThe quality of the product delivered is of the highest importance and Penguin Engineeringmaintains and operates a quality assurance management system fully compliant with the intent ofISO 9001:2008 standards. Quality Assurance Plan and Inspection Test Plans will be developedspecifically for Project PEGASUS.

    5.8.HSE MANAGEMENTHealth, Safety and Environmental performance are core values and will be managed as an integral

    part of our project to benefit stakeholders. Health, Safety and Environmental will be managed basedon the Project HSE Philosophy as below.

    Carry out monitoring tentative various hazards and safety issue to eliminate all incidents. Comply with all environmental, health and safety laws and regulations Make health, safety and environmental friendly ways with the primary aim of project

    execution

  • 8/22/2019 Heavy oil Extraction Project

    19/26

    18 PENGUIN EPCM

    6. RISK MANAGEMENT STRATEGYA comprehensive risk management strategy has been developed to ensure that the key parameters tothe success of the project are not just overlooked. This also ensures that the evaluation of the

    potential risks, their effects and their impact using three steps:

    Risk Identification.

    Risk Analysis.Risk Mitigation.

    6.1.RISK IDENTIFICATIONThe potential risks were identified during the project based on the evaluation of the various

    parameters such as technicality, financial, project resources, etc. involved within the project overthe range of cost, time and quality.

    Table 11: Risk Identification

    Tender / Contract Engineering Fabrication Installation Commissioning1. Schedule.2. Scope of

    Supply.3.Delay in Funds4. Inflation & Oilprice.

    5. Regulations.

    1. Schedule.2. Lack of field data.3. Interfacemanagement.4. Human Resources.5. Design errors.

    1. Schedule.2. Quality.3. HSE.4. Test failure.

    1. Schedule.2. Weatherdowntime.3. Topsidemodification.4. Accidents.5. VesselMobilization.

    1. Schedule.2.Topsidemodification3.HumanResources4. HSE.5. Technicalerrors.

    6.2.RISK ANALYSISThe risk analysis is carried by assigning values for the risk identified to determine the category ofimpact and probability. These values were multiplied to give the resultant risk i.e. Exposure =Probability x Impact. A measure to manage each risk is applied to develop a mitigated risk value.The original and mitigated risks are presented on a block diagram of impact versus probability.

    The categories that the risk impact and probabilities are shown below:

    Table 12: Risk Probabilities

    Table 13: Risk Impact

    Category Cost Time Safety Assigned Value

    High > 2 million > 2months > 5 LTIs 3

    Medium 500K to 2million 1 to 2 months 3-5 LTIs 2

    Low

  • 8/22/2019 Heavy oil Extraction Project

    20/26

    19 PENGUIN EPCM

    Risk matrix after risk assessment has been carried out as shown below:

    Figure 10: Risk Matrix

    Impact

    H 0 0 0

    M 0 2 7

    L 1 5 9

    L M H

    Probability

    6.3.RISK MITIGATIONRisk mitigation has been effectively worked out to keep the as low as reasonably practicable(ALARP). A matrix with the mitigated risk has been developed as shown below.

    Figure 11: Mitigated Risk Matrix

    Mitigated

    Probability

    H 0 0 0

    M 1 4 0

    L 4 15 0

    L M H

    Mitigated

    Impact

    6.4.RISK REVIEWIt is very important to carry out risk reviews regularly to evaluate the risks associated with the

    project and if new risks are identified, they need to be evaluated for their impact and theirconsequences. The risks that were identified at the beginning of the project have to be reevaluatedto looked if it was initial evaluated effectively and have been successfully mitigated. This activityshall be carried out quarterly with an objective reduce the possibilities of an event.

    A risk register has been developed for this project at Section 9.0

  • 8/22/2019 Heavy oil Extraction Project

    21/26

    20 PENGUIN EPCM

    7. PROJECT WORK BREAKDOWN STRUCTUREThe work breakdown structure has been used for arranging project schedule and estimating budgetwithin execution plan.

    Figure 12: Work Breakdown Structure

  • 8/22/2019 Heavy oil Extraction Project

    22/26

    21 PENGUIN EPCM

    8. PROJECT SCHEDULEThe schedule has been developed as shown below and the critical path has been identified and shaded in RED.

    Figure 13: Project Schedule

  • 8/22/2019 Heavy oil Extraction Project

    23/26

    22 PENGUIN EPCM

    9. ESTIMATED BUDGETThe cost breakdown of the project is shown in the table below. The main costs are the engineeringcosts, installing and commissioning costs. The sum total of the above mentioned three would giveyou the CAPEX of the project.

    Figure 14: Estimated Budget

    Unit Grane Field Total Cost

    Engineering 5 % of OverallProject Cost

    $ 4 million $ 4.2 million

    Subsea Separation Unit

    - In-Line Desander- In-Phase Separator- In-Line Electrocoalescer

    Lump Sum111

    1

    $ 40 million $ 40 million

    Pipeline Carbon Steel X65 13 km $ 1.3 million $ 1.3 million

    Riser $ 750,000 $ 750,000

    Umbilical

    - Umbilical Termination Unit 10km $ 850,000/km $ 8.5 millionFlying Leads 5Nos, 30m $ 125,000 $ 125,000

    Topside Control Equipment

    - Subsea Control Unit- Subsea Power

    Communication Unit

    - Hydraulic Power Unit- Topside Umbilical

    Termination Unit

    Lump Sum $ 13 million $ 13 million

    Logistics Lump sum $ 4.9 million $ 4.9 million

    Installation (40 Days)

    - Pipe laying Vessel- Installation Vessel- Vessel Mob/Demob Cost ($)- ROV

    1 Vessel / day1 Vessel / day

    per each trip1 Work Class/day1 Observation/day

    $200,000/DAY$200,000/DAY$ 1 million$45,000$15,000

    $ 4 million$ 4 million$ 4 million$ 2.4 million

    Commissioning

    - Topside Control- Hydrostatic Testing

    Lump Sum $900,000 $900,000

    Total $ 88.05 million

    Contingency - 40% $ 35 million

    Estimated Budget with contingency $ 123.05 million

  • 8/22/2019 Heavy oil Extraction Project

    24/26

    23 PENGUIN EPCM

    Table 14: NPV & IRR Calculation

    Year Fixed CostVariable

    CostTotal Cost

    Production(bb/day)

    RevenueTaxableIncome

    Book Valueof Asset

    DepreciationValue ofCapital

    AllowanceIncome Tax

    Netcash flow

    2013 0 US$123,050,000 US$0 US$123,050,000 0 US$0 US$0 US$123,050,000 US$30,762,500 US$0 US$0 (US$123,050,000)

    2014 1 US$0 US$20,000 US$20,000 1,000 US$9,307,500 US$9,287,500 US$92,287,500 US$23,071,875 US$9,228,750 US$0 US$9,287,500

    2015 2 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$69,215,625 US$17,303,906 US$6,921,563 (US$6,442,500) US$43,652,500

    2016 3 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$51,911,719 US$12,977,930 US$5,191,172 US$4,241,438 US$32,968,563

    2017 4 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$38,933,789 US$9,733,447 US$3,893,379 US$5,971,828 US$31,238,172

    2018 5 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$29,200,342 US$7,300,085 US$2,920,034 US$7,269,621 US$29,940,379

    2019 6 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$21,900,256 US$5,475,064 US$2,190,026 US$8,242,966 US$28,967,034

    2020 7 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$16,425,192 US$4,106,298 US$1,642,519 US$8,972,974 US$28,237,0262021 8 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$12,318,894 US$3,079,724 US$1,231,889 US$9,520,481 US$27,689,519

    2022 9 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$9,239,171 US$2,309,793 US$923,917 US$9,931,111 US$27,278,889

    2023 10 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$6,929,378 US$1,732,344 US$692,938 US$10,239,083 US$26,970,917

    2024 11 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$5,197,033 US$1,299,258 US$519,703 US$10,470,062 US$26,739,938

    2025 12 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$3,897,775 US$974,444 US$389,778 US$10,643,297 US$26,566,703

    2026 13 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$2,923,331 US$730,833 US$292,333 US$10,773,222 US$26,436,778

    2027 14 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$2,192,499 US$548,125 US$219,250 US$10,870,667 US$26,339,333

    2028 15 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$1,644,374 US$411,093 US$164,437 US$10,943,750 US$26,266,250

    2029 16 US$0 US$20,000 US$20,000 1,000 US$37,230,000 US$37,210,000 US$1,233,280 US$308,320 US$123,328 US$10,998,563 US$26,211,437

    Oil Price 102 USD/bbl

    Production daysper year

    365 days/year

    Income TaxRate

    30% Net Present Value USD 38,113,092

    Depreciation 25%Internal Rate ofReturn

    22%

    Discount Rate 15%

  • 8/22/2019 Heavy oil Extraction Project

    25/26

    24 PENGUIN EPCM

    10.RISK REGISTERAfter the various risks associated with project PEGASUS were identified, a risk assessment was carried out. After assessment, various mitigationtechniques were used for reducing.

    Table 15: Risk Register

    Ref. No. Description of Risk Risk Assessment Risk Management Mitigated Risk Assessment

    P I E MP MI MR

    Time

    1. Delay in Tendering L M 2 Proper tendering schedule and procedures L L 1

    2. Weather Downtime L M 2 Proper Planning Considering Weather L L 1

    3. Accidents L H 3 Incentive for LOW LTI L M 24. Late Delivery of Equipments M H 6 Dispatch expediter L M 2

    5. Delay in Approvals M H 6 Proper Identification & Documentation M M 4

    6. Vessel Mobilization Delay L H 3 Contact in advance L M 2

    7. Poor Management M H 6 Frequent Project Management Review L M 2

    Cost

    1. Inflation L L 1 Contingency L L 1

    2. Oil Price L M 2 Evaluation of the project based on an average oil price L M 2

    3. Accuracy in Cost Estimation M M 4 Routine Assessment L M 2

    4. Unexpected Cost M M 4 Contingency L M 2

    5. Delay in Funds L M 2 Alternative Financial Source L M 2

    6. Project Delay M H 6 Monitoring Project Progress M M 4

    7. Accidents L H 3 Insurance L M 2

    8. Change in Scope L H 3 Add Reimbursable Man-hour L M 2

    9. Fabrication defect L M 2 Quality Inspection Procedure / 3rd Party Inspection L L 1

    10. Installation defect L H 3 Marine Warranty Surveyor L M 2Safety

    1. Human Errors M H 6 Detailed Commissioning Procedures M M 4

    2. Oil spill L H 3 Emergency Response Plan L M 2

    3. Safety Equipment failure L H 3 Redundancy in Safety Equipment L M 2

    4. Loss of integrity M H 6 Integrity Management M M 4

    5. Blowout L H 3 SSIV L M 2

    6. Pipeline/Riser failure L H 3 Integrity Management L M 2

    7. External factors M H 6 Protection Structure M M 4

  • 8/22/2019 Heavy oil Extraction Project

    26/26

    11.REFERENCE BASS, R.M., 2006. Subsea Processing and Boosting-Technical Challenges and

    Opportunities, Offshore Technology Conference, - 2006.

    CAVANAGH, J., 2012. Project Management Lecture Note. Aberdeen: John Cavanagh. COWIE, D., SCHMOLL, J.K., SUTTON, J.E., ROBERTSON, D.S. and ROBINSON, S.A., 1994.Investigation Of A Novel Facility Design Concept For Heavy-Oil North Sea

    Development, Offshore Technology Conference, - 1994.

    EUPHEMIO, M., OLIVEIRA, R., NUNES, G., CAPELA, C. and FERREIRA, L., 2007. SubseaOil/Water Separation of Heavy Oil: Overview of the Main Challenges for the Marlim

    Field-Campos Basin, Offshore Technology Conference, - 2007.

    FMC TECHNOLOGIES, Available:http://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechn

    ologies.aspx.

    GILL, H., ALNAHDI, A.A., FARID, U., MORRIS, R.D. and OMIDIYA, A.B., 2011. Engineeringa Successful Sour, Heavy Oil Test in a Sensitive Offshore Environment in Saudi Arabia,

    SPE Heavy Oil Conference and Exhibition, 12-14 December 2011, Society of Petroleum

    Engineers.

    HANNISDAL, A., WESTRA, R., AKDIM, M.R., BYMASTER, A., GRAVE, E. and TENG, D.T.,2012. Compact Separation Technologies and Their Applicability for Subsea Field

    Development in Deep Water, Offshore Technology Conference, - 2012.

    SUBSEA SEPARATION AND PROCESSING OF OIL, GAS & PRODUCED WATER PAST,PRESENT AND FUTURE WHY WE NEED IT NOW, . Available:

    http://www.forum.rice.edu/past-events/past-forums/.

    http://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechnologies.aspxhttp://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechnologies.aspxhttp://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechnologies.aspxhttp://www.forum.rice.edu/past-events/past-forums/http://www.forum.rice.edu/past-events/past-forums/http://www.forum.rice.edu/past-events/past-forums/http://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechnologies.aspxhttp://www.fmctechnologies.com/en/SeparationSystems/Technologies/InLineTechnologies.aspx

Recommended