Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014
Transcript
Page 1: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

Herndon Station - North Pavilion Construction

Town of Herndon – Town CouncilAugust 6, 2014

Page 2: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

Overview of Project Schedule

Page 3: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

Existing Site and Traffic Pattern

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 4: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

Existing Underground SWM

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 5: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence

PHASE 1.1 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 6: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade

PHASE 1.1 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Page 7: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade•Demo Staircase

PHASE 1.1 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Laydown

Page 8: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall

PHASE 1.1 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Laydown

Page 9: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall•Build Construction Access

PHASE 1.1 - Target Start: February 2016, Duration: 1 Month

Cons

truc

tion

Acce

ss

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Laydown

Page 10: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall•Build Construction Access•Install Fence

PHASE 1.2 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 11: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall•Build Construction Access•Install Fence•Demo Median

PHASE 1.2 - Target Start: February 2016, Duration: 1 Month

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 12: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 1.3 - Target Start: February 2016, Duration: 1 Month•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall•Build Construction Access•Install Fence•Demo Median•Construct New Aisle

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 13: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 1.3 - Target Start: February 2016, Duration: 1 Month•Install Fence•Clear & Grade•Demo Staircase•Install Retaining Wall•Build Construction Access•Install Fence•Demo Median•Construct New Aisle•Relocate Dumpster•Pave to Existing•Permanent Traffic Shift

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 14: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 2 - Target Start: March 2016, Duration: 2 Months•Relocate Existing Utilities•Install New Utilities•Relocate Transformer

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 15: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 3 - Target Start: May 2016, Duration: 4 Months•Erect Service Crane•Excavate •Install Footings•Install FDN/SOG•Concrete Columns/Beams•Install Precast Concrete

Crane

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 16: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 4 - Target Start: September 2016, Duration: 5 Months•Install Escalators•Erect Pedestrian Bridge

Crane

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 17: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 4 - Target Start: September 2016, Duration: 5 Months•Install Escalators•Erect Pedestrian Bridge•Install Curb & Gutter•Install Pavers•Install Sidewalks•Install Finishes

Crane

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Cons

truc

tion

Acce

ssLaydown

Page 18: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 5 - Target Start: February 2017, Duration: 2 Months•Remove Service Crane

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Cons

truc

tion

Acce

ss

Page 19: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 5 - Target Start: February 2017, Duration: 2 Months•Remove Service Crane•Install Sidewalk

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 20: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 5 - Target Start: February 2017, Duration: 2 Months•Remove Service Crane•Install Plaza & Sidewalk•Install Landscaping

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 21: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

PHASE 5 - Target Start: February 2017, Duration: 2 Months•Remove Service Crane•Install Plaza & Sidewalk•Install Landscaping•Remove Fencing

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site

Page 22: Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014.

Parking Impacts – Parcels 225 and 227

Pavilion

198 Van Buren

Parcel #226

575 Herndon Parkway

Parcel #225 593 Herndon Parkway

Parcel 227

Pavilion Site


Recommended