Community DevelopmentDepartment
Holland Park Renovations
Playground & Splash Park Design
Community DevelopmentDepartment
James F. Holland Memorial ParkExisting Conditions
Community DevelopmentDepartment
James F. Holland Memorial ParkProject Milestones
• 2007• Master Plan Study Completed (updated in 2009 & 2011).
• 2008• City Council approved contract for design services.
• 2013• Completion of the design & permitting phase.
Capital Projects FundProject Name December 2013 March 2014 June 2014 September 2014
Holland Park Improvements Design (Playground & Splash Park)
Construction (Phase 1)
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
City of Palm Coast2014 Capital Projects Timeline
10/8/2013
Community DevelopmentDepartment
MASTER PLAN
Improvements• Replace Utility
Infrastructure• Correct Drainage Issues• Enhance Traffic
Circulation• Add Parking• Correct ADA Issues• Repair/Renovate existing
Structures• New Bocce Ball Court
Covering• 2 New Horseshoe Pits• New Enlarged Dog Park• New Enlarged
Playground• New Splash Park• New Roadway & Parking
Lot Lighting• New Sports Activity
Lighting• Perimeter Walking Trail• New Fitness Stations• Landscape & Irrigation
Playground & Splash Park Design
Community DevelopmentDepartment
PLAYGROUND & SPLASH PARK
• City Council Action• City advertised Request for Qualifications (RFQ-CD-CP-14-02)
• 3 Qualification Submittals Received.• Littlejohn Engineering Associates, Inc. was selected as the
top ranked firm.• City negotiated a scope and fee for an amount of $49,730.00
• December 17, 2013: City Council to consider design contract with Littlejohn Engineering Assoc.