‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
1.0 EXECUTIVE SUMMARY
The NHAI has proposed to widen certain stretches of NH-9 to 4/6 lane under NHDP Phase III programme. The Work of 4/6 laning of existing 2-lanes from Malkapuram (km 40.000) to Totacherla village ( km 221+500) on NH-9 with partial access control has been awarded to M/S GMR Hyderabad Vijayawada Expressway Pvt. Ltd.(Concessionaire) under DBFOT (Design-Build-Finance-Operate and Transfer) scheme. The Project road presently starts from km 40+000 to km 190+861 falls in Nalgonda District of Telangana State and km190+861 to km 221.500 falls in Krishna District Andhra Pradesh State. This section of NH-9/NH-65(New) provides connectivity from the Telangana State Capital of Hyderabad to Vijayawada. The Supervision Team of the Independent Consultancy Services for the Project is carriedout the design review as well as regular site inspections as per the Contract. The compliance to the instructions /comments is being attended by the Concessionaire.
The Land acquisition in approximately 100.00% area for 4-Laning has been completed. The land acquisition is hindering the present phase of Construction 6-Laning for 165m, future 6-Laning for 1025m, for Service Road in 1255m and 3005m ROW drain as per the record submitted by the Concessionaire. The additional land required at Junction location has been submitted by the Concessionaire in the month of Sept’ 2012 to the Authority, and its acquisition is under process. The encumbered land is hindering the works in various forms i.e. at some locations it is hindering the service road, junctions and the additional lane for future six laning accordingly the utility shifting. Most of the utility shifting has been completed except for Choutuppal, the same is under progress. The Authority has made part payment for the utility services shifting and thus the utility removal/shifting are still in progress. The Concessionaire has been raising the issue regarding payment of storage and contingencies charges, the issue has refered to Executive Committee,NHAI and Executive Committee given its decision and communicated the same to the Concessionaire. The progress of electrical lines, RWS/ Krishna Water pipeline, Tree cutting are 97.40%, 93.30%, 100.00% respectively. The major balance works included in punch list are Drains, Balance works of Service Road some of them are under CA scope and balance are under COS, Part of Toll Plazas such as Static weigh bridges,Street lighting, way side amenities etc. Most of these works were left untouched due to land constraint, for Change of scope order and Approval from Authority. The long awaited notice for COS-2 (additional service roads as per public demand), Service roads and foot over bridges was issued by the Authority in the month of July’2013, but these works under COS Service roads has not been started by the Concessionaire even after many instructions from the NHAI and IE’s office for want of COS order. The submission for COS costing analysis from the Concessionaire is completed and ICT,HQ forwarded the COS with comments to PD,NHAI for further necessary action,but the PD,NHAI returned back the same with comments. The Concessionaire submitted the drawings and cost analysis of footover bridges and additional service roads after incorporating the corrections suggested by RO office and PD office to IE and IE subsequently after scruitiny forwarded the same to the Authority for their verification and issuing “Change of Scope order” and relesing advance payment as per clause 16.2/3 of CA. As per directions from PD,NHAI the IE issued “change of scope order” for 5 nos of “footover passes” to Concessionaire and on recommendation from IE, The PD,NHAI released advance payment of 20% as per CA to the Concessionaire. The fabrication work of these 5 footover bridges started during April 2014 and are to be completed by June 2014 as per initial programme but not completed in all respects till end of July 2014 The Engineer recommended for issue of Completion Certificate as per Article 14.2 on the 19th March 2013, as all the items indicated in the Punch list have been completed except for those stretches where the occupation or encumbrance free land could not made available by the Authority or reasons not attributable to the Concessionaire, the submission is under review of the NHAI. Further as per decision at NHAI head quarted the IE recommended revised Provisional completion in the month of May 2014.by additing 2km chillakallu stretch, which is not included earlier during PCOD. From 00 hours of 22-07-2014 after consent of CGM,RO and PD,NHAI on recommendation by IE, the Concessionire started collecting additional toll at TP-3 for 2 km Stretch i.e. from Km 202+250 to Km 204+250. The Plan and Profile for the 181.873 km of main carriageway from km 40+000 to km 221+873 had been reviewed, commented. The P&P of the additional service road of 8.94 km length notified under COS-1 by NHAI had also been reviewed and commented. The plan & profile of additional length of service road communicated under recent COS( of 10.314 km) due to re-adjustment of lengths and widths of existing service roads of original scope and COS-1 were also reviewed except for 6.440 km of Chityal, Chikatigudem, Tirumalagiri-1,Madavaram, Mukundapuram village and Tirumalagiri-2.
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
All the drawings of Junctions from km 40+000 to km 221+873 have been reviewed and commented. The Junctions have been constructed as per the reviewed drawing except for the locations/ areas, where the required land width is not yet acquired or available, which shall be completed by the Concessionaire as and when the required land is made available. The recorded completed works on the Main carriageway towards Clearing & Grubbing, Embankment, Sub Grade, GSB,WMM-1st, WMM-2nd, DBM 1stlayer,DBM 2nd layer, BC and kerb casting construction has been completed except for the RUB approach construction at km 77+800( which is now under progress). The work progress of Structures is 100% for HP culverts, Box Culverts and Minor Bridges, PUP, CUP, VUP. The PD,NHAI instructed for starting execution of RUB approaches as the Pushing work of RUB is completed. The audited Escrow account has not been submitted by the Concessionaire since the start of the Project. The Mile stone-I, II & III, achievement could not be concluded /commented by the financial expert of IE, however the conditions other than financial expenses of the Milestones I, II and III have been achieved and Provisional completion recorded on 20th Dec 2012, which is within 90 day of Scheduled Completion date. Due to land constraint the service road work at Chityal, Chouttupal, Munagala, Wayside amenities at two locations, six lane at Chityal, chouttupal, Munagala and balance works at Toll Plazas are effected. The Vigilance Team has checked the Project works in the month of Dec’2012 and have forwarded its observations/deficiencies in the work. The concessionaire has been asked to report the corrective measures taken at site. The reply for the same is received from the Concessionaire. The IE has prepared its comments/compliance on the observation concerning to the IE and submitted the same to the Authority for their further needful action. During the July 2013 the high power committee of NHAI HQ approved additional service roads at different locations like veliminedu-BHS, Aitipamula-BHS, additional S.R. at chityal on LHS, additional at suryapet - LHS, Mukundapuram-BHS, Madavaram-BHS, Chikatigudem-RHS, Uppalapahad-RHS, Tirumalagiri-BHS, Jaggayyapeta to Tirumalagiri-BHS, foot over bridges at 5 locations i.e. at Choutuppal-2 nos, Chityal -2 Nos and Khetapalli - 1 no. The Concessionaire has been advised for submitting the programme for completing the approved COS, but,the Concessionaire start execution of foot over bridge in the month of April 2014 but work still not completed The Work of replacement of dead median plantation and Avenue trees is not satisfactory, the night traffic is facing lots of bright light glare. This is being informed to the Concessionaire regularly. The services of IE had asked to be extended till 31st Dec.2013, further in the month of December 2013, NHAI instructed the IE to extend the services up to June 2014 or till the appointement of Operation & Maintenace Consultant which ever is earlier. Recently in the Month of June 2014 PD,NHAI instructed for further extension of services up to Sep 2014 The Concessionaire has raised claim for losses under Article 34 and 41 for Change in Sand Mining Law and Force Majeure, due to Talangana agitation. The IE has given legal opinion for the same to the Authority. Further the Concessionaire has asked for permission to display Commercial advertisement boards at the Toll plaza and Bus Shelters. Proposal of area distribution etc. as per Ministry circular received recently and comments are already forwarded to NHAI by IE. Recently the CGM(RO),NHAI instructed not to erect the Advertisement boards on the highway.But, the Concessionaire again represented by showing latest circular to IE, after review IE forwarded to PD,NHAI, which is under scrutiny at PD,NHAI office The Concessionaire started execution of utility shifting at Chouttupal.The safety precautions like Solar blinkers,bar Marking as directed by CGM,RO has been done at 24 Median openings/junctions and at balance locations work yet to be taken up. The IE issued revised Provisional completion certificate by including balance 2.000 km length of Main carriageway on 26-04-2014, the approval from Authority is received on 19-07-2014 and 2nd PCOD recommended on 21-07-2014 . The monthly site inspection for checking the maintenance work executed for the month of July 2014 was carried out on 6th August 2014. The site inspection reports of IE are also enclosed herewith.
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
1.1 Introduction
Andhra Pradesh is a State in South-Eastern India and is part of the linguistic-cultural region of South India. It lies between 12°41' and 22°N latitude and 77° and 84°40'E longitude, and is bounded by Maharashtra, Chhattisgarh and Orissa in the north, the Bay of Bengal in the East, Tamil Nadu to the South and Karnataka to the West. Andhra Pradesh is the fifth largest State in India covering an area of 275,068 sq km and is the major linking State between the North and the South of India. It is the biggest and most populous State in the South of India and is considered as the rice bowl of India. The State is crisscrossed by two major rivers, the Godavari and Krishna. Andhra Pradesh can be broadly divided into three regions, namely Coastal Andhra, Telangana and Rayalaseema. Coastal Andhra occupies the coastal plain between Eastern Ghat ranges, which run along the length of the State, and the Bay of Bengal. Telangana lies west of the Ghats on the Deccan Plateau. The great Godavari and Krishna rivers rise in the Western Ghats of Karnataka and Maharashtra and flow east across Telangana to fall into the Bay of Bengal in a combined river delta. Rayalaseema lies in the southeast of the State on the Deccan plateau, in the basin of the Penner River. It is separated from Telangana by the low Erramala Hills and from Coastal Andhra by the Eastern Ghats.
1.2 Project Road Alignment
The National Highway No. 9 starts at Pune and ends at Machhilipatnam enroute Hyderabad, Vijayawada, and Sholapur. The highway traverses a distance of about 841 km through the States of Maharashtra (336km), Karnataka (75km) and Andhra Pradesh (430km) as shown in Figure.
The Government of India has decided to create a world-class infrastructure facility in order to keep the excellent momentum of economic development in the country, of which National Highway holds prime role. National Highways Authority of India (NHAI) is responsible for the development and management of these Highways under the National Highways Development Programme (NHDP).
NH 9 Hyderabad
Vijayawada
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
The NHAI has proposed to widen certain selected stretches of National Highways to 4/6 lanes connecting capital states and Seaports with contries NH networks. Under this NHDP Phase III programme, it is proposed to widen the existing 2-lane to 4/6-lane with partial access control under BDFOT (Build-Design-Finance-Operate-and Transfer) scheme from km 40+000 to km 190+861 and km 190+861 to km 221.500 in Nalgonda and Krishna Districts of Andhra Pradesh State respectively. National Highway No-9 provides connectivity from the State Capital of Hyderabad to Vijayawada. The present Project covers 4/6 laning of the stretch from Malkapuram (km 40.000) to Totacherla village (km 221+500) on Hyderabad-Vijayawada section of NH-9.
The Concession Agreement for the Project was signed between M/S GMR Hyderabad-Vijayawada Expressway Pvt. Ltd. and NHAI on 9th Oct. 2009.
The Independent Consultancy Agreement for supervision of the Project was signed on 16th April 2010 between M/S Intercontinental Consultants and Technocrats Pvt. Ltd. and NHAI.
1.3 CONDITION OF EXISTING PROJECT ROAD
The existing project road is a two-lane carriageway of about 7.0m wide with 1.0m-2.0m earthen shoulders on either side. The formation width varies from 7.7m to 25.3m. Earthen shoulder width varies from 1.0m to 2.0m on either side all along the road. The condition of the shoulders varies from fair to poor with frequent rain cuts and at places is in loose condition. Almost throughout the section the earthen shoulder were found to be at level with the pavement but at some locations with reverse camber. Paved shoulder is present at built-up and commercial areas, width varying between 1.0-2.0m in good to fair condition. The height of embankment varies from 0.5 to 5.0m. Existing high embankment of 6m to 7m is available in approaches to the bridges. The condition of the embankment is fair to poor with rain-cuts at some locations.
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
2.1 SALIENT FEATURES OF THE PROJECT:-
S.No Particulars Details
1. Grant / Revenue Share 32.6% of the total realizable fee + 1% additional for each year for the subsequent years to be paid to NHAI.
2. Construction Period 30 months (2 ½ years)
3 Concession Period 25 Years including construction period of 2 ½ years.
4 Name of SPV GMR Hyderabad Vijayawada Expressways Pvt. Ltd
5 Designed length of the Project 181.50 Kms
6 Proposed ROW 60m
7 Estimated Project Cost (Civil Works)
Rs. 1170 Cr.
8 Total Project Cost Rs 1740 Cr
9 Date of agreement 09th October 2009.
10 Schedule Date of Completion 30 months from Appointed Date i.e.6th April 2010 Completion date=2nd Oct 2012
11 Name of Independent consultant and date of appointment
M/s Intercontinental Consultants and Technocrats Pvt. Ltd. Agreement date 16th April 2010, Commencement date 19th April 2010
2.2 SUMMARY OF TECHNICAL DETAILS OF THE PROJECT:-
S.No Particulars Details
1 Total project Road 181.500 km of 4/6 lanes from km 40+000 to km 221+500
2 Total No. of Bypasses 6 Nos (i) Narketpally: (From Existing Km. 85.338 to 88.826) (ii) Nakrekal: (From Existing Km. 110.506 to 115.592) (iii) Kodada: (From Existing Km. 175.6 to 183.585) (iv) Akupamula: (From Existing Km. 171.800 to 173.400) (v) Sher Mohammad Peta: (From Existing Km. 195.30 to 198.80) (vi) Navabpet: (From Existing Km. 214.7 to 217.700)
3 Total No.of CD Structures 399 Nos as per CA
a) Major Bridges 3 /3 Nos as per CA / as constructed
b) Minor Bridges 45 /44 Nos. as per CA /as constructed
c) Slab / Box Culverts 77/133 Nos as per CA/as constructed
d) Pipe Culverts 108/234 Nos. as per CA/as constructed
4 Total No. of Major Junctions 19/19 Nos. as per CA/as constructed
5 Total No. of Minor Junctions 41/41 Nos. as per CA/as constructed
6 Total No. of RUBs 2 Nos. to be constructed by Railways (i) Km. 77/950 (Chityala) (ii) Km. 203/850 (Chillakallu)
7 Reserve Forest 1.265 Ha
8 Total length of service roads Length 51.660 Kms–additional approved 15.394 Kms- during 4 Laning
9 Total No. of Way side amenities 2 Nos
10 Total No. of Truck laybyes 7 Nos (Km. 48.87(L), Km. 63.280 (L), Km. 123.799 (L), Km. 135.340 (L), Km. 158.12 (L), Km. 191.5 (L) & Km. 201.60 (L)
11 Total No. of Vehicular Underpasses
17/15 Nos as per CA/as per site
12 Total No. of PUP / Cattle Underpass
28/30 Nos ((10/10 Nos Cattle Underpass) + (18/20 Nos Pedestrian Underpass)) as per CA/as per site
13 Total numbers of toll Plazas
3 Nos
At Km 60/650 at Narketpalli
118/250 at Nakrekal
205/025 at Kodada
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
2.3 PRE-CONSTRUCTION ACTIVITIES:-
A) LAND ACQUISITION STATUS:
Sl.no Description Total Km
Completed Progress Balance Completed Progress Balance Remarks
1 Land
Acquisition 181.500 181.400 0.100 0.000 99.9% 0.100% 0.0%
Considering present Scope of work(4-Laning)
B) Status of Utility Shifting and Tree cutting:-
Sl.no Description Total Km Completed Progress Balance Completed Progress Balance Remarks
1 Electrical works 117.230 114.180 3.050 0.000 97.4% 2.6% 0.0%
2 Rural water Works 133.046 124.167 8.879 0.000 93.3% 6.7% 0.0%
3 Tree Cutting 181.500 181.500 0.000 0.000 100.0% 0.0% 0.0%
2.4 Status of RUBs:-
S.No
Name of item Status
1. RUB at NH Km 77/834
GAD was submitted to Railways and also Centage charges of Rs. 20.16 lakhs also deposited with Railways. Approval of the Competent Authority has been accorded to take up the construction of RUB by Railways under Deposit Works. The Work of RUB construction started and completed and pushing of the box structure completed balance wing and return wall works balance
2. RUB at NH Km. 203.850 Centage charges of Rs. 21.01 lakhs paid to Rlys. Approval of the Competent Authority has been accorded to take up the construction of RUB by Railways under Deposit Work. The Rlys. Submitted the GAD along with Detailed Estimate for Rs. 15,37,54,481/- and the same has been submitted to NHAI HQ for the approval of the Competent Authority. The construction work started in the month of January’2012 and completed except return wall work
2.5 COMMENTS OF THE INDEPENDENT ENGINEER:
STATUS OF OBLIGATION OF CONCESSIONAIRE
a. The Concessionaire has not submitted the details or incorporated the comments regarding the following
activities: I. The maintence work is delaying due to dependency of Concessionaire on their EPC contractor
14.
Progress Mile Stones
1. 10% progress by -180th day from appointed date- 2nd October 2010 2. 35% progress by -400Th day from appointed date-11th May 2011 3. 70% progress by -650th day from appointed date-16th January 2012
4. 100% progress by-910th day from appointed date- 2nd October 2012
15 Provisional Completion Certificate issued date
1. 20-12-2012
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
2.6 STATUS OF LAND ACQUISITION AS ON 31st July 2014 (as per Concessionaire)
S.
No
Nam
e of
Mand
al
Name
of
Village
Fro
m
Ch
To
Ch
Len
gth
in
M
dist.
Fro
m
PCL
Si
de
Descripion of the
Obstruction Status As on 14.07.2014
4 lanin
g
6 lanin
g
Service Roa
d
Future 6
laning
ROW &
Drain
1 Choutuppal
Malkapur 40.485
40.510
25 11 Mts
LHS
Religious
structure
Mysamma Temple &
Uppalamma Temple
Compensation deposited with the Endowment Dept on 07.09.2010. The Endowment Dept has to undertake relocation. Due to local influence and political pressure, NHAI advised to hold relocation.
25
2 Choutuppal
Malkapur 40.950
41.000
50 18 Mts
RHS
structure
Cooperative Textile
park compound
wall.
Compensation paid but on the advise of RDO, demolition of compound wall in abeyance.
50
3 Choutuppal
D.Nagaram
48.280
48.310
30 Median
Religious
structure
Muslim Grave /
Kabristan
Muslim graves in median portion, Median width increased by 13 Mts (in RHS) to accommodate graves for construction of 4-Laning. 4-Lane shoulder edge at 23 Mts from PCL. Future 6 Lane can be adjusted in balance land width. If possession of land obtained, RHS side 6-laning can be adjusted in median side to make alignment smoother. As per Waqf board resolution (No. 1225 dated 13.12.2011), religious structure of minorities can not be disturbed
30
4 Choutuppal
D.Nagaram
48.747
48.777
30 11 Mts
LHS
Religious
structure
Vinayaka Temple.
Compensation awarded in favour of Endowment Dept. Mandal Administration identified alternate land for reloaction. The Endowment Dept and Mandal Administration to jointly take steps for relocation.( Ref MOM with collector NLG held on 17-09-2013)
30
5 Choutuppal
Lakkaram 51.350
51.420
70 22 Mts
RHS
Structure and land
1. VVR gardens
Compound wall (350 to 420) - at 22
mts from PCL.
2. Land dispute (300 to
400) at 15 Mts from
PCL - Affecting
service road
VVVR garden compound wall. Land (From 51+300 to 51+400 - 15 Mts from PCL) affecting service road construction (merging length) Initially this property was identified to be in Sy.No. 129 which is a Govt. Land, accordintly notified. But later the property owner disputed about the Sy.No. stating that it is a Patta land and he should get compensation for that. On Re-survey it is proved to be in Sy.No. 136 which is not notified. Therefore the matter is pending.SD and 3 A (1) are due.
70
6 Choutuppal
Lakkaram 52.140
52.160
20 22 Mts
LHS
Land & structur
e
Land & Structure
This property was attributed to Sy.No. 84 and notified. But the property owner produced document for Sy.No.82 which is not notified. Compensation for structures released but the land owners are insisting for land compensation. CALA is unable to pay for sy.No.82. Matter is unsettled.
20
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
7 Choutuppal
Lakkaram 52.350
52.800
450 22 Mts
RHS
Land & structur
e
Land & Structure
With Court Orders in W.P.18948/2009 not to disturb the Dargah on the LHS, the Central line was shifted 7.5mtr towards right to accommodate the 4 lane Road. Balance land is not sufficient to form the 9 mtrs Service Road. The LA process has to be intiated. It will affect 46 pakka structures.
450
8 Choutuppal
Lakkaram 52.450
52.650
200 10 Mts
LHS
Religious
structure
Dargah & Graves
As per the Wakf Board resolution No. 1225 Dt: 13.12.2011, Religious structures of Minorities are not to be disturbed. Even as per Wakf Act, we can not disturb them. Also Muthawali filed W.P.18948/2009 and obtained an order in his favour.
200
9 Choutuupal
Choutuppal
53.350
53.400
50 15 to 20 Mts
RHS
structures
Buildings
Compensation released to the Gramapanchayath Office, being vacated. Another structure owner sought for revaluation.Revaluation report recevied on 16-07-2014. proccedings to be issued by CALA for releseing compenstion.
50 50
10 Choutuppal
Choutuppal
53.250
53.280
Length Considered
13 Mts
LHS
Religious
structure
Hindu Grave Yard and Buildings
1 structure is covered by W.P.25129/2011. Ready for dismantling but it is conjoined with another structure which is covered by W.P.35199/2012, which is yet to be disposed. With regard to Hindu Graves in Pvt. Land, the GPLA yet to clarify legal positition sought by CALA.
30 30
11 Choutuppal
Choutuppal
53.500
53.515
15 13 Mts
LHS
Land
Ownership dispute – As per Govt. record, it is Govt. land whereas as per record with enjoyer it is patta land. Validity of supplementary Sethwar claiming the ownership for compensation to be finalised by the Joint Collector-Nalgonda. The enjoyer also approached the Court through W.P.21019/2012, which is yet to be decided.
15 15
12 Choutuppal
Choutuppal
54.120
54.220
100 26 Mts
LHS
structures
Buildings
Award for 3 structures is under process with CALA. These structures are falling in the land to be acquired for the Junctions. The Priliminary Valuation and Award passing is due.
100
13 Choutuppal
Choutuppal
54.700
54.750
50 24.5 mtr
RHS
Electrical
Electrical line (HT Tower (feeder
line) @ 132 KV
substation)
1.NHAI provided approved estimate after curtailment of some amount. 2.Provisions are denied to be paid out of approved estimate of Rs. 99 Lakhs. 3.No contractor is ready to take up work at that cost. Same is duly informed to NHAI for consideration. 4.Yet to receive reply. However present P.D. is of opinion that Concessionaire is to get relocation done in approved estimate only. 5.As per document, estimate is not final and is liable to change as per site condition. Also, rates confirming to SOR 2009-2010 only which is in variance with present market rate.
50
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
14 Choutuppal
Panthangi 59.860
59.880
20 27 Mts
LHS
structure
Land & Building
Survey dispute of village limit (Lingojigudem or Panthangi) These lands are actually notified under Panthangi Village but on Re-survey it is found to be incorrect. Fresh notification has to be issued after this land is propoerly identified by the Survey Dept. Regional Deputy Director-Survey and Land Records verified the issue physically and the report is awaited.
20
15 Choutuppal
Panthangi 60+6
50
BHS
Land
Land problem for Toll Plaza-
1
After dimissal of W.P. 3087/12, the petitioners filed appeal No. W.A.66/14, whereupon the vacation Court granted Status Quo Order. In the hearing held on 21.01.2014 the High Court ordered .. " we refuse to allow continuation of the interim Order granted earlier. We make it clear that every thing will abide by the result of this Appeal". From this second interim order it is evident there is risk of foregoing the construction cost if the appeal is decided in favour of the appellants.
16 Chitya
la Valimined
u 65.900
66.000
100 10.5 Mts
RHS
Religious
structure
Hanuman temple
Concessionaire was directed by NHAI not to disturb the temple due to local political pressure.( As recorded in MOM dated 29.01.2013 issued by JC - Nalgonda)
100
17 Chitya
la Velimined
u 69.700
RHS
Land Way side Amenity
T, R & B (Roads III) Department has sought proposal under G.O.Ms.No. 571 Dt 14-09-2012 from EnC (R&B), SR and CGM NHAI for taking further action in the matter. The assignees of this land obtained interim direction in W.P.13928/2013 from the A.P.High Court not to alienate till further orders in the matter.Besides , delivery posseesion is inevitable for compliance GO.MS .NO 571 dated 14-09-2012.
18 Narketpally
Goplaipally
84.360
84.380
20 27.5 Mts
LHS
structure
Sivanada Plastics.
Payment made, but enjoyer not allowing to for demolition ( Partner is a leading Politician pressurizing Administration not to demolish)
20
19 Narketpally
A.P.Lingottam
90.600
90.610
10 23 mts
LHS
structure
Huts
Enjoyer approached court against GMR (OS No. 48/2012) stating that concessionaire is trying to grab more land than payment made.GMR counter filed. Case pending.
10
20 Kattangoor
Pamangundla
94.300
94.400
100 25 to 28.7 Mts
RHS
Land Govt. Land
Assigned land bought by present enjoyer . Enjoyer constructed houses. CALA not accepting ownership of enjoyer, confirming land as Govt. land and not processing payment, Dist Admn has to take over the land and hand it over to us.
100
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
21 Kattangoor
Pamangundla
95.015
95.020
5 15 Mts
RHS
Religious
structure
Muslim Grave
As per Waqf board resolution (No. 1225 dated 13.12.2011), religious structure of minorities can not be disturbed. Structure is in earthen shoulder portion of 6 lane carriage way. Construction of carriage way without earthen shoulder , along with suitable toe wall can be considered to avoid relocation.
5
22 Kattangoor
Dugnevalli
98.450
98.460
10 20.5 Mts
RHS
Religious
structure
Anjanaiya Swami Temple
The locals prevented us from dismantling the Temple on four attempts, they have not accepted the compensation, approached the A.P.High Court and lost the case. Also went in Appeal which was also dismissed. For relocating, the Mandal Admn is exploring for an alternate site for relocation.(Ref MOM 17-09-2013)
10
23 Kattangoor
Kattangur 100.800
100.830
30 28 Mts
LHS
Land Evacuee
Land
Land defined under EP Land. As per GO 610, structure payment to be made. Payment received by enjoyers for structure but resisting demolition asking payment for land also. Enjoyers approached court W.P. 29083/2013.The enjoyers filed W.P.29083/13 not to interfere with this structure.
30
24 Kattangoor
Kattangur 101.030
101.060
30 13 Mts
LHS
Religious
structure
Masjid
As per Waqf board resolution (No. 1225 dated 13.12.2011), religious structure of minorities can not be disturbed. In another WP (No. 202/2013), High Court granted stay against Masjid demolition.
30
25 Kattangoor
Kattangur 101.200
101.205
5 27.5 Mts
LHS
structures
Bathrooms Missing structures. GK Land. 3A1 proposal sent to NHAI by CALA for initiation of notification (for 3A) in March'12. Notification still to be issued by NHAI.
5
26 Kattangoor
Kattangur 101.180
101.270
90 27.5 Mts
RHS
structures
Buildings 90
27 Katangoor
Aitipamula
104.770
104.780
10 27.5 Mts
RHS Religiou
s structur
e
Id Gah As per Waqf board resolution (No. 1225 dated 13.12.2011), religious structure of minorities can not be disturbed. When attempted by CALA to convince the locals, they revolted against him.
10
28 Kattan
gur Aitipamul
a 105.200
105.270
70 26 Mts
RHS
Kabristan 70
29 Kattan
gur Aitipamul
a 105.480
105.490
10 28 Mts
LHS
Structu
res House
Sy. No. 626 Extent: 303.52 sq. mts. 3A1 proposal sent to NHAI by CALA for initiation of notification (for 3A) in March'12. Notification still to be issued by NHAI.
10
30 Nakre
kal Nakrekal
109.750
109.830
80 28 Mts
RHS
Structu
res
Land
ownership
dispute
As per present enjoyer, private land in his name. As per revenue record, it is Govt. land. RDO to take initiative to dismantle up to ROW
80
31 Kethepally
Korlapahad
119.540
119.560
20 26 Mts
LHS
Religious
structure
Anjaneyaswami
temple
Temple missedout in the original notification. Temple managers reluctant to relocate. To take over it has to be notified for acquisition. Notification due.
20
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
32 Surya
pet Rayangud
em 129.200
129.205
5 28 Mts
LHS
Religious
structure
Venkateswara swamy
Temple (28m from
PCL)
Compensation released. Regarding relocation of this Temple it was discussed in the review meetings with the Dist Collector-Nalgonda on 29.01.2013, 05.03.2013 & 17.09.2013. CALA has to take possession.
5
33 Surya
pet Pillalamar
ri 131.590
131.600
10 22 Mts
LHS
Religious
structure
Shivalayam Arch
Missed earlier. Estimate for arch to be prepared by R&B Dept (as per MOM of JC dated 29.1.13). Estimated value Rs.3,75,000/-. Ref RC No.3/3488/2010 Dt: 08.10.2010 from Endowment Dept. Awrad has to pass before removal.
10
34 Surya
pet Pillalamar
ri 131.850
131.860
10 24 Mts
RHS
Land &
Structure
Land & Buildings
Legal dispute between present and past enjoyer on ownership issue. (Maragoni Nageswara Rao
VS Nandala Varalaxmi)) Compensation deposited in the court. OP No. 122/2011 In ADJ Suryapet.
10
35 Surya
pet
Suryapet (Santhina
gar)
139.770
139.780
10 27 Mts
RHS
Religious
structure
Veerabramhendra swamy temple
Payment dispute as temple constructed after 3A publication (as per record of revenue department). Local people resisting further acquisition. CALA, RDO has to assist NHAI officials for demolition the structure.
10
36 Surya
pet
Suryapet (Santhina
gar)
139.800
139.820
20 28 to
30 Mts
LHS
Structures 28 to
30 m from PCL
4 lane & SRcomplet
ed. Compensation not paid
for the structures 28 to 30m from PCL.
WP.NO 19609/14 and WP.NO 19613/14 were filled by the ocupants. Court orderd not to disposes without following due process of law.
20
37 Surya
pet
Suryapet (Santhina
gar)
139.800
139.820
Length already Considered
28 Mts
RHS
Religious
structure
Hanuman Mandir
(Removed upto 26 m from PCL)
Temple committee received the compensation. Temple removed up to 28m from PCL. People are objecting the removal from there onwards. The temple committee to be served notices under the control of National Highways (Land & Traffic) Act 2002 by NHAI.
20
38 Surya
pet Durajpalli
141.400
141.470
70 26 Mts
LHS
Navaratna rice
mill (Owner: Meela
satyanarayana)
4 lane completed. Affecting only 60 m
ROW.
Compound Wall Removed but Compensation not released for Chimney. Estimates are under scrutiny of R&B Dept. To be compensated after the estimates are approved.
70
39 Surya
pet Durjapllay
142.600
142.660
60 28 to
30 Mts
LHS
Structure
ESSGE plastic
Enjoyers represented that to the extent of compensation paid structures are dismantled. The part of another structure which is falling in the ROW not compensated as per him. Our best efforts to explain with the estimate copy failed. CALA to address R&B of NH Division to verify the claim . His claim for compensation of Rs.88 Cr under several heads is pending before
Arbitrator cum Joint Collector. The acquiring authority has to take steps to give possession upto 60 mtr ROW by dealing with the property owners.
60
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
40 Surya
pet Durjapllay
143.100
143.105
5 15 Mts
RHS
Religious
structure
Durga MathaTem
ple
Dist Admn has to take up relocation as locals are not permitting us to dismantle. Since the structures beyond ROW , the structures to be compensated as agreed in the MOM dated 14-09-2010 with The principal Secretary T R&B. In the meeting also held on 21-11-2010 with Dist, Collector that it was orderd to compensate and remove all those temples which are not the then ROW. (i.e 30 meters ROW)
5
41 Surya
pet Durjapllay
143.400
143.420
20 27 Mts
LHS
Religious
structure
Lingamatula Temple
arch
When compensation was paid for the Religious structures in this Revenue Division, this Arch was omitted considering in Shikam land. Due to social pressure, NHAI is suggesting to leave it as not interfering with operations.
20
42 Munagala
Munagala 162.050
162.200
150 24 Mts
LHS
Structure
Electric sub station
Compensation for boundary wall not paid. CALA has written to R&B for estimate.
150
43 Munagala
Munagala 163.290
163.360
70 14 Mts
LHS
WAKF Land & Muslim Grave yard
4 laning completed Affecing for 6 lane +SR
WAKF Land.
Compensation for Wakf
structures and their
removal is due.
As per Wakf resolution No.1225 the Award passed and compensation made ready. CEO-Wakf Board is not inclined to collect the compensation. Locals are not permitting us to dismantle the old Graveyard and its compound wall. CALA promised to resolve the issue.
70 70
44 Munagala
Munagala 164.400
164.480
80 13 Mts
RHS
Missed out bits
Sy No. 423/1, 447,448,449 Missed out in notification. Proposal for direct purchase sent to NHAI, later it was included in the 3A (1) notification proposal of missed out Bits to be notified by NHAI.
80
45 Munagala
Bharakatgudem
166.020
166.040
20 27 Mts
RHS
Religious
structure
Masjid
Compensation paid and when the dismantling was in progress in 2010, District Collector intervened. Thereafter the Wakf Board intervened. The structures is at 27 mtrs from PCL. Drain constructed.
20
46 Munagala
Bharakatgudem
166.350
166.360
10 24 to
28 LHS
Structure
Buildings Private structures in Govt land. Not compensated then now propose to be compensated under G.O.Ms.No.610 Dt: 31.05.2011 for which estimates are being verified by R&B prior to release the compensation by CALA..
10
47 Munagala
166.400
166.410
10 24 to
30 Mts
LHS
Structure
Buildings 10
48 Munagala
Akupamula
168.150
168.400
250 18.5 to 30 mts
RHS
Revenue boundaries to be fixed by Revenue
department
As per revenue survey, no further land to be acquired As per site, land available varies from 19 to 30 Mts. CALA to provide administrative support for fixing boundaries.
250
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
49 Munagala
Akupamula
168.200
Way Side Aminity LHS
Land Land
This piece of land is spread over Sy. No’s 350, 351, 353, 354 and 371; comprising of abandoned NH 9 road, government land and patta land. CALA is processing the case for alienation. The private land owners are objecting through political forces and are not allowing us to work even in the government land and abandoned NH 9 road. Collector Nalagonda assured on 12/12/2013 to resolve the matter early.
50 Munagala
Akupamula
171.450
171.700
250 18 to
20 mtr
LHS
Items Missed out in
acquisition
Notification of land missed
out. 4 lane completed.
ROW affected.
Missed in initial notification Land shortage already notified to NHAI for land acquisition. All details provided to NHAI to initiate LA process. Acquisition process yet to be commenced.
250
51 Jaggaiahpet
Garikapadu
191.350
191.365
15 24 to
28 Mts
RHS
Structure
Compound wall
The Awarded extent is morethan actual affected in the alignment. Therefore the enjoyers refused to take compensation. Revised estimates prepared. Now the proceedings have to be revised by the CALA.
15
52 Jaggaiahpet
Anumanchipalli
192.450
192.650
200 18 to
25 mts
RHS
structures
4 laning completed. Affecting
for future 6 laning.
Anumanchipally SC
/ST colony cheques
rcd & Distributed
(20 nos distri buted against 54
nos .).
This is SC Colony in assigned land. Compensation released
recently for all the eligible assignees. The CALA has to
vacate in-eligible occupants, so that the total structures can be
removed.
200
53 Jaggaiahpet
Shermohammadpet
a
197.300
197.550
250 13 Mts
LHS
Missed out bits
Earlier Missed 3G completed, Award to be passed by CALA.
250
54 Jaggaiahpet
Jaggayyapeta
199.370
199.400
30 20 Mts
RHS
structure
Compensation yet to be released
by CALA. 30
55 Jaggaiahpet
Chillakallu 202.250
202.300
50 17 Mts
LHS
Land Missed out
bits
Missed out in initial acquisition Acquisition process restarted. 3G (3) yet to be published.
50
56 Jaggaiahpet
Chillakallu 202.300
203.100
800 28 to
30 Mts
LHS
Land & Structur
e
Missed out bits,
school, Police Station
Land available not matching with alignment. Acquisition process restarted. 3G (3) yet to be published.
800
57 Jaggaiahpet
Chillakallu 202.400
202.520
120 23 to
25 mts
RHS
Land
Missed out bits,
school, Police Station
Missed out in initial acquisition Acquisition process restarted. 3G (3) yet to be published.
120 120
58 Jaggaiahpet
Chillakallu 202.520
203.100
580 24 to
30 mts
RHS
Land & Structur
e
Missed out bits, shops & temple
Land available not matching with alignment. Additional land required as per site. Details already forwarded to NHAI for acquisition. Work completed by pursuing with land owners. 3D proposal submitted by CALA to NHAI for publication.3D SO.NO 749 Published on 13-03-2014.3G under process with MRO.
580
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
59 Jaggaiahpet
Chillakallu 205.295
BHS
Land
Land problem for Toll Plaza-
3
Some plot owners approched A.P.High Court in W.P.No.s15467/2012, 16349/2012, 25663/2012 & 31263/2012 inrespect of Patta lands of Bhimavaram (V). With respect to the Govt. Land in Chillakallu falling in Sy.No. 122, 127 & 261, the alienation process is in progress with the CALA
60 Penuganchip
rolu
Konakanchi
212.380
212.400
20 26 to
28 mts
RHS
Religious
structure
Anjayneya swamy temple.
Anjayneya swamy temple. Payment ready with MRO. Temple authority not willing to shift the temple claiming work already completed. Local Political Pressure not to remove temple.
20
61 Nandigama
Munagacharla
219.200
219.350
150 22 mts
RHS
Land - Archeological
department
4 laning completed.
No
As per Notice board fixed in land, land belongs to archeological dep't. Board indicating it as prohibited land NHAI has been informed and requested for possession of land. NHAI to initiate land acquisition.
150
62 Nandigama
Nandigama
221.330
221.350
20 19 mts
LHS
open well
Well paymnet to be made. Matter is pending
with NHAI
Well valuation not done while structural valuation. Payment of well to be released.
20
63
Junctions
formation
All Divisions:
Structures estimation completed and verified by R&B-NH division. Awaiting for reports in Nalgonda District (from km 40 to 190). Preparation of PV’s in progress for land acquisition in Krishna District (km 190 to 221.5). Vijayawada Division 3D SO.NO 749 Published on 13-03-2014.3G under process with MRO.
0 165 1125 1025 3005
Sr. No. Description
Length Remarks
A 4 lane 0
B
Present Phase
6 laning 165
D Service Road 1125
C
Future Six
Laning 1025
E
ROW &
Drain 3005
NOTE:-
1. TP-1 & TP-3 has also some balance work due to land problem
2. 2 no,s Wayside Amenity balance due to land not available
3. 59 no,s Junctions developed in available land due to land problem
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
3.1) WORK PROGRESS a) STATUS OF HIGHWAY WORK PROGRESS
S.No Description Side Total Km Completed Progress Balance Completed In Progress Balance Remarks
1 Cle & Grub LHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
2 Emb LHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
3 Subgrade LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
4 GSB LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
5 WMM I LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
6 WMM II LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
7 DBM I LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
8 DBM II LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
9 BC LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
10 Kerb LHS 181.635 181.555 - 0.080 99.96% 0.00% 0.04% RUB portion
RHS 181.635 181.635 - 0.000 100.00% 0.00% 0.00%
B) PROGRESS BAR CHART OF HIGHWAY WORKS
LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS
CLE & GRUB EMB SUBGRADE GSB WMM I WMM II DBM I DBM II BC KERB
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
99
.96
%
10
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
0.0
4%
0.0
0%
Completed In Progress Balance
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
C ) STATUS OF STRUCTURE/BRIDGE/CROSS DRAINAGE WORK PROGRESS
S.No Description Side Total Str Completed Progress Balance Completed In Progress Balance Remarks
1 PIPE
CULVERT
LHS 223 223 0 0 100.00% 0.00% 0.00%
RHS 218 218 0 0 100.00% 0.00% 0.00%
2 BOX
CULVERT
LHS 132 132 0 0 100.00% 0.00% 0.00%
RHS 129 129 0 0 100.00% 0.00% 0.00%
3 MIN BRIDGE LHS 38 38 0 0 100.00% 0.00% 0.00%
RHS 25 25 0 0 100.00% 0.00% 0.00%
4 MAJ BRIDGE LHS 1 1 0 0 100.00% 0.00% 0.00%
RHS 3 3 0 0 100.00% 0.00% 0.00%
5 CUP LHS 10 10 0 0 100.00% 0.00% 0.00%
RHS 10 10 0 0 100.00% 0.00% 0.00%
6 PUP LHS 20 20 0 0 100.00% 0.00% 0.00%
RHS 20 20 0 0 100.00% 0.00% 0.00%
7 VUP LHS 15 15 0 0 100.00% 0.00% 0.00%
RHS 15 15 0 0 100.00% 0.00% 0.00%
8 RUB LHS 1 1 0 0 100.00% 0.00% 0.00%
RHS 1 1 0 0 100.00% 0.00% 0.00%
D) PROGRESS BAR CHART OF STRUCTURES/ CROSS DRAINAGE WORKS
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
10
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS
PIPECULVERT
BOXCULVERT
MINBRIDGE
MAJBRIDGE
CUP PUP VUP RUB
Completed
In Progress
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
E) STATUS OF MOBILIZATION OF PLANT AND MACHINERY
Plant & Machinery Mobilization status
S.No Equipment
Available at camp
Total available
Km 73 Camp Km 159 Camp
1 Dozer 0 0 0
2 Excavator 1 1 2
3 Motor Grader 1 1 2
4 Soil Compactor 2 1 3
5 Dumper 3 1 4
6 WMM Paver 1 2 3
7 Asphalt Paver 1 2 3
8 PTR 1 2 3
9 Tandem Roller 1 2 3
10 Kerb Machine 1 1 2
11 Concrete Pump 1 2 3
12 Hydraulic Crane 0 2 2
13 Water Tanker 3 3 6
14 Transit Mixer 1 1 2
15 Hydra Crane 1 1 2
16 JCB 1 1 2
17 Bitumen Distributor 1 1 2
18 loader 1 1 2
19 Stone Crushers 200TPH 0 0 0
20 Concrete Batching Plants 0 1 1
21 Wet Mix Plant 0 1 1
22 Hot Mix Plant 0 1 1
23 Boom placer 0 0 0
24 Road Marking Machine 1 0 1
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
F)PLANNED VS ACHIEVED TARGET OF ROAD WORK UP TO DBM 2ND LAYER AND BC
Month
DBM Top Layer Status
EPC 1 EPC 2 GHVEPL Total
BIPL Section PLL Section
Cumulative Planned
Cumulative Achieved
Cumulative Planned
Cumulative Achieved
Cumulative Planned
Cum Achieved by both EPC
Sep-11 65.00 79.04 115.00 113.89 180.00 192.92
Oct-11 70.00 88.42 124.00 126.06 194.00 214.48
Nov-11 77.00 99.65 137.00 142.38 214.00 242.03
Dec-11 84.00 106.02 150.00 153.15 234.00 259.17
Jan-12 91.00 108.17 163.00 161.88 254.00 270.05
Feb-12 98.00 112.69 176.00 169.63 274.00 282.32
Mar-12 107.00 116.39 193.00 187.59 300.00 303.97
Apr-12 117.00 118.47 209.00 196.02 326.00 314.49
May-12 126.00 120.78 226.00 206.32 352.00 327.10
Jun-12 130.59 127.24 232.60 220.15 363.19 347.38
Jul-12 130.59 128.61 232.60 223.92 363.19 352.53
Aug-12 130.59 128.76 232.60 225.99 363.19 354.75
Sep-12 130.59 129.00 232.60 226.30 363.19 355.30
Oct-12 130.59 129.00 232.60 229.06 363.19 358.06
Nov-12 130.59 130.59 232.60 229.98 363.19 360.57
Dec-12 130.59 130.59 232.60 229.98 363.19 360.57
Jan-13 130.59 130.59 232.60 231.22 363.19 361.81
Feb-13 130.59 130.59 232.60 232.60 363.19 363.19
Mar-13 130.59 130.59 232.60 232.60 363.19 363.19
Apr-13 130.59 130.59 232.60 232.60 363.19 363.19
May-13 130.59 130.59 232.60 232.60 363.19 363.19
Jun-13 130.59 130.59 232.60 232.60 363.19 363.19
Jul-13 130.59 130.59 232.60 232.60 363.19 363.19
Aug-13 130.59 130.59 232.60 232.60 363.19 363.19
Sep-13 130.59 130.59 232.60 232.60 363.19 363.19
Oct-13 130.59 130.59 232.60 232.60 363.19 363.19
Nov-13 130.59 130.59 232.60 232.60 363.19 363.19
Dec-13 130.59 130.59 232.60 232.60 363.19 363.19
Jan-14 130.59 130.59 232.60 232.60 363.19 363.19
Feb-14 130.59 130.59 232.60 232.60 363.19 363.19
Mar-14 130.59 130.59 232.60 232.60 363.19 363.19
April-14 130.59 130.59 232.60 232.60 363.19 363.19
May-14 130.59 130.59 232.60 232.60 363.19 363.19
June-14 130.59 130.59 232.60 232.60 363.19 363.19
July-14 130.59 130.59 232.60 232.60 363.19 363.19
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
Month
BC Top Layer
EPC 1 EPC 2
BIPL Section(2-Lane) PLL Section(2-Lane) GHVEPL
Total Cum Achieved
by both EPC
Cumulative Planned
Cumulative Achieved
Cumulative Planned
Cumulative Achieved
Cumulative Planned
Sep-11
Oct-11 1.50 2.61 2.50 3.71 4.00 6.32
Nov-11 16.00 16.51 28.00 30.30 44.00 46.80
Dec-11 30.00 28.81 54.00 63.26 84.00 92.07
Jan-12 46.00 39.02 83.00 91.00 129.00 130.01
Feb-12 62.00 49.78 112.00 103.53 174.00 153.31
Mar-12 78.00 68.93 141.00 142.94 219.00 211.87
Apr-12 95.00 82.07 169.00 163.84 264.00 245.91
May-12 112.00 111.05 200.00 183.83 312.00 294.88
Jun-12 130.59 121.26 232.60 199.40 363.19 320.66
Jul-12 130.59 128.30 232.60 221.30 363.19 349.60
Aug-12 130.59 128.35 232.60 224.23 363.19 352.58
Sep-12 130.59 128.66 232.60 224.54 363.19 353.19
Oct-12 130.59 128.95 232.60 224.54 363.19 353.49
Nov-12 130.59 130.59 232.60 228.60 363.19 359.19
Dec-12 130.59 130.59 232.60 228.60 363.19 359.19
Jan-13 130.59 130.59 232.60 228.60 363.19 359.19
Feb-13 130.59 130.59 232.60 232.60 363.19 363.19
Mar-13 130.59 130.59 232.60 232.60 363.19 363.19
Apr-13 130.59 130.59 232.60 232.60 363.19 363.19
May-13 130.59 130.59 232.60 232.60 363.19 363.19
Jun-13 130.59 130.59 232.60 232.60 363.19 363.19
Jul-13 130.59 130.59 232.60 232.60 363.19 363.19
Aug-13 130.59 130.59 232.60 232.60 363.19 363.19
Sep-13 130.59 130.59 232.60 232.60 363.19 363.19
Oct-13 130.59 130.59 232.60 232.60 363.19 363.19
Nov-13 130.59 130.59 232.60 232.60 363.19 363.19
Dec-13 130.59 130.59 232.60 232.60 363.19 363.19
Jan-14 130.59 130.59 232.60 232.60 363.19 363.19
Feb-14 130.59 130.59 232.60 232.60 363.19 363.19 Feb-14 130.59 130.59 232.60 232.60 363.19 363.19
Mar-14 130.59 130.59 232.60 232.60 363.19 363.19
April-14 130.59 130.59 232.60 232.60 363.19 363.19
May-14 130.59 130.59 232.60 232.60 363.19 363.19
June-14 130.59 130.59 232.60 232.60 363.19 363.19
July-14 130.59 130.59 232.60 232.60 363.19 363.19
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
4.1) Material/ Laboratory Report
(Enclosed as Annexure A)
4.2) STATUS OF APPROVAL OF BORROW AREAS /Mix Designs
GIL Section
Sl. No
B.A. No
Survey No Chainage Side Lead
in Km
No of Grids Pits
Area Proposed
Sqm
Approved Quantity in Cum
DOS /DOT
AVG. MDD (g/cc)
AVG. OMC
(%)
Material Suitability
1 14 420 70+000 LS 1.000 14 6250 9375 20.02.10 26.02.10
2.028 8.43 SG
2 14,EX 1 420 70+000 LS 1.000 10 7500 11250 21.06.10 23.06.10
2.04 8.35 emb
3 BA 14 control
tests 420 70+000 LS 1.000 14 - 21000
Upto 30.06.2011
2.105 8.4 emb
4 31 73/E,
74/E, 75/E 43+600 LS 3.50 10 6250 9375
13.02.10 28.03.10
2.071 6.39 SG
5 BA 31 control
tests 73/E,
74/E, 75/E 43+600 LS 3.50 3 4500
Upto 30.06.2011
2.04 9 emb
6 29 80,82&84 54+400 LS 1.50 10 6250 9375 01.03.10 18.04.10
2.049 8.66 SG
7 29 ,EX
1 80,82&84 54+400 LS 1.50 30 18750 28125
24.04.10 30.04.10
2.041 8.1 emb
8 BA 29 control
tests 80,82&84 54+400 LS 1.50 32 - 48000
Upto 30.06.2011
2.095 8.6 Emb/sub
9 32 7,74 &75 48+500 RS 1.50 10 6250 9375 30.03.10 12.04.10
2.09 7.76 SG
10 32,EX 1 7,74 &75 48+500 RS 1.50 40 25000 37500 20.04.10 25.04.10
2.082 8.05 emb
11 32,EX 2 7,74 &75 48+500 RS 1.50 20 12600 18900 17.06.10 22.06.10
emb
12 33 58 47+000 LS 1.5 10 6250 9375 30.03.10 10.04.10
2.087 7.95 SG
13 36 357 82+000 RS 1.0 10 6375 9563 26.04.10 04.05.10
2.058 8.98 SG
14 36,EX 1 357 82+000 RS 1.0 10 6525 9787 18.06.10 20.06.10
2.055 7.8 emb
15 38 162,204 74+000 LS 1.0 10 6225 9338 29.04.10 07.05.10
1.995 8.29 emb
16 1 97+200 RS 2.5 10 6375 9563 31.01.10 20.02.10
1.988 8.44 SG
17 3 100+275 RS 2.75 10 6300 9450 01.02.10 10.02.10
2.059 8.65 SG
18 8 74+000 LS 0.8 10 6225 9338 3.02.10
12.03.10 2.036 8.01 SG
19 BA 8
Control tests
74+000 LS 0.8 28 - 42000 Upto
30.06.2011 2.1 8 emb
20 24 75 91+700 LS 2.500 10 6375 9563 25.02.10 07.04.10
2.101 8 SG
21 24,EX 1 75 91+700 LS 2.500 30 18750 28125 24.04.10 28.04.10
2.086 8.1 emb
22 24,EX 2 75 91+700 LS 2.500 30 18750 28125 25.07.10 30.07.10
2.085 8.05 emb
23 BA 24 control
tests 75 91+700 LS 2.500 44 - 66000
Upto 30.06.2011
2.118 8.2 Sub
24 34 85+800 RS 3.600 10 6375 9563 31.03.10 30.04.10
2.057 8.42 SG
25 37 76+260 RS 1.750 10 6375 9563 28.04.10 10.05.10
2.04 8.18 SG
26 39 66,02 95+500 LS 2.000 10 6375 9563 02.05.10 2.059 8.34 SG
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
22.05.10
27 40 422,418,719 41+200 RS 1.500 10 6375 9563 04.05.10 04.06.10
2.063 8.24 SG
28 42 719 50+000 RS 1.000 10 6375 9563 07.06.10 08.06.10
2.07 8.04 SG
29 10 420 69+640 LS 0.200 10 6225 9338 17.02.10 18.02.10
2.075 8.3 SG
30 BA 10 control
tests 420 69+640 LS 0.200 42 63000
Upto 31.07.2011
2.15 8 emb
31 44 744 85+250 LS 2.000 10 6225 9338 10.06.10 15.06.10
2.076 8.3 SG
32 44,EX 1 744 85+250 LS 2.000 35 18750 34125 22.06.10 25.06.10
2.067 8 emb
33 BA 44
Control tests
744 85+250 LS 2.000 52 - 78000 Upto
30.06.2011 2.13 8.1 emb
34 46 119 103+500 RS 0.300 20 12500 18750 09.07.10 17.07.10
2.1 7.9 SG
35 BA 46
Control tests
119 103+500 RS 0.300 14 21000 Upto
30.06.2011 2.12 8.3 emb
36 48 343 87+780 RS 1 20 12500 18750 15.07.10 25.07.10
2.1 7.4 SG
37 49 362 64+500 RS 0.5 20 12000 18000 26.07.10 10.08.10
2.02 8.4 SG
38 BA 49
Control tests
362 64+500 RS 0.5 45 - 67500 Upto
30.06.2011 2.125 7.2 emb
39 50 97+390 RS 1.5 20 13000 19500 13.08.10 18.08.10
2.07 8.05 SG
40 51 100+930 LS 3.5 20 12500 18750 17.08.10 22.08.10
2.075 8.1 SG
41 52 100+930 LS 3.9 20 16000 24000 17.08.10 23.08.10
2.082 7.9 SG
42 53 69+600 RS 0.85 20 12600 18900 18.08.10 25.08.10
2.07 8.17 SG
43 62 271 85+750 RS 1.5 5 8075 12113 28.12.10 30.12.10
2.106 7.1 SG
44 60 294,298 74+600 RS 0.5 4 8500 12750 08.12.10 10.12.10
2.056 9.2 EMBK
45 61 165 57+700 LS 1 12 9000 22500 14.12.10 20.12.10
2.077 8.1 SG
46 BA 61
Control tests
165 57+700 LS 1 19 - 28500 Upto
31.08.2011 2.07 8 SG
47 65 599,600 77+360 LS 1.5 5 9000 13500 07.01.11 12.01.11
2.108 7.74 SG
48 BA 65
Control tests
599,600 77+360 LS 1.5 33 - 49500 Upto
30.06.2011 2.1 7.5 SG
49 66 101+000 LS 5 33 9000 49500 Upto
30.06.2011 2.106 7.8 SG
50 64 78+990 LS 2 49 9000 73500 Upto
31.5.2012 2.066 8.3 SG
51 57 51+500 LS 3 23 9000 34500 Upto
30.06.2011 2.102 8.2 SG
52 67 100+640 RS 2.5 47 9000 70500 Upto
30.06.2011 2.051 9 SG
53 69 49+630 LS 3.5 6 9000 9000 Upto
30.06.2011 2.09 8.4 SG
54 71 744 85+780 RS 4 5 24220 36330 Upto
30.09.2011 2.108 7.9 SG
72 78+100 LS 4 12 7500 18000 Upto
30.09.2011 2.11 7.4 SG
55 73 97+360 RS 2.5 39 75000 58500 Upto
30.11.2011 2.095 8.6 SG
56 74 65+050 LS 3 66 7500 99000 Upto 2.07 8 SG
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
31.3.2012
57 90+000 crusher
dust 90+000 LHS 1.5 11 10000 16500
Upto 31.3.2012
2.09 8 emb
58 75 100+640 RHS 3 4 15000 6000 Upto
30.11.2011 2.09 8 emb
59 76 86+700 RHS 4.5 31 50000 46500 Upto
31.3.2012 2.16 6.8 emb
60 77 50+560 LHS 1.5 20 15000 30000 Upto
30.11.2011 2.135 7.3 emb
61 78 74+600 RHS 1 45 40000 67500 Upto
31.8.2012 2.06 7.8 emb
62 79 78+900 LHS 3 3 7500 4500 Upto
31.8.2012 2.08 7.7 SG
63 80 54+650 LHS 2 36 7500 54000 Upto
31.8.2012 2.08 8 SG
64 81 47060 LHS 1.2 23 9000 34500 Upto
31.8.2012 2.08 8 SG
65 82 100+640 RHS 2.5 26 15000 39000 Upto
30.11.2012 2.08 8.4 SG
66 83 95+900 RHS 2 24 10000 36000 Upto
31.8.2012 2.12 8.8 SG
67 84 102+000 LHS 2 8 9000 12000 Upto
31.8.2012 2.1 6.8 SG
68 85 101+960 LHS 2 8 10500 12000 Upto
31.8.2012 2.12 6.8 Emb
69 Cutting
Soil 82 123000
Upto 30.11.2012
2.1 8.5 Emb
70 86 85+700 RHS 2.5 3 4500 Upto
31.8.2012 2.07 8.4 EMB/SG
71 87 86+700 RHS 2 25 37500 Upto
31.8.2012 2.14 7.8 R/W
72 88 80+270 RHS 2.1 6 9000 Upto
31.8.2012 2.07 8.33 EMB/SG
73 89 88500 lhs 2.5 111 200000 166500 Upto
31.8.2012 2.1 7.5 EMB/SG
74 90 50400 lhs 3 8 40000 12000 Upto
31.8.2012 2.08 8.3 EMB/SG
75 91 49150 RHS 2 18 55000
27000 Upto
31.8.2012 2.085 8 EMB/SG
76 92 101950 RHS 1 7 55000
10500 Upto
30.11.2012 2.11 7.4 EMB/SG
77 93 97360 RHS 1.5 14 60000 21000 EMB
Total quantity approved 2270961
Sl. No.
Date of casting
Trial Mix No.
Grade of
Concrete
Source Ceme
nt Brand
Cement
Content
(Kg)
ADMIXTURE Water Ceme
nt Ratio
%
Slump at 90
min (mm)
CA 20mm
(Kg/Cum)
CA 10mm
(Kg/Cum)
FA (Kg/Cu
m)
CA : FA
RATIO %
Brand Name
%
1 20.05.10 TM
No:3 M-15
74+000 GMRCrus
her
Ramco -
OPC 43
grade
280 BASF
(Rehobuild 920
h)
0.8 0.50 60 634 632 760 62:38
2 31.05.10 TM
NO:4 M-20 320 0.8 0.45 80 620 618 743 62:38
3 04.06.10 TM
NO:1 M-30 380 Fosroc
(SP 430 AA)
0.8 0.39 100 601 599 720 62:38
4 04.06.10 TM
No:2 M-35 400 0.8 0.38 105 592 590 710 62:38
5 28.07.10 TM
No:02 M-15
44+000 GMRCrus
her
290
Fosroc SP 430
AA
1 0.50 45 722 482 745 62:38
6 28.07.10 TM
No:02 M-20 320 0.8 0.50 60 699 467 722 62:38
7 06.08.10 TM
No:02 M-30 380 0.8 0.40 85 651 496 710 62:38
8 03.08.10 TM
No:02 M-35 400
0.85
0.40 100 678 450 696 62:38
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
9 07.09.10 TM
NO:1 Kerb M20
320 0.2 0.50 25 454 674 761 60:40
10 30.09.10 TM
NO:1 M40 430
0.75
0.40 110 661 437 681 62:38
11 12.11.10 TM
NO:2 M-15 290 1 0.50 45 722 482
Coasre:fine
522:222 62:38
12 23.10.10 TM
NO:2 M-20 320 0.8 0.50 65 703 464
Coasre:fine
505:215 62:38
13 01.11.10 TM
NO:2 Kerb M20
320 0.2 0.50 20 379 711 Coasre:fi
ne 558:238
58:42
14 12.11.10 TM
NO:2 M-30 380 0.8 0.40 100 651 496
Coasre:fine
497:211 62:38
15 22.10.10 TM
NO:2 M-35 400
0.85
0.40 100 678 447 Coasre:fi
ne 487:207
62:38
16 12.11.10 TM
NO:2 M40 430
0.75
0.40 110 658 433 Coasre:fi
ne 473:201
62:38
17 06.07.10 TM
No:03 M-15
90+000 Crusher
280
Fosroc SP 430
AA
0.9 0.50 55 839 446 734 63:37
18 06.07.10 TM
No:03 M-20 320 0.8 0.45 85 820 436 718 63:37
19 09.07.10 TM
No:03 M-25 350 0.8 0.45 100 737 480 696 63:37
20 08.08.10 TM
No:03 M-30 380
0.75
0.40 120 733 477 692 63:37
21 06.08.10 TM
No:03 M-35 400 0.7 0.40 140 699 468 697 62:38
22 13.09.10 TM
No:01 M-45 470
0.65
0.36 110 686 447 648 63:37
23 18.09.10 TM
No:02 M-45 460 0.8 0.36 100 695 454 659 63:37
24 25.11.10 TM
No:01 Kerb M20
320 0.3 0.45 30 423 708 784 60:40
25 27.01.11 TM
No:25 M-15
44+000 RHS
MAHA
290 1 0.50 25 742 492 Coasre:fi
ne 526:225
62:38
26 27.01.11 TM
No:26 KERB M20
320 0.2 0.5 20 449 670 Coasre:fi
ne 563:241
62:38
27 27.01.11 TM
No:27 M-20 320 0.8 0.45 45 733 488
Coasre:fine
520:222 62:38
28 28.01.11 TM
No:28 M-15
90+000 LHS
MAHA
280 0.9 0.50 25 776 514 740 63:37
29 28.01.11 TM
No:29 KERB M20
320 0.2 0.45 20 483 719 784 60:40
30 28.01.11 TM
No:30 M-20 320 0.8 0.45 50 759 502 724 63:37
31 30.01.11 TM
No:32 M-15
44+000 RHS
RAASI
290 1 0.50 25 742 492 Coasre:fi
ne 526:225
62:38
32 01.02.11 TM
No:35 KERB M20
320 0.2 0.5 20 449 670 Coasre:fi
ne 563:241
62:38
33 01.02.11 TM
No:36 M-20 320 0.8 0.45 45 733 488
Coasre:fine
520:222 62:38
34 30.01.11 TM
No:34 M-15
90+000 LHS
RASI
280 0.9 0.50 25 776 514 740 63:37
35 29.01.11 TM
No:31 KERB M20
320 0.2 0.45 20 483 719 784 60:40
36 30.01.11 TM
No:33 M-20 320 0.8 0.45 50 759 502 724 63:37
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
37 11.03.11 TM
No:44 M-35
44+000 RHS
MAHA
400 0.85
0.41 105 685 453 Coasre:fi
ne 484:206
62:38
38 12.03.11 TM
No:45 M-30 380
0.75
0.42 100 696 461 Coasre:fi
ne 492:209
62:38
39 17.03.11 TM
No:47 M-25 350 0.8 0.45 100 719 476
Coasre:fine
487:207 63:37
40 18.03.11 TM
No:48 M-40 430
0.75
0.40 100 668 442 Coasre:fi
ne 473:201
62:38
41 25.02.11 TM
No:37 M-30
90+000 LHS
MAHA
380 0.9 0.42 100 721 476 684 63:37
42 28.02.11 TM
No:40 M-35 400 0.8 0.40 110 714 472 678 63:37
43 09.03.11 TM
No:42 M-45 460
0.75
0.40 110 671 443 637 63:37
44 10.03.11 TM
No:43 M-25 350 0.8 0.45 100 733 484 696 63:37
45 26.02.11 TM
No:38 M-35
90+000 LHS
RAASI
400 0.8 0.40 105 714 472 678 63:37
46 27.02.11 TM
No:39 M-30 380 0.9 0.42 100 721 476 684 63:37
47 13.03.11 TM
No:46 M-25 350 0.8 0.45 100 733 484 696 63:37
48 21.03.11 TM
No:49 M-30
44+000 RHS
RAASI
380 0.8 0.42 105 696 461 Coasre:fi
ne 492:209
62:38
49 22.03.11 TM
No:50 M-35 400
0.85
0.41 110 685 453 Coasre:fi
ne 484:206
62:38
50 27.03.11 TM
No:51 M-25 350 0.8 0.45 100 719 476
Coasre:fine
487:207 63:37
51 19.07.11 TM
No:68 M-45
90+000 LHS Ramc
o - OPC
43 grade
460 BASF
(Rehobuild 920
h)
0.8 0.36 120 749 400 659 63.37
52 19.07.11 TM
No:69 M-35
90+000 LHS
400 0.9 0.42 105 768 410 675 63.37
53 24.07.11 TM
No:73 M-30
90+000 LHS
380 1 0.42 105 784 419 689 63.37
54 20.07.11 TM
No:70 M-35
44+000 LHS
MAHA
400
BASF (Rehobuild 920
h)
0.85
0.41 120 685 453 Coasre:fi
ne 484:206
62.38
55 25.07.11 TM
No:74 M-30
44+000 LHS
380 0.9 0.41 120 757 406 Coasre:fi
ne 496:212
62.38
56 27.07.11 TM
No:76 M-40
44+000 LHS
430 1 0.39 105 743 398 Coasre:fi
ne 466:199
63.37
57 29.07.11 TM
No:78 M-40
44+000 LHS
430 0.7 0.37 55 570 568 Coasre:fi
ne 485:207
62.38
58 10.10.11 TM -1 DLC 44+000
LHS Maha 155 Nil
0 - - 607.4 651 911.4
58:42
59 08.11.11 TM-85 M-45 90+000
Maha 460
BASF (Rehobuild 920
h)
0.9 0.36 125 748.9 400
Coasre:fine
492:209 63:37
60 21.11.11 TM-86 M40 90+000
Maha 430 0.7 0.36 25 582 577
Coasre:fine
492:209 62:38
61 24.10.20
11 PQC-3 M40
44+000 LHS
maha 390 1 0.38 30 750 401
Coasre:fine =547 :
181 61:39
62 08.11.11 PQC-4 M40
44+000 LHS
Ramco 390 0.7 0.37 25 742 397
Coasre:fine 565 :
182 60:40
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
63 2.2.12 TM 91 M25
90+000
Maha 340
BASF (Rehobuild 920
h)
0.9 0.45 65 731.5 484
727.7 62:38
64 4.2.12 TM 92 M25 90+000
Ramco 340 0.9 0.45 70 731.5 484
727.7 62:38
Section -1(PNJ)
Sl. No
B.A No Survey No
Ch
ain
ag
e
Side
Lea
d in
Km
No of Grids Pits
Area Proposed
Sqm
Prop /App. Qty.
in Cum
DOS DOT
MDD/ OMC
Ma
terial
Su
itab
ility
1 C1-1 557/A1 106+400 LS 2.70 10 30000 9375 29.03.10 30.03.10
2.12/7.61 Emb
2 C1-2 288/E, 289,290/E 142+800 RS 1.00 11 21000 10312 31.03.10 01.04.10
2.013/8.8 Emb
3 C1-3 52,56 126+800 LS 3.40 12 48000 11250 03.04.10 07.04.10
1.97/8.4 Emb
4 C1-4 506,509&510 106+400 LS 3.40 12 15680 11250 08.04.10 09.04.10
2.051/9.1 Emb
5 C1-1(A) 557/A1 106+400 LS 2.70 10 45000 9375 29.04.10 30.04.10
2.090/7.7 Emb
6 C1-5 435 106+400 LS 3.20 11 82500 10312 13.05.10 17.05.10
2.052/8.4 Emb
7 C1-5(a) 435 106+400 LHS 3.20 26 16250 24375.0 01.06.10 03.06.10
2.053/8.33 EMB
8 C1-6 232 116+100 RS 1.50 10 40500 9375 19.05.10 20.05.10
2.102/8.2 Emb
9 C1-2(a) 288/E,289, 290/E 142+800 RS 1.00 21 21000 19687.5 19.05.10 20.05.10
2.05/7.05 Emb
10 C1-2(b) 288/E,289, 290/E 142+800 RS 1.00 17 21000 31500 21.05.10 02.06.10
2.063/8.50 SG
11 C1-8 574 126+950 LS 5.00 10 11760 9375 05.06.10 06.06.10
2.013/8.3 EMB
12 C1-9 160 126+950 LS 5.10 8 7840 11760 14.06.10 16.06.10
1.996/7.7 Emb
13 C1-10 436/1, 439/2
123+580 LS 1.00 10 7500 9375 16.06.10 17.06.10
2.321/7.4 Emb
14 C1-11 574 126+800 LS 5.00 10 5000 7500 16.06.10 19.06.10
2.035/8.00 Emb
15 C1-2(c ) 288/E, 289, 290/E 142+800 RS 1.00 30 210000 28125 18.06.10 28.06.10
2.051/7.7 SG
16 C1-5(b) 435 106+400 LS 3.20 20 12500 18750 26.06.10 27.06.10
2.024/7.4 EMB
17 C1-12 135 125+000 LS 2.50 8 5000 7500 30.06.1030.06.10 2.018/7.8 Emb
18 C1-5( c) 435 106+400 LS 3.20 20 12500 18750 29.06.10 08.07.10
2.089/7.75 SG
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
19 C1-13 109&111 125+000 RS 3.50 8 5000 7500 29.06.10 08.07.10
2.023/7.83 Emb &
SUB
20 C1-2(d) 288/E, 289,290/E 142+800 RS 1.00 30 21000 28125 03.07.10 16.07.10
2.103/7.7
Emb & SUB
21 C1-14 657 122+000 RS 3.00 13 38808 12188 21.07.10 26.07.10
2.064/8.13 Emb
22 C1-15 463 114+300 RHS 0.50 15 9375 14063 23.07.10 29.07.10
2.095/8.4 Emb
23 C1-16 188 118+200 RHS 0.50 8 5000 7500 03.08.10 03.08.10
2.091/8.2 SUB
24 C1-17 1029& 1030 134+000 LHS 3.00 10 6250 9375 09.08.10 21.08.10
2.136/7.9 EMB
25 C1-15(a) 463 114+300 RHS 0.50 25 15625 23437.5 12.08.10 18.08.10
2.141/7.3 EMB
26 C1-18 476 112+600 RHS 1.60 20 12500 18750 20.08.10 24.08.10
2.009/8.00 SUB
27 C1-19 102,103 131+610 LHS 3.60 10 6250 9375 19.08.10 23.08.10
2.085/8.36 EMB
28 C1-20 599/A1 106+400 LHS 1.80 15 9375 14062.5 31.08.10 11.09.10
2.126/7.81 SUB
29 C1-2(e) (288,289,290) / E 142+800 RHS 1.00 30 18750 28125 31.08.10 15.09.10
2.117/8.32 SUB
30 C1-15(b) 463 114+300 RHS 0.50 33 20625 30937.5 04.09.10 16.09.10
2.189/7.44 EMB
31 C1-6(a) 232 116+100 RHS 1.50 15 9375 14062.5 09.09.10 27.09.10
2.157/7.75 SUB
32 C1-21 108&109 109+400 RHS 0.80 10 6250 9375 20.09.10 02.10.10
2.133/7.77 SUB
33 C1-22 667 122+000 RHS 3.00 30 18750 28125 14.09.10 21.09.10
2.12/7.98 EMB
34 C-23 126 136+380 RHS 3.00 6 3750 5625.0 28.09.1030.09.10 2.12/7.99 EMB
35 C1-15(
c) 463 114+300 RHS 0.50 15 9375 14063
08.10.10 15.10.10
2.18/7.37 SUB
36 C1-
15(d) 463 114+300 RHS 0.50 30 18750 28125
26.10.10 06.11.10
2.12/7.23 SUB
37 C1-24 44,46,48,55,65,66&72 127+900 RHS 0.90 4 2500 3750 29.10.10 31.10.10
2.11/7.98 EMB
38 C1-25 804 to 807 131+000 LHS 3.00 15 9375 14063 29.10.10 13.10.10
2.107/8.18 SUB
39 C1-26 810,811 129+500 LHS 1.00 24 15000 22500.0 13.11.10 21.11.16
2.12/7.104 SUB
40 C1-6(b) 232 116+100 RHS 1.50 30 18750 28125 15.11.10 22.11.10
2.10/7.20 SUB
41 C1-27 278,279 117+300 RHS 1.00 15 9375 14063 24.11.10 28.11.10
2.16/8.01 SUB
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
42 C1-6(c) 232 116+100 RHS 1.50 15 9375 14063 29.11.10 09.12.10
2.13/7.8 SUB
43 C1-28 70 112+600 RHS 1.60 15 9375 14063 29.11.10 09.12.10
2.13/7.9 SUB
44 C1-29 75,76,78 125+500 RHS 2.00 21 13125 19687.5 05.12.10 15.12.10
2.124/8.11 SUB
45 C1-30 657 122+000 RHS 3.00 20 12500 18750.0 10.12.10 20.12.10
2.074/8.48 SUB
46 C1-31 78,79 125+500 RHS 2.00 8 5000 7500.0 30.12.10 05.01.11
2.099/8.25 SUB
47 C1-30(a) 657 122+000 RHS 3.00 20 12500 18750.0 04.01.11 14.01.11
2.073/8.41 SUB
48 C1-15(e) 463 114+300 RHS 0.50 15 9375 14062.5 05.01.11 22.01.11
2.156/8.01 SUB
49 C1-28(a) 70 112+600 RHS 1.60 30 18750 28125.0 08.01.11 14.01.11
2.100/8.25 EMB
50 C1-32 578 112+280 RHS 2.50 15 9375 14062.5 08.02.11 22.02.11
2.101/7.92 SUB
51 C1-32 38/E,27 126+300 RHS 3.00 15 9375 14062.5 17.02.1125.02.11 2.108/8.07 SUB
52 C1-32(a) 578 112+280 RHS 2.50 10 6250 9375.0 22.02.11 25.02.11
2.091/7.99 EMB
53 C1-30(b) 657 122+300 RHS 3.00 15 9375 14062.5 20.02.11 07.03.11
2.081/8.19 SUB
54 C1-34 577 112+280 RHS 2.70 8 5000 7500.0 26.02.11 04.03.11
2.122/7.96 SUB
55 C1-34(a) 577 112+280 RHS 2.70 10 6250 9375.0 03.03.11 11.03.11
2.127/7.94 SUB
56 C1-25(a) 804,805,806&807 131+000 LHS 3.00 9 5625 8437.5 10.03.11 18.03.11
2.107/8.26 SUB
57 C1-34(b) 577 112+280 RHS 2.70 10 6250 9375.0 12.03.11 19.03.11
2.135/7.87 SUB
58 C1-35 407 134+000 LHS 3.00 15 9375 14062.5 15.03.11 26.03.11
2.089/8.07 SUB
59 C1-2(f) (288,289,290) / E 142+800 RHS 1.00 15 9375 14062.5 17.03.11 27.03.11
2.111/8.06 SUB
60 C1-32(b) 578 112+280 RHS 2.60 4 2500 3750.0 24.03.11 29.03.11
2.120/7.85 SUB
61 C1-32(
c) 578 112+280 RHS 2.60 4 2500
3750
30.03.11 03.04.11
2.104/7.87 SUB
62 C1-36 172 126+800 LHS 4.00 12 7500 11250.0 26.03.11 01.04.11
2.114/7.53 SUB
63 C1-27(a) 278,279 117+300 LHS 1.00 12 7500 11250.0 01.04.11 07.04.11
2.137/7.88 SUB
64 C1-28(a) 70 112+600 RHS 1.60 12 7500 11250.0 09.04.11 15.04.11
2.107/8.08 SUB
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
65 C1-37 629,417, 637/1 122+400 LHS 0.50 15 9375 14062.5. 12.04.11 19.04.11
2.102/8.19 SUB
66 C1-28(b) 70 126+800 LHS 2.00 10 6250 9375.0 25.04.11 06.05.11
2.085/8.18 SUB
67 C1-38 629,417, 637/1 126+800 LHS 3.70 10 6250 9375 06.05.11 14.04.11
2.067/8.24 SUB
68 C1-2(g) (288,289,290) / E 142+800 RHS 1.00 15 9375 14062.5 07.05.1114.05.11 2.112/8.0 SUB
69 C1-39 420,416 122+400 LHS 0.60 10 6250 9375 09.05.11 24.05.11
2.098/8.24 SUB
70 C1-34(b) 577 112+280 RHS 2.65 10 6250 9375.0 22.05.11 09.06.11
2.086/8.17 SUB
71 C1-40 385,390,391 122+400 LHS 0.60 20 12500 18750 06.06.11 22.06.11
2.105/8.15 SUB
72 C1-34(
c) 577 112+280 RHS 2.65 8 5000 7500.0
20.06.11 22.06.11
2.087/7.91 SUB
72 C1-2(h) (288,289,290) / E 142+800 RHS 1.00 15 9375 14062.5 07.05.11 14.05.11
2.112/8.0 SUB
73 C1-2(I) (288,289,290) / E 142+800 RHS 1.00 15 9375 14062.5 06.06.11 27.06.11
2.113/7.99 SUB
74 C1-41 387,388,389,390/1 122+400 LHS 0.60 20 12500 18750.0 01.07.11 11.07.11
2.097/8.11 SUB
75 C1-2(J) (288,289,290) / E 142+800 RHS 1.00 15 9375 14062.5 23.07.11 11.08.11
2.115/8.09 SUB
76 C1-41(a) 387,388,389,390/1 122+400 LHS 0.60 20 12500 18750.0 01.08.11 11.08.11
2.081/8.20 SUB
77 32(D) 578 112+280 RHS 2.70 10 6250 9375.0 09.08.11 20.08.11
2.086/8.10 SUB
78 32(E) 578 112+280 RHS 2.70 10 6250 9375.0 11.08.11 14.08.11
2.089/7.90 EMB
79 CI-42 552,554,559 113+195 RHS 10.00 5 3125 4687.5 11.08.11 17.08.11
2.123/7.78 EMB
80 C1-6(C) 285 116+100 RHS 1.50 15 9375 14062.5 19.08.11 26.08.11
2.115/8.09 SUB
81 C1-K 288/E,289,290/E 142+800 RHS 1.00 15 9375 14062.5 25.8.11 02.09.11 2.137/8.0 SUB
82 C1-43 975,976,977 104+100 LHS 1.00 12 7500 11250.0 02.09.11 09.09.11
2.063/8.2 SUB
83 C1-
41(B) 388,389,390 122+400 LHS 0.60 12 7500 11250.0
09.09.11 18.09.11
2.085/8.13 SUB
84 C1-32(F) 578 112+280 RHS 2.70 10 6250 9375.0 15.09.11 21.09.11
2.117/7.79 EMB
85 C1-42(a) 552,554,559 113+195 RHS 10.00 10 6250 9375.0 23.09.11 25.09.11
2.105/7.92 EMB
86 C1-44 388,389,390 122+400 LHS 0.60 18 11250 16875.0 28.09.11 08.10.11
2.080/8.3 SUB
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
87 C143(a) 975,976,977 104+100 LHS 1.00 10 6250 9375.0 08.10.11 15.10.11
2.099/8.05 SUB
88 C1-45 561,565 113+195 RHS 10.00 15 9375 14062.5 16.10.11 20.10.11
2.125/7.88 EMB
89 C1-46 163/A 142+800 LHS 2.00 6 3750 5625.0 20.10.11 27.10.11
2.067/8.45 SUB
90 C1-47 41,42 112+280 RHS 2.75 6 3750 5625.0 24.10.11 24.10.11
2.073/8.25 EMB
91 C1-49 217,224 116+200 LHS 1.00 6 3750 5625.0 29.10.11 6.11.11 2.089/8.45 SUB
92 C1-47(a) 41,42 112+280 RHS 2.75 6 3750 5625.0 2.11.11 2.11.11 2.097/7.92 EMB
93 C1-45(a) 561,565 113+195 RHS 10.00 10 6250 9375.0 24.10.11 2.11.11 2.098/7.96 EMB
94 c1-44(a) 388,389,390 122+400 LHS 0.60 10 6250 9375.0 4.11.11 10.11.11 2.063/8.1 SUB
95 C1-49(a) 217,224 116+200 LHS 1.50 6 3750 5625.0 5.11.11 12.11.11 2.075/8.1 SUB
96 C1-47(b) 41,42 112+280 RHS 2.75 6 3750 5625.0 7.11.11 7.11.11 2.099/7.75 EMB
97 c1-46(a) 163/A 142+800 LHS 2.00 12 7500 11250.0 08.11.11 16.11.11
2.095/8.2 SUB
98 C145(b) 561,565 113+195 RHS 10.00 9375 14062.5 11.11.11 13.11.11
2.094/8.0 EMB
99 C1-45(c) 561,565 113+195 RHS 10.00 15 9375 14062.5 14.11.11 16.11.11
2.100/8.0 EMB
100 C1-50 55 131+600 RHS 3.00 10 6250 9375.0 18.11.11 20.11.11
2.038/8.2 SUB
101 C1-44(b) 388,389,390 122+400 LHS 0.60 20 12500 1875.0 22.11.11 29.11.11
2.094/8.1 SUB
102 C1-49(b) 217,224 116+200 LHS 1.50 12 7500 11250.0 24.11.11 4.12.11 2.070/8.3 SUB
103 C1-50(a) 55 131+600 RHS 3.00 15 9375 14062.5 29.11.11 7.12.11 2.046/8.23 SUB
104 C1-44C 388,389,390 122+400 LHS 0.60 18 11250 16875.0 06.12.11 12.12.11
2.083/8.2 SUB
105 C1-51 413 109+500 RHS 2.00 12 7500 11250.0 09.12.11 10.12.11
2.072/8.36 EMB
106 C1-51(a) 413 109+500 RHS 2.00 12 7500 11250.0 12.12.11 13.12.11
2.091/7.88 EMB
107 C1-51(b) 413 109+500 RHS 2.00 18 11250 16875.0 19.12.11 26.12.11
2.087/8.2 EMB
108 C1-
46(B) 163/A 142+800 LHS 2.00 12 7500 11250.0
21.12.11 26.12.11
2.086/8.1 SUB
109 C1-51© 413 109+500 RHS 2.00 12 7500 11250.0 02.01.12 03.01.12
2.112/7.89 EMB
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
110 C1-50(b) 55 131+600 RHS 3.00 25 11250 16875.0 28.12.11 09.1.12 2.071/8.3 SUB
111 C1-52 119+300 LHS 2.50 6 3750 5625.0 10.1.12 23.1.12 2.029/8.38 SUB
112 C1-
51(d) 413 109+500 RHS 2.00 6 3750 5625.0 16.1.12 16.01.12
2.116/7.80 EMB
113 C1-
51(E) 413 109+500 RHS 2.00 12 7500 11250.0 17.1.12 19.1.12
2.112/7.82 EMB
114 C1-53 576 112+280 RHS 3.50 15 9375 14062.5 24.1.12 02.2.12 2.082/8.16 EMB
115 C1-54 125+500 RHS 2.00 15 9375 14062.5 24.1.12 05.2.12 2.081/8.28 SUB
116 C1-55 129+480 LHS 2.00 15 9375 14062.5 27.01.12 10.2.12 2.060/8.36 SUB
117 C1-49 C 217,224 116+200 LHS 1.50 24 15000 22500.0 3.02.12 09.02.12 1.996/9.0 SUB
118 C1-
53(A) 576 112+280 RHS 3.50 15 9375 14062.5
08.02.12 15.02.12
2.101/7.9 EMB
119 C1-56 227 117+450 LHS 1.50 12 9375 14062.5 18.02.12 26.02.12
2.085/8.13 SUB
120 C1-56A 227 117+450 LHS 1.50 12 9375 11250.0 03.03.12 15.03.12
2.100/8.0 SUB
121 C1-57 172 126+500 LHS 5.00 12 9375 11250.0 21.03.12 13.03.12
2.070/8.2 SUB
122 C1-56B 227 117+450 LHS 1.50 12 9375 11250.0 24.03.12 01.04.12
2.088/8.20 SUB
123 C1-47C 41,42 112+280 RHS 2.75 6 3750 5625.0 02.04.12 09.04.12 2.117/7.6 SUB
124 C1-58 159/E 116+200 LHS 1.60 6 3750 5625.0 05.04.12 11.04.12 2.103/7.8 SUB
125 C1-32G 578 112+280 RHS 2.70 10 6250 9375.0 05.04.12 15.04.12 2.103/7.80 SUB
126 C1-59 56 126+500 LHS 5.50 12 9375 11250.0 14.04.12 20.04.12 2.065/8.30 SUB
127 C1-58A 159/E 116+200 LHS 1.60 6 3750 5625.0 17.04.12 29.04.12 2.098/7.9 SUB
Sl. No.
Date of casting
Trial Mix No.
Gra
de o
f
Co
ncre
te
Cem
en
t Bra
nd
Ce
men
t
Co
nte
nt (K
g)
ADMIXTURE
W/C
ratio
Slu
mp
at 9
0
min
. (mm
)
CA
20m
m
(Kg
/Cu
m)
CA
10m
m
(Kg
/Cu
m)
SAND CONTENT (Kg/Cum)
CA : FA RATIO Brand
Name %
Munner Sand
Krishna Sand
1 06.06.10 PLL/QC1/CONC/M35/TM-1 M-35 Ram
co - O
PC
43 g
rad
e
410
Fosroc
Conplast (430 AA)
0.8 0.40 90 720 482 431 228 64:36
2 15.06.10 PLL/QC1/CONC/M30/TM-1 M-30 380 0.8 0.43 105 719 482 450 238 63:37
3 08.06.10 PLL/QC1/CONC/M25/TM-1 M-25 360 0.7 0.45 90 727 487 455 241 63:37
4 12.06.06 PLL/QC1/CONC/M20/TM-1 M-20 320 0.9 0.45 85 758 508 474 251 63:37
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
5 14.06.10 PLL/QC1/CONC/M15/TM-1 M-15 290 0.7 0.50 60 755 506 493 261 62:38
6 14.06.10 PLL/QC1/CONC/M20/TM-2 M-20 320 Sikament NN(SP) South
0.9 0.45 85 758 508 474 251 63:37
7 12.06.10 PLL/QC1/CONC/M15/TM-2 M-15 290 0.8 0.50 65 755 506 493 261 62:38
8 02.08.10 PLL/QC1/CON/M35/TM-4 M-35 400
Fosroc Conplast (430 AA)
0.5 0.38 105 (45min)
725 486 453 240 63:37
9 31.08.10 PLL/QC1/CON/M35/TM-5 M-35 400 0.7 0.40 105 716 480 448 237 63:37
10 03.07.10 PLL/QC1/CON/M25/TM-4 M-25 350 0.7 0.45 105 712 477 484 257 61:39
11 16.08.10 PLL/QC1/CON/M40/TM-1 M-40 430 0.7 0.38 120 703 471 440 233 63:37
12 25.10.10 PLL/QC1/CON/M40/TM-3 M-40 430 0.6 0.37 100
(45min) 708 474 443 234 63:37
13 08.10.10 PLL/QC1/CON/M20/TM-6 M-20 Kerb 320 0.3 0.45 20 478 721 531 281 59:41
14 28.10.10 PLL/QC1/CON/M20/TM-9 M-20 Kerb 320 Fair crete
AE 0.3 0.45 20 474 714 526 279 59:41
15 12.07.10 PLL/QC1/CONC/M35/TM-2 M-35
Zu
ari - O
PC
43
gra
de
400
Fosroc Conplast (430 AA)
0.5 0.40 100 717 480 448 237 67:37
16 06.07.10 PLL/QC1/CONC/M30/TM-2 M-30 380 0.6 0.42 105 723 485 452 240 63:37
17 05.07.10 PLL/QC1/CONC/M25/TM-2 M-25 350 0.6 0.45 105 712 477 485 257 61:39
18 11.07.10 PLL/QC1/CONC/M20/TM-3 M-20 310 0.9 0.45 100 754 505 492 260 62:38
19 11.07.10 PLL/QC1/CONC/M15/TM-3 M-15 280 0.8 0.50 80 763 511 498 264 62:38
20 15.10.10 PLL/QC1/CON/M40/TM-2 M-40 430 0.6 0.36 100 (45
min) 712 477 445 236 63:37
21 07.10.10 PLL/QC1/CON/M20/TM-7 M-20 Kerb 320 0.3 0.45 20 474 714 526 279 59:41
22 13.10.10 PLL/QC1/CON/M35/TM-6 M-35 400 0.5 0.38 100 (45
min.) 725 486 453 240 63:37
23 14.10.10 PLL/QC1/CON/M20/TM-8 M-20 Kerb 320 Fair crete
AE 0.3 0.45 20 474 714 526 279 59:41
24 18.07.11 PLL/QC1/CON/M40/TM-5 M-40 440 Fosroc
Conplast (430 AA)
0.8 0.36 110 705 471 441 234 63:37
25 26.08.11 PLL/QC1/CON/PQC/TM-1 PQC 400 0.70 0.36 35 745 498 447 236 64:36
26 13.07.10 PLL/QC1/CON/M20/TM-4 M-20 310 Sikament NN(SP) South
0.9 0.45 82 754 505 492 260 62:38
27 14.07.10 PLL/QC1/CONC/M15/TM-4 M-15 280 0.8 0.50 82 763 511 498 264 62:38
28 16.06.11 *PLL/QC1/CONC/DLC/TM-5 DLC 150 - - 675 608 967.5 - Dust 18.4(3days strength)
29 05.12.11 PLL/QC1/CONC/PQC/TM-1 PQC(Revised) 410 Fosroc
Conplast
(430 AA)
0.9 0.38 65 717 487 449 231 64:36
30 09.07.10 PLL/QC1/CON/M35/TM-3 M-35
Ma
ha -
OP
C 4
3
gra
de
400 Fosroc
Conplast 0.5 0.40 100 717 480 448 237 63:37
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
29 12.01.11 PLL/QC1/CON/M35/TM-7 M-35 400 (430 AA)
0.7 0.38 120
(45min) 724 485 453 240 63:37
30 20.01.11 PLL/QC1/CON/M40/TM-4 M-40 430 0.7 0.35 115
(45min) 716 480 448 237 63:37
31 21.08.10 PLL/QC1/CON/M25/TM-3 M-25 350 0.7 0.45 115 712 477 484 257 61:39
32 10.07.10 PLL/QC1/CON/M20/TM-5 M-20 320 0.8 0.45 85 746 500 487 258 62:38
33 09.07.10 PLL/QC1/CONC/M15/TM-5 M-15 280 0.9 0.50 75 763 511 498 264 62:38
Section-2(PNJ)
Sl. No
B. A
. No
Su
rve
y N
o
Ch
ain
ag
e
Sid
e
Lea
d in
Km
No.of Grids Pits
Area
Pro
po
sed
Sq
m
Pro
p /A
pp
Q
uan
tity
in C
um
DOS DOT
MDD /OMC
Ma
terial
Su
itab
ility
1 C2-1 120 181+00 RS 4.00 12 7500 12600 22.01.10 19.02.10
2.049 /8.4
Emb
2 C2-2 179 145+600 LS 0.50 14 13200 13125 04.03.10 06.03.10
1.94 /7.6
EMB
3 C2-2A 179 145+600 LS 0.50 14 8125 12187 12.04.10 12.04.10
1.939 /7.6
SG
4 C2-2B 179 145+600 LS 0.50 14 10000 15000 19.05.10 24.05.10
2.00 /8.4
EMB
5 C2-2
EXTN. 180 145+600 LS 0.50 14 13200 13125
16.06.10 28.06.10
2.094 /8.3
EMB
6 C2-3 125/1 158+950 LS 1.80 18 12100 18150 25.03.10 29.03.10
2.013 /9.53
EMB
7 C2-4 105/1 & 105/5 158+950 LS 2.00 18 12000 18000 29.03.10 01.04.10
2.004 /9.4
emb
8 C2-5 289 151+100 RS 2.00 6 5400 5625 10.04.10 19.04.10
1.91 /8.8
emb
9 C2-5A 289 151+100 RS 2.00 12 7500 11250
2.012 /8.57
EMB
10 C2-6 155 157+750 RS 1.20 12 10500 11250 02.04.10 22.04.10
1.99 /8.5
emb
11 C2-7 683/A,684/E,686/A 152+500 LS 0.30 10 10220 9375 20.04.10 24.04.10
2.07 /8.45
EMB
12 C2-8 306 151+180 RS 2.20 16 10000 15000 15.05.10 27.05.10
2.075 /8.30
EMB
13 C2-8A 307 151+180 RS 3.20 16 14400 15000 25.05.10 27.05.10
2.138 /8.00
EMB
14 C2-9 413&519 181+000 RS 6.00 17 11424 15937 29.05.10 31.05.10
2.018 /8.64
EMB
15 C2-10 190 172+500 LS 2.50 14 8750 13125 25.05.10 02.06.10
2.001 /8.67
EMB
16 C2-11 36/1& 36/3 165+890 LS 1.70 9 9000 8437.5 29.05.10 04.06.10
2.006 /8.8
EMB
17 C2-12 297/1,2, 105/1,3,5
125/1 155+500 LS 0.5 11 9000 10312.5
05.06.10 07.06.10
2.013 /8.6
EMB
18 C2-13 190 172+500 LS 2.60 30 22500 28150 12.06.10 16.06.10
2.021 /8.61
EMB
19 C2-14 413 & 519 181+000 RS 6.10 14 10800 13125 15.06.10 18.06.10
2.025 /8.61
EMB
20 C2-15 289 142+800 RS 1.50 45 37500 56250 16.06.10 24.06.10
2.024 /8.83
EMB
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
21 C2-15A 289 142+800 RS 1.50 6 66817 103226 21.09.10 26.0.10
2.016 /8.3
EMB&SG
22 C2-16 245 143+700 RS 0.20 22 22500 22500 22.06.10 26.06.10
2.03 /8.8
EMB
23 C2-17 190 172+500 LS 2.8 17 12500 18750 07.07.10 11.07.10
2.072 /8.6
EMB
24 C2-18 172-175 180+890 RS 4 20 16000 18750 07.07.10 09.07.10
2.086 /8.70
EMB
25 C2-19 120 180+890 RS 2.5 30 18750 28125 10.07.10 12.07.11
2.013 /8.60
EMB
26 C2-20 305 151+180 RS 2.22 18 17500 16875 19.07.10 21.07.10
2.081 /8.50
EMB
27 C2-21 65/E 157+000 RS 2 18 17500 16875 20.07.10 23.07.10
2.089 /8.2
EMB
28 C2-22 190 172+500 LS 3 12 7500 11250 10.08.10 13.08.10
2.104 /8.4
EMB
29 C2-23 317/3 162+450 LS 2 33 20625 30937.5 10.08.10 19.08.10
2.071 /8.3
EMB
30 C2-24 36/1,36/3 165+890 LS 1.7 30 18750 28125 10.08.10 29.08.10
2.053 /8.6
EMB
31 C2-25 242,243 143+700 RS 0.5 15 9375 14062.5 21.08.10 31.08.10
2.081 /8.3
EMB
32 C2-26 410,412 180+890 RS 4.5 15 9375 14062.5 10.08.10 02.09.10
2.085 /8.6
EMB
33 C2-27 159,164 143+850 LS 1.9 20 12500 18750 01.09.10 04.09.10
2.073 /8.4
EMB
34 C2-28 190 172+500 LS 2.5 30 18750 28125 21.08.10 08.09.10
2.085 /8.6
EMB
35 C2-29 306 151+180 RS 2.22 15 15000 14062.5 13.09.10 16.09.10
2.085 /8.7
EMB
36 C2-30 30 180+890 RS 11 25 22500 23437.5 16.09.10 25.09.10
2.089 /8.4
EMB
37 C2-31 31 169+600 LS 0.9 20 18750 18750 04.10.10 18.10.10
2.082 /8.5
EMB
38 C2-32 292/3 160+650 LS 2.5 6 7500 5625 21.10.10 22.10.10
2.061 /8.3
EMB
39 C2-33 190 180+890 RS 4 10 11250 9375 26.10.10 27.10.10
2.012 /8.8
EMB&SG
40 C2-34 79 155+200 RS 1.5 5 7500 4687.5 18.11.10 24.11.10
2.061 /8.5
EMB&SG
41 C2-35 190 172+500 LS 3 12 12500 18750 20.11.10 03.12.10
2.069 /8.3
EMB&SG
42 C2-36 190 172+500 LS 2.5 18 17500 16875 20.11.10 01.12.10
2.054 /8.4
EMB&SG
43 C2-37 292 160+750 LS 2.5 8 7500.0 7500 13.12.10 21.12.10
2.039 /8.1
EMB&SG
44 C2-38 625 181+000 LS 5.5 11 10312.5 18750 15.12.10 18.12.10
2.048 /8.2
EMB&SG
45 C2-38A 625 181+000 LS 5.6 6 36000.0 54000 04.11.11 10.11.11
2.067 /8.30
EMB&SG
46 C2-39 626/7 182+200 LS 1.7 11 10312.5 18750 25.12.10 30.12.10
2.035 /8.3
EMB&SG
47 C2-40 292/3 160+760 LS 2.5 6 5625 11250 17.01.11 18.01.11
2.025 /8.3
EMB&SG
48 C2-41 36/1& 36/3 165+890 LS 1.5 6 5625 11250 27.01.11 31.01.11
2.022 /8.4
EMB&SG
49 C2-41A 36/1& 36/ 165+891 LS 1.5 6 20800 15000 28.03.11 02.04.11
2.013 /8.2
EMB&SG
50 C2-42 190 172+500 LS 3.0 8 7500 14063 11.02.11 15.02.11
2.014 /8.4
EMB&SG
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
51 C2-43 190/1 170+500 LS 2.0 6 5625 11250 11.02.11 17.02.11
2.021 /8.3
EMB&SG
52 C2-43A 190/1 170+500 LS 2.0 6 43750 36000 06.04.11 11.04.11
2.037 /8.6
EMB&SG
53 C2-44 292 160+750 LS 1.8 6 5625 11250 16.02.11 19.02.11
2.027 /8.4
EMB&SG
54 C2-45 666 182+300 RS 3.5 6 5625 11250 09.02.11 20.02.11
2.027 /8.4
EMB&SG
55 C2-46 292/3 160+760 LS 1.7 6 5625 11250 09.03.11 10.03.11
2.036 /8.4
EMB&SG
56 C2-47 190 165+850 LS 2.0 6 20300 16875 12.04.11 19.04.11
2.038 8.6
EMB&SG
57 C2-48 155 156+600 RS 2.0 6 23000 30000 16.04.11 22.04.11
2.039 /8.6
EMB&SG
58 C2-48A 155 156+600 RS 2.0 6 24750 45000 06.07.11 11.07.11
2.041 /8.2
EMB&SG
59 C2-49 657, 666 182+200 RS 3.0 6 17550 26000 14.05.11 21.05.11
2.044/ 8.4
EMB&SG
60 C2-49A 657, 666 182+200 RS 3.0 6 17550 26325 04.08.11 10.08.11
2.022/ 8.5
EMB&SG
61 c2-50 658,662 182+400 RS 3.0 6 29700 44550 17.05.11 25.05.11
2.051/ 7.3
EMB&SG
62 c2-50A 658,662 182+400 RS 3.0 6 29700 44550 17.08.11 23.08.11
2.057/ 8.0
EMB&SG
63 c2-51 36/1, 36/3 165+890 LS 3.0 6 19320 28980 17.05.11 25.05.11
2.049/ 7.4
EMB&SG
64 c2-51A 36/1, 36/3 165+890 LS 3.0 6 19320 28980 16.02.12 17.02.12
2.058/ 8.4
EMB&SG
65 C2-51B 36/1, 36/3 165+890 LS 3 6 19320 28980 20.06.12 21.06.12
2.035/ 8.51
EMB&SG
66 c2-52 485, 495, 497, 498 181+000 LS 11 6 27000 40500 02.09.11 08.09.11
2.046/ 8.2
EMB&SG
67 c2-53 163A 143+400 LS 1.5 6 30400 45600 15.10.11 20.10.11
2.040/ 8.4
EMB&SG
68 c2-53A 163A 143+400 LS 1.5 6 30400 45600 17.02.12 18.02.12
2.015/ 8.6
EMB&SG
69 c2-54 176 181+000 RS 4 6 29469 44204 14.12.11 22.12.11
2.053/ 8.3
EMB&SG
70 c2-55 163A 143+400 LS 1.6 6 36100 54150 24.12.11 27.12.11
2.060/ 8.6
EMB
71 c2-55A 163A 143+400 LS 1.6 6 36100 54150 03.10.12 08.10.12
2.045 8.2
EMB&SG
72 c2-56 657, 666 182+350 RS 1.6 6 40490 60735 13.02.12 18.02.12
2.057/ 8.2
EMB&SG
73 c2-57 663 137+500 LS 7 6 60733.5 91102.5 23.04.12 24.04.12
2.028/ 8.77
EMB
74 C2-58 663 137+500 LS 7 6 60733.5 60733.5 09.05.12 10.05.12
2.019/ 8.90
EMB
75 c2-57B 663 137+500 LS 7 6 60733.5 91102.5 11.06.12 18.06.12
2.033/ 8.3
EMB&SG
Sl. NO
Date of casting
Trial Mix NO
Gra
de o
f Co
ncre
te
Cem
en
t Bra
nd
Cem
en
t Co
nte
nt
(Kg
)
ADMIXTURE W/C
ratio
Slu
mp
at 9
0 m
in.
(mm
)
CA
20m
m
(Kg
/Cu
m)
CA
10m
m
(Kg
/Cu
m)
SAND CONTENT (Kg/Cum)
CA : FA RATIO
Brand Name
% Munner
Sand Krishna
Sand
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
1 07.06.10 TM No:1 M-35
Ram
co - O
PC
43 g
rad
e
410
Fo
sroc S
P-430 A
A
0.8 0.40 90 707 468 443 232 63:37
2 19.06.10 TM No:2 M-30 380 0.7 0.43 95 704 467 462 245 62:38
3 14.06.10 TM No:3 M-.25 350 0.7 0.45 90 708 470 484 257 61:39
4 11.06.10 TM No:4 M-20 320 0.8 0.49 75 708 469 503 267 60:40
5 13.08.10 TM No:52 M-40 430 0.8 0.38 95 651 529 460 194 64:36
6 16.07.10 PLL/QC1/CON/M35/TM-3 M-35 Mah
a - O
PC
43 g
rad
e
400
Fo
sroc S
P-430 A
A
0.8 0.4 105 653 531 482 203 63:37
7 09.07.10 PLL/QC1/CONC/25/TM-2 M-25 340 0.8 0.45 100 656 534 527 222 63:39
8 17.07.10 PLL/QC1/CONC/M20/TM-3 M-20 310 1 0.45 55 665 541 557 236 63:40
9 16.07.10 PLL/QC1/CONC/M15/TM-3 M-15 280 1.1 0.50 55 564 238 673 548 63:40
10 15.07.10 PLL/QC1/CONC/M15/TM-2 M-15
Ram
co - O
PC
43
gra
de
280
Fo
sroc S
P-430 A
A
1.1 0.50 55 673 548 563 238 63:40
11 15.07.10 PLL/QC1/CON/M20/TM-2 M-20 310 1 0.45 55 665 541 557 235 60:40
12 03.07.10 PLL/QC1/CONC/25/TM-3 M-25 340 0.8 0.45 100 656 534 527 222 61:39
13 14.07.10 PLL/QC1/CON/M30/TM-2 M-30 370 0.8 0.43 100 652 531 502 212 62:38
14 14.07.10 PLL/QC1/CON/M35/TM-2 M-35 400 0.8 0.4 100 653 531 482 203 63:37
15 20.09.10 PLL/QC2/CON/M15/TM-3 M-15
Zu
ari O
PC
43
Gra
de
280
Fo
sroc S
P-430 A
A
1.1 0.5 50 673 548 563 238 60:40
16 27.09.10 TM No:61 M-20 310 1.0 0.45 85 665 541 557 235 60:40
17 PLL/QC2/CON/M20/TM-3 M-20 Kerb
320 0.4 0.45 35 382 773 290.00 531.00 63:38
18 06.09.10 PLL/QC2/CON/M25/TM-3 M-25 340 0.8 0.45 50 655 533 526 222 61:39
19 28.07.10 PLL/QC2/CON/M30/TM-1 M-30 380 0.7 0.43 85 645 525 497 209 62:38
20 28.07.10 PLL/QC2/CON/M35/TM-2 M-35 400 0.8 0.4 100 653 531 482 203 63:37
21 29.07.11 PLL/QC2/CON/M35 P/TM-1 M-35P 440 0.8 0.40 130 650 431 499.00 210.00 60:40
22 29.07.11 PLL/QC2/CON/M 40/TM-2 M-40 450 0.8 0.38 105 639 520 438.00 185.00 65:35
23 18.11.12 PLL/QC2/CON/M 45/TM-1 M-45 470 0.9 0.38 115 643 523 435.00 184.00 65:35
Section-3(PNJ)
Sl. No
Bo
rrow
Are
a
No
Survey No
Ch
ain
ag
e
Sid
e
Lea
d in
Km
No of Grids Pits
Area Proposed
Sqm
Prop/App Quantity in Cum
DOS/ DOT
MDD /OMC
Approved Qty.
Material Suitability
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
1 C3-1 137/E F LHS 3.500 11 6000 9000 05.02.10
/08.02.10 2.275 /8.5
9000 Emb
2 C3-2 323/A,324/E 188 LHS 4.000 9 4800 7200 09.02.10
/18.02.10 1.971 /8.8
7200 SG
3
C3-3 127ML 187 RHS 1.500
16 10500 15750 04.03.10
/05.03.10 1.979 /8.1
30750
Emb
4 10 10500 15000 24.11.10
/25.11.10 2.001
/9.053 Emb. & SG
5 C3-4 160/7-
14/1999, 15/1999
215 LHS 1.500 10 6585 9000 14.03.10
/18.03.10 2.072 /8.1
9000 Emb
6 C3-5 283/A, 293,293
184.6 LHS 1.500 14 13720 14000 14.03.10
/19.03.10 2.153 /8.2
14000 EMB
7 C3-6 53/1 219.7 RHS 1.000 10 9632 14448 07.04.10
/08.07.10 2.052 /9.4
14448 EMB
8 C3-7 84/1 199.15 LHS 1.000 8 7440 11160 13.04.10
/16.04.10 2.050 /9.4
11160 EMB
9 C3-8 34/1 192.5 RHS 3.000 6 6070 9106 30.04.10
/01.05.10 2.017 /9.7
9106 EMB
10 C3-9 292/1 196.22 RHS 1.300 9 7080 10620 08.05.10
/08.05.10 1.973 /9.3
10620 EMB
11 C3-10 626 182.4 RHS 0.500 8 5420 8130 28.04.10
/30.04.10 2.029 /10.1
8130 EMB
12 C3-11 34/9 192.5 RHS 3.500 18 7932 11898 30.04.10
/02.05.10 1.955 /10.1
11898 EMB
13 C3-12 23 194.4 LHS 0.900 14 9106 13659 16.05.10
/22.05.10 1.978 /9.1
13659 EMB
14 C3-13
277/1 206.400 RHS 0.500
14 8740 13110 24.05.10
/25.05.10 1.966 /9.22
380152.5
EMB
15 C3-13 A 22 8740 20625 20.07.10
/26.07.10 1.993 /9.18
EMB
16 C3-13 B 20 8740 18750 28.08.10
/29.08.10 1.999 /9.05
EMB
17 C3-13 C 30 64350 45000 03.10.10
/05.10.10 2.026
/9.165 Emb. & SG
18 C3-13 D 30 64350 45000 02.02.11
/03.02.11 1.991 /9.48
Emb. & SG
19 C3-13 E 30 64350 45000 27.06.11
/28.06.11 2.053
/9.145 Emb. & SG
20 C3-13 F 30 64350 45000 10.10.11
/11.10.11 2.051 /9.16
Emb. & SG
21 C3-13 G 30 64350 45000 07.12.11
/08.12.11 2.026 /9.10
Emb. & SG
22 C3-13 H 30 64350 45000 09.01.12
/10.01.12
2.025
/9.11 Emb. & SG
23 C3-13 I 6 38445 57668 16.02.12
/17.02.12 2.028 /9.12
Emb. & SG
24 C3-14
17/7,17/8 197.25 RHS 5.500
9 37272 8438 06.05.10/09.05.10 1.975/9.4
179438
EMB
25 C3-14 A 38 37272 57000 21.02.11
/22.02.11 2.038
/8.956 Emb. & SG
26 C3-14 B 38 37272 57000 02.06.11
/03.06.11 2.023
/9.106 Emb. & SG
27 C3-14 C 38 37272 57000 12.11.11
/13.11.11 2.032 /9.01
Emb. & SG
28 C3-15 98 196.2 RHS 2.000 15 8944 13416 10.06.10
/11.06.10 1.968 /9.38
13416 EMB
29 C3-16
132/3 204.4 RHS 1.500
16 8094 12141 10.06.10
/13.06.10
1.978
/9.4
42141
EMB
30 C3-16 A 10 8094 15000 11.12.10
/12.12.10 2.013
/9.044 Emb. & SG
31 C3-16 B 10 8094 15000 15.01.11
/16.01.11 2.018
/9.135 Emb. & SG
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
32 C3-17
30 194.4 LHS 0.500
35 18212 27137 12.07.10 24.06.10
1.988 /8.7
36137
Emb. & SG
33 C3-17 A 6 18212 9000 13.12.10
/14.12.10 2.007
/9.138 EMB
34 C3-18
456/A,456/EE & 457/A
190.3 RHS 3.500
9 37270 31566 09.12.10 10.12.10
2.017 /9.14
126066
Emb. & SG
35 C3-18 A 21 37270 31500 18.03.11
/19.03.11 1.987
/9.634 Emb. & SG
36 C3-18 B 21 37270 31500 25.07.11
/26.07.11 2.006
/9.249 Emb. & SG
37 C3-18 C 21 37270 31500 02.11.11
/03.11.11 2.000
/9.286 Emb. & SG
38 C3-19
21/6 225.8 LHS 2.000
6 50600 75000 09.12.10 10.12.11
2.021 /9.17
150000
Emb. & SG
39 C3-19 A 12 50000 75000 30.01.12
/04.02.12 2.037 /9.14
Emb. & SG
40 C3-20
96/1 & 96/3 192.45 RHS 5.000
8 16572 24858 29.12.10 04.01.11
2.016 /9.17
131358
Emb. & SG
41 C3-20 A 17 16572 25500 01.04.11
/02.04.11 2.038
/8.956 Emb. & SG
42 C3-20 B 17 16572 25500 08.07.11
/09.07.11 2.023
/9.106 Emb. & SG
43 C3-20 C 17 16572 25500 03.10.11
/04.10.11 2.023 /9.11
Emb. & SG
44 C3-20 D 20 16572 30000 18.11.11
/19.11.11 2.020 /9.08
Emb. & SG
45 C3-21 205.8 RHS 1.500 8 16000 32000 21.04.11 25.04.11 2.006 /
8.92 32000 Emb. & SG
46 C3-22 2/77 & 22/2 212.5 RHS 9.500 5 15863 23794 20.07.11
/20.07.11 2.034 /9.21
23794 Emb. & SG
47 C3-23 293 203.45 RHS 8.000 3 60000 90000 27.08.11
/29.08.11 2.042 /9.10
90000 Emb. & SG
48 C3-24 349/3 215.5 RHS 5.000 3 11776 17664 09.09.11 /8.10.11 1.942 /9.17
17664 Emb. & SG
49 C3-25 79/2 192.45 LHS 4.000 6 15620 23430 31.01.12
/03.02.12 2.019 /9.11
23430 Emb. & SG
50 C3-26 74 203.45 RHS 4.500 10 15418 15418 31.01.12
/02.02.12 2.033 /9.16
23127 Emb. & SG
51 C3-27 309 203.45 RHS 4.000 6 30000 45000 14.04.12
/15.04.12 2.020 /9.09
45000 Emb. & SG
52 C3-28 60 196.6 LHS 4.000 6 12141 18211 22.05.12
/23.04.12 2.027 /9.18
18211 Emb. & SG
53 C3-29 196.25 LHS 15.000 6 9000 10.08.12
/18.08.12 2.020 /9.17
9000 Emb. & SG
Sl. No.
Date of casting
Trial Mix No.
Gra
de o
f Co
ncre
te
Cem
en
t Bra
nd
Ce
men
t (Kg
/m3
)
ADMIXTURE W/C
ratio
Slu
mp
at 9
0 m
in.
(mm
)
CA
20m
m
(Kg
/Cu
m)
CA
10m
m
(Kg
/Cu
m)
SAND CONTENT (Kg/Cum) CA :
FA Ratio
Brand Name
% Munner
Sand Krishna
Sand
1 23.06.10 TM No:17 M-35
Ram
co - O
PC
43 G
rad
e
400 Fosroc Conplast (430 AA)
0.8 0.40 90 779.4 516 464.4 195.8 63:37
2 18.06.10 TM NO:16 M-25 350 0.7 0.45 90 799.9 529 476.59 200.94 62:38
3 09.06.10 TM NO:8 M-20 310
Sik
am
ent N
N(S
P) S
ou
th
0.7 0.5 90 820.8 543 510.61 215.28 62:38
4 09.06.10 TM No:7 M-15 280 0.7 0.50 55 830.7 550 576.79 217.89 62:38
5 24.06.10 TM-18 M15
Mah
a -
OP
C 4
3
Gra
de
280 0.7 0.50 25 836 554 523 220 62:38
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
6 09.06.10 TM-8 M20 310 0.7 0.45 25 825 547 516 217 62:38
7 25.06.10 PLL/QC3/CONC/M35/TM-2 M-35 400 Fosroc Conplast (430 AA)
0.7 0.40 85 469.8 198 784.1 520.1 64:36
8 29.06.10 PLL/QC3/CONC/M30/TM-2 M-30 380 0.7 0.42 85 474.1 200 791.3 524.8 64:36
9 24.06.10 PLL/QC3/CONC/M20/TM-2 M-20 310 Sikament NN(SP) South
0.7 0.45 75 516.3 217 825.3 547.35 63:37
10 24.06.10 PLL/QC3/CONC/M15/TM-2 M-15 280 0.7 0.50 70 522.5 219.8 835.3 554.0 63:37
11 13.08.10 PLL/QC3/CONC/M40/TM-1 M-40
Ram
co - O
PC
43 G
rad
e
420
Fo
sroc C
on
pla
st (430 A
A)
0.8 0.38 128 478.3 201.2 700.8 570.4 63:37
12 23.06.10 PLL/QC3/CONC/M35/TM-1 M-35 400 0.7 0.40 90 469.6 198 783.8 519.8 64:36
13 18.06.10 PLL/QC3/CONC/M25/TM-1 M-25 350 0.7 0.45 85 481.9 202.7 804.3 533.4 64:36
14 09.06.10 PLL/QC3/CONC/M20/TM-1 M-20 310
Sik
am
ent N
N(S
P) S
ou
th
0.7 0.45 83 516.3 217 825.3 547.4 636:37
15 09.06.10 PLL/QC3/CONC/M15/TM-1 M-15 280 0.7 0.50 78 522.5 219.8 835.3 553.9 63:37
16 09.09.10 PLL/QC3/CONC/M15/TM-3 M-15
Zu
ari 4
3 G
rad
e
280 0.7 0.5 70 835 554 523 220 63:37
17 08.09.10 PLL/QC3/CONC/M20/TM-1 M-20 310 0.7 0.45 80 825 547 516 217 63:37
18 07.09.10 PLL/QC3/CONC/M20/TM-2 M-25 350
Fo
sroc S
P-430 A
A
0.7 0.45 100 726 591 495 208 63:37
19 10.09.10 PLL/QC3/CONC/M30/TM-4 M-30 380 0.7 0.42 120 725 590 474 199 64:36
20 10.09.10 PLL/QC3/CONC/M35/TM-5 M-35 400 0.7 0.40 100 707 576 483 203 63:37
21 13.09.10 PLL/QC3/CONC/M40/TM-6 M-40 420 0.8 0.38 130 701 570 478 201 63:37
22 14.11.10 PLL/QC3/CONC/M40/TM-7 M-20 Kerb
320 0.3 0.45 30 714 584 548 235 59:41
23 17.07.11 PLL/QC3/CONC/M15/TM-75 M15 280 0.7 0.5 30 787 640
Go
dav
ari San
d
700 65:35
24 16.07.11 PLL/QC3/CONC/M20/TM-74 M20 310 0.7 0.5 28 762 620 677 65:35
25 19.07.11 PLL/QC3/CONC/M20/TM-76 M20K 320 0.2 0.45 0 522 660 881 55:45
26 22.07.11 PLL/QC3/CONC/M25/TM-78 M25 350 0.7 0.44 100 750 610 666 65:35
27 08.07.11 PLL/QC3/CONC/M35/TM-67 M35 410 0.7 0.4 100 708 576 658 64:36
28 09.07.11 PLL/QC3/CONC/M40/TM-68 M40 420 0.8 0.38 100 720 586 640 65:35
29 17.12.11 PLL/QC3/DLC DLC 150 - - OMC=5.5
% - 743 675 833
-
30 09.11.11 PLL/QC3/PQC/M40/TM-79 PQC 400
Fo
sroc S
P-430 A
A
0.6 0.37 60 736 597 650 65:35
31 19.12.11 PLL/QC3/CONC/M15/TM-80 M15 Ram
co - O
PC
43 G
rad
e
280 0.7 0.5 30 787 640 700 65:35
32 19.12.11 PLL/QC3/CONC/M20/TM-81 M20 310 0.7 0.5 28 762 620 677 65:35
33 20.12.11 PLL/QC3/CONC/M20/TM-83 M20K 320 0.2 0.45 0 522 660 881 55:45
34 19.12.11 PLL/QC3/CONC/M25/TM-82 M25 350 0.7 0.44 100 750 610 666 65:35
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
35 08.07.11 PLL/QC3/CONC/M35/TM-84 M35 410 0.7 0.4 100 708 576 658 64:36
36 09.07.11 PLL/QC3/CONC/M40/TM-85 M40 420 0.8 0.38 100 720 586 640 65:35
4.3) WEATHER REPORT up to 31st July 2014 Q.C. Lab at Km 73(GIL) ( Camp-1 (Km. 40+000 to Km 105+000)) EPC Contractor partially demobilized their staff and no data submitted Q.C. Lab at Km 116(PNJ) ( Camp-1 (Km. 105+000 to Km 140+000))
EPC Contractor demobilized their camp Q.C. Lab at Km 159(PNJ) ( Camp-2 (Km. 140+000 to Km 180+000)) EPC Contractor partially demobilized their staff and no data submitted Q.C. Lab at Km 204 (PNJ) ( Camp-3 (Km. 180+000 to Km 221+500))
EPC Contractor demobilized their camp
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
5.1) MISCELLANEOUS a) SITE VISIT REPORT
Mr. N.C.Saxena inspected the site on 09,10-07-2014 along with Acting Team Leader Mr K.Satyanarayana Reddy and Concessionaire Project Manager Mr. Vamshidhar Mannava and Concessionaire COO Mr.N.V.Shetty
Mr.I.G.Reddy inspected the site on 16-07-2014 along with Mr P.Ramesh reddy,PD,NHAI, Mr K.Nageswar Rao,Manager(T),NHAI, Acting Team Leader Mr K.Satyanarayana Reddy and Concessionaire Project Manager Mr. Vamshidhar Mannava
b) MONTHLY PROGRESS REVIEW MEETING for July’2014
Mr.N.C.Saxena during the visit met the PD,NHAI and review the satus of workson 10-07-2014 The District Collector Mr Chiranjeevulu reviewed the status of Avenue plantation and service
Roads,drain and Lighting on 25-07-2014 5.2) MANNING SCHEDULE OF INDEPENDENT ENGINEER
(a) Key Professional :
Sr. no.
Name of Expert Position Mobilisation /
Demobilisation
As per Contract
(MM)
Used (MM)
Bal. (MM)
Remarks
Key Personnel (Professional Staff)
1 Mr. Naresh Shard Team Leader-cum-Senior Highway Engineer
04.05.2010 36.00 31.94 4.06
2 Mr. Rajesh Chandra Senior Bridge Design Engineer 31.05.2010 19.00 16.48 2.52
3 Mr. Inapanuri Prasada Rao Traffic and Transportation Expert 01.08.2010 5.00 4.70 0.30
4 Dr. P.K. Nanda Senior Pavement Specialist 05.07.2010 14.00 0.96 13.04
5 Mr. Shaik Asif Ahmed Senior Quality cum Material Expert 25.05.2010 36.94 36.90 0.04
6 Mr. Amitava Basu Financial Expert 01.08.2010 3.00 1.44 1.56
7 Mr. Rohit Jaiswal/Mr.Dipak Rao Legal Expert 01.08.2010 4.00 1.47 2.53
8 Mr. Jacob George Road Safety Expert 01.09.2010 5.00 1.54 3.46
9 Mr. Satyanarayana Reddy Karri Resident cum Highway Engineer 11.05.2010 36.23 48.46 (12.23)
10 Mr. Ramesh Tanuku Highway Design Engineer 04.05.2010 37.33 35.83 1.50
11 Mr. Ram Chandradhan Singh/ Radha Krishna
Bridge / Structural Engineer 20.05.2010 33.00 20.60 12.40
I Sub-Professional
-
1 Mr.S.Prasad Rao Survey Engineer 25.05.2010 32.00 28.66 3.34
2 Mr.Manish Kumar Tiwary Assistant Highway Engineers 01.07.2010 31.50 29.90 1.60
3 Mr.Ravi Kumar/Mr.GHS Chakravarthi
Assistant Highway Engineers 01.07.2010 32.96 43.93 (10.97)
4 Chinmaya Kr. Mallic CAD Expert 08.08.2011 8.00 6.40 1.60
5 Dr N Karunakaran/Mr Sujeet Kumar
Environmental Engineer 17.05.2011 8.00 2.07 5.93
6 Mr.G.Krishnan Assistant Bridge Engineer. 18.05.2010 33.77 44.71 (10.94)
7 Mr.G.T.Srinath/RP singh Assistant Bridge Engineer. 01.08.2010 31.50 28.09 3.41
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
8 Mr.E.Venkateswarlu Assistant Quality-cum-Material Engineers 07.06.2010 35.27 36.74 (1.47)
9 Mr.Gangumalla Satti Raju Assistant Quality-cum-Material Engineers 01.07.2010 35.06 47.44 (12.38)
10 Mr.V.N.Kohli Electrical Engineer 24.07.2010 7.00 4.81 2.19
11 Mr Manish K Deshpandey HTMS / Toll Expert 28.09.2012 5.00 2.65 2.35
II Support Staff
1 Mr.Nitin Jolly/Mr.P.K.Das/Harsh Vardan/Prasanth K Behera/M.Ganesh
Office Manager (1 No.) 04.05.2010 37.79 50.12 (12.33)
2 Mr. Abishek Mishra/ Md Karimuddin/sunil Kr Rana
Accountant (1 No.) 04.05.2010 37.53 36.70 0.83
3 Mr. Mora Suresh Cashier (1 No.) 13.05.2010 37.50 37.50 (0.00)
4 Mr. Anwar/Ganasyam Kumar/Kumod Kalita
Photocopy Machine Operator (1 No.) 10.05.2010 37.67 50.67 (13.00)
5 Mr. Laksmidhar Sahoo Steno (1 No.) 24.05.2010 37.27 37.27 -
6 Md. Saquib Azmi/Balina Srikant/Prakesh
Computer Operator (1 No.) 10.05.2010 37.70 47.70 (10.00)
7 Mr. Madan Verma Guard 14.05.2010 37.60 50.60 (13.00)
8 Mr. Banot Shrinu/G. Nagesh Guard 13.05.2010 37.63 50.63 (13.00)
9 Mr. Kumod Kalita/rakesh Kr. Sahoo/jani
Office Boy (1 No.) 10.05.2010 37.73 49.73 (12.00)
5.3) Progress Strip Chart of Road work
(Enclosed as Annexure B)
5.4) Site Photographs (Enclosed as Annexure C)
5.5) Relevant Correspondences (Enclosed as Annexure D)
5.6) S-Curve (Enclosed as Annexure E)
5.7) Balance works and status of Service roads
Sr. No. From To Length Width CA/COS Side As per CA As per COS
notified
As per COS recently notified
(July 2013) Land Problem
1 46970 47960 990 7.5 CA LHS Completed
2 51600 52120 520 5.5 COS LHS
Completed
3 52120 54650 2530 9 CA LHS 550m DBM
completed,
1080 m Part width WMM top completed and balance length
yet to be strated ( few structures at
issolated locations are pending due to
court cases)
4 56530 57180 650 5.5 COS LHS
Completed
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
5 63190 63860 670 5.5 COS LHS
Completed
6 67250 67700 450 5.5
Instructed by NHAI-
1676 dated 12.09.2012
LHS
Completed
7 72750 73180 430 5.5 COS LHS
Completed
8 78080 79800 1720 9 CA LHS Completed
9 91380 92000 620 3.75 COS LHS
Completed
10 97350 98000 650 3.75 COS LHS
Completed
11 100830 101550 720 5.5 CA LHS Completed
12 104900 105700 800 5.5
Instructed by NHAI-
1676 dated 12.09.2012
LHS
Completed
13 119400 119700 300 3.75 COS LHS
Completed
14 121000 122200 1200 7.5 CA LHS Completed
15 129100 129600 500 5.5
Instructed by NHAI-
1676 dated 12.09.2012
LHS
Part length of 400m completed
as per public requirement even
though COS Order not issued.
100m balance
16 132925 134200 1275 9 CA LHS Completed
17 135800 138000 2200 9 CA LHS Completed
18 139300 140700 1400 5.5 CA LHS Completed
19 162700 164300 1600 5.5 CA LHS 1500m length
Completed
100m land acquisition problem due to Wakf
land
20 165540 166750 1210 5.5 CA LHS Completed
21 168750 169800 1050 5.5
Instructed by NHAI-
1676 dated 12.09.2012
LHS
Work not taken up due to COS order and initial advance as per Article 16 not received till
date
22 178640 179640 1000 3.75 CA LHS Completed
23 180600 181300 700 3.75 CA LHS Completed
24 185900 186700 800 5.5 CA LHS Completed
25 188400 190400 2000 7 CA LHS Completed
26 191080 191740 660 5.5 CA LHS Completed
27 193600 194400 800 5.5 CA LHS Completed
28 197960 198680 720 3.75 CA LHS Completed
29 202300 203640 1340 7 CA LHS Completed
30 209600 210600 1000 5.5 CA LHS Completed
31 213840 214560 720 5.5 CA LHS Completed
32 46970 47960 990 7.5 CA RHS Completed
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
33 51350 52120 770 5.5 COS RHS
170m Completed
Embankment work is in progress
Most of the land is acquired except at
one locations land yet to be acquired.
34 52120 54650 2530 9 CA RHS
Most of the land is acquired except at
few issolated locations, shifting of
Utilities are completed partly,
almost 1Km completed up to GSB
35 56530 57180 650 5.5 COS RHS Completed
36 63190 63860 670 5.5 COS RHS Completed
37 67250 67700 450 5.5
Instructed by NHAI-
1676 dated 12.09.2012
RHS
Completed
38 72750 73180 430 5.5 COS RHS
Completed
39 78080 79800 1720 9 CA RHS 880m DBM
completed
Land acquisition completed in Feb.
2014, Embankment work is in progress.
40 91380 92000 620 3.75 COS RHS
Completed
41 97350 98000 650 3.75 COS RHS
Completed
42 100830 101550 720 7.5 CA RHS
Completed
43 104900 105700 800 5.5
Instructed by NHAI-
1676 dated 12.09.2012
RHS
Completed
44 119400 119700 300 3.75 COS RHS
Completed
45 121000 122200 1200 7.5 CA RHS Completed
46 125200 125570 370 5.5
Instructed by NHAI-
1676 dated 12.09.2012
RHS
Completed
47 129100 129600 500 5.5
Instructed by NHAI-
1676 dated 12.09.2012
RHS
Part length of 300m completed
as per public requirement, the
balance not taken up for COS order and advance as per Article 16.
200m balance
48 132925 134200 1275 9 CA RHS Completed
49 135800 138000 2200 9 CA RHS Completed
50 139300 140700 1400 9 CA RHS Completed
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
51 162700 164300 1600 5.5 CA RHS Completed
52 165540 166450 910 5.5 CA RHS Completed
53 168750 169800 1050 5.5
Instructed by NHAI-
1676 dated 12.09.2012
RHS
Work not taken up due to COS order and initial advance as per Article 16 not received till
date
54 178640 179640 1000 3.75 CA RHS Completed
55 180600 181300 700 3.75 CA RHS Completed
56 185900 186700 800 5.5 CA RHS Completed
57 188400 190400 2000 7 CA RHS Completed
58 191080 191740 660 5.5 CA RHS Completed
59 193600 194400 800 5.5 CA RHS Completed
60 197960 198680 720 3.75 CA RHS Completed
61 202300 203640 1340 7 CA RHS Completed
62 209600 210600 1000 5.5 CA RHS Completed
63 213840 214560 720 5.5 CA RHS Completed
62770
Details of works affected due to land constraint
S.No Description Chainage
From Chainage
To Length in m Side Remarks
1 Toll Plaza-1 at Km 60+650
Rigid pavement Tapering 60.460 60.620 160.000 RHS
Hon'ble High Court handed over the land with Conditions due to which Concessioniare sought NHAI response,recently PD,NHAI
given clearance
60.700 60.900 200.000 RHS -do-
60.400 60.560 160.000 LHS -do-
High Mast Lighting
1 No RHS -do-
Maintenance Building
LHS -do-
Rest Area and traffic aid post
LHS -do-
Land Scaping and foot path,BHS partially completed
BHS -do-
Static weigh Bridge,RHS (Land restriction)
RHS -do-
Maintenance Stores,LHS
LHS -do-
Barbed fencing and Chain link fencing to be completed
BHS -do-
2 Toll Plaza-3 at Km 205+025
Rest area and Traffic Aid Post,LHS temporary arrangement is made in a container.
LHS
Parking for Vehicles,LHS (Land restriction)
LHS
Land Scaping and foot path completed in available land
BHS
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
Static weigh Bridge,BHS (Land restriction)
BHS
Maintenance Stores,LHS (Land restriction)
LHS
Barbed wire fencing,BHS to be done as per design after availability of land
BHS
3 6-Lane balance Stretches
Chouttupal 52.700 53.500 800.000 RHS COS, Balance due to land problem
Chouttupal 53.450 53.550 100.000 LHS COS, Balance due to land problem
Chityal 78.450 78.880 430.000 RHS
COS, Land acquisition completed in Feb. 2014, shifting of Utilities in progress
Munagala 163.000 163.360 360.000 LHS 260 m completed balance land problem
4 Service Road
Lakkaram 51.350 51.950 600.000 RHS
Around 1260m length at 17 locations are under acquisition process
Chouttupal 52.120 54.650
550 mtr DBM completed,
balance 1980 due to land
LHS
Chouttupal 52.120 54.650 2530.000 RHS
Chityal 78.450 79.250 800.000 RHS
Land acquisition completed in Feb. 2014, shifting of Utilities in progress .
Munagala 163.000 163.360 360.000 LHS
260m completed, Balance 100m due to land problem
Dwarakunta 185.900 186.100 Completed LHS Completed
5 RCC Drain
Chouttupal 52.120 52.200 80.000 LHS Land cleared recently
Chouttupal 52.530 52.630 100.000 LHS Land cleared recently
Chouttupal 53.220 53.280 60.000 LHS Land cleared recently
Chouttupal 52.580 52.810 230.000 RHS Land cleared recently
Kattangore 100.870 100.910 40.000 LHS Land cleared recently
Kattangore 101.000 101.050 50.000 LHS
Kattangore 101.170 101.200 30.000 RHS
Kattangore 101.230 101.260 30.000 RHS
Munagala 163.000 163.400 400.000 LHS
300m completed, Balance 100m due to land problem
Dwarakunta 186.000 186.100 Completed LHS Completed as per Site requirement
Ramapuram 188.400 188.450 50.000 LHS Land cleared in Jan.'14
Ramapuram 189.940 190.010 70.000 RHS Land cleared
Chillakallu 202.400 202.520 120.000 RHS Balance due to land problem
6 Pedestrian Guard Rail
Chouttupal
652.000 BHS Service road work not completed
Chityal
900.000 RHS Service road work not completed
Munagala
300.000 LHS
200m public resistance, 100m Balance due to Land problem
Suryapet
100.000 RHS Public Resistance
7 Way side amenities
Km 69+700,RHS
RHS Land problem
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
Km 168+200,LHS
LHS Land problem
8 Street Lighting
Chouttupal-Service Road 52.120 54.650 2530.000 BHS Service road work still not completed
Chityal-Service Road 78.080 79.800 1720.000 RHS Service road work still not completed
Munagala-Service Road 162.700 163.360 660.000 LHS
560m completed, Balance due to Land problem
Dwarakunta 185.900 186.100 200.000 LHS Completed
9 Junctions
Junctions are constructed based on availability of land, and are functioning well, but these junctions are to be reconstructed/improved after the land made available as per original issued GFC
land acquisition is in progress
10 Bus shelter on Service Road
Chouttupal Service Road
1 no Each BHS Balance due to Land problem
Munagala Service Road
1 No LHS Balance due to Land problem
Chillkallu
1 No, Completed LHS
Balance Shifted to Km 219 as per directions of PD,NHAI which is in progress
Service Road work instructed vide letter No:4205 dated 03-07-2013 ( Not started for COS order)
Sr.
No.
Chainage
From
Chainage
To Length Width Side As per COS notified Remarks
1 77850 78080 230 5.50 LHS Not Started
2 138500 139300 800 5.50 LHS Not Started
3 150700 151200 500 5.50 LHS Not Started
4 154700 155450 750 5.50 LHS Not Started
5 200823 201000 177 5.50 LHS Not Started
6 122800 123200 400 5.50 RHS Not Started
7 150700 151200 500 5.50 RHS Not Started
8 154700 155450 750 5.50 RHS Not Started
9 200823 201000 177 5.50 RHS Not Started
Total 4284
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
Status of as built drawings as on July 2014
AS BUILT DRAWINGS - SUBMISSION STATUS - HYDERABAD VIJAYAWADA PROJECT AS ON 31.07.2014
Ref
As
per
Sche
dule
H -
Ann
ex I
List of
Drawing
(as per
Schedule
H - Annex
I)
BIPL SECTION - KM. 40 TO 105 PLL SECTION - KM. 105 TO 221.50
DETAILS OF
THE ASBUILT
DRAWINGS
SUMISSION/APPRO
VAL STATUS REMARKS
DETAILS OF THE
ASBUILT
DRAWINGS
SUMISSION/APPRO
VAL STATUS REMARKS
A
Horizontal
Alignment,
Vertical Profile and
cross
sections
1) Plan and Profile
- Main Carriageway
2) Plan and Profile
- Service/Slip
Road
3) Plan and Profile
- Cart Track 4) Typical Cross
Section &
Schedule 5) Running Cross
Section
6) Horizontal Alignment Report
7) Vertical
Alignment Report 8) GPS Pillar
Details
1) Consented by IE 2) Consented by IE
3) Consented by IE
4) Consented by IE 5) Consented by IE
6) Consented by IE
7) Consented by IE 8) Consented by IE
5) Running Cross sections -
Revision duly
incorporating comments in
compliance with
IE's observations is awaited
1) Plan and Profile -
Main Carriageway
2) Plan and Profile -
Service/Slip Road
3) Plan and Profile -
Cart Track 4) Typical Cross
Section & Schedule
5) Running Cross Section
6) Horizontal
Alignment Report 7) Vertical Alignment
Report
8) GPS Pillar Details
1) Consented by IE
2) Consented by IE
3) Consented by IE 4) Returned by IE
5) Consented by IE
6) Consented by IE 7) Consented by IE
8) Consented by IE
4) IE has sought
Justification for
changes in the typical cross sections in
comparison to the
sections provided in the CA (schedule- B).
The Concessionaire
submitted their proposal, which is
not in order
B
Cross
Drainage
Works
1) Pipe Culverts 2) Box Culverts
3) Major Bridge
4) Minor Bridges 5)Miscelleneous
Drawings
1) Consented by IE
2) Consented by IE
3) Consented by IE
4) Consented by IE
5) Consented by IE
-----
1) Pipe Culverts 2) Box Culverts
3) Major Bridge
4) Minor Bridges 5)Miscelleneous
Drawings
1) Consented by IE
2) Consented by IE
3) Consented by IE
4) Consented by IE
5) Consented by IE
C
Interchang
es, Major
Intersections, Grade
Separators
and Underpasse
s
1) Major Junction - Plan and Profile
2) Minor Junction
- Plan and Profile 3) Vehicular
Underpasses
4) Cattle Underpasses
5) RCC Retaining
Wall Structures 6) MAC RES
Paraweb Soil Wall
(RE Wall)
1) Consented by IE
2) Consented by IE 3) Consented by IE
4) Consented by IE
5) Consented by IE 6) Consented by IE
-----
1) Major Junction -
Plan and Profile 2) Minor Junction -
Plan and Profile
3) Vehicular Underpasses
4) Cattle Underpasses
5) Details of RE wall Structures
1) Consented by IE
2) Consented by IE
3) Consented by IE 4) Consented by IE
5) Consented by IE
D
Toll Plaza
Layout, Toll
Collection
Systems and
roadway
near Toll Plaza,
Control
Centre
1) All toll plaza
related drawings
including Layout Plan, Site Details,
Island & Booth
Details, Tunnel Details, Canopy
Details, Control
block, Service Block Details
1) Consented by IE -----
1) All toll plaza related
drawings including Layout Plan, Site
Details, Island &
Booth Details, Tunnel Details, Canopy
Details, Control block,
Service Block Details
Consented by IE
E
Busbay and
Bus sheleter
with
furniture and
drainage
system
1) Layout Plan &
Sections - Bus
Bay
2) Layout Plan,
Section &
Elevation - Bus shelter
1) Consented by IE
2) Consented by IE -----
1) Layout Plan &
Sections - Bus Bay
2) Layout Plan,
Section & Elevation -
Bus shelter
1) Consented by IE
2) Consented by IE -----
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
F
Truck
Parking lay bye with
furniture
and drainage
system
1) Details of Truck Laybye
2) Details of
Truck laybye Toilet Block
1) Consented by IE 2) Consented by IE
-----
1) Details of Truck
Laybye 2) Details of Truck
laybye Toilet Block
1) Consented by IE 2) Consented by IE
-----
G
Road
furnitures
likeTraffic Signage,
Markings,
Safety Barriers
1) Typical Details
of Traffic Signs & Signage Layout
for the Corridor2)
W Beam Metallic Crash Barrier
Details &
Schedule3) Road Marking Details4)
Toll plaza sign
boards5) Delineator Details
& Schedule6)
Details of Road Studs &
Schedule7) Details
of Pedestrian Guard Rail &
Schedule8)
Typical Details of Median
openings9) Details
of Kilometer stone, Hectometer
stones & Guard
Posts & Schedule10)
Details of
Shoulder mounted Cantilever
Gantry11) Details
of Overhead Gantry12) Details
of Boundary
Stones13) Details of Median
Openings14) RUB
Diversion plan
1) Consented by IE
2) Consented by IE 3) Consented by IE
4) Consented by IE
5) Consented by IE 6) Consented by IE
7) Consented by IE
8) Consented by IE 9) Consented by IE
10) Consented by IE
11) Consented by IE 12) Consented by IE
13) Consented by IE
14) Consented by IE
-----
1) Typical Details of
Traffic Signs &
Signage Layout for the Corridor
2) W Beam Metallic
Crash Barrier Details & Schedule
3) Road Marking
Details 4) Toll plaza sign
boards
5) Delineator Details & Schedule
6) Details of Road
Studs & Schedule 7) Details of
Pedestrian Guard Rail
& Schedule 8) Typical Details of
Median openings
9) Details of Kilometer stone,
Hectometer stones &
Guard Posts & Schedule
10) Details of
Shoulder mounted Cantilever Gantry
11) Details of
Overhead Gantry 12) Details of
Boundary Stones
13) Details of Median Openings
1) Returned by IE
2) Consented by IE 3) Service Road not
submitted
4) Yet to be submitted 5) Consented by IE
6) Consented by IE
7) Consented by IE 8) Consented by IE
9) Consented by IE
10) Consented by IE 11) Consented by IE
12) Consented by IE
13) Consented by IE
1) Corrections in compliance with IE's
observations is
awaited. 3)Road marking
schedule for Service
Road not submitted 4) Submission is
still awaited
6)one drawing correction is to be
done.
H
Road Drainage
Measures
1) Earthen Drain
Plan and Profile
2) RCC Drain
Plan and Profile
1) Consented by IE
2) Consented by IE -----
1) Earthen Drain Plan
and Profile
2) RCC Drain Plan
and Profile
1) Returned by IE
2) Returned by IE
1) IE has sought
justification on the locations, where the
provision of drain is
not provided.
2)corected drawings
not submitted till
date
I
Typical
Details
Slope Protection
Measures
1) Details of Embankment
Protection and
Schedule 2) Details of
Energy
Dissipation Basins 3) Details of Drain
and Drain Slab
4) Details and Schedule of
Median Chute
5) Schedule for Edge Kerb
6)Gabion wall
1) Consented by IE
2) Consented by IE 3) Consented by IE
4) Consented by IE
5) Consented by IE 6) Still awaited
-----
1) Details of Embankment
Protection and
Schedule 2) Details of Energy
Dissipation Basins
3) Details of Drain and Drain Slab
4) Details and
Schedule of Median Chute
5) Schedule for Edge
Kerb
1) Consented by IE
2) Consented by IE 3) Yet to be submited
4) Consented by IE
5)Consented by IE
3) Submission
awaited
‘Independent Consultancy Services for Design, Engineering, Construction, Development, Finance, Operation and
Maintenance of 4/6 laning of Hyderabad-Vijayawada Section from Km 40.00 to Km 221.500 of NH-9 in the State of
Andhra Pradesh under NHDP Phase-III
Monthly Report for July 2014
J
Landscapin
g and horiticultur
e
1) Typical Cross
section for Plantation &
Schedule
1) Consented by IE -----
1) Typical Cross
section for Plantation
& Schedule
1)Returned by IE
1) Corrections in
compliance with IE's observations is
awaited.
K Pedestrian
Crossings
1) Pedestrian
Underpasses 1) Consented by IE -----
1) Pedestrian
Underpasses 1) Consented by IE -----
L Street
Lighting
1) Street Lighting
Layout 2) High Mast
Lighting Details
3) VUP lighting Details
4) Lighting Plan in
Truck laybye & Bus bay
5) Miscellaneous
electrical drawings including Single
Line Diagrams,
Equipment Layout of service block,
Illumination &
SW socket plan of service block,
Earthing Plan,
Cable Routing Plan, Illumination
Plan - Canopy,
Illumination plan - Control Block,
SW Socket Plan -
Control Block,
Lighting
Protection Plan -
Control Block, illumination and
SW socket Plan -
Booths
1) Consented by IE
2) Consented by IE 3) Consented by IE
4) Consented by IE
5) Consented by IE
-----
1) Highway Lighting
Plan and SLD
2) SLD for Toll Plaza Area
3) VUP Lighting
Details 4) Service Road Plan
and SLD
5 Bus bay Lighting Plan
6) Miscellaneous
electrical drawings including Single Line
Diagrams, Equipment
Layout of service block, Illumination &
SW socket plan of
service block, Earthing Plan, Cable Routing
Plan, Illumination Plan
- Canopy, Illumination plan - Control Block,
SW Socket Plan -
Control Block,
Lighting Protection
Plan - Control Block,
illumination and SW socket Plan - Booths
1) Consented by IE 2) Consented by IE
3) Consented by IE
4) Consented by IE 5) Consented by IE
6) Consented by IE
-----
M
Rain water
harvesting
Structure drawings
Consented by IE
Consented by IE -----
Note:
1). Submission of as built drawings as per Article 12.3 (g) and Schedule H of Concession Agreement is still awaited from Km 105 to Km 221+500.
2). As per the instruction of the Chairman, NHAI the design booklets hard copies from Km 40+000 to 221+500 are submitted and some more balance are still
awaited (The Concessionaire submitted soft copies from Km 40+000 to 105+000 excluding RE walls, Minor bridges at Km 77+950 and 96+290).