Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
ISGF 2016in India, 17 March, 2016
TEPCO‘s Smart Grid Initiatives
◆Service Area : 39,576 km2
・One-tenth of Japan’s land area
◆Population : 44.8 million
◆Electricity Sales :
257,000 GWh (FY 2014)
◆Peak Demand :
64.3 GW (July 2001)
49.8 GW (Aug 2014)
・One-third of Japan’s total demand
Takashi OharaPower System Engineering Center,
Power Grid Company, Tokyo Electric Power Co., Inc.
Position of TEPCO
Theme-C: Part(ⅰ) SG Project Outcome –Utility Perspective
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
2Contents
Ⅰ. Power System Reforming in Japanwer System
Reforming in J
Ⅱ. Change of TEPCO’s business administration system
Ⅲ. Major management challenges regarding power
transmission and distribution section in TEPCO
Ⅳ. TEPCO’s initiatives for Smart Grid
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
3
Phase1
2015
Foundation of Wide-Area Grid Operator
・ Planning of Wide-Area Power Supply and Demand Balancing
・ Wide-Area Grid Operation
・ Planning of Interconnecting Lines and Area Trunk
Transmission Lines
・ Supply and Demand Balancing Emergency Control
Preparation for Retail Complete Liberalization
Phase 2
2016
Retail Complete Liberalization
Transition Term of Tariff Regulation
Abolition of Tariff Regulation
Last Resort Service and Universal Service to be secured
・Preparation of Rules for More Neutral Grid Utilization
・Design of Capacity Market and Bidding System of Power Plants
Legal Unbundling of Transmission and Distribution Sector
Realization of
Competitive
Market
Phase 3
2020
Organization for Promoting Wide-Area Grid Operation
I. Power System Reforming in JAPAN
Road Map for Power System Reforming in JAPAN from 2013
Preparation of Wide-Area Grid Operator
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
4
April 2013~
Po
we
r Grid
Co
mp
an
y (P
GC
)
Cu
sto
me
r Se
rvic
e
Co
mp
an
y (C
SC
)
Fu
el &
Po
we
r
Co
mp
an
y (F
PC
)
Corporate
April 2016~
TE
PC
O P
ow
er G
rid
Co
mp
an
y
TE
PC
O E
ne
rgy P
artn
er
(Re
tailin
g)
TE
PC
O F
ue
l & P
ow
er
Co
mp
an
y
Tokyo Electric Power
Company Holdings, Inc.
II. Change of the business administration system of TEPCO
Holding Company System in TEPCO (2016-)
Holding Company System
In house Company System
Tokyo Electric Power
Company, Inc.
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
Electricity Supply Facilities (International Comparison)
III. Major management challenges of power transmission and distribution section in TEPCO
Coexistence of lower wheeling charges and stable supply
Frequency of Outage
(SAIFI)
Duration of Outage
(SAIDI)
Japan : 0.16 (times / per year)
TEPCO : 0.07 (times / per year)
Japan : 16 (minutes / per year)
TEPCO : 4 (minutes / per year)
SAIFI : System Average Interruption Frequency Index
SAIDI : System Average Interruption Duration Index
As of the end of FY 2014
Source: TEPCO
Source: TEPCO
(Notes)
1. For Japan, the data was acquired in FY 2013 by the federation of
Electric Power Companies
2. For USA, the data was acquired in FY 2013, which includes bad
storms. (Ref)”Statistics of foreign electric power business (2014)
“by Japan Electric Power Information Center
3. For Germany, France and UK, the data was acquired in FY 2012,
which includes heavy weather. (Ref) CEER [Benchmarking Report
5.1 on the Continuity of Electricity Supply]
5
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
III. Major management challenges of power transmission and distribution section in TEPCO
Coexistence of lower wheeling charge and stable supplyW
heelin
g C
osts
(yen/k
Wh)
Wheeling Costs (International Comparison)
Source : Mitsubishi Research Institute, Inc., March 2012
6
Yr
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
0
10
20
2011 2012 2013 2014 2030
7III. Major management challenges of power transmission and distribution section in TEPCO
Upgrade of network use environment
Installed capacity of Renewable energyIn
sta
lled c
apacity (
GW
)
FIT(2012.7~)
(Prospected)
・・・
FIT : Feed-in-tariff
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
8
Solar
HydroNuclear
Battery
Thermal
TEPCO
Central Dispatch Center
Other
Utility
1 Upgrade of Distribution system
【36P】
WindBattery
Substation2.1 Wind Generation
Enhancement
2.2 Increase of East-West
Interconnection Capacity
3.1 Development of Integrated
Battery System
3.2 V2G Demonstration
Organization for Cross-regional
Coordination of
Transmission Operators
IV. TEPCO’s initiatives for Smart Grid
Overview of TEPCO’s Smart Grid activities
Transmission
Network
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
9
:Communication line
★ Remote setting for
control devices
東京電力
:Sensor built-in switch
Monitoring data
Measurement
Data (V, I, etc)
New information
<Office>DG
Substation
SVR, etc
Wind, PV
Smart meter
:Distribution Line
<Modernization of Distribution>
★ Prompt system
impact study for
interconnection
★ Fault point
detection by
monitoring V0, I0
★ Switching based on
phase angle
measurement
IV. TEPCO’s initiatives for Smart Grid
1. Upgrade of Distribution System
Optimization of Distribution Network Operation
Merits of monitoring and controlling system with sensor built-in switch- Securing of power quality using measurement data (V, I) for RE integration study
- Quick fault detection and prompt restoration to prevent faults
- Improvement of efficiency using remote control
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
10
TEPCO receives power from Hokkaido and Tohoku,- to reduce frequency fluctuation in Hokkaido.- to enhance regulation control volume in Tohoku.
Power from Hokkaido
Power from Tohoku
Inter-tie line (DC)
remote control
Wind-Farm
Curtailment
New control scheme
Utilization
New control scheme
Utilizationremote control
Curtailment
Wind-Farm
Inter-tie line (AC)
TEPCO
・If necessary, curtail power output of wind-farms.
Now
Supply
Demand
調整力
Transmission amount
for TEPCO
Future
Demand
調整力Supply
Generation Control of wind power
Base
power
supply
Base
power
supply
Regulation power
IV. TEPCO’s initiatives for Smart Grid
2.1 Expansion of wind power generation by power system operation
with wide area coordination
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
11
East-West Interconnection
1,200→2,100MW(+900MW)
Shin-Shinano 2FC thyristor valves
60Hz System(West)
50Hz System(East)
IV. TEPCO’s initiatives for Smart Grid
2.2 Increase of East-West Interconnection Capacity by HVDC
Shin-Shinano 600MW
Sakuma 300MW
Higashi-Shimizu300MW
New HVDC 900MW
Frequency converter station
FY2020
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
12
Distribution System
Utility-side Batteries
Thermal Power
SubstationICDSystem
ICDSystem
Customer-side Batteries
Battery SCADA
Hydro PowerFunctions of Battery SCADALoad Frequency Control
Daily Demand & Supply Balance
Spinning Reserve
Virtual Large
Battery
SCADA: Supervisory Control And Data Acquisition, ICD: Information Collection & Distribution
Central Loading Dispatch Center
Power System
Information Network
Transmission System
Connecting toBatteries of
SHARP & SONY
-200
-150
-100
-50
0
50
100
150
200
11:30 11:40 11:50 12:00Time
Output[kW
]
Control ValueOutput
Trial result
IV. TEPCO’s activities for Smart Grid
3.1 Development of integrated control of battery energy storage
Battery SCADA enables the System Operator to control Multiple Dispersed
Batteries as a Virtual Large Battery.
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
13
V2G System
Solar panel
Smart HouseAC/DC
Distribution Line
EV
Electricity Electricity
Energy Services
TEPCO’s Smart House Concept
Electricity
Life HEMS Screen
IV. TEPCO’s initiatives for Smart Grid
3.2 Vehicle to Grid (V2G) demonstration project
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
14
Monitoring and
control server
Charge/
Discharge
A/CHeat Pump
EV/PHV
Electric Light
Solar
HEMS/
Smart Interface
Control
Mega SolarBattery
Control CenterDistribution
network
PCSPCS
EMS
Smart Meter
control
Generation
control
EMS
Hotel
EMSHeat Pump
Generator
Minimize battery capacityFuel costs reduction
Energy ManagementMonitoring/
control
Geothermal energy
Monitoring/
control
Monitoring/
control
Fishing port Refrigerator・Local industry
IV. TEPCO’s initiatives for Smart Grid
Island Field Test
Through an island field, the cost-minimum system is verified by the cooperative
control of power plants and storage facilities.
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
15IV. TEPCO’s initiatives for Smart Grid
Development and Introduction of Smart Meters
EV
Watching service etc.
Smart meterEnergy Efficiency
Consult
PV
Visualization (Direct offer)
Battery
Automatic metering
Demand Response etc.
Visualization(Web)
MDMS
TEPCO (PGC)
Mobile phone, Internet
New service・Demand Response(DR) etc.
Retailers System
A route
B route
MDMS : Meter Data Management System
Communication
Configuration of smart meter system
Measuring function
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
16IV. TEPCO’s initiatives for Smart Grid
Schedule of Smart Meter installation
2015FY 2017 2018 2019 202020162013~14
Installation
Plan
Approx.
27 million
houses
Introduction period Acceleration periodDevelopmental
period
5.7million
Meter
Total10 million 27 million
Smart meter
Copyright ©2016 Tokyo Electric Power Co., Inc. All Rights Reserved
17
• TEPCO's Power Grid Company has secured a stable power supply, utilizing scale merit of large capacity and bulk power transmission.
• Smart Grid will be a platform for realizing energy use efficiency and optimization through a revolution in energy services.
• TEPCO will work to realize this platform with:– Smart meters and new services pursuing the ideal
business model in the liberalized market
– Various R&D challenges and Technologies
Conclusions