+ All Categories
Home > Documents > IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the...

IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the...

Date post: 12-Jun-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
55
IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 30 TH DAY OF JULY 2014 PRESENT THE HON’BLE MR.JUSTICE K.L.MANJUNATH AND THE HON’BLE MR.JUSTICE RAVI MALIMATH Regular First Appeal No.958 of 2010 (DEC-INJ) BETWEEN: M/s.Kolte Patil Developers Ltd Being a Company incorporated Under the Companies Act 1956 Having its registered office at: Navipeth District Jalagaon Maharastra. And Branch Office at: No.22/11, Vittal Malya Road, 1 st Floor, “Park West” Bangalore – 560 001. Represented by its Joint Managing Director Mr.Naresh A.Patil. APPELLANT (By Sri Yoga Narasimha, Senior Advocate and Sri Raju Ramachandran, Sr.Advocate for Sri G.L. Vishwanth, Advocate) ®
Transcript
Page 1: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

IN THE HIGH COURT OF KARNATAKA AT BANGALORE

DATED THIS THE 30TH DAY OF JULY 2014

PRESENT

THE HON’BLE MR.JUSTICE K.L.MANJUNATH

AND

THE HON’BLE MR.JUSTICE RAVI MALIMATH

Regular First Appeal No.958 of 2010 (DEC-INJ) BETWEEN: M/s.Kolte Patil Developers Ltd

Being a Company incorporated Under the Companies Act 1956 Having its registered office at: Navipeth District Jalagaon Maharastra.

And Branch Office at: No.22/11, Vittal Malya Road, 1st Floor, “Park West” Bangalore – 560 001.

Represented by its Joint Managing Director Mr.Naresh A.Patil. … APPELLANT

(By Sri Yoga Narasimha, Senior Advocate and Sri Raju Ramachandran, Sr.Advocate for

Sri G.L. Vishwanth, Advocate)

®

Page 2: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

2

AND:

1. NTI Housing Co-Operative Society

No.5, ‘C’ Palace Orchards Apartments No.51, RMV Extension 6th Cross, 9th Main road, Bangalore – 560 080.

2. Sri CVL Shastry

S/o late N.Venkatasubba Shastry Aged about 75 years No.73, 9th Main, RMV Extension Bangalore – 560 080

*Since deceased by LRs 2(a) Smt.Sharadamma

W/o late CVL Shastry Aged about 72 years

2(b) B.L.Nagendraprasad S/o late CVL Shastry Aged about 50 years 2(c) L.Narendra Prasad

S/o late CVL Shastry Aged about 45 years All are residing at No.73, 9th Main, RMV Extension Bangalore – 560 080. … RESPONDENTS

*Amended as per Court order dated 14.9.2012

(By Sri K.S. Nagaraja Rao, Advocate for C/R1; Sri C.V. Nagesh, Sr. Advocate for

Sri K. Suman, Advocate for R2 (a to c))

Page 3: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

3

This RFA is filed under Section 96 of CPC, against the

judgment dated 19.3.2010 passed in O.S.No.1572/2005 on the file of the XVII Additional City Civil Judge, (CCH.No.6), Bangalore, dismissing the suit for declaration and permanent injunction.

This RFA coming on for final hearing this day,

K.L.Manjunath J., delivered the following:-

J U D G M E N T The legality and correctness of the judgment and

decree passed by the XVII Additional City Civil Judge,

Bangalore dated 19.03.2010, passed in O.S. No.1572/2005

is called in question by the unsuccessful plaintiff.

2. Heard the learned counsel for both the parties.

3. On an earlier occasion, this Court had heard two

learned Senior Counsel appearing for the appellants

Sri.Yoga Narasimha and Sri.Raju Ramachandran and the

learned Senior Counsel, Sri.C.V.Nagesh for respondents

2(a) to (c) and Sri.Nagaraja Rao, the learned counsel for

respondent no.1. After conclusion of the arguments, an

application was filed by the appellant under Order-6,

Page 4: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

4

Order-17 of C.P.C., to amend the plaint which application

was considered and rejected by this Court by a detailed

order dated 25.02.2014 and thereafter the matter is again

heard on merits.

4. The facts leading to this appeal are as hereunder:

The plaintiff is a private limited company. The first

defendant is a society registered under the provisions of the

Karnataka Cooperative Societies Act. According to the

plaint averments, the first defendant-society was the owner

of 16 acres, 20 guntas of land situated in survey Nos. 12/6,

13/1, 13/2 and a portion of survey No.19 of

Nagashettyhalli Village, Kasaba Hobli at Bangalore, which

was purchased from the first defendant-society from the

Bangalore Development Authority under a registered

transfer deed dated 23.11.1988. According to the plaint

averments, the second defendant was instrumental in

bringing about the transfer of the land in his capacity as a

General Power Attorney Holder of the original land owners

Page 5: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

5

which was the subject matter of the writ petitions before

this Court in W.P. No.21168-72/1997, which matter was

taken up to the Hon’ble Supreme Court in SLP (Civil)

No.21317-321/2001 decided on 25.01.2002.

5. The plaintiff was put in possession of 5 acres of land

in the aforesaid survey numbers in the month of

October’1995 under different agreements executed by the

first defendant-society in favour of the plaintiff. Later the

society also confirmed the delivery of possession to an

extent of 5 acres of land. The first defendant-society also

executed the Power of Attorney in the name of Sri.N.A.Patil

and Sri.A.V. Patil, who are directors of the company and

also executed declaration under indemnity bond on

21.10.1995 and deed of no objection in favour of the

plaintiff to develop the property.

6. During October’1995, the plaintiff was put in

possession. The first defendant had already obtained a

sanction plan from BDA on 10.11.1995 for construction of

Page 6: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

6

the entire 5 acres of land for residential multistoried

apartment buildings. The plaintiff accepted the project and

later discovered that there was discrepancy in the

measurement of the property and thereafter the entire land

was fenced and commenced the construction. The plaintiff

constructed a multistoried apartments complex known as

‘Whispering Meadows’ which comprise four blocks.

7. In 1997 some disputes arose between the society and

the plaintiff which resulted in the society filing a suit

against the plaintiff before the City Civil Court, Bangalore

in O.S. No.5649/1997 for a perpetual injunction from

restraining the plaintiff from exercising any rights under

the agreements executed and further restraining the

plaintiff from proceeding with the construction. It was

contended in the suit that the agreements and the General

Power of Attorney executed by the society in favour of the

plaintiff was got cancelled. Ultimately, the said suit came to

be compromised by virtue of an agreement and declaration

Page 7: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

7

dated 24.07.1999. In the compromise petition the society

withdrew all the allegations made against the plaintiff and

similarly the plaintiff withdrew the allegations made against

the respondent-society and as per the compromise petition,

the society confirmed the enforcement of the General Power

of Attorney by the plaintiff and further agreed not to

obstruct the construction work. As per the terms and

conditions of the compromise entered in

O.S.No.5649/1997, the plaintiff agreed to allot 35,000 sft.

of built-up area in the project called ‘Whispering Meadows’

to the Society in two installment of 20560 sft. and 14440

sft., respectively. Accordingly, the parties identified the

areas to be allotted to the first defendant and later on

allotment letter was also issued on 02.08.1999.

8. As per the terms of the compromise and settlement

entered into on 29.07.1999, the first defendant-society had

undertaken to sanction all the revised building plan within

9 months from the said date, after the revised building plan

Page 8: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

8

was obtained, the plaintiff has to put up construction and

put the first defendant-society in possession of the

remaining portion of 14,440 sft. and an additional

extension of 15,000 sft. built-up area provided the revised

building plan is obtained by the first defendant-society on

or before 29.04.2000.

9. As per the terms of the compromise, in order to

secure the revised building plan, the first defendant-society

entered into a Memorandum of Understanding with the

second defendant on 30.10.1999 and entrusted the work of

obtaining sanction of the revised plan from the Bangalore

Development Authority, with some other

conditions. As per the terms of the Memorandum of

Understanding, the first defendant-society undertook the

transfer of 50,000 sft. of the built-up area to the second

defendant and the second defendant has to pay an amount

of Rs.1,00,00,000/- (Rupees One Crore Only) to the first

defendant.

Page 9: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

9

10. According to the plaintiff, in terms of the letter dated

18.02.2000, the first defendant-society informed the

plaintiff to allot 10045 sft. of built-up area to the second

defendant. Accordingly, the same was allotted to the second

defendant. Again certain disputes arose between the

defendants interse, on account of the same the

Memorandum of Understanding was cancelled by the

society on 13.02.2000. Consequently, the allotment of

10045 sft. was also cancelled.

11. On account of the cancellation of the Memorandum of

Understanding, the second defendant initiated arbitration

proceedings against the society in A.C. No.42/2000 before

City Civil Court, Bangalore under Section-9 of the

Arbitration and Reconciliation Act to restrain the society

from alienating or encumbering or parting with the

possession of the 7 flats approximately measuring 10045

sft. Thereafter, an arbitrator was appointed. The Arbitral

Tribunal gave a verdict in favour of the second defendant

Page 10: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

10

and based on the findings of the Arbitrator the first

defendant-society has sold 3 acres of land which is the

subject matter of the present suit without the knowledge of

the plaintiff. Therefore, the present suit is filed contending

that the first defendant-society has no right to alienate the

suit property and any sale deed executed by the first

defendant is not binding on the society and for perpetual

injunction.

12. The prayer in the suit are as hereunder:

a) “For declaration that the Sale Deed dated rd September 2004 bearing registration No.44576/04-05 registered in the Office of the Sub-Registrar, Bangalore North Taluk obtained by the Second Defendant from the first Defendant is a sham, collusive and

fictitious document, not intended to be acted upon and therefore the second Defendant has derived no right, title, interest or possession in respect of the Schedule Property and the said Sale Deed is not binding on the Plaintiff and does not affect its rights or interest in the

Schedule Property. b) For a permanent injunction restraining the

second Defendant or his agents or any one claiming under him from alienating, transferring, encumbering or otherwise

Page 11: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

11

creating any third party rights or raising any

loans or finance on the strength of and under the Sale Deed dated 3rd September, 2004, executed in his favour by the first Defendant with respect to the Schedule Property.

c) For permanent injunction restraining the

Defendants, their agents or any one claiming through them from interfering with the Plaintiff’s possession and enjoyment of the Schedule Property and /or from trespassing on the Schedule Property in any manner whatsoever.

d) For costs and such other relief/s.”

13. The suit property is 3 acres of land situated in survey

Nos.12/6, 13/1, 13/2 and part of survey No.19 situated in

Nagashettyhalli Village, Kasaba Hobli, Bangalore North

Taluk, Bangalore. The suit came to be contested by both

the defendants. The contention of the first defendant is as

hereunder:

The suit is not maintainable, since no notice as

required under Section-125 of the Karnataka Cooperative

Societies Act is issued to the first defendant-society. The

first defendant-society admitted its ownership of the land in

Page 12: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

12

question by the society and having obtained sanction from

the Bangalore Development Authority and also admitted

the earlier litigation initiated by the owners of the land.

14. It is the specific case of the first defendant-society

that the first defendant-society has not executed any

registered sale deed or documents confirming the right, title

or interest in favour of the plaintiff either in respect of the

entire five acres of land or to the extent of the suit schedule

property. However, the first defendant admitted the

execution of the Joint Development Agreement in respect of

45 plots in 5 acres of land for the benefit of the first

defendant-society.

15. It is also the specific case of the defendant that the

plan was obtained to develop the entire 5 acres of land in

the name of the first defendant and the plaintiff has

developed only 2 acres of land and constructed residential

apartments known as ‘Whispering Meadows’ also known as

‘Dollar Apartments’. It is also the contention of the first

Page 13: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

13

defendant that the plaintiff was never in the possession of 5

acres of the land and that only 2 acres of the land was in

possession of the plaintiff as a developer.

16. It is the case of the first defendant-society that since

the plaintiff committed a breach of the agreement at

various stages and non-compliance of terms and conditions

of the development agreement, a suit came to be filed which

ended in compromise. According to the society, the plaintiff

has never derived any title because the development

agreement, power of attorney, declaration and indemnity

bond are documents that are compulsorily to be registered

and on account of non-registration of the documents, the

plaintiff cannot rely upon these documents.

17. It is also denied that the plaint schedule properties is

integral and inseparable part of plaintiff’s alleged project.

The first defendant was the owner of 5 acres of land and

that no right is granted in favour of the plaintiff and the

status of the plaintiff was that of a developer only and they

Page 14: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

14

cannot claim ownership of the land at any stretch of

imagination and further confirmed that the plaintiff can

claim legal possession to an extent of two acres of land and

not to the extent of the entire property. It was also

contended that the first defendant-society was in

possession of the suit schedule property till the same was

sold in favour of the second defendant and that the plaintiff

has no right to question the sale deeds executed by the first

defendant-society in favour of the second defendant and

further confronted that the second defendant is in actual

possession of the suit schedule property.

18. It is also contended that the plaintiff having not filed

any suit for specific performance against the first defendant

and since the development agreements are barred by

limitation, the plaintiff has lost its rights over the same and

that the plaintiff having violated the terms and conditions

of the compromise, the first defendant-society filed a suit in

O.S. No.2482/2001 restraining the plaintiff-developer from

Page 15: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

15

alienating or encumbering the remaining 2 acres of land

which is the subject matter of the suit.

19. It is also the case of the first defendant that even if

the compromise petition is filed under Order-23, Rule-3

read with Section-151 of C.P.C., the same is not binding

upon the parties since no decree is drawn as the suit is one

for bare injunction and the terms and conditions were

altogether different and on account of non-drawing up of a

decree, the plaintiff cannot maintain the suit.

20. It is also the case of the defendant that in terms of the

compromise also, the plaintiff did not adhere to the terms

and conditions of the compromise. Therefore, the first

defendant-society was to sell the property in favour of the

second defendant on account of the lapses committed by

the plaintiff. The first defendant-society has also stated in

detail, the circumstances, which compelled the first

defendant-society to sell the property in favour of the

second defendant. It is also contended by the first

Page 16: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

16

defendant that the right of the plaintiff is only to seek

enforcement of the development agreement in the court of

law and nothing more than that the joint development

agreement executed by the first defendant-society in favour

of the plaintiff and others is barred by limitation and does

not create any ownership in favour of the plaintiff in order

to seek cancellation of the sale deed executed by the first

defendant in favour of the second defendant. According to

the first defendant, they are seeking the relief under the

Specific Relief Act since the development agreements have

become barred by time, the suit filed is not maintainable.

21. It was also contended by the first defendant that all

the development agreements that are executed by the first

defendant in favour of others are unregistered and does not

create any contract of agency coupled with interest at any

stretch of imagination and that all the development

agreements have become time barred and the plaintiff has

no subsisting or enforceable contract in respect of the land

Page 17: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

17

in question against the plaintiff. It was also contended that

the society has already cancelled the joint development

agreement entered into by the plaintiff and in favour of

others long back, for non-payment of the amount payable

by the plaintiffs and others to an extent of

Rs.7,50,00,000/- (Rupees Seven Crores Fifty Lakhs Only).

It was also contended that the suit is also barred by the

provisions of C.P.C. and the suit is bad for non-joinder of

the parties.

22. The second defendant filed the written statement

separately. The contention of the second defendant is more

or less similar to that of the first defendant and therefore

we are of the view that there is no necessity to traverse the

averments made in the written statement filed by the

second defendant.

23. Based on the above pleadings, the following issues

were framed by the court:

Page 18: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

18

“1. Whether the Plaintiff has proved that the

suit property is in his possession? 2. Whether the Plaintiff has proved interference? 3. Whether the Plaintiff is entitled for the

reliefs?

4. What order or decree?”

Additional Issues framed on 30.11.2007:

Whether the suit filed in the present form is maintainable in law?

Additional issues framed on 10.02.2010:

“1. Whether the Plaintiff is entitled for the

declaration as prayed for in the Plaint?

2. Whether the 1st Defendant has proved that the suit has to be dismissed for non-joinder of necessary parties and proper parties?

3. Whether the Court Fee of Rs.75/- paid by

the Plaintiff is proper? 4. Whether the Defendants have proved that

the suit is liable to be dismissed for there being no cause of action.

Page 19: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

19

Additional issue framed on 11.02.2010:

5. Whether the Defendants have proved that

the Sale Deed dated 03.02.2004 executed

by 1st Defendant in favour of the 2nd Defendant is a sham, collusive and fictitious document?”

24. In order to prove their respective contentions on

behalf of the plaintiff one of the Director’s of the plaintiff

company, Shri.A.V.Patil got examined himself as PW-1 and

he relied upon Exhibits P1 to P195. The former secretary of

the first defendant Shri.Vijaysingh, got examined as DW-1

and the second defendant was examined as DW-2. The

defendants relied upon Exhibits-D1 to D75. The trial court

after appreciating the oral and documentary evidence held

issue nos.1 to 3 and additional issue framed on 30.11.2007

and additional issue nos.1 to 3 framed on 10.02.2010 and

additional issues framed on 11.02.2010 in negative and

additional issue no.2 framed on 10.02.2010 in affirmative,

issue nos. 2 and 4 in affirmative and ultimately the suit of

the plaintiff came to be dismissed by the judgment and

Page 20: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

20

decree dated 19.03.2010. The Registry was directed to draw

the decree by the court below provided the plaintiff pays the

court fee on the basis of the sale consideration shown in

Exhibit-P7, dated 03.09.2004.

25. Challenging the legality and correctness of the

judgment and decree of the court below the present appeal

is filed. Though several grounds are urged in the

memorandum of appeal at the time of arguments, the

Learned Senior Counsel who argued the matter from time

to time and the instructing counsel for the plaintiff during

the course of the their arguments have raised the following

grounds:

i. According to them the trial court has committed an

error in dismissing the suit as not maintainable. It was

contended by the learned counsel for the appellant that the

appreciation of the evidence by the court below is perverse

and liable to be reappreciated by this court. According to

them, the trial court did not appreciate that the first

Page 21: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

21

defendant-society having entrusted the entire 5 acres of

land to the plaintiff for development and having allowed the

plaintiff to develop and construct the residential

apartments in 2 acres of land and in view of the

compromise entered into in O.S. No.5649/1997, the first

defendant-society could not have executed the sale deed in

favour of the second defendant and execution of such sale

deed does not bind the plaintiff who has been in possession

of the suit schedule property as a developer.

ii. According to him there is a collusion between the

defendants interse, since the second defendant was aware

of the development agreement of the plaintiff. It is also

contended that in view of the settlement arrived at in O.S.

No.5649/1999 as the plaintiff was ready and willing to

perform its part of contract to deliver the possession of the

constructed area and also another 50,000 sft. constructed

area pursuant to the revised plaint, the first defendant

could not have sold the property in favour of the second

Page 22: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

22

defendant and they further contend that the very initiation

of the arbitration proceedings in A.C. No.4/2001, the award

being obtained behind the back of the plaintiff and such an

award having not been challenged by the first defendant

and thereafter having agreed to sell the property, amply

proves that all was not well within the defendants inter se

and only to knock the valuable rights given to the plaintiff

the sale deed has been executed.

iii. According to the plaintiffs, the Trial Court has also

committed an error in coming to the conclusion that the

suit was not maintainable in the absence of 17 purchasers,

who had agreed to develop the property. According to them

PW-1, the Managing Director of the Company, has

represented the remaining agreement holders, since all of

them are family members of PW-1. They further contend

that when the remaining development agreement holders

have not questioned and when they are represented by the

plaintiff, the trial court was required to hold that the

Page 23: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

23

plaintiff, in a representative capacity, has filed the suit to

protect the interest of the remaining 17 development

agreement holders in respect of the suit schedule property.

According to them, the compromise petition entered into in

O.S.No.5649/1997 has not been properly appreciated by

the court below.

26. Sri C V Nagesh, learned senior counsel for Sri K

Suman, appearing for the second respondent, submits that

the plaintiff, which has filed the suit claiming ownership

over three acres of land, has not placed any materials to

show its existing rights over the property either on the date

of institution of the suit or subsequent to the suit.

According to him, the appellant-plaintiff has not placed any

material to show that it was the owner of the suit schedule

property pursuant to any document executed by the first

defendant in the manner known to law. According to him,

when the plaintiff is claiming ownership under a joint

development agreement, it has to produce the documents

Page 24: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

24

to show that such a document was executed in respect of

the whole extent of the suit schedule property, since a right

has to be transferred in respect of an immovable property

whose worth is more than Rs 100/-. According to him, the

plaintiff has relied upon the joint development agreements

said to have been executed by the first defendant in favour

of different persons, in all 45 persons. Amongst the 45

persons, the plaintiff has entered into an agreement to

develop the property to an extent of 5100 sqft and that the

document relied upon by the plaintiff to show the existence

of the joint development agreement in favour of the

plaintiff, is only in respect of an extent of 5100 sqft as per

ExP55. Relying on ExP55, he contends that when the

plaintiff can claim only an extent of 5100 sqft to develop the

property and when PW1 has admitted that other

agreements with 44 different persons have been entered

into to develop the property, the plaintiff alone could not

have instituted the suit. He further submits that the

plaintiff cannot rely upon the terms and conditions of the

Page 25: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

25

compromise entered into in OS No 5649 of 1997, since a

decree is not drawn by the court below based on the

compromise, on account of non-payment of court fee by the

plaintiff.

27. It is also the contention of the learned Senior Counsel

that OS No 5649 of 1997 was filed by the first defendant-

society against the plaintiff for a perpetual injunction to

restrain the plaintiff in the present suit from interfering

with the possession of the property by the society and to

restrain the plaintiff herein from proceeding with the

construction. In the suit, the parties have settled the

dispute amicably and filed a compromise petition, the trial

court has accepted the compromise petition subject to

payment of court fee. However, the plaintiff has failed to

pay the court fee to draw a decree based on the terms of

the compromise and hence the plaintiff cannot be permitted

to file a suit for negative declaration.

Page 26: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

26

28. According to him, even if the plaintiff has

acquired a right under the compromise petition, without

getting its right crystallized by filing a suit for specific

performance of the contract in the manner known to law,

the plaintiff cannot maintain a suit for negative declaration

to declare that the sale deed executed by the first

defendant-society in favour of the second defendant is not

maintainable. He contends that as such, filing of such a

suit is contrary to the judgment of the Hon’ble Supreme

Court in the case of SARDESH ORES (P) LTD vs HEDE

AND COMPANY [(2007) 5 SCC 614]. He further submits

that when the suit for negative declaration is not

maintainable, the plaintiff is also not entitled for perpetual

injunction, since under ExP55, the plaintiff has secured

possession of only an area of 5100 sqft and the remaining

extent of the land, even according to the plaintiff, it is in

possession of other agreement holders. When the other

agreement holders having not come before the court and

when the plaintiff has not filed the suit on behalf of the

Page 27: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

27

remaining agreement holders, either as a power of attorney

holder or in any other capacity, the plaintiff cannot claim

that the plaintiff company is in possession of the same. He

further submits that PW1, the then managing director of

the plaintiff-company, in his cross-examination has

admitted that the plaintiff is not in possession of the suit

schedule property. If the plaintiff is not in possession of

the suit schedule property, either on the date of filing of the

suit or subsequent to the institution of the suit, no court

can grant a decree for perpetual injunction. In the

circumstance, he requests the court to dismiss the appeal.

29. Sri K S Nagaraja Rao, learned counsel for first

respondent contends that since the plaintiff did not adhere

to the terms and conditions of the agreement entered into,

the first defendant-society had every right to execute a sale

deed in favour of the second defendant and the sale deed

executed by the first defendant in favour of the second

defendant cannot be attacked by the plaintiff, since the

Page 28: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

28

plaintiff has no existing right and has not derived any right,

title or interest over the suit schedule property. He also

contends that under ExP55, the plaintiff has agreed to

develop the property to an extent of 5100 sqft, but the suit

is filed in respect of three acres of land. He also contended

that at no point of time, the plaintiff or any other agreement

holders were put in possession of the property. He further

contends that in order to claim right over the suit schedule

property by the plaintiff for itself or as representative of

other agreement holders, the agreement should be a

compulsorily registered document, since under the

agreement, a right has been created to transfer the interest

in an immovable property in favour of the agreement

holders permitting them to develop the property.

Therefore, he contends that the suit is not maintainable.

He further contends that the plaintiff being a company

cannot represent the other family members of PW1 –

managing director of the company. When the suit is filed

only in the name of a company, the company cannot

Page 29: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

29

represent the family members of the managing director or

any director of the company and such an argument is

unknown to law. In the circumstances, he requests the

court to dismiss the appeal.

Having heard the learned counsel for the parties, we

have to consider the following points in this appeal:

i) Whether the plaintiff being an agreement holder could have filed the suit seeking for a negative declaration, to declare the sale deed executed by the first defendant in favour of second defendant as not binding on the plaintiff and that the second

defendant has not derived any title, without filing a suit for specific performance on the basis of compromise entered into in O.S. No. 5649/1997 dt. 24.07.1999?

ii) Whether the plaintiff was in lawful

possession of the suit schedule property on the date of institution of the suit and whether the plaintiff is entitled for a decree of perpetual injunction even if the first relief is not granted to the plaintiff; and

iii) Whether the judgment and decree of the trial court requires to be interfered with in this appeal?

Page 30: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

30

The admitted facts in this appeal are that: The

plaintiff is claiming right through the first defendant

society. According to the plaint averments, first defendant

society had agreed to permit the plaintiff to develop a total

extent of 5 acres of land situated in different survey

numbers of Nagashettihalli village and the plaintiff has

developed the property only in an area of 2 acres by

constructing residential apartments known as ‘Whispering

Meadows’. The only dispute is in regard to the remaining

three acres of land, which is the subject matter of the suit.

30. According to plaint averments, the first defendant has

executed joint development agreements to develop different

extents of land in the suit schedule property in favour of 44

persons. The plaintiff is a private limited company

registered under the Companies Act, 1956. The first

defendant is a cooperative society, registered under the

provisions of Karnataka Cooperative Societies Act, 1959. It

is also not in dispute that on an earlier occasion, the first

Page 31: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

31

defendant-society had filed a suit against the plaintiff in the

present suit in OS No 5649 of 1997 for the relief of

permanent injunction only with a request to restrain the

plaintiff herein from proceeding with any construction

work, which suit was contested by the plaintiff-company.

The said suit came to be disposed of by virtue of a

compromise petition filed in the suit. As per the terms and

conditions of the compromise, the averments made in the

plaint in the aforesaid suit and the contentions raised by

the defendants in the suit in the written statement were to

be withdrawn and thereafter the first defendant-society has

to confirm the agreements and general powers of attorney

which were executed earlier and they should be in force

and withdraw the revocation of the agreements and GPAs.

31. It was agreed that the first defendant-society has to

receive a sum of Rs 3,50,00,000/- from the plaintiff herein

and also 35000 sqft of super built-up area. It was further

agreed in the compromise petition that the plaintiff herein

was required to construct flats and deliver 20560 sqft area

Page 32: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

32

amounting to 13 flats and deliver to the first defendant-

society in three blocks viz., B, C, C, which were already

constructed and the remaining 14460 sqft of super built-up

area was to be delivered to the first defendant-society after

constructing all the buildings by obtaining necessary plan.

It was also agreed in the compromise that an additional

area of 15000 sqft built-up area has to be delivered to the

first defendant within nine months from the date of

approval of the revised plan.

32. Though the compromise petition was filed, the trial

court has not drawn a decree in terms of the compromise,

on the ground that the joint development agreements and

the terms of the compromise required registration and

payment of stamp duty. The trial court has specifically

directed the office to draw the decree only after payment of

the court fee by the plaintiff. The compromise petition was

accepted by the court below subject to the aforesaid

condition on 29-7-1999. It is also an admitted fact that till

Page 33: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

33

today, the court fee has not been paid by the parties and a

decree as such has not been drawn. Therefore, it is the

contention of the defendants that on account of non-

payment of court fee and on account of non-drawing of the

decree, the terms of the compromise agreed upon between

the parties in the earlier suit cannot be looked into, since

the compromise has not been acted upon.

33. It is the case of the defendants that on account of the

non-payment of court fee, the terms of the compromise are

unenforceable. It is also their case that if the plaintiff was

interested in getting the compromise culminating in

drawing up of a decree by the court, the plaintiff was

required to pay the court fee. The other alternative

argument of the learned counsel for the respondents is that

even if the court fee had not been paid in the earlier suit, at

least the plaintiff was required to file a suit for enforcement

of the terms of the compromise within three years from the

date of filing of the compromise petition. On account of

Page 34: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

34

date of filing of the compromise petition. On account of

non-filing of a suit for specific performance, the plaintiff

cannot contend that the plaintiff-company is having a right

over the suit schedule property.

34. The plaintiff is not sure as to whether the suit is

based on ExP55 or on the base of the compromise petition.

If the suit is based on the compromise petition, this court

has to consider the validity of the compromise petition and

its enforceability in favour of the plaintiff. If the suit is not

based on the terms of the compromise and if the claim of

the plaintiff has to be considered based on the joint

development agreement executed between the plaintiff and

the first defendant-society, then the question would be

whether the plaintiff can lay claim on three acres of land,

even though under ExP55 the plaintiffs is having a right

only to an extent of 5100 sqft, and whether the plaintiff can

file a suit on behalf of the other agreement holders, as

Page 35: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

35

representative of individuals or family members of the

directors or managing director of the company.

35. In order to appreciate these contentions, we have to

advert to the evidence let in by both parties. As stated

supra, on behalf of the plaintiff, its managing director A V

Patil has been examined as PW1. His examination-in-chief

is nothing but a replica of the pleadings in the plaint. In

the cross-examination, he has made several admissions.

He has admitted as hereunder:

… It may be that the 1st Defendant Society has executed 45 Joint Development Agreements in favour of 45 individuals in respect of these lands. The Witness volunteers that the Deed executed is not Development Agreements but they are Agreements of Sale. I do not remember if the

Agreement are executed between 4.10.1995 to 09.10.1995. I do not remember whether the Agreements are not registered. I have to enquire if the Plaintiff Company is in possession of the said Agreements. I have not looked into these Agreements before giving evidence before the

Court Commissioner. Witness again says that I have looked into them.

Page 36: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

36

In para-21 of his cross-examination, PW1 admits to the

following effect:

I am not aware if the Katha of the Suit Schedule Property stands in the name of 2nd Defendant. May be that the Plaintiff Company has filed

objections before the Bangalore City Corporation objecting to transfer of Katha of the Suit Schedule Property in favour of 2nd Defendant.

In para-24, PW1 admits to the following effect:

It is true that Plaintiff Company was a party to the Arbitration Case No. 42/2000 on the file of the City Civil Court, Bangalore filed by the 2nd Defendant. It was so in the beginning but not afterwards.

In para-31 of his cross-examination, PW1 admits to the

following effect:

In order to indicate the Title or Possession of an

immovable property basic thing is a document. Question: To show one’s title to the property or one’s possession to the property the primary evidence is the document under which the title is acquired or the document under which

possession is delivered? Answer: It is so if it is a lawful document.

Page 37: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

37

Question : The documents that would indicate

possession in relation to an immovable property are title deed under which possession is delivered, agreement under which possession is delivered, Katha endorsement, tax paid receipts, licence, plan, if any.

Answer: It is so if the documents are lawful.

In paras-32 & 33 of his cross-examination, PW1 admits to

the following effect:

The Plaintiff have not acquired title or possession to the suit schedule property under a Sale Deed. Plaintiff has acquired title and possession to the suit property under an Agreement of Sale.

Question: The Plaintiff is put in possession of the suit schedule property in part performance under the Agreement of Sale.

Answer : Yes. I do not remember the total amount of consideration agreed for the sale of suit schedule property. The witness volunteers that there were 45 Agreements of Sale.

Under those 45 Agreements of Sale each one of the purchasers mentioned in the Agreements were put in possession separately. Plaintiff is one such Agreement Holder in respect of a portion of suit schedule property.

Page 38: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

38

Question: Out of the 45 persons who entered

into Agreements of Sale the Plaintiff is one such person and has alone filed the suit. Answer: The Plaintiff includes all the 44 persons.

In para-36 of his cross-examination, PW1 admits to

the following effect:

I cannot name all those 44 persons.

The Plaintiff does not have Power of Attorney of all the 44 persons. The suit is filed on behalf of Plaintiff only and not on behalf of 44 persons.

Without looking into the record I cannot say the date, month and year of the Agreement of Sale of a portion of suit schedule property in favour of the Plaintiff.

[Emphasis is supplied by us]

In para-41 of his cross-examination, PW1 admits to the

following effect:

The Plaintiff is in possession of the Agreement of

Sale in respect of a portion of the suit schedule property.

In para-51 of his cross-examination, PW1 admits to the

following effect:

Page 39: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

39

I did not feel it necessary to institute suit for

specific performance on receiving the notice of termination/cancellation of the Agreements, GPA and Indemnity bond from the 1st Defendant Society. Witness volunteers because the Owner had no right to do the said things.

In para-52 of his cross-examination, PW1 admits to the

following effect:

It was on the date of Agreement of Sale the Plaintiff was put in possession of the portion of

the property which is the subject matter of Agreement of Sale. Question: Please point out the documents produced in the Court under which the Plaintiff came to be put in actual physical possession of

the portion of the suit property in respect of which the contract is entered into. Answer: I require reasonable time to go through the records produced in the Court to point out

the document under which actual physical possession is delivered. I have gone through the records and it seems that the possession document executed by the Land owner in favour of Plaintiff is not submitted in the Court.

In para-57 of his cross-examination, PW1 admits to the

following effect:

The Plaintiff Company has purchased the share of other buyers in respect of suit property. The

documents are not registered. They are with the

Page 40: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

40

Plaintiff Company. I cannot say the Day, Month

and Year of purchase of the share of others by the Plaintiff Company.

In para-58 of his cross-examination, PW1 admits to the

following effect:

After looking into the records the Witness says “I have not produced the records referred above”. The other purchasers of different potions of suit property never surrendered possession of the portions of suit property to the 1st Defendant

Society from the date they acquired possession till today.

In para-59 of his cross-examination, PW1 admits to the

following effect:

Different purchasers of portions were not parties to the document.

In para-67 of his cross-examination, PW1 admits to the

following effect:

I visited the suit property on the last occasion about 3 or 4 months back. I cannot say whether the vacant land shown in photographs Ex. D-11 & D-12 is the suit property. The vacant land

shown in Ex.D-8 is not the suit property. The Plaintiff is not possession of the vacant land shown in Ex.D-8. Similarly the Plaintiff is not in possession of the vacant land shown in Ex.D-11 & D-12. The Plaintiff is also not in possession of the vacant land shown in Ex.D-9 & D10. The

Page 41: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

41

Plaintiff has also not exhibited any board as

seen in Ex.D-9 & D10. It is true that Ex.D-9 & D-10 it is a board of stating “This property belongs to CVL Sastry”.

On perusal of the evidence of PW1, it is clear that the

plaintiff has filed the suit based on ExP55 joint

development agreement. ExP55 is a development

agreement entered into between the plaintiff and the first

defendant-society on 5-10-1995, wherein it is agreed to

develop the suit schedule property for a consideration of Rs

22,93,317/- and of course certain amount was paid as

advance. The balance consideration of Rs 7,83,317/- was

to be paid by the plaintiff to the first defendant after

fulfilling certain conditions by the first defendant-society.

36. By looking into the pith and substance of this

document [ExP55], though the document is styled as a

‘development agreement’, it is virtually a deed transferring

the property in favour of the plaintiff-company. The

schedule to ExP55 is only in respect of 5100 sqft, which is

Page 42: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

42

mentioned as schedule-C to the agreement. Admittedly, it

is not a registered document. Under ExP55, the plaintiff

cannot claim any right over and above 5100 sqft of land.

Even if it is considered that the plaintiff has acquired any

right under ExP55, at the best, the court can come to the

conclusion that the plaintiff is having right only to an

extent of 5100 sqft, but not the whole extent of 3 acres.

Along with ExP55, a sketch is also annexed to show that

site No 5 earmarked in the sketch is a land granted to the

plaintiff for development. In the sketch, in all 45 sites

have been formed and the remaining 44 sites are sold to

different persons under similar agreements. They are

marked as ExP56 to 99. These are the all similar

agreements of sale as that of ExP55. These agreements

are executed by the first defendant-society in favour of

different individuals.

37. If the first defendant-society has executed different

agreement in favour of different persons and even if those

Page 43: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

43

persons are relatives or family members of the managing

director of the plaintiff-company, the company cannot

institute a suit on behalf of family members of the director

or managing director of the company. It is also not the

case of the plaintiff that it has filed the suit on behalf of the

remaining 44 agreement holders. In the cross-examination

of the PW1, he has stated that he has not obtained any

powers of attorney from such persons and it is not

represented the aforesaid persons.

38. When such being the case, this court has to consider

as to whether based on the compromise entered into earlier

in OS No 5649 of 1997, the plaintiff has acquired right to

file a suit to claim 3 acres of land and based on such

existing right, a negative declaration relief can be granted

in favour of the plaintiff, holding that the sale deed

executed by the first defendant-society in favour of second

defendant does not bind it? To seek such a relief, the

plaintiff must have a right over the property in question.

Page 44: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

44

Learned counsel for both parties are not disputing the fact

that a decree has not been drawn on the basis of the

compromise on account of non-payment of commensurate

court fee. If the decree is not drawn, it can be assumed

that the terms of the compromise have not been accepted

by the court. Then, this court has to see whether the

plaintiff can still maintain a suit seeking a negative

declaration based on the terms of the compromise petition?

39. According to Sri G L Viswhanath, learned counsel for

the appellant-plaintiff, the terms of the compromise are

more in the nature of an agreement and the same is

binding on the plaintiff and the first defendant-society.

According to him, even if the compromise petition is

accepted by the court below in the earlier suit and the

decree is not drawn on account of non-payment of court

fee, still the compromise petition and its terms are binding

upon the parties.

Page 45: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

45

40. Even if we accept the contention of Sri Vishwanath,

still, the plaintiff has to enforce the terms of the

compromise when it styled the document as an agreement.

If it is an agreement entered into between the plaintiff and

the first defendant, it is nothing but a contract. When it is

a contract between the parties, unless and until the

contract is got crystallized by executing a sale deed in

respect of the immovable property in favour of the plaintiff

by the first defendant-society, the plaintiff cannot contend

that it has acquired the right, title or interest over the suit

schedule property.

41. After arriving at the terms of the compromise petition,

both the plaintiff and the first defendant-society were

required to perform their parts of contract. According to

the first defendant-society, the plaintiff committed breach

of terms of the compromise and therefore it has terminated

the contract and the plaintiff cannot enforce the same.

Page 46: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

46

42. PW1, who entered in the witness box on behalf of the

plaintiff, has spoken about the receipt of notice got issued

by the first defendant-society, terminating the agreement.

But unfortunately, for the reasons best known to the

plaintiff-company, it did not file a suit for specific

performance of the contract, even to enforce the terms of

the compromise. If the plaintiff had filed a suit to enforce

the terms of the compromise, this court could have

appreciated the contentions of the learned counsel for the

appellant-plaintiff. Unfortunately, the plaintiff did not

exercise its right within three years from the date of

compromise petition, even though a decree is not drawn in

accordance with law due to non-payment of court fee.

During the final hearing of this appeal, the plaintiff had

filed an application before this court under Order VI Rule

17 CPC, to amend the prayer to incorporate the following

additional prayer:

a [i] or in the alternative to declare that the terms of compromise dated 29.07.1999 entered in O.S. No. 5649/1997 are valid

Page 47: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

47

and binding on the Defendants and

consequently to direct them to abide by and comply with the terms, conditions and obligations of the said compromise petition

This application was heard and rejected on merits by the

order dated 25-2-2014, holding that such a relief cannot be

considered by this court 15 years after the filing of the

compromise petition in the earlier suit.

However, it is also to be seen that with regard to the

appropriate relief to be claimed by the plaintiff, the plaintiff

has admitted to the fact that the relief sought for by him

was not proper. The trial court referred to this issue in

para-25 of its Judgment which reads as follows:-

“25. When the Court questioned the Advocate for the Plaintiff regarding the declaratory relief, he admitted that he should not

have sought declaratory relief in this way and that the Plaintiff had been given power to develop even the 3 acres of suit land and as the 2nd Defendant attempted to interfere with the said 3 acres of land and as the numbers put by the Plaintiff were removed, the Plaintiff was forced

to come to the Court. As the Advocate for the Plaintiff directly admitted that the declaratory

Page 48: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

48

relief sought by him was not proper, the said

matter was not discussed in detail.”

Therefore, it is not a case of any inadvertence in not

seeking the relief. But the fact is that even during the

pendency of the suit, the plaintiff was aware that the relief

sought by him is inappropriate.

43. When the plaintiff has not filed a suit in terms of the

compromise petition within three years, contending that

the plaintiff is having a right over three acres of land and

on the basis of the same, the sale deed executed by the first

respondent-society in favour of second defendant is not

binding on the plaintiff, the same cannot be countenanced

by this court, because, at the first instance the terms of

compromise cannot be enforced by the plaintiff by filing a

suit based only on ExP55, which agreement permits the

plaintiff only to develop the property to an extent of 5100

sqft only. Of course the said assertion has also been denied

by the defendants, and that the plaintiff has not even filed

a suit to enforce the said agreement. Under these

Page 49: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

49

circumstances, if the trial court has held that the suit filed

by the plaintiff is not maintainable and such an equitable

relief cannot be granted, this court cannot interfere with

such a decision and cannot grant any relief to the plaintiff,

more particularly in view of the law laid down by the

Hon’ble Supreme Court in the case of SARDESH ORES (P)

LTD [supra], wherein it is held as under, in regard to grant

of negative relief:

39. We are of the view that the respondents are right in contending that enforcement of the negative covenants presupposes the existence of

a subsisting agreement. As noticed earlier, the law is well settled that the renewal of an agreement or lease requires execution of a document in accordance with law evidencing the renewal. The grant of renewal is also a fresh grant. In the instant case, the appellant-plaintiff

did exercise their option and claimed renewal. The respondents denied their right to claim renewal in express terms and also unequivocally stated that the agreement did not stand renewed as contended by the appellants. Having regard to these facts it must be held that

a cause of action accrued to the appellant-plaintiff when their right of renewal was denied by the respondents. This happened in December, 2001 and, therefore, within three years from that date they ought to have taken appropriate proceedings to get their right of

Page 50: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

50

renewal declared and enforced by a court of law

and/or to get a declaration that the agreement stood renewed for a further period of 5 years upon the appellants' exercising their option to claim renewal under the original agreement. The appellants-plaintiffs have failed to do so. However, the plaint proceeds on the assumption

that the original agreement stood renewed including the negative covenants contained in clauses 15 and 20 of the original agreement which authorised only the appellants to extract ore from the mine with an obligation cast on the respondents-defendants not to interfere with the

enjoyment of their rights under the agreement. In the facts of this case, in the suit prayer for injunction based on negative covenants could not be asked for unless it was first established that the agreement continued to subsist. The use of the words "during the subsistence of this

agreement" in clause 15, and "during the pendency of this indenture" in clause 20 of the agreement is significant. In the absence of a document renewing the original agreement for a further period of 5 years and in the absence of any declaration from a court of law that the

original agreement stood renewed automatically upon the appellants exercising their option for grant of renewal, as is the case of the appellants, they cannot be granted relief of injunction, as prayed for in the suit, for the simple reason that there is no subsisting

agreement evidenced by a written document or declared by a court. If there is no such agreement, there is no question of enforcing clauses 15 and 20 thereof. The appellants ought to have prayed for a declaration that their agreement stood renewed automatically on

Page 51: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

51

exercise of option for renewal and only on that

basis they could have sought an injunction restraining the respondents from interfering with their possession and operation. Having not done so, they cannot be permitted to camouflage the real issue and claim an order of injunction without establishing the subsistence of a valid

agreement. In the instant suit as well they could have sought a declaration that the agreement stood renewed automatically but such a claim would have been barred by limitation since more than 3 years had elapsed after a categoric denial of their right claiming

renewal or automatic renewal by the respondents-defendants.

Under these circumstances, we are of the view that the

finding of the trial court on the question of maintainability

of the suit and consideration of the prayer (a) has to be

accepted and the appreciation of evidence by the trial court

cannot be held to be perverse. Accordingly, the first point

is answered against the appellant-plaintiff.

44. In so far as the relief of injunction is concerned, even

according to the plaintiff there are 45 agreements and in

each agreement different persons are claiming to be in

possession of specific and defined extents. The plaintiff is a

Page 52: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

52

company, which is said to have been in possession of only

5100 sqft in a vacant piece of land. The plaintiff has no

right, title or interest over the property, because, ExP55 is

not an enforceable agreement by the plaintiff in a manner

known to law. There is nothing on record to show that the

plaintiff is in possession of the property. On the contrary,

the evidence of PW1 shows that the plaintiff is not in

possession of the suit schedule property. If the plaintiff is

not in possession of the suit schedule property, the

question of considering the second prayer to grant a decree

of perpetual injunction will also not arise for consideration.

45. If the plaintiff’s right in respect of vacant site is

emphatically denied by the defendants, the remedy

available to the plaintiff is only to seek the comprehensive

relief of positive declaration with the consequential relief of

permanent injunction, if it is of the firm opinion that it is in

possession of the same or for possession if the adversary is

in possession of the same. Principles to this effect have

Page 53: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

53

been clearly laid down by the Hon’ble Apex Court in the

case of ANATHULA SUDHAKAR Vs BUCHI REDDY [AIR

2008 SC 2033]. Plaintiff has not adopted this approach.

On the other hand the plaintiff has very intelligently made

an attempt to seek the negative relief of declaration in lieu

of positive declaration of having acquired absolute title. As

already discussed at length, plaintiff has not acquired any

title on the basis of a compromise entered into in a suit

filed for permanent injunction by the 1st defendant earlier,

more particularly, in not attempting to enforce the alleged

right acquired on the basis of compromise. Even on this

count also the present suit is not at all maintainable in law

or on facts.

46. Though the learned counsel for the appellant-plaintiff

contends that the plaintiff is in possession of the land,

which is a fact on the face of the compromise petition filed

by the parties in the earlier suit, the plaintiff is bound to

show that as on the date of filing of the present suit, it was

Page 54: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

54

in possession of the entire suit schedule property. When

the plaintiff’s witness admits that the plaintiff is not in

possession of the property but different agreement holders

are in possession of the property, even if the case of the

plaintiff is accepted, no injunctive relief can be granted in

favour of the plaintiff. Accordingly, the second point is

also answered against the appellant-plaintiff.

47. The trial court has properly analyzed the entire

evidence on the touchstone of intrinsic probabilities after

properly narrating the facts. It has adopted right approach

to the real state of affairs and has applied proper law to the

facts of the case.

48. In the result, we do not find any merit in this appeal

and accordingly appeal is dismissed.

49. At this juncture, learned counsel for the appellant-

plaintiff submits that the interim order granted earlier at

the time of admission of the appeal may be continued for a

Page 55: IN THE HIGH COURT OF KARNATAKA AT BANGALOREjudgmenthck.kar.nic.in/judgmentsdsp/bitstream/... · the Bangalore Development Authority and also admitted the earlier litigation initiated

55

further period of eight weeks to enable the plaintiff-

appellant to take up the matter to Hon’ble Supreme Court.

50. This appeal was admitted on 31-8-2010. While

admitting the appeal, this court had directed the parties to

maintain status quo and not to change the nature of the

property. If the appellant is intending to challenge this

judgment, we are of the view that the interim order granted

on 31-8-2010 shall be in force for a period of eight (8)

weeks only from today. Ordered accordingly. There is no

order as to costs.

Sd/-

JUDGE

Sd/-

JUDGE

JJ/*pjk


Recommended