+ All Categories
Home > Documents > Incremental Launching Method

Incremental Launching Method

Date post: 02-Apr-2018
Category:
Upload: santhu256
View: 232 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 7/27/2019 Incremental Launching Method

    1/14

    INCREMENTAL

    PUSH LAUNCHINGMETHOD

  • 7/27/2019 Incremental Launching Method

    2/14

    Concept

    The basic concept of INCREIMENTAL PUSH

    LAUNCHING METHOD (ILM) is to prefabricate

    approximately 10m to 30m long units of the bridge under

    factory conditions behind an abutment and launch the units by

    sliding them on Teflon bearings into final position without the

    aid of scaffolding.

  • 7/27/2019 Incremental Launching Method

    3/14

    The total deck slab of the bridge is subdividedlongitudinally into section of 10m to 30m length,depending upon the length of the span and time

    available for construction.

    Each section is concreted immediately behind theabutment of the bridge in steel framed forms.

    These steel frames which remain in same placefor concreting all sections.

  • 7/27/2019 Incremental Launching Method

    4/14

  • 7/27/2019 Incremental Launching Method

    5/14

    The forms are designed in such a way that it can be moved

    transversely or rotated on hinges to facilitate easy stripping

    after sufficient hardening of the concrete.

    The forms are hydraulically or mechanically activated to

    ensure rapid stripping.

  • 7/27/2019 Incremental Launching Method

    6/14

    This is the launching

    equipment, which consists

    of a combination of

    hydraulic jacks acting

    vertically and horizontally

    on sliding bearings.

    The sliding bearing consists

    of concrete blocks covered

    with stainless steel andTeflon-coated reinforced

    elastometic pads.

  • 7/27/2019 Incremental Launching Method

    7/14

    A section is manufactured in formwork in lengths

    corresponding to one-third to one-half of the normal spanlength. After the stripping of the forms, tendons are inserted

    and stressed.

    The section is then jacked forward, sliding on the Teflon,

    which, in turn, is affixed to stainless steel plates on top of the

    piers.

    A new section is then constructed immediately adjoining the

    rear end of the first. Pre-stressing tendons are spliced so that

    the two segments are joined as one longer pre-stressed unit and

    then jacked forward another length.

  • 7/27/2019 Incremental Launching Method

    8/14

    At the head of the first section, a steel nose consisting of alight truss is attached to facilitate reaching of the first and

    subsequent piers without including a too large cantilever

    moment during construction.

    The second and following sections are concreted directly on

    the face of the hardened portion and the longitudinal

    reinforcement can continue across the construction joint.

    The pushing is achieved by hydraulic jack which acts against

    the abutment.

  • 7/27/2019 Incremental Launching Method

    9/14

    Launching Process

  • 7/27/2019 Incremental Launching Method

    10/14

  • 7/27/2019 Incremental Launching Method

    11/14

    Low capacity hydraulic jack would be enough to movethe bridge decks.

    Intermediate pier supports or towers may be used to

    give temporary support across longer spans since the

    practical limit of a span length for this type of

    construction is about 60 meters.

  • 7/27/2019 Incremental Launching Method

    12/14

    When launching from both ends of the bridge, differentcurvatures may be used, but this must be constant for each

    launching point. Similarly, the super-elevation must be

    constant.

    After the launched bridge is in place, the bearing seats may be

    jacked up to remove the Teflon, and the permanent bearings

    are installed. Jacking points should have the required

    supplemental reinforcing to permit this application of force ata location offset from the permanent bearings.

  • 7/27/2019 Incremental Launching Method

    13/14

    Features of the incremental

    launching method

    Construction is carried out completely without falsework, so

    that there is no problem in passing over obstacles below, such

    as roads, railways, rivers, buildings areas.

    The superstructure is made up of units of 15 to 25 m length,each completed in one week; there are no joints, since each

    unit is concreted directly against the preceding one.

    It is a economic construction technique.

    To achieve quality work with reduced amount of labour.

    It is a speedy construction technique.

  • 7/27/2019 Incremental Launching Method

    14/14

    THANK YOU


Recommended