Date post: | 03-Jan-2016 |
Category: |
Documents |
Upload: | wesley-manning |
View: | 214 times |
Download: | 0 times |
Individual Subsystem Testing Report
New Jersey Space Grant Consortium with Rutgers University
Stevens Institute of Technology2/13/2012
Mission Overview
• Mission statemento To collect and analyze data for future space research
operations through various experiments designed and implemented on a payload.
• Experiments:o Atmospheric
O3, CH4, CO2o Vibration
Piezo vibration of sensor plateo Temperature
Infrared sensor pointed at inside of rocket skin
Schedule Update
• The project is slightly behind schedule due to late material procurement (i.e., CO2 sensor, ACV polycarbonate housing).
• This is not a major concern since all items are ordered and most of the subsystems have been constructed.
Subsystem Overview
• What are your subsystems?o Atmospheric Containment Vessel (ACV)o AVR Boardo Electrical Power Supply (EPS)
• Who will discuss each subsystem?o ACV: Mike Gigliao AVR: Ethan Hayono EPS: Sean Watts
Atmospheric Containment Vessel (ACV)
• Statuso Re-Design of old ACV
Instead of two halves being mounted to each other there is now a lid to allow for fittings to be mounted easily.
o Problems with fabrication The poly carbonate that has been ordered is on back order
so fabrication has not been possible unfortunately.
•
AVR Subsystem• The AVR board consists of a custom manufactured
shield for an Arduino Mega 2560.• We are finishing up the prototyping phase. • All of our sensors have been breadboarded (except
the CO2 sensor, which we just received)• Code has been written to read data from the IR temp
sensor and the Accelerometer. o These code "modules" can easily be used with the
final payload software.
AVR Subsystem Update
• Measurements seem to be correct. Testing will take place to ensure the correct value for the temperature and accelerometer are correct.
• The code for the CO2 sensor is currently being written and will soon be tested.
Electrical Power Supply Subsystem Update
• We have successfully tested the power latching circuit with our AVR board.
• We have decided to use three 9v batteries connected in series to ensure we have the necessary 24v to power our pinch valves.
Electrical Power Supply Subsystem Update
• Our original power latch circuit did not work correctly with higher level loads, however our new circuit latches work properly to power our AVR board.
Plan for Subsystem Integration
• We have adjusted our schedule to accommodate late acquisition of the CO2 sensor.
• We are working on the design for the AVR shield. It will be sent to Batch PCB over the next two weeks for manufacture.
• The only major hurdle to overcome is the construction of the ACV and assembly of the payload plate. Once this is complete, the only remaining element will be electrical wiring and software.
Lessons Learned
• It is important to plan and design subsystems adequately prior to construction. o Create subsequent parts lists, schematics, and 3d
models. • What would you do differently?
o More teammates would make organization an easier task. Rather than stop construction completely to work on a report, a small portion of the team would work on the report.
• What has worked well so far?o Meeting participation