Date post: | 08-Nov-2014 |
Category: |
Documents |
Upload: | muhammad-fahmi-bin-abd-talib |
View: | 591 times |
Download: | 12 times |
INDUSTRIAL TRAINING REPORT:
AT
LAFARGE MALAYAN CEMENT
LANGKAWI PLANT
BY
MUHAMMAD FAHMI BIN ABD TALIB
(ME 083597)
COLLEGE OF ENGINEERING
UNIVERSITI TENAGA NASIONAL
START DATE: 25 JANUARY 2012
END DATE: 18 APRIL 2012
MUHAMMAD FAHMI BIN ABD TALIB
(ME 083597)
COLLEGE OF ENGINEERING
i
ACKNOWLEDGEMENT
Special thanks to my helpful supervisor, Ir. Dr. Azmi Ahmad. The supervision and
support that he gave truly helps the progression and smoothness of my internship
program. The cooperation is much indeed appreciation.
My grateful thanks also to Lafarge Malayan Cement Plant Manager, Mr. E. R. Kim in
giving me an opportunity to work in his plant and also for both host supervisors, Mr.
Ibrahim bin Muhammad and Puan Nor Ain Yahya. A big contribution and hard worked
from both of you during the 12 weeks is very great indeed. All knowledge obtained during
the internship program would be nothing without the enthusiasm and passion from both of
you. Besides, the internship program also make me realized the value of working together
as a team and as a new experience in working environment, which challenges us each
minute.
Not forgotten teammates from both Maintenance and Process Department especially to
Mr. Abu Yamin, Mr. Rusli and Mr. Rafie for their kindness on guiding me throughout my
internship there. The whole program really brought us together to appreciate the true
value of friendship and respect of each other.
Great deals appreciated also to College of Engineering. The well planned and systemic
procedures plus some useful advices help me in doing internship Lafarge Malayan
Cement who is the biggest cement producer in the world.
Last but not least, thanks to Lafarge Malayan Cement trainees from Kolej Polytech Mara
Alor Setar (POLISAS) for their kindness. Discussions and memorable activities that we
had done together give me enjoyment while completing this internship program.
ii
ABSTRACT
University Tenaga Nasional (UNITEN) offers an Industrial Training Program
especially for third year students as a requirement for them to complete their engineering
course in UNITEN Putrajaya campus. With 4 credits hours, students will be allocated in a
hosted company decided by them in order to gain real life working experience.
Throughout the 12 weeks industrial training, the students’ performance will be fully
monitored by host supervisor and will be guided by UNITEN selected lecturer as their
supervisors.
Industrial Training Program is conducted with objectives to give opportunities for
students to gain their own real life experience before entering actual working life.
Besides, this could be an opportunity for them to gain as much knowledge as they could
in the things that they have learnt before. In order to join an industrial training, students
are needed to attend a Safety and Health briefing organized by CIDB.
The industrial training could be a good starting point for students to gain their
knowledge in the field that they want next preparing themselves with the real working life
that they will experience soon. Hopefully, this report will be used as a reference for
students and lecturers who interested in Cement Production.
iii
Industrial Training Objectives
Industrial training has its own objectives for students to work at any company or
institution in order to fulfill the education syllabus requirements. The main objective of
this industrial training is to give opportunities for students to gain experience and to be
exposed in real working life, so that they could make a good preparation before starting
their job after graduation. This opportunity is a one of the future challenges to practice
their ability to do a given job or task as well as possible.
This training also gives opportunity for students to know the association between
theories studied with real practicalities practice and skill in career world. Nevertheless the
other purpose of the Industrial Training is to provide exposure for students on practical
engineering fields. Through this exposure, students will have better understanding of
engineering practice in general and sense of frequent and possible problems.
Industrial training also makes students to be high characteristics, proactive,
dedicated, in discipline, dynamic, work in team work and trust. As we know, during
training students is under pressure with many problems and new environment. So that,
students should know how to handle it with the appropriate way and also try to solve all
the problems with their best.
Widen relationship and social intercourse nicely with current employee to
improve team work spirit. At the same time, student also exposed up-to-date with
technology such as computer system and technology used inside construction sector and
maintenance. Indirectly it does also improve knowledge of the technology.
iv
WEEKLY TRAINING OVERVIEW
Week 1
I reached the Lafarge Malayan Cement Langkawi Plant and reported to HRA Executive,
Mr Azis Bahari. I was given all the Personal Protective Equipment (PPE) like working
attire, boots, helmets and safety goggle in order to ensure my safety throughout the
industrial training there. After that, some interpersonal interviews between HR Manager,
Mr Syafik and I was done. Throughout this week, I need to attend the Familiar Program
organized by Human Resource where this program had introduced me the overall
information regarding Lafarge Plant. At the end of this program, I had been given a
chance to decide which department I would like to be undertrained. I decided that I will
be undertrained by Maintenance Department for the first 1 and the half month and at the
Process Department for the other 1 and the half month.
Week 2
I was assigned to follow the Quarry Section Supervisor, Mr. Abu Yamin for this whole
week. For the first day, I was brought to limestone and clay quarry in order to familiarize
me with their daily routine. By using a pickup, I was brought to the limestone crushers
(1200TPH and 850TPH). There, I had been explained and shown the mechanism of a clay
crusher and how the process of crushing the limestone. Moreover, I also had been
introduced to the limestone transportation, belt conveyor. For the second and the third
day, I joined the execution team where a serious problem regarding the clay crusher had
been reported. The clay crusher experienced some blockage at the chute thus causing the
clay did not been crushed to the respective sizes properly. In order to overcome the
problem, the chute was enlarged. The execution team took three days for this project.
v
Week 3
For the week 3, I was sent to the cement mill section in order to learn the last stage of
cement production. At the early of the week, I was brought to see the Dust Collector
System where this system is very important in maintaining the dust emission. Poor Dust
Collector results high level dust emission thus polluting the environment. In that week
also, I involved in replacing the outer slotted plate for Cement Mill 4. Moreover, I also
attended a safety briefing organized by Safety Department on Procedures Working in
Hole.
Week 4
I had been brought by Mr. Rusli to see a problem occurred at Cement Mill 4 involving the
leakage of shell liners. In the observation, we conclude that the leakage did not caused by
shell liner but the bolts that loosen. Thus, process of retighten the bolts had been done.
Together with the process was a Preventive Maintenance (PM). For this PM, iching had
been done in order to identify the condition of the shell liners and the broken shell liners
were replaced by the new one. Throughout this week also, I was given a project by a
Young Engineer, Mr. Mahzuz where this project will be ran in July. It was a joint project
leaded by Mr. Mahzuz and this project involves the Sealing Air Fan for Cement Mill 4.
Week 5
In this week I was undertrained by Raw Mill Section Young Engineer, Mr. Joshter. I was
assigned to follow an Inspector to do a Mechanical Vibration Test at Raw Mill 2. In this
test, we had identified a problem in a gearbox. From the data obtained high level of
vibrations occurred at the bearing of the gearbox. A report had been issued to
Maintenance team. Besides joining the Raw Mill Section team, the Sealing Air Fan
Project still ran by schedule. I was assigned by Mr. Mahzuz to calculate the volume of air
vi
in the lubrication system and determine what type of fan suitable for this project. For this
assignment, I managed to obtain 4.1096 m3 of air needed and this volume was close to the
value provided by a consultant company.
Week 6
This week was the first week I was undertrained by Process Department. I was asked by
Human Resources Executive, Mr. Azis Bahari to report myself to Puan Nor Ain who will
be my supervisor for the next one and the half month. For the first day in Process
Department, I was brought by Mr. Zakrullah, a Young Engineer to see the Raw Mill
section in term of a Process Engineer view.
Week 7
In this entire week, few programs had been successfully done by Human Resource and
Process department. The programs were Quality Award program and Kill-A-Watt
program. Besides the launched of both programs, I also had learned on how to calculate
the fan performance curve for Line 2. Last but not least, I also helped Process engineers
in determining the wet bulb temperature at Raw Mil 2 (RM2).
Week 8
Some inspections were done in order to find leakages that occur in Silo Compressors and
Coal Mill 2 (COM2). The inspections were done in order to find the source of leakages
that affect the entire process before. In this week also I attended a safety briefing on the
procedure and rules when working a confined space.
Week 9
Week 9 was the week that I learned a lot on tests that had been done by Quality Control
Department. The tests were Residue test for both Normal Blaine and High Blaine and
vii
Sieve test. Both tests are done daily in order to ensure cement that produced is under the
required quality of cement needed by plant. I also helped one of the teammate in Process
department in sealing leakage at hot ducting in Raw Mill 2.
Week 10
Lafarge Malayan Cement had given me a one week holiday so that I can take some rest at
home with my family. This holiday was given to all trainees there. In order to apply it, I
was needed to fill up a form where the location I went for the whole week and days of
holiday taken were asked. The form then was submitted to Human Resource Department
for their record.
Week 11
Inspections and fire drill had been done in this week. 2 inspections were done involving
the dust collector system (purging air) and Grinding Mill at Coal Mill 2 (COM 2). Other
than that, a preventive maintenance and a fire drill on Confined Space were done.
Week 12
In took almost the entire week to do projects given to me. I was briefed by Mr.
Zakhrullah, a young engineer from Process Department on my first project which was to
trace the pressure vessels available in LMC Langkawi Plant started by Cement Mill
section. To trace the vessels, I joined some inspectors to trace each of the pressure
vessels. Through the visit, I was able to note the location, serial number and conditions of
the pressure vessels. At the end of the week, I was able to draw a complete drawing for
cement mill I presented it to the process engineers.
viii
Table of Contents
Acknowledgement i
Abstract ii
Weekly Training Overview iv
Table of Contents viii
Company Profiles
1.1 Lafarge Cement 1
1.1.1 History of Lafarge Cement 1
1.1.2 Lafarge Cement Timeline 2
1.2 Lafarge Malayan Cement 14
1.2.1 History of Lafarge Malayan Cement 14
1.2.2 Lafarge Malayan Cement Timeline 15
1.3 LMC Langkawi Plant Overview 21
1.3.1 Location of LMC Langkawi 21
1.3.2 Organizational Structure of LMC Langkawi 23
1.3.3 Technical Data in LMC Langkawi 24
1.3.4 LMC Langkawi Plant Visions and Missions 25
1.3.5 Components of LMC Langkawi 26
1.3.6 Products of LMC Langkawi 28
ix
Manufacturing Process of Cement
2.1 What is Cement? 31
2.2 Process 33
2.2.1 Raw Material Preparation 33
2.2.2 Grinding and Storage of Raw Material 35
2.2.3 The Firing of Raw Material 36
2.2.4 Storage and Grinding of Raw Material 38
2.2.5 Packaging and Shipment 40
2.3 Summary 41
Crushers
3.1 Introduction 43
3.2 Type of Crusher Used in LMC Langkawi 44
3.2.1 Jaw Crusher 44
3.2.2 Roller Crusher 47
3.2.3 Hammer Crusher 48
3.3 Preventive Maintenances 50
3.3.1 Modify Scraper Outlet Chute of Jaw Crusher 50
3.3.2 Change the Teeth of Jaw Crusher 52
Grinding Mill
4.1 Introduction 53
4.2 Vertical Mill (Roller Mill) 54
4.2.1 Introduction 54
4.2.2 Mechanism 55
x
4.3 Ball Mill (Tube Mill) 56
4.3.1 Introduction 56
4.3.2 Mechanism 57
4.4 Grinding Aid 58
4.5 Preventive Maintenances 59
4.5.1 Outer Slotted Plate Renewed 59
4.5.2 Feed End Liner and Shell Liner Retighten 60
4.5.3 Alignment Motor for Driver Raw Mill 2 (RM2) 61
4.5.4 Taking Flow Rate Reading of Grinding Aid for Cement Mill 3 62
Dust Collector
5.1 Introduction 63
5.2 Type of Dust Collectors Used in LMC Langkawi 64
5.2.1 Gravity Settling Chamber 64
5.2.2 Cyclones 65
5.2.3 Multicyclones 66
5.2.4 Fabric Filters 67
5.2.5 Electrostatic Precipitators 69
5.3 Preventive Maintenances 70
5.3.1 Change the Air Bag Filter for Cement Mill 3 70
5.3.2 Inspection of COM 2 Dust Collector System Purging Air 71
Preheater
6.1 Introduction 72
6.2 Mechanism 73
6.3 Preventive Maintenances 76
xi
6.3.1 Measuring Temperature and Pressure Reading 76
6.3.2 Coating Leakage at Single Flap Damper, Hot Meal Duct 77
6.3.3 Take Pressure, Temperature and Air Flow Reading of Kiln 78
6.3.4 Measuring the Wet Bulb Temperature 79
Quality Control
7.1 Introduction 80
7.2 Hard Grain Index 81
7.3 Sieve Test 82
7.4 Residue Test 83
7.5 Drop Test 84
Projects
8.1 Project 1: Sealing Air Fan for Cement Mill 4 (CM4) 85
8.1.1 Background 85
8.1.2 Objective 87
8.1.3 Expected Benefits 87
8.1.4 Cost Justification 87
8.1.5 Resource Requirements 88
8.2 Project 2: Tracing Pressure Vessel Tank in Cement Mill Section 89
8.2.1 Introduction 89
8.2.2 Problem 90
8.2.3 Solution 90
8.2.4 Completed Drawing 91
8.3 Measuring the Actual Fan Performance Curve for LK1 and LK2 92
8.3.1 LK2 – Raw Mill EP Fan 93
xii
8.3.2 LK2 – Cooler Exhaust Fan 94
8.3.3 DOPOL Waste Gas Fan 95
8.3.4 Raw Mill Fan 96
Discussions
9.1 Safety at Workplace 97
9.1.1 Personal Protective Equipment (PPE) 99
9.1.2 Safety Reporting System (SRS) 100
9.2 Environmental Issue 101
9.2.1 Lafarge Group Policies 101
9.2.2 Lafarge Malayan Cement Initiatives 103
9.2.2.1 Biomass to Energy 103
9.2.2.2 Lafarge Roofing 105
Conclusion 107
References 108
Appendices 111
1
CHAPTER 1: COMPANY PROFILES
1.1 LAFARGE CEMENT
1.1.1 HISTORY OF LAFARGE CEMENT
Lafarge is a French industrial company specializing in four major products which are
cement, construction aggregates, concretes and gypsum wallboard. The Lafarge Cement
began operations in 1833 with lime operation in France leaded by Auguste Pavin de
Lafarge. Through the numerous acquisitions of lime and cement industries throughout the
countries, Lafarge became France’s largest cement producer by the late 1930s.
The company first expanded internationally in 1864 with the supply of lime for
construction of the Suez Canal. International expansion continued in the early twentieth
century when operations began in North Africa, United Kingdom, Brazil and Canada.
Through the 1981 acquisition of General Portland Inc., Lafarge became one of the largest
cement manufacturers in North America. Further expansion of Lafarge continued with the
purchase of Blue Circle Industries in 2001 next took on acquisitions around the
Mediterranean Basin, Eastern Europe, the Middle East and Asia. By the expansion
Lafarge has become the joint leader in the worldwide cement industry, with production
facilities in almost 51 countries.
The aggregates and concrete business, now operating in 29 countries, made a significant
leap in 1997 with the acquisition of Redland plc, one of the principal manufacturers of
aggregates and concrete worldwide at the time.
2
1.1.2 LAFARGE CEMENT TIMELINE
1833
The Beginning
The story of the world leader in building materials began in the Ardèche region at a place
called “Lafarge”, which means “the forge”, near the village of Teil. Joseph-Auguste
Pavin de Lafarge began regular extraction operations in the limestone quarries. He had 2
major advantages which are geological and geographical. The geographical means the
limestone of the region is of excellent quality and can be used to replace mortar and the
Rhone River makes in relatively easy to transport goods. Joseph’s two sons, Eduord and
Lèon developed the family company, which then became known as “Lafarge Frères”
which means Lafarge Brothers in 1848.
1864
First major project: the Suez Canal
Lafarge won the “contract of the century” in Egypt. 200,000 tons of hydraulic lime
delivered in wooden barrels, were needed to build the piers of Suez canal. Although its
production capacity was limited to just 20 kilns, which produced 50,000 tons per year,
Lafarge rose to the challenge. The canal was inaugurated on 17 November 1869,
connecting the Mediterranean Sea to the Red Sea.
1866
First operations in Algeria and development in North Africa
The Suez Canal contract, the company’s first success in the Mediterranean basin, was the
prelude to expansion and the opening of commercial offices in Marseilles, Sète, Tunis
3
and Algiers. Within a few years, the Group had become the leading producer of Portland
Cement in Algeria.
1887
Creation of the world’s first research laboratory specialized in cement
On the back of its commercial success, Lafarge opened a research laboratory near Teil,
France. This laboratory was the first in the world to specialize in cement. The gifted
scientists working there placed the laboratory at the forefront of technological progress.
To this day, Lafarge works with the most talented research teams. Physical, chemical and
mechanical research allows Lafarge to retain its position as the leader in building
materials and respond ever more closely to customer requirements.
1889
Social policy rewarded at the Universal Exhibition
From the outset, Lafarge has paid close attention to the living and working conditions of
its employees and has invested in facilities ranging from dormitories, canteens and
hospitals to schools, gardens and rent-controlled housing. The Group’s social policy was
rewarded with a gold medal at the Universal Exhibition. Lafarge received this award
again in 1900.
1899-1906
Elaboration of the “revolving extinction technique”
Lafarge’s teams developed the “revolving roller extinction technique”, an innovative
procedure used to create white lime, maritime lime and extra-white cement. The first
buildings made with these Lafarge products were the New York Stock Exchange (cut
4
stone with white cement joints) and prestigious buildings in the Mediterranean region
including the pier in Venice, the port of Algiers and Corinth canal.
1908
Ciment Fondu®, resistant to external forces and high temperatures
Lafarge research director Jules Bied filed a patent for Ciment Fondu®, obtained by
mixing limestone and bauxite. This cement quickly acquired an excellent reputation
thanks to its many properties, notably rapid hardening and resistance to corrosion and
high temperatures. It was put to a range of uses and can be found in the Paris metro, on
oil rigs, in equipment for the world’s leading steel manufacturers and more recently, in
the launch pad for the Ariane rocket in Kourou, French Guiana. Ciment Fondu® is the
base ingredient for a number of innovative products including special mortars and
refractory concretes.
1921
First patent for white cement
During the fabrication process for white cement, clay is replaced by kaolin, which
contains low quantities of iron oxide. White cement has the same properties as
comparable grey cement but offers additional esthetic qualities. White cement is still used
today.
1930
First quarry rehabilitation in Draveil, France
Lafarge has long been aware of the environmental impact of its extraction activities. In
1930, the Group carried out its first quarry rehabilitation project. Today, the Group plans
5
the rehabilitation of each site before it begins extraction. An environmental impact study,
carried out in advance of operations, identifies all measures that will be required to
protect the environment, biodiversity and local communities.
1931
Diversification into gypsum, the production of gypsum powder
In 1931, the Group acquired “Gypses et Plâtres de France”, a company based in the South
France that owned a number of Gypsum quarries. This acquisition marked Lafarge’s
entry into a promising market later it became the 3rd
largest producer of gypsum in the
world.
1947
The leading cement producer in France and North Africa
Throughout the first part of the 20th
century, the Lafarge lime and cement company
continued to develop by acquiring companies across France. After the Second World
War, Lafarge consolidated its position as the leading cement producer in France and
International development increased while greater demand for building materials saw
production double in just 10 years.
1956
The first cement plant in North America and the creation of Lafarge Cement of North
America (LCNA)
Lafarge built its first cement plant in North America at Richmond in western Canada. It
was a bold move to locate a plant 10,000 km and 24 hours by plane from France.
6
1959
First operations in Brazil
Lafarge acquired a stake in Cominci, a Brazillian company, and built its first cement plant
in Brazil at Matozhinos. This plant was the first to produce the famous “Campeâo” brand
of cement.
1970
Creation of Canada Cement Ltd. (CCL), the country’s leading cement producer
1970 saw the merger between Lafarge Cement of North America (LCNA), founded in
1956, and Canada’s largest cement producer, Canada Cement Company which had been
founded in 1909. The new company was called Canada Cement Lafarge Ltd. (CCL)
became the largest cement producer in Canada with 11 plants.
1971
Agreement with the French Ministry for the Environment on dust emissions
Since 1971, Lafarge has been taking active steps to reduce dust emissions from its cement
plants. The Group does more than simply comply with regulations and the equipment and
processes used in plants, such as chimney evacuation filters are constantly being
improved through the use of new technologies.
1972
Development of superplasticizers and modernization of the Group
Following the oil crisis, the Group was reorganized and the Lafarge holding company was
created. New management methods and more effective industrial processes allowed the
Group to pursue renewed growth. Lafarge’s research and development team (R&D)
7
developed water-reducing admixtures also known as “superplasticizers” which create a
fluid concrete without the addition of water.
1974
First use of industrial waste as an alternative fuel
In the mid-70s, as petrol prices soared, Lafarge realized that industrial and agricultural
waste products such as coffee pods, rice husks, tires, solvents and bone meal could be
used to add value in its processes. This industrial ecology approach safely reduces the use
of fossil fuels, diversifies energy sources and provides a service to communities by
recycling waste. It also reduces CO2 emissions which is particularly important given that
the cement industry is responsible for 5% global emissions.
1977
Publication of the Group’s Principles of Action
Lafarge’s humanist traditions, passed down the generations since the company was
founded, inspired the Group’s Principle of Action. As Olivier Lecerf, Chairman from
1974 to 1989, said “We try to manage by serving rather than by dominating. The true
legitimacy of a leader lies in his capacity to serve.” The Principles of Action are a set of
humanist values and commitments shared by all employees. They incorporated a vision of
becoming the undisputed market leader, commitments to stakeholders and the Lafarge
Way, which is a code of conduct that encourages individual success within a multi-local
organization.
8
1980
Lafarge achieves leadership on the North American cement market – Perfection of
high performance concretes
The newly-created Lafarge Coppèe Group, born of the merger between Lafarge and
Coppèe, became North America’s leading cement producer. The Groups’s workforce
increased from 12,000 to 17,000. The following year, Lafarge consolidated its position in
North America when it acquired a majority shareholding in General Portland, the 3rd
largest cement producer in the world.
1985
First operations in Cameroon and sub-Saharan Africa
Lafarge took its first steps in sub-Saharan Africa in 1985, when it opened a site in
Cameroon. Lafarge now has activities in 10 countries in sub-Saharan Africa.
1995
Sustainable development at the heart of the Group'
Lafarge implemented its first recycling programs which was production waste was used
as an alternative to standard raw materials and fuels at all industrial sites where this was
technically possible. The Group published its environmental policy and made
commitments regarding the conservation of extraction sites. In the 1995 also Lafarge
launched its first employee stock option plan to allow employees to share the Group’s
financial success and encourage a sense of community. This operation has been repeated
regularly and enjoys growing success.
9
1997
Acquisition of Redland: a new business portfolio and further consolidation
The acquisition of Redland, a British group strengthened Lafarge’s positions in
aggregates and concrete, turned the Group into the leader in building materials in North
America and allowed Lafarge to enter the roofing sector.
1998
First operations in India and South Korea
Continuing its growth strategy in Asia, Lafarge acquired 2 plasterboard factories in South
Korea, close to the town of Busan. The South Korea plasterboard market is the second
largest in the region and offers excellent potential for further growth. Lafarge also entered
the Indian cement market by purchasing the cement division of Tata Iron & Steel
Company Ltd (TISCO), India’s leading steel manufacturer. This acquisition gave the
Group a strong presence on the market in western Bengal and an efficient industrial
operation in the form of a cement plant and a grinding plant.
2000
A turning point: acquisitions, new product launches and partnerships
Lafarge and WWF, the world’s largest environmental protection organization, signed a 5-
year agreement as part of the “Conservation Partner” program. Besides, the merger
between Lafarge’s Aggregates Business and that of the Warren Paving & Materials
Group saw Lafarge became one of the leading aggregates producers on the North
American market.
10
2001
Lafarge, the world’s leading cement producer, targets sustainable growth
With the acquisition of Blue Circe, the Group became the world’s leading cement
producer and strengthened its position in emerging markets. Lafarge’s first sustainability
report received an award for the private sector company which provides the best
environmental communication tools.
2002
Framework agreement with the CNRS and the launch of PLAtecTM
Lafarge and the French National Center for Scientific Research (CNRS), Europe’s
leading research organization, signed a framework agreement to reinforce their
cooperation. Besides, the Group launched PLAtecTM, a range of made-to-measure
plasterboard solutions which has been used in interior design projects from government
building in Vaucluse to the headquarters of Virgin, designed by Renzo Piano.
2003
Signature of the UN Global Compact, creation of the Stakeholder Panel and further
efforts in the fight against AIDS
Lafarge signed a 5-year partnership agreement with Care, a non-governmental
organization, to fight against AIDS. The Group created a stakeholder panel to gain an
external perspective on its activities and strategy.
11
2004
Expansion in emerging markets, the launch of SignaTM, humanitarian aid,
sponsorship
The Group developed its Businesses in emerging countries by building new plants in Asia
(Thailand, India, Cambodia, etc.), by consolidating its position in Korea, by expanding its
cement capacities in North Africa and Eastern Europe. Following the tsunami of
December 2004, Lafarge acted quickly to bring emergency aid to employees and their
families.
2005
Recognition for the Group’s sustainable development activities – Increased production
capacities
Through a joint venture, Lafarge doubled its production capacity in China and became the
third largest cement producer in the country. It also invested 300 million euros to expand
the production capacities of its Gypsum Business. Lafarge ranked among the 100 best
performing multinationals in terms of sustainable development, and signed an agreement
on Group social responsibility and international social relations with three international
trade unions.
2006
Bruno Lafont and the Excellence 2008 Plan – Commercial launch of Sensium® -
Launch of the Hypergreen concept
Bruno Lafont was appointed as CEO of the Group and launched the Excellence 2008
strategic plan. The program will improve industrial performance, consolidate positions on
emerging markets and drive further action on sustainable development. Lafarge
12
purchased Lafarge North America minority shares and became the leader in North
America across all of its Businesses.
2007
Divestment of the Roofing Business, focus on sustainable growth, launch of 2
concretes with high added value
Lafarge divested its Roofing Business to the PAI partners investment fund to concentrate
on its core activities. The Group expanded its research center, adding a new experimental
concrete plant that allows researchers to test laboratory research results in real time and
on an industrial scale.
2008
Acquisition of Orascom Cement, the leading cement group in the Middle East and the
Mediterranean Basin
This operation is a decisive acceleration of the Group’s strategy in fast-growing, highly
profitable emerging markets. Orascom cement is located in high-potential markets, with
number-one positions in the key markets of Egypt, Algeria, United Arabs Emirates and
Iraq. Its geographical presence is highly complementary with Lafarge’s emerging markets
portfolio.
2009
Growth in emerging markets – Concrete innovation
Lafarge continues to grow in emerging countries in Ecuador, Nigeria and Iraq. Innovation
is in the spotlight with the launch of Thermedia® 0.6B, a new generation of insulating
concretes.
13
2010
Innovation strategy – Shanghai World Expo – Strengthening business in Brazil and
Central Europe
Lafarge accelerates its innovation strategy and introduces Aether – a project aiming at
reducing CO2 footprint. In additions, Lafarge strengthens its presence in Brazil following
the sale of its Cimpor stake to Votorantim and becomes one of the three main cement
operators in the country. Lafarge and STRABAG, Central and Eastern Europe’s largest
construction company then create a holding company located in Austria.
2011
Significant divestment and new organization
Lafarge and Anglo American announce the creation of a leading UK construction
materials company. Lafarge also presents a new organization project more agile and
responsive, focused on its markets and its clients.
14
1.2 LAFARGE MALAYAN CEMENT
1.2.1 HISTORY OF LAFARGE MALAYAN CEMENT
Lafarge Malayan Cement Bhd (formerly known as Malayan Cement Bhd) is the producer
of cement in Malaysia with plants strategically located in Rawang, Kanthan, Langkawi
and Pasir Gudang in Peninsular Malaysia. In addition, it is the owner and operator of a
cement grinding plant and a bulk import terminal in Singapore.
The Group sells cement and other related building materials in Malaysia and Singapore.
The acquisition of the operating companies and a majority interest in Kedah Cement
Holdings Bhd in 1999 transformed the company into Malaysia’s largest cement producer
with an increased presence in Singapore.
Being a member of the Lafarge Group, the company is able to draw from an even wider
international base of experience and technical expertise and a broader international
trading network.
On 30 July 2003, the company unveiled its proposal for an internal reorganization of the
Group’s corporate structure of its Singapore subsidiaries, with the intent of streamlining
its holdings in its various subsidiaries under one Singapore incorporated company
wholly-owned by Lafarge Malayan Cement (LMC)
15
1.2.2 LAFARGE MALAYAN CEMENT TIMELINE
1950
Incorporation of Malayan Cement Berhad (now known as Lafarge Malayan Cement Bhd)
as a subsidiary of Blue Circle Industries PLC, United Kingdom.
1953
Establishment of Rawang Works, Malaysia’s first cement plant. (Rawang Kiln No.1-
110,000 tonnes per annum)
1958
Commisioning of Rawang Kiln No. 2 (190,000 tonnes per annum)
1961
Malayan Cement Berhad was listed in the Kuala Lumpur Stock Exchange Berhad on 17
March 1961.
1964
Opening of Kanthan Works by Pan Malaysia Cement Works Bhd (PMCW).
1965
Commisioning of Kanthan Kiln No. 2 (190,000 tonnes per annum). Opening of a grinding
plant in Singapore by Pan Malaysia Cement Works Singapore (PMCWS)).
16
1967
Merger of cement operations with PMCW and the formation of Associated Pan Malaysia
Cement Sdn Bhd. Also acquired 50% stake in PMCWS.
1980
Commisioning of Rawang Kiln No. 3 (1,200,000 tonnes per annum). Incorporation of
Supermix Concrete Pte Ltd (SPMS).
1983
Incorporation of Supermix Concrete (Malaysia) Sdn Bhd (SPMM)
1984
Kedah Cement Sdn Bhd (now known as Lafarge Cement Sdn Bhd) commissioned
Langkawi Plant.
1985
Commisioning of Kanthan Kiln No.3 (800,000 tonnes per annum).
1989
The company launches its first differentiated bulk product, Mascrete.
1992-1993
Uprating of Rawang Kiln No. 3 and Kanthan Kiln No. 3 to 1.5 and 1.0 million tons per
annum.
17
1995
Rawang Plant becomes the first location within the Group and the first cement plant in
Malaysia to be awarded the ISO 9002 (now changed to ISO 9001:2000) certification.
Kanthan Plant received the same certification about three months later.
1997
Southern Cement Industries Sdn Bhd (SCI) commissioned its grinding plant with a rated
capacity of 770,000 tons per annum in Pasir Gudang, Johor. Commisioning of Bulk
Import Terminal with silo capacity of 55,000 tons in Jurong Port, Singapore to replace
PMCWS grinding facility.
1998
Commisioning of Kanthan Kiln No. 4 (1,800,000 tonnes per annum) Acquisition of the
remaining 50% stake in APMC). Rawang and Kanthan Plants were awarded the ISO
14001 certification, making us the first cement company in Malaysia to achieve this
certification.
1999
Acquisition of Kedah Cement and merger between APMC and Kedah Cement.
2000
Opening of a dry-mix cementitious product plant in Tuas, Singapore. We become the first
cement company to be awarded the OHSAS 18001 certification when Rawang Plant
receives the certification on 8 December 2000 closely followed by Kanthan Plant on 15
December.
18
2001
Becoming part of Lafarge Group following Lafarge’s acquisition of Blue Circle. SPMM
acquired Pengkalan Concrete and spread its wings to East Malaysia. The company
celebrated the launch of the first fly ash bag cement, Phoenix. Besides, Malayan Cement
was awarded the Corporate Awards 2001, Sectorial Award, Main Board – Industrial
Products awarded by the Kuala Lumpur Stock Exchange.
2002
Malayan Cement launched a new corporate identity which reflects its membership in the
Lafarge Group. In addition, Malaya Cement was awarded the Corporate Awards 2002,
Merit Award, Main Board – Industrial Products, Kuala Lumpur Stock Exchange.
2003
Company name officially changed from Malayan Cement Berhad to Lafarge Malayan
Cement Berhad to better reflect its corporate identity as a member of the Lafarge Group.
Lafarge Malayan Cement was recognized as a Leader – Construction Sector by Malaysia
1000, Malaysia’s top corporate directory.
2005
We secured a long-term contract with Tanjung Bin power plant for the exclusive supply
of all their fly ash production. Lafarge also launch the Logistics Safety Conference with
the objective of increasing awareness on road safety amongst the company’s transporters
and drivers towards achieving zero accident in loading and transportation. Lafarge Young
Engineers Programme also had been launched where fresh graduates from local
19
universities are recruited and enrolled annually in a cement professional development
programme to nurture them into skilled engineers.
2006
Launch of a new differentiated bulk product, Mascrete Pro and the Industrial Safety
Conference in order to instill greater safety awareness amongst the company’s members.
Besides the opening of the residential housing area, Desa Kuala Garing, built and
contributed by LMC to relocate 124 squatters in Rawang.
2007
An annual production record of 3 million tons of clinker by Kanthan Plant. Pasir Gudang
Plant launched its first Pulverized Fly Ash (PFA) blended cement.
2008
Lafarge Malayan Cement was honored with the Industry excellence Award
(Construction) and Merdeka Corporate Award by Malaysia 1000, Malaysia’s top
corporate directory.
2009
Lafarge Malayan Cement was selected as one of the twenty finalists (Marketplace
dimension) in the StarBiz-ICR Malaysia Corporate Responsibility Awards. The award
focuses on how well companies demonstrate their understanding of Corporate
Responsibility throughout the business operations.
20
2010
Lafarge Malayan Cement was honored with “Technology Innovation Award for
Sustainable Production of Cement” by Frost & Sullivan Green Excellence Awards on 9
June for demonstrating its firm commitment to a continuous focus on reducing the
decency on finite resources and resolving to reduce the impact for climate change and
overall ecological footprint. LMC also was honored with a plaque by StarBiz ICR
Malaysia Corporate Responsibility for being one of the finalists in the segment above
RM1 billion market capitalizations. Lafarge Malayan Cement also was placed 11th
for
Best Corporate Governance Company in Malaysia by Finance Asia, a Hong Kong-based
publication reporting on Asia’s financial and capital markets.
2011
Lafarge Malayan Cement receives the Singapore Green Building Product certification for
Mascrete LH cement and Phoenix cement by the Singapore Green Building Council.
Moreover, LMC also has been awarded an Innovative Award for Sustainable Production
of Building Materials by the Malaysian French Chamber of Commerce & Industry on 24
June 2011. Plus, Lafarge Malayan Cement was recognized as a sustainable development
leader and was presented the “Enterprise Governance Award 2011 for Green initiative”
by The Malaysia Business and the Chartered Institute of Management Accountants
Malaysia on 27 September 2011 and short while later was awarded the SIRIM Eco-Label
for Phoenix and Mascrete LH on November 2011.
21
1.3 LAFARGE MALAYAN CEMENT LANGKAWI PLANT OVERVIEW
1.3.1 LOCATION OF LAFARGE MALAYAN CEMENT LANGKAWI PLANT
Figure 1.1: Langkawi Plant Layout
Figure 1.2: Location of LMC Langkawi
22
Figure 1.3: Plant Layout of LMC Langkawi
23
1.3.2 ORGANIZATIONAL STRUCTURE
24
1.3.3 TECHNICAL DATA
Lafarge Malayan Cement Langkawi Plant (LMC) formerly known as Kedah Cement Sdn
Bhd is one of the plant built in Malaysia. First built by the 4th
former Prime Minister, Tun
Mahathir Mohamad in 1981, the plant had been named with Kedah Malayan Cement
however the plant had been acquainted by Blue Circle, a UK cement producer in 1999.
The Blue Circle has been acquainted by Lafarge Cement in 2001 short while later. Till
now, the plant remains organized by Lafarge Malayan Cement centered at Petaling Jaya
and supervised by the board of directors in Paris, France.
With the area of 1162.25 acres and 398 employees, the Lafarge Malayan Cement
Langkawi Plant produces approximately 3.38 million of cement per annum thus
becoming the largest producers and the only exporter of cement products in Peninsular of
Malaysia to Singapore, Bangladesh, Myanmar, Hong Kong, Sri Lanka, Mauritius Nigeria
and Australia.
The plant operates with 2 lines called line 1 (LK1) and line 2 (LK2) which use Japan
technology and German technology respectively. Technology that is used from Japan
technology is from Ishikawajima Harima Heavy Industries while for German technology
of Krupp Polysius of Germany is implemented. Each line consist of Raw Mill, Cement
Mill, Coal Mill and Preheater and these sections are monitored and ran under supervision
of Maintenance, Quality, Process and Production Department.
25
1.3.4 LMC LANGKAWI PLANT VISION AND MISSION
People Mobilization
• Succession Planning
• Retention of talents
• Follow up on IDP program
implementation and close coaching
• Front Line Supervisor development
program
Plant Mastery
• Job ownership/Core functions
competency
• Improve competency of our talent
• 5G 3S shift operation
LANGKAWI PLANT 2012 HOUSE
To achieve
total Plant Masteryfor our customer with
Safety as our way of life
•Health & Safety-cultured workforce in all the sites•Towards mastered and robust plant with sustainable improvement
•Clean and Environmental friendly plant for our employees & community
•Meeting external and internal customers expectations•Leadership through performance culture
Health & Safety
• Zero total injury
frequency rate
• Area ownership JHP
and HK
• Practice safety
interventions
• Zero environmental
infringements
• 12 hrs Safety training
• Compliance with
group standards and
advisories
• POM Compliance
• Industrial standards (LQTS, LQMS,
Power, heat to come, first 5 rules
are mandatory)
• Kiln RF => 97.13%
• Kiln PF => 93.42%
• Cement mill RF =>97.27% @
UF64.48%
• Cementitious C/K => 1.1165
• Cost ownership & control (VC
HC3,335 MJ/ton clk, Power 77.92
kwhr/Clk, grinding 51.26 kwhr, IFC
compliance 74.54 mMYR
• AF replacement 13.24%
• Maintenance project, MCI <= 1.29,
• Engg.Spares: RM53.23m, Gr.media :
RM 0.3m, Refractory: RM 0.8m
Customer Satisfaction
• OTIFIC => 92%, for
both Domestic and
Export
• Consistent
Product Quality
IQP => 95%
• Product quality
complaints =
Reduction by 50%
vs. previous year
• LP Ship loaders
RF => 96%
Plant Mastery
26
1.3.5 COMPONENTS OF LMC LANGKAWI
Human Resource Department
Create and preserve relationship between company and stakeholders.
Maintenance Department
Management
Results-driven based upon delegation with clear goals and objectives.
Execution team
o Mechanical team
Service and repair machines in plant
o Electrical team
Service and repair electrical components in plant.
Method team
o Inspection team
Maintain- in depth knowledge of equipment conditions.
o Mechanical Planner
Every actions needed in each of the project is well planned.
o Electrical Planner
Every actions needed in each of the project is well
planned.
27
Production Department
Monitoring production’s equipment ran in the plant.
Finance Department
Manage the cash flow and budget of Lafarge Malayan Cement Bhd.
Health and Safety Department
Responsible to give briefing and safety information plus ensuring the safety
procedures are followed by each of members.
Process Department
Monitor and Control each of the process took place in each section.
28
1.3.6 PRODUCTS OF LMC LANGKAWI
Ordinary Portland Cement
Ordinary Portland Cement (OPC) is the most common cement used in general concrete
construction when there is no exposure to sulphates in the soil or groundwater. The raw
materials required for the manufacture of OPC are calcareous material such as limestone
or chalk and argilaceous materials such as shale or clay. A mixture of these materials is
burnt at a high temperature of approximately 1400 0C in a rotary kiln to form clinker. The
clinker is then cooled and grounded with a requisite amount of gypsum into fine powder
known as Portland cement.
OPC is a gray coloured powder. It is capable of bonding mineral fragments into a
compact whole when mixed with water. This hydration process results in a progressive
stiffening, hardening and strength development.
Cement Products
Ordinary Portland Cement (OPC)
Phoenix
Walcrete Mascrete
Rumah
29
Portland Composite Cement (Phoenix)
PHOENIX is the brand name of specifically
blended bagged Portland-composite cement. It is
manufactured by grinding calcium sulfate as a
setting regulator with Portland Cement clinker
and other carefully selected secondary
constituents (pozzolanic materials, fly ash and other constituents permitted under BS EN
197-1:2000). There are some advantages provided by PHOENIX which are improved
compactibility, improve cohesiveness, richer mix, improved surface finish, reduced
bleeding and lastly it improves board life.
Masonry Cement (Walcrete)
Masonry Cement is an extremely versatile. It is
recommended highly for bedding and pointing
brickwork and blockwork, interior and exterior
plastering and wall finishes. It is a homogenous blend
of controlled amounts of Portland Cement, plasticizing
material and air entraining agent, inter-ground to a high
fineness to give consistent quality.
Unlike conventional mortar which is a mixture of four ingredients (i.e. Portland Cement,
lime, sand and water), WALCRETE masonry mortar requires only three ingredients,
which are WALCRETE, sand and water.
30
Its excellent water tetaining property prevents premature loss of water therefore ensuring
strong bonding, low drying shrinkage, better weather resistance, good workability, easier
handling and smoother finishing.
Portland Pulverised-Fly Ash Cement (MASCRETE LH)
MASCRETE LH is the trade name of a specially manufactured Portland Pulverized-Fuel
Ash Cement or also called Portland-fly ash cement.
Mascrete LH is manufactured by intergrinding in order to
ensure homogeneity and consistency in the quality of the
product, under an effective system of testing, control and
monitoring, confirming to requirements under SIRIM’s
Product Certification Licence MS ISO/IEC 17025.
This product is effective in reducing core temperature of
big concrete structures, also to resist Chloride and Sulfate
attack for marine situations and to improve overall concrete durability.
Portland Limestone Cement (RUMAH)
RUMAH is the brand name for multi-purpose
bagged cement suitable for any project. Compared
to the conventional OPC, its good early strength,
workability and cohesiveness make it suitable for
use in wide variety of general applications.
31
CHAPTER 2: MANUFACTURING PROCESS OF CEMENT
2.1 WHAT IS CEMENT?
Cement is a hydraulic binder and is defined as a finely ground inorganic material which,
when mixed with water, forms a paste which sets and hardens by means of hydration
reactions and processes which, after hardening retains its strength and stability even under
water. Ordinary Portland Cement (OPC) is one of several types of cement being
manufactured in Lafarge.
OPC consists mainly of Lime, Silica, Alumina, Iron and Sulphur Trioxide,
Magnesium and other Oxide elements are present in small quantities as an impurity
associated with raw materials. When cement raw materials containing the proper
proportions of the essential oxides are ground to a suitable fineness and then burnt to
incipient fusion in a kiln, chemical combination takes place, largely in the solid state
resulting in a product named clinker. This clinker, when ground to a suitable fineness,
together with a small quantity of gypsum is Portland cement. Gypsum is added at the
grinding stage to retard the settling time of finished cement.
Figure 2.1: Portland Cement
32
Figure 2.2: Langkawi Works Flow Chart
33
2.2 PROCESS
2.2.1 RAW MATERIAL PREPARATION
The raw materials required to manufacture cement are limestone, clay, iron and iron ore.
Rocks extracted from the quarry either by extraction or blasting are routed to the nearby
cement plant on a belt conveyor. Each quarry is subjected to a rehabilitation plan adopt to
its situation, including promotion of local biodiversity, creation of a touristic and
environmental park, residential, agricultural or redevelopment program.
Figure 2.3: Elements involved in the making of cement
34
Figure 2.4: Blasting process
Figure 2.5: Raw materials crushed and transported via belt conveyor
35
2.2.2 GRINDING AND STORAGE OF RAW MATERIALS
The minerals from the quarry are routed to the grinding plant where they undergo initial
milling before being reduced to a fine powder. The raw materials (80% limestone and
20% clay) are then stored in the pre-homogenization pile. Grinding produces a fine
powder called “raw meal” which is preheated and then sent to the kiln.
In the wet process, each raw material is
proportioned to meet a desired chemical
composition and fed to a rotating ball mill with
water. The raw materials are ground to a size
where the majority of the materials are less than
75 microns. Materials exiting the mill are called
"slurry" and have flow ability characteristics.
This slurry is pumped to blending tanks and homogenized to insure the chemical
composition of the slurry is correct. Following the homogenization process, the slurry is
stored in tanks until required.
In contrast with the process done in Lafarge Malayan Cement, each raw material
is grinded in a dry condition so called dry process. In the dry process, each raw material is
proportioned to meet a desired chemical composition and fed to either a rotating ball mill
or vertical roller mill. The raw materials are dried with waste process gases and ground to
a size where the majority of the materials are less than 75 microns. The dry materials
exiting either type of mill are called "kiln feed". The kiln feed is pneumatically blended to
insure the chemical composition of the kiln feed is well homogenized and then stored in
silos until required.
Figure 2.6 Raw Meal
36
Figure 2.7: Red hot clinker falls
onto the grate, cooled
by air blown from
beneath
2.2.3 THE FIRING OF RAW MATERIALS
The raw mix is fed into a preheating tower at
800°C before returning to the rotary kiln where it
is heated to a temperature of 1450°C. Combustion
causes a chemical reaction called “decarbonation”
which releases the CO2 contained in the
limestone. The fired materials take the form of
hard granules called “clinker”.
For the production of the clinker, the raw
meal which is known as kiln feed at this stage has to
be heated to a temperature of about 1450°C in the long cylindrical rotating kiln. The kiln
feed enters the system at the top of the pre-heater and fall until the lower end of the kiln.
The heat exchange occurs during this process when the hot gases from the kiln end rise up
to the top of the pre-heater. The clinker formation process is divided into four parts which
are drying, calcining, sintering and cooling. As the kiln feed moves towards the lower end
of the kiln it undergoes some successive reactions.
The red hot clinker is then discharged into the cooler, where it is quenched cooled
to around 100 degrees centigrade. The heat dissipated by the clinker is used as secondary
air for the combustion in the calciner. This hot gas is also used in the dryers at the raw
materials preparation stage. Rapid cooling of the clinker is essential as this hampers the
formation of crystals, causing part of the liquid phase to solidify as glass. The faster the
clinker cooling the smaller the crystals will be when emerging from the liquid phase.
37
Figure 2.8: Burning process occur in the
rotating kiln from 1200°C to
1400°C
Figure 2.9: Clinker that produced will be air quenched to
reduce clinker temperature from 1400°C to
120°C
38
2.2.4 STORAGE AND GRINDING OF CEMENT
Following re-cooling, the clinker is stored in silos then transformed into cement
according to production requirements. During the final manufacturing stage, gypsum is
added to the clinker, in a proportion of 3% to 5%, and the mixture finally ground. Clinker,
gypsum and grinding aid are ground together in ball mills to form the final cement
product. Fineness of the cement product, amount of gypsum added, and the amount of
process additions added are all varied to develop a desired performance in each of the
final cement products.
Figure 2.10: Elements used in clinker milling
39
Various substitute materials such as fly ash and slag can also be used in the composition
of cement. The fly ash is the residue from thermal power plant activity while for slag, it
comes from blast furnaces. Their use has the dual advantage of reducing the quantity of
clinker required next creating a wider range of cements, with qualities corresponding to
customers’ specific needs.
Figure 2.11: Clinker Silo - clinker storage before
milling process for producing cement
40
2.2.5 PACKAGING AND SHIPMENT
The cement is stored in silos before being delivered by tanker trucks or packaged into 23-
35kg bags and stacked on pallets. Various means of transport may be used according to
the local infrastructure and topography. The use of transportation methods with a low
carbon footprint is given preference wherever possible.
Tanker Truck
Ship Bulk
Ship Loader
Figure 2.12: Product is exported via trucks or
ships
41
2.3 SUMMARY
Mining the raw material
Limestone and clay are blasted from quarries by boring the rock and setting off
explosives with a negligible impact on the environment, due to modern technology
employed.
Transporting the raw material
Once the huge rocks have been fragmented, they are transported to the plant in
specialised trucks or by conveyor belt.
Crushing
The quarry stone is then delivered through conveyor belt to the crushers, where it is
reduced by crushing to chunks approximately less than 25 mm in size.
Prehomogenisation
Prehomogenisation is the proportional mix of the different types of shale, limestones, or
any other required material to form the right combination for cement.
Raw Material Storage
Each of the raw materials is transported separately to silos, where it later will be added in
specific amounts according to the particular type of cement being produced.
42
Raw Material Mill
This takes place in ball or vertical steel mill, which grinds the material through the
pressure exerted by three conical rollers which roll over a turning milling table.
Horizontal mills, inside which the material is pulverized by means of steel balls, are also
used in this phase.
Raw Meal Homogenization
This process takes place in silos equipped for obtaining a homogenous mix of the
material.
Calcination
Calcination is the core portion of the process, in which huge rotary kilns come into play.
Inside, at 1400 °C, the raw material is transformed into clinker; small, dark gray nodules
3-4 cm in diameter.
→
Cement Milling
The clinker is ground by different size steel balls while it works its way through the mill's
2 chambers, with gypsum being added to extend cement setting times.
Cement packaging and shipping
The cement is then housed in storage silos, from where it is hydraulically or mechanically
extracted and transported to facilities where it will be packaged in bags or supplied in
bulk. In either case, it can be shipped by rail car, freighter truck or ship.
43
CHAPTER 3: CRUSHERS
3.1 INTRODUCTION
Cement raw material blasted in the quarry, requires size reduction for further process.
Size reduction is performed in crushers. Crushing is comminution in the coarse range
which process amplified by mechanical advantage is transferred through material made of
molecules that bond together more strongly and resist deformation more than those in the
material being crushed do.
Crushing devices hold material between two parallel or tangent solid surfaces and applies
sufficient force to bring the surfaces together to generate enough energy within the
material being crushed so that its molecules fractured and deformation in each other.
In operation, the raw material is delivered to the primary crusher's hopper by dump
trucks. A feeder device such as an apron feeder and belt conveyor controls the rate at
which this material enters the crusher, and often contains a preliminary screening device
which allows smaller material to bypass the crusher itself, thus improving efficiency.
Primary crushing reduces the large pieces to a size which can be handled by the
downstream machinery.
Figure 3.1: Line 2 crusher
44
3.2 TYPES OF CRUSHERS
3.2.1 JAW CRUSHER
In the cement industry the jaw crusher is in general use due to its relatively simple design
and also to the circumstance that this crusher is manufacturing large units. The jaw
crusher serves mainly as primary crusher. This jaw crusher is one of the 3 crushers used
in LMC Langkawi plant.
The size reduction of the crusher feed is performed between two crusher jaws where one
of it is stationary and the other is moved by toggle pressure. The jaws are lined with
ribbed liners consisting of chill cast or quenched steel.
To crush hard, semi-hard and brittle rocks, ribbed liners are used. The included angle of
the rib amounts to 90-100°. For crushing of coarser and considerably harder rocks, the
Figure 3.2: A jaw crusher
45
ribs should be corrugated. For large and very hard rocks, liners with more widely spaced
ribs are used.
Depending on the size of the crusher feed, the width of the ribs in jaw crushers employed
as primary crushers is 50-150mm. Jaw crushers employed as secondary crushers have ribs
with a width of 10-40 mm. The width of the crusher’s discharge opening is being
measured from the top of the rib of one liner to the opposite notching of the other liner.
When working very hard materials, the ribs generate lateral forces which have a negative
influence on the swing jaw shaft is such cases even jaw liners are preferred.
The greatest wear shoes at the lower part of the fixed jaw plate. The constructional design
of the jaw liners makes it possible to turn over a worn jaw liner 180° so that the worn side
comes upwards. This will make the lifetime of the jaw liner becomes longer.
Figure 3.3: Jaw Crusher with convex-concave shaped crusher plate
46
Double-toggle jaw crusher
In the double-toggle jaw crusher, the movement of the swing jaw is oscillating thus the
crusher feed is being squashed. High compression is applied not only to the crushed
material but also to the crusher jaws. This crusher serves for size reduction of hard and
very hard material in the form of large size rocks.
Single-toggle jaw crusher
In the single-toggle jaw crusher, the motion of the swing jaw is differ from that of the
double-toggle crusher. Here the swing jaw moves not only backwards and forwards but
also up and down. The size reduction is characterized by attrition and squashing.
Compression and friction work simultaneously. This crusher is employed for the
reduction of semi-hard material in smaller feed sizes.
Figure 3.4: Movement of swing jaw Figure 3.5: Schematic of the double-
toggle
Figure 3.6: Movement of swing jaw Figure 3.7: Schematic of single-toggle
47
3.2.2 ROLLER CRUSHER
This is the second type of crusher operating in LMC Langkawi plant. Comminution in a
roller crusher is based on the passage of material between two rotating rolls which crush
the material by compression. The particle size of the crushed material depends on the
distance of both rolls from each other. Depending on the kind of crusher feed, the surface
of the crushing rolls can be smoothed, ribbed or toothed. Subject to the hardness of the
crusher feed, the ribs can be arranged along or across to
the axis of the rolls.
In roller crusher, one of the crushing rolls is rigidly
installed in the crusher frame, whereas the other roll
slides horizontally under spring pressure. The elastic
springing on one of the rolls is a safeguard against
unbreakable material.
To prevent friction between crusher feed and the rolls, both crushing rolls have the same
speed of rotation. The drive is off a motor through a V-belt sheave and a gear wheel to the
fixed roll, and through a suitable linkage to the sliding roll.
Figure 3.8: Schematic of a roller crusher
Figure 3.9: 1200tph limestone
crusher
48
3.2.3 HAMMER CRUSHER
The third crusher operating in LMC Langkawi plant, hammer crushers are widely used in
the cement industry. They are used for size reduction of hard to medium hard limestone.
Hammer mills work with reduction ratios as high as 1:60, depending on the crusher feed.
However, this ratio can increase to 1:80. Sometimes the high reduction ratio of hammer
crushers does away with the need for the installation of multi-stage crushing plants.
Generally two types of hammer crushers are manufactured which are single shaft and
double shaft hammer crushers. These crushers work with the impact effect of the
hammers according to the formula for the kinetic energy of impact (P);
Figure 3.10: A hammer crusher
49
Starting from this point the mass of the hammers in hammer mills was reduced to a
minimum while at the same time increasing the velocity v as far as possible. The result
was greater impact force combined with reduced wear.
In both types of crushers, the crusher feed first passes through the upper or primary grid.
This follows preliminary size reduction of the material by the impact hammers. The final
crushing then occurs on the bars of the lower grid. Because of the two grids with different
spacing, the hammer mills can be considered two-stage crushers.
The impact of the hammers upon the crusher feed is not even. This means the load upon
the crusher and the drive motor is not continuous. Massive flywheels are used to stabilize
the operation. The double rotor crusher has separate drive motors for each shaft.
Purpose Crushing material
Type Hammer Crusher
Processed Material Limestone
Size of Processed Material 1200 mm maximum
Capacity 850 tph
Rotor Speed 185 rpm
Number of Hammer 84
Power Consumption 850 kW
Table 3.1: Information on Hammer Crusher Used in Lafarge Limestone Quarry
50
3.3 PREVENTIVE MAINTENANCES
3.3.1 MODIFY SCRAPER OUTLET OF JAW CRUSHER
Problem
The clay comes in clots block the rollers from keep rotating and functioning.
Solution
Enlarge the scraper outlet chute.
Procedures
1. Power 21602, 21603 and 21604 are isolated.
2. The chute plate is cut out.
3. The crusher casing is cut out.
4. A new plate is fabricated.
5. The new plate is welded to the crusher.
6. New paint is painted on the crusher plate.
7. Test run is done.
8. Housekeeping the work area.
9. The power is connected back.
51
Figure 3.11: Power is isolated and
LOTOTO is applied
Figure 3.12: Chute plate is cut out
Figure 3.13: Chute casing is cut out Figure 3.14: A new plate is fabricated
and welded to the chute
Figure 3.15: The new plate is painted
nicely Figure 3.16: Housekeeping the work
area
52
3.3.2 CHANGE THE TEETH OF JAW CRUSHER
Problem
The continuous operation will cause the wear of rollers’ teeth thus the efficiency of the
crusher has decreases.
Solution
The teeth of the rollers need to be changed with the new teeth.
Procedures
1. Power of the rollers is isolated.
2. The dust on the rollers needs to be cleaned.
3. The teeth that have wear is welded and replaced.
4. The power is turned on again and the rollers can continue its operation.
Figure 3.17: A wear roller Figure 3.18: A cleaned roller
Figure 3.19: New teeth welded
53
CHAPTER 4: GRINDING MILLS
4.1 INTRODUCTION
Grinding mill is a unit operation designed to break a solid material into smaller pieces.
There are many different types of grinding mills and many types of materials processed in
them. Historically mills were powered by hand, working animal, wind or water. Today
they are also powered by electricity.
The grinding of solid matters occurs under exposure of mechanical forces that trench the
structure by overcoming of the interior bonding forces. After the grinding the state of the
solid is changed: the grain size, the grain size disposition and the grain shape. In Lafarge,
vertical and ball mills are used.
Figure 4.1: Grinding mills
54
4.2 VERTICAL MILL (ROLLER MILL)
4.2.1 INTRODUCTION
Roller mills belong to the group of vertical mills and are particularly suitable for the
grinding of medium-hard to soft minerals. They can, however, also be used for the
grinding of comparatively hard substances.
To increase the retaining time of the material on the grinding bowl and improve
the structure of the bed of material, the roller path is designed in the form of a double
groove. The different radii of the grinding elements have a great influence on the way the
material is drawn under the rollers. Besides, this design also ensures the specific energy
consumption remain practically constant in spite of the increasing wear. The grinding
force is distributed to match the wear and ensure maximum utilization of the roller path.
Figure 4.2: Vertical mill
55
4.2.2 MECHANISM
The material to be ground is fed to the roller mill via a flow-regulating device and a feed
chute. It drops directly onto the center of the grinding bowl and for commination is
carried under the roller by the rotation of the bowl. Due to the exerted centrifugal force,
the crushed material is flung outwards over the edge of the grinding bowl and entrained in
the stream of gas from the nozzle ring. All of the material ejected from the grinding bowl
or a certain portion of it is carried in the gas stream to the dynamic separator located
above the grinding chamber. The separator classifies the material entrained in the gas
stream into finished product and oversize. The oversize material falls back onto the center
of the grinding bowl while the finished product is carried by the gas stream to the dust
collector where it is precipitated.
Figure 4.3: Process in vertical mill
56
4.3 BALL MILL (TUBE MILL)
4.3.1 INTRODUCTION
Ball Mill is a cylindrical device used to
grind or mix materials like raw materials
and clinker. The ball mill is an equipment to
grind the crushed materials and carrying on
the smashing again to obtain the desired
particle size.
Consist of several parts which are charging, discharging, cyclone and rotation part, the
ball mill is used in dry and wet material. Hollow axis is made of steel parts with lining
replaceable. It rotates around a horizontal axis, which partially filled with the material to
be ground plus the grinding medium, media. Different materials are used for media
including ceramic balls, flint pebbles and stainless steel balls. In LMC Langkawi, the
various sizes of stainless steel balls are used to grind the raw material.
Figure 4.5: Stainless Steel Used As
Media Figure 4.6: Intermediate Diaphragm
Figure 4.4: Ball mill
57
4.3.2 MECHANISM
Materials shall be evenly charged through quill shaft in feeding device into the first
chamber, which has step or waved lining with steel balls in different specifications. Steel
balls are taken to a certain height by centrifugal force from drum rotation and then fall.
Thus it will give a heavy blow to materials, playing a role of grinding. Materials after
crushed in the first bin shall enter bin across single-layer diaphragm into the second,
which is provided with flat lining with steel balls, to go through further grinding. Powder
shall be discharged from discharging grating, ending the milling process.
Figure 4.8: Shell Liner (side
view) Figure 4.9: Shell Liner (top
view)
Figure 4.7: Inside the ball mill
58
4.4 GRINDING AID
Grinding aids are materials which facilitate grinding in ball or vertical mills by
eliminating ball coating or by dispersing the ground material. When grinding cement, the
additive must also have been shown not to be harmful to the finished cement.
Grinding aids may be added in solution, as solids to the mill feed or directly to the mill
itself.
The addition of a fluid may be more readily controlled than the additional of a small
amount of granular material. Grinding aids are metered in quantities from 0.006% to
0.08% of the clinker weight.
The majority of grinding aids are substances which become strongly absorbed by the
ground particles, so that surface energy requirements are satisfied and no bonds remain to
attract other particles and cause agglomeration.
Figure 4.10: Grinding aid is pumped to the mill
59
4.5 PREVENTIVE MAINTENANCE
4.5.1 OUTER SLOTTED PLATE RENEWED
Procedures
1. Power is isolated and LOTOTO is applied.
2. The manhole mill inlet is opened.
3. The old slotted plate is cut out by cutting bolt.
4. By using a forklift, the new slotted plates are lifted to the floor mill.
5. A chain block is used to lift the plates into mill.
6. Steps 3 to 5 are repeated for each of the new plates.
7. Iching mill is done for the next slotted plate.
8. The housekeeping is done on the work area.
9. Power is connected back and test run is done.
Figure 4.11: Manhole mill inlet
Figure 4.12: Liners are cut out
60
4.5.2 FEED END LINER AND SHELL LINER RETIGHTEN
Problem
There are loosening bolts and missing bolts at Cement Mill 4. Besides, the old shell liners
also need to be replaced.
Solution
The loosening bolts are retightened and the missing
bolts are replaced with the new one.
Procedure
1. Power is isolated and LOTOTO is applied.
2. All the end liners are retightened.
3. If there is a missing bolt, a new bolt needs to
be fixed.
4. If necessary, iching mill is conducted.
5. Steps 2 to 4 are repeated.
6. Safety precautions; extra precautions need to
be taken when lifting the bolt as it is heavy.
7. Use scaffolding is necessary.
8. Housekeeping the work area.
9. Power is turned ON and LOTOTO is removed.
10. Steps 2 to 9 are repeated for the shell liner.
Figure 4.14: Details are needed to be
written at the tag
Figure 4.13: Locked out, Tagged Out,
Try Out (LOTOTO)
61
4.5.3 ALIGNMENT MOTOR FOR DRIVER RAW MILL 2
Problem
The high vibration is detected at the driver for Raw Mill 2.
Solution
Motor alignment need to be done in order to prevent the motor from being damaged and
the shaft may be broken. Other than that, the vibration of the motor also can be reduced.
Procedure
1. LOTOTO is applied.
2. Safety corner is unlocked and opened.
3. The coupling bolt is jacked by a Jacker.
4. Motor bolt is opened.
5. Do alignment for the motor.
6. Tighten back the motor bolt.
7. Fix back the coupling bolt.
8. Close the safety corner.
9. Tighten the bolt of the safety corner.
Figure 4.15: Motor alignment is done
by a qualified engineer
62
4.5.4 TAKING FLOW RATE READING OF GRINDING AID FOR CEMENT
MILL 3 (CM3)
Problem
During the inspection, it was found that some coatings occurred at the inlet pipe of the
solution
Solution
In order to free the coatings, the pipe is knocked
several times. After that, the flow rate is calibrated
again.
Procedure
1. Pipe transferring the grinding aid is knocked
several times to release the coating.
2. Valve at the pipe transferring the grinding aid
from pump into the mill is opened.
3. By using a stopwatch, time taken for beaker to be filled with 1 Liter is recorded.
4. Steps 2 and 3 are repeated till the required
flow rate is achieved.
Figure 4.16: Cement Mill is
inspected by an
engineer
Figure 4.17: Time taken for grinding aid
to achieve 1 Liter is taken
Figure 4.18: Measuring tube used to
measure the volume of
grinding aid
63
CHAPTER 5: DUST COLLECTOR
5.1 INTRODUCTION
Dust is the primary emission in the manufacture of cement. For the control of dust,
Lafarge employs mechanical collectors, from cyclone collectors to a much smaller size
like gravity settling chambers, fabric type dust collectors, gravel bed filters and finally
electrostatic precipitators. To meet the emission standards, combinations of various
collectors are employed, depending on the intensity and temperature of the effluents.
Dust collectors are evaluated by their efficiencies. The efficiency of dust collector
equipment is the ratio of the quantity of precipitated dust to the total quantity of dust
introduced into the collection device expressed in percentage.
Figure 5.1: Dust collection system in LMC Langkawi
64
5.2 TYPES OF DUST COLLECTORS USED IN LAFARGE LANGKAWI PLANT
5.2.1 GRAVITY SETTLING CHAMBERS
Gravity settling chamber is used for pre-cleaning of high dust laden gases. The chamber
works on the principle of removing the dust by reducing the velocity of the gas or air
stream. The gas is directed from the dust generating equipment into the large volume
settling chamber where velocity drops low enough to let large dust particles drop out by
gravity. Dust settling chambers are equipped with deflectors in order to change the
direction of gas flow and so to shorten the settling path of the particles, improving
collection efficiency. However, only relatively coarse particles are removed. For
removing of fine dust particles for instance in the range of 20 microns, large settling
chambers are required.
Technical Data
Efficiency : 30% – 70%
Gas Velocity : Not exceed 0.5 m/sec
Pressure drop : 5 – 25 mm W.G
65
5.2.2 CYCLONES
Cyclone consists essentially of two sections
which are a cylindrical and a conical one. At
the top of the cylindrical section the gas enters
tangentially and spirals along the walls
downward into the conical section. Then, it starts to occupy the center space of the
cyclone and spirals upward to the outlet thimble.
Centrifugal forces push the dust particles towards the wall where they accumulate and
descend down by gravity. Most of the particles fall down to the bottom into a hopper
where the particles are removed by rotary valves or screw conveyors.
In plant, cyclones are used for application with rotary kiln, clinker coolers, crushers,
dryers, grinding mills, conveyor and others. It can be designed for high throughput and
medium efficiency and medium pressure drop as well as for medium throughput, higher
dust collection efficiency and a higher pressure drop.
Technical Data
Diameters : 300 – 2300 mm
Efficiencies : 96.7 %, 92.6 %, 88.2 % and 57.5 %
Temperature : Up to 975 °C
Pressure drop : 30 – 165 mm
Gas throughput: 17 m3/min (1 cyclone) – 8500 m
3/min (6 cyclones)
Cyclone
Figure 5.2: A cyclone
66
5.2.3 MULTIPLE CYCLONES
Multicyclones are enclosed units and arranged in banks for parallel flow with feed gas
from a plenum chamber and with a common dust discharge hopper. Multicyclones units
can operate up to 400 individual cyclones.
In countries with less stringent air pollution regulations, the Multicyclones is in the
cement industry a major component in collection of dust from kiln gases, grate clinker
coolers, dryers and grinding mills. However, in countries with stricter dust control
regulations, the Multicyclones serve mostly as a primary dust collector ahead of high
efficiency dust collectors.
Technical Data
Efficiency : 85 % – 94 %
Diameter : 15 – 20 micron diameter
Pressure drop : 130 mm – 180 mm
Figure 5.3: A multiple cyclone / multicyclone
67
5.2.4 FABRIC FILTERS
Fabric filters are woven or felted cloth made
from natural or synthetic fibers. Fabric filters
can handle small particles in the submicron
range at high efficiency. Depending on the type
of fabric, the filters can withstand temperature
up to 285 °C.
The dust laden gases flow through a porous
medium of the filter fabrics and deposits particles in the voids. After filling the voids, a
cake starts to build up on the fabric’s surface which does most of the filtering. During the
precoating period which lasts only moments, the efficiency may drop. When the dust
layer on the fabric becomes too thick, an increase in pressure drop results thus requires
cleaning of the fabric.
Cleaning is accomplished periodically mostly response to a timer. During cleaning action
there is no air flow through the filter bag in the normal direction thus requires the
particular dust collector compartment must be taken off-stream.
Air bag fabric filter
Cage of the fabric filter
Figure 5.4: A fabric filter bag
Figure 5.5: A fabric filter bag with its cage
68
Cleaning Method
a. Bag swinging
This method imparts a gentle oscillating motion to the tops of the filter bags thus help to
dislodge the dust cake.
b. Reverse air
This method collapses the filter tube by differential air pressure thus releasing the filter
cake.
c. Pulse pressure
The plenum chamber of the isolated compartment is supplied with a burst of compressed
air. This pulse of air expands rapidly and sets up a shock wave.
d. Sonic cleaning
This method employs sound generators which produce a low frequency sound, causing
the filter bags to vibrate. These vibrations combined with reversed air loosen dust
particles from the surface of the fabric.
Figure 5.6: A pulse pressure fabric filter
69
5.2.5 ELECTROSTATIC PRECIPITATORS
The principle of this type of dust collection is based on the utilization of the effect of gas
ionization in a strong electric field which is formed by discharge electrodes and collecting
electrodes.
With a sufficiently high electrical voltage
between two electrodes, the discharge
electrode begins to emit electrons resulting
in charging the gas molecules surrounding
the electrode in positive and negative ions.
Under the influence of the strong electric
field, the negative ions migrate to the grounded positive or collecting electrode. If the gas
is dust laden, the negative ions impose their charge onto the dust particles which then are
attracted by the positive electrode.
By rapping or vibration, the collected dust is removed from the collecting electrode,
dropping into a dust bin. However, a small part of the dust particles will also be charged
positively and precipitate on the discharge electrode. Therefore for cleaning, the
discharge electrode must also be rapped.
Technical Data
DC voltage : 40 – 80,000 V
Efficiency : 85 % - 90 %
Temperature : 200 °C – 250 °C
Pressure drop : 15 mm – 20 mm
Figure 5.7: An Electrostatic Precipitator
70
5.3 PREVENTIVE MAINTENANCE
5.3.1 CHANGE THE AIR BAG FILTER FOR CEMENT MILL 3 (CM3)
Fabric filtration has been applied for many years before. In essence, a dust bearing gas is
intercepted by a permeable fabric in such manner that all the gas passes through the fabric
whilst the dust impinges on the fibre of the fabric and is thereby retained.
Problem
The increases of emission level are caused by
broken filter bags. Besides, the increase of
emissions also can be caused by leaks in the
tubesheet or internal chambers. For this case, the
air filter bags are broken thus the dust cannot be
fully trapped.
Solution
The broken filter bags need to be replaced with the new filter.
Procedure
1. Power is isolated and LOTOTO is applied.
2. Check for the damaged air bag filter.
3. The broken filter bags are replaced with the new
one.
4. Housekeeping the work area.
5. Turn back the power ON and test run the system.
Figure 5.8: Damaged filter bags are
gathered at one place
Figure 5.9: Dust collector
at CM 3
71
5.3.2 INSPECTION AT COM2 DUST COLLECTOR SYSTEM PURGING AIR
In dust collector system, air is purged to filter bags at 6 mbar to make dust in the filter
bags drop. However, low pressure will cause the dust does not drop and this will damage
the filter bags.
Problem
A weird sound is detected when air is purged in the dust collector system.
Solution
An inspection is done to find the source of the weird sound. The inspection needs
Maintenance Department engineers and Process engineers to work together in order to
run this inspection.
Result
It is found that the weird sound comes from the broken nuts of the dust collector. Besides,
it also found that some leakages occur and purging air system is damaged.
Leakage
Figure 5.10: A leakage is found Figure 5.11: Inside the dust
collector
72
CHAPTER 6: PREHEATER
6.1 INTRODUCTION
Preheater is a device used to heat air before the air is used for another process. With the
primary objective to increase the thermal efficiency, preheater recovers the heat from the
boiler flue gas by reducing the useful heat loss. As a result, the flue gas is also sent to the
flue gas stack at low temperature thus allowing the simplified design of the ducting and
the flue gas stack. It also allows control over the temperature of gases leaving the stack.
There are six standard Dry-process kiln system configurations used in high industry
especially for cement production. The all 6 kiln systems are as below;
a. Suspension Preheater Kiln
b. In-Line Calciner using Excess air
c. In-Line Calciner
d. Separate Line Calciner-Downdraft
e. Separate Line Calciner
f. Separate Line Calciner with In-Line Calciner
Figure 6.1: Preheater towers
73
6.2 MECHANISM
Figure 6.2: Temperature preheater LK2
Multi-Stage Cyclone Preheater
Modern cement manufacturing plant like Lafarge preheats raw meal to calcination
temperature in a multi-stage cyclone preheater. Most of the calcination process takes
place in a separately fired, stationary calciner, while the remaining calcination and
clinkerization process takes place in a rotary kiln.
Raw meal is introduced at the inlet gas duct to the Cyclone I. It is subsequently preheated
by hot, countercurrent gas flow as it is continuously collected and passed down the other
cyclone stages in the preheater to the calciner. Fuel is burned in the calciner to achieve
92-95% of the total material calcination before collection in the bottom cyclone and
entrance into the kiln.
74
Combustion air
Combustion air for the calciner is taken from the kiln via the riser duct and through a
separated tertiary air duct from the cooler. Compared with other conventional preheater,
it’s a very uncomplicated and effective way for FL Smith’s preheater used by Lafarge to
create low NOx emissions with only one firing location, one meal split and one tertiary
air stream entering tangentially to the calciner as the preheater design is based on dividing
the meal from the second-lowest stage cyclone to the kiln riser and the calciner. These
feed points are separated by an expanded riser duct that forms a NOx reducing zone. That
is, the calcining chamber is built into the kiln riser. All of the calciner fuel is introduced
to the kiln riser duct with less oxygen than required for complete combustion, thereby
forming a reducing atmosphere.
Above the reduction zone is the main calciner vessel, which is divided into two or more
sections separated by a notch. The changes in cross-sectional areas create turbulence that
ensures effective mixing of fuel, raw meal and gas, improving heat transfer and
combustion. The calciner outlet loop duct ensures optimum gas retention time, further
mixing and complete fuel combustion section of the calciner. This creates a “hot zone” in
the lower section of the calciner that is conducive to burning difficult fuels and further
NOx reduction.
Combustible waste
Used car tyres and wood chips are used as partial substitution for ordinary types of fuel as
they contain no chemical compounds that might damage clinker quality or affect kiln
operation. Such fuels are normally fed into the kiln riser for subsequent complete
combustion at the kiln inlet.
75
Figure 6.3: Parts of preheater
76
6.3 PREVENTIVE MAINTENANCES
6.3.1 MEASURING TEMPERATURE AND PRESSURE READING
In preheating process, the material will be fed on the top of the preheater and fell into the
ground. In the process of material flows from the top to the bottom, the material will
experience the increase of temperature from as low as 300°C to 1000°C. In order to
maintains an efficient process, temperature, pressure, oxygen and carbon monoxide
readings are taken. This will help engineers to detect if any problem occurs.
Equipments that have been used are digital thermocouple, manometer and Flue Gas
Analyzer. Besides, the tools are steel rod and Pitot tube.
Figure 6.6: Thermocouple
Figure 6.4: The amount of oxygen is
measured by a Fluid Gas
Analyzer
Figure 6.5: Manometer used to
measure pressure
77
6.3.2 COATING LEAKAGE AT SINGLE FLAP DAMPER, HOT MEAL DUCT
Problem
There is a leakage identified at each of the flap damper, Hot Meal Duct in Preheater Line
2 (LK2). The leakages occur at the bearings of the damper.
Implications
The leakage allows fresh air flowing inside the preheater thus affecting the heating
process. If this problem keep occur, it may cost lot to plant as more fuel is needed in keep
maintaining the required heating temperature.
Solution
As the flap damper keep moving, normal glue cannot be used. Thus, silicon glue has been
used to cover the leakages. The ductility of the silicon glue after it dries make it the most
suitable glue to be used to encounter this problem.
Figure 5 A flap damper
Silicon Glue
Figure 6.8: Leakage has been blocked
Figure 6.7: Flap damper
78
6.3.3 TAKE PRESSURE, TEMPERATURE AND AIR FLOWS OF KILN
There are 3 types of flows that have been
calculated which are axial, swirl and coal. All
these flows have been measured its pressure.
It is a need to measure the pressure,
temperature and air flows as this helps
engineers especially for Process Engineers in
determining the exact shape of burning flame
generated in kiln. The correct shape of
burning flame produced will cause an
efficient burning process in kiln thus high
clinker quality and optimum power
consumption can be achieved. The desired
flame for burning is the compact medium-
length flame. In order to obtain the shape,
magnitude of swirl and axial flow need to be the same.
Figure 6.10: A rotating kiln
Figure 6.9: Temperature is measured
by a thermoscan
Figure 6.11: Type of flames in rotating kiln
79
6.3.4 MEASURING THE WET BULB TEMPERATURE
Wet bulb temperature indicates the humidity of air. This temperature indicated by a
moistened thermometer bulb exposed to the air flow. The wet bulb temperature can be
measured by using a thermometer with the bulb wrapped in wet muslin. The rate of
evaporation from the wet muslin on the bulb, and the temperature difference between dry
bulb and wet bulb depends on the humidity of air.
Procedure
1. Coat the wet muslin at the sensor of thermocouple.
2. With half minute intervals, the temperature reading is noted.
3. As the temperature constant, the wet bulb temperature is obtained.
Figure 6.13: Muslin is wet by water
Figure 6.12: A muslin is tied up at thermocouple
80
CHAPTER 7: QUALITY CONTROL
7.1 INTRODUCTION
In the manufacture of cement, proportioning of raw materials is strictly controlled at all
stages to ensure the quality of product well exceeds the quality requirements stipulated in
the relevant standard specification, ISO 9000.
Besides, researches and various tests are keep doing by the Quality Control Team in order
to keep and at the same time enhancing the quality products ordered by customers. Any
complaints regarding to their products are taken serious and further inspections are done
to find the main cause of the problem so that the same problem will not occur again.
ISO 9000
ISO 14001
OHSAS 18001
Figure 7.1: Qualifications obtained by Lafarge Malayan Cement
81
7.2 HARD GRAIN INDEX
Hard Grain Index Test is done to ensure the quality of product in term of fineness. Good
quality of product has not too large nor too small. Good fineness product will provide
cement that will be easily mixed and has great strength.
Step Pictures Descriptions
1
Clinker is filtered until 600 micron clinker is
obtained
2
The clinker then is weighed
3
By using Hard Grove, the clinker is crushed to
small
4
Disc Mill Grinding is used to crush the clinker till
45 micron
5
The index is calculated by using information
obtained
Table 7.1: List of procedures
82
7.3 SIEVE TEST
Sieve test is done in order to determine the size of limestone that has been crushed by
limestone crushers. The appropriate size of limestone is necessary so that the limestone
can be crushed and mixed easily in millers. The most suitable size of limestone for
milling is less than 25mm however limestone size up to 50mm is still acceptable.
Figure 7.2: List of procedures
Samples obtained is filtered by 100mm, 50mm and 25mm
filters
For each of the size obtained, the weight
of it is measured.
The percentage of the weight to the overal weight is calculated
83
7.4 RESIDUE TEST
Residue test is done to ensure the fineness of product that has been produced. This test is
done for both Normal Blaine product and High Blaine product. For Normal Blaine
product, the 2.5g samples is needed while for High Blaine product the 5g samples is
needed.
Figure 7.3: List of procedures
STEP 1
•Normal Blaine product is weighed to the respective weight needed
STEP 2
•The sample then is filtered to obtain 60 micron residue
STEP 3
•The residue is weighed back
STEP 4
•By using formula, the product residue is calculated
84
7.5 DROP TEST
Drop test is a test where the feed rate of each raw materials entering into machines is
calculated. The feed rate is very important in achieving the desired product with optimum
power consumption.
Figure 7.4: List of procedures
STEP 1
• Speed of belt conveyor is measured by a contact tachometer
STEP 2 • Power of the belt conveyor is isolated
STEP 3 • A 1m long is marked on the belt conveyor
STEP 4
• Material in the 1m range is put onto the weigher
STEP 5 • The weight of material is recorded
STEP 6
• By using a formula, the feed rate is calculated
85
CHAPTER 8: PROJECTS
8.1 SEALING AIR FAN FOR CEMENT MILL 4
8.1.1 BACKGROUND
This project covers the following scope of works:
To purchase and install one unit air sealing fan complete with accessories (filter, ducting
etc) to prevent dust from entering into Cement Mill 4 (CM4) combiflex system.
LANGKAWI PLANT CM4 DATA
Cement mill no. 4 (CM4) was commissioned by Krupp Polysius AG in 1997. The mill
that has shell diameter 5200 mm and nominal length 15,000 mm is driven by 2 units of
gear box supplied by Flender AG. In the combiflex system (consist of gear box, girth gear
and supporting equipment) the lubrication oil is sharing between gear box and girth gear
by means of one LO unit system.
Since commissioned, the gear box had been overhauled a few times due to high vibration
as follows:
Year overhauled Reason
Nov 2007 High Vibration
May 2008 Output shaft bearing damage
Aug 2009 Input shaft crack – Total Overhauled (CAPEX)
May 2010 High vibration (Gear Misalignment)
May 2011 High vibration (CAPEX)
Jan 2012 Gear box replaced (CAPEX)
Table 8.1: Maintenance done for Cement Mill
86
After some various brain storming sessions with Lafarge Malayan Cement engineers, dust
ingression into gearbox oil circulation system was shortlisted as one of the main factors
causing the failure. In addition to precautions of reducing suspended dust and improved
lubrication filters, it was decided to incorporate positive pressure dust suppression
systems in gear-gearbox guard sealing.
On most occasions, the Combiflex arrangement is at the mill feed end making the
Combiflex system highly vulnerable to dust contamination. The ingress dust through seal
combines with oil to form clots at the lubrication nozzles for mesh lubrication and bearing
lubrication resulting in lubrication and gearbox components failure. Due to dynamic
application of seal, 100% theoretical sealing of dust ingress is not possible. Additionally,
the abrasive nature of clinker dust in the inlet aggravates the situation further.
The only way to effect 100% sealing from dust ingress in Combiflex system is by
creating a positive air pressure inside the combined gear and gearbox guard. This can be
achieved by installing low pressure high volume blower (forced draft) with discharge
connections directly into the common guard seal areas. The blower inlet is mounted with
suction filter which is regularly cleaned. The individual pipes branching off to the guard
are to be mounted with flow adjustment dampers. This will help in ensuring uniform flow
of air in all sealing areas.
This main objective of this project is to sustain Cement Mill 4 operation and improve mill
reliability by securing CM4 operation from major failure caused by gears damage due to
oil contamination.
87
8.1.2 OBJECTIVE
This main objective of this project is to sustain Cement Mill 4 operation and improve mill
reliability.
8.1.3 EXPECTED BENEFITS
Main benefit is to secure CM4 operation from major failure caused by gears damage due
oil contamination.
8.1.4 COST JUSTIFICATION
The justification for installation of sealing air fan is Strict Sustaining Capital as this work
is essential to sustain the operation of Cement Mill no 4 (CM4). The project cost can be
justified based on loss of maintenance cost due to gearbox repaired as follows
No Equip Year
Overhaul Duration
(day)
Cost (RM)
Specialist Contractor Rental Spare part
Total
1 CM4-No 2
2008 May 14 250000 100000 N/A 150000 500000
2 CM4-No 1
2007 November
15 150000 100000 60000 150000 460000
3 CM4-No 1
2009 August
23 250000 100000 85000 850000 1285000
4 CM4-No 2
2010 May 14 150000 108000 25000 200000 483000
GRAND TOTAL 2,728,000
For year 2011, CM4 mill inlet lubrication oil had been renewed 4 times due to oil badly
contaminated which cost of RM 140 000.
Table 8.2: Project cost justified based on loss of maintenance cost
88
8.1.5 RESOURCE REQUIREMENTS
Budget
Total estimated investment of RM 262,500.00 is required for this project to be
implemented.
The details breakdown of the budget is as follows:
No Part Description Cost (RM) Remark
1 Sealing air fan (1 unit) 40,000 Quotation
2 Air filtering chamber 30,000 Estimation
3 Ducting and other accessories 80,000 Estimation
4 Electrical parts 20,000 Estimation
5 Contractor for installation 80,000 Estimation
6 Contingency cost (5%) 12,500
TOTAL 262,500
Table 8.3: Detail breakdown
89
8.2 TRACING PRESSURE VESSEL TANK IN CEMENT MILL SECTION
8.2.1 INTRODUCTION
In manufacture of cement, the usage of compressed air is very important. The compressed
air is used by almost all parts available in plant especially machines. In Lafarge Malayan
Cement Langkawi Plant, compressed air is generated by 6 units of compressor located in
Silo 4 and Silo 5. From the Silos, the compressed air is flowed to each of the sections in
plants and it then will be distributed to each of parts and machines needed by pressure
vessel tank.
Pressure vessel tank is a closed container designed to hold gases or liquids in transferring
compressed air throughout the entire sections in plant. As pressure may drop when
flowing throughout the system, the pressure vessel tank is important in keep maintaining
the required pressure needed thus machines can keep operating with suitable pressure.
Figure 8.1: A pressure vessel
90
8.2.2 PROBLEM
Damages and malfunction of pressure vessel tanks may cause disruption on operating
machines like millers, grinders and dust collectors. Moreover, a long period taken to trace
and repair the damage pressure vessels may cause the damages of machines plus
unavoidable accidents like pressure vessel tank explosion to occur. This might seem to be
a simple problem however if the problems occur, it might cost lot to plant.
8.2.3 SOLUTION
In order to solve the problems, an initiative to trace each of the pressure vessels in
Langkawi plant is started by Process Department and well supported by LMC Langkawi
Safety and Health Department.
Each of the pressure vessel tanks is traced and the condition of each tanks are remarked in
a proper document for official reference later on. For more easily, a diagram indicates all
tanks available in Cement Mill Sections are drawn. This helps engineers to know where a
pressure vessel tank is located if problems occur.
The official reference document and drawing are attached in Appendix.
91
Figure 8.2: Drawing of Pressure Vessel Tanks for Cement Mill 4
92
8.3 MEASURING THE ACTUAL FAN PERFORMANCE CURVE FOR LK1 AND LK2
8.3.1 INTRODUCTION
Since each type and size of fan has different characteristics, fan performance curve must
be developed by the fan manufacturers.
A fan performance curve is a graphical presentation of the performance of a fan. Usually
it covers the entire range from free delivery (no obstruction to flow) to no delivery (an air
tight system with no air flowing). Generally, these curves are determined by laboratory
tests, conducted according to an appropriate industry test standard, and obtained under
ideal conditions.
The fan curves used to predict the pressure-flow rate performance of each fan. With the
curve also, engineers can determine which fan gives the volumetric flow rate needed for
their system pressure drop. In additions, engineers also can choose fan that has its peak
efficiency at or near to their operating point.
For this special task, I was asked to calculate the actual fan performance curve for Raw
Mill EP fan in Line 2 and Cooler Exhaust Fan. The produced curve will help engineers at
Process Department in analyzing the actual performance at the existing fan thus can
identify and overcome problems occur.
Formula that has been used;
93
8.3.2 LK2 – RAW MILL EP FAN
Figure 8.3: Raw Mill EP fan curve
Figure 8.4: Performance Curve plotted for RM EP Fan
94
8.3.3 LK2 – COOLER EXHAUST FAN
Figure 8.5: Cooler Exhaust Fan curve
Figure 8.6: Performance Curve plotted for Cooler Exhaust Fan
95
8.3.4 DOPOL WASTE GAS FAN
Figure 8.7: Dopol Waste Gas Fan curve
Figure 8.8: Performance Curve plotted for Dopol Waste Gas Fan
96
8.3.5 RAW MILL FAN
Figure 8.9: Raw Mill Fan curve
Figure 8.10: Performance Curve plotted for Raw Mill Fan
97
CHAPTER 9: DISCUSSIONS
9.1 SAFETY AT WORKPLACE
Heavy industries may be a great place to work and earn big salaries however with the
speeds in which events occur mixed with the sum of possible safety hazards, it might be
our own grave.
The Main Dangers at Work Place
Dangers are elsewhere in the site of heavy industries. Dangers could come from our own
negligence, others’ negligence or the condition of the site itself. It can be avoided if all
site hazards are well avoided and safety precautions are seriously taken.
The top hazards recorded in heavy industry are as follows:
1. Trip and fall
This item always makes the top of the list for heavy industry site hazards. Falls from
equipment, scaffolding, and other high places are dangerous and far too common to
occur.
Figure 9.1: Signs of hazards
98
2. Scaffolding
This also causes falls and if put together improperly can cause injuries and death. People
seldom think about heavy industrial equipment safety with respect to equipment that
moves but standstill equipment can be just as dangerous when not used properly.
3. Electrical appliances
This hazard involves all the electrical appliances used seldom in site. Explosion, electrical
shock or electrocution may occur on these appliances if it is not well maintenance. If this
occurs, serious injury and fatality may occur. To prevent this from occur in their
workplace, continuous inspection need to be executed to all electrical appliances used in
their site.
4. Over-exertion and stress
This repetitive use injury has been recorded as the fastest growing type of injury in the
workplace. It is caused by repeating the same actions or maintaining the same position for
a long time. The effects of this problem are unconscious and injuries at wrist hand or
back.
5. Excessive Noise
Most of heavy industries workers are exposed to excessive noise that comes from
operating machines. The louder the noise, the more damage it can cause. The excessive
noise may cause permanent injury like hearing loss either progressively, or by the
exposures over a long period of time. To overcome this, workers need to wear ear buds
when working in a noise site.
99
9.1.1 PERSONAL PROTECTIVE EQUIPMENT (PPE)
PPE which stands for Personal Protective Equipment is defined as equipment which is
intended to be worn or held by a person at work and it protects him against one or more
risks to his health or safety.
Figure 9.2: Basic Personal Protective Equipments
Employers have basic duties concerning the provision and use of personal protective
equipment (PPE) at work and they have no right to ask for money from an employee for
that equipment, whether it is returnable or not. If employment has been terminated and
the employee keeps the PPE without any permission, as long as it has been made clear in
the contract, employer may be able to deduct the cost of replacement from any wages
owed.
To allow the right type of PPE to be chosen, employer need to be carefully consider the
different hazards in the workplace. This will enable them to access which type of PPE are
suitable to protect them against hazard for the job need to be done.
100
9.1.2 SAFETY REPORTING SYSTEM (SRS)
Safety Reporting System (SRS) is an online database which allows members of Lafarge
to share and learn effective and efficiently and at the same time follow up the corrective
actions. Analysis of accident is circulated on weekly basis to all employees throughout
the organization worldwide.
For this reporting system, each members of Lafarge Cement is needed to submit at least 2
reports on any near miss or faulty observed in plant. The report shall be based on
members of Lafarge, contractors, or the plant condition itself which if it is continually
ignored will cause accidents later on.
The structure of the report will be picture of the situations, who involve, time taken, the
location and lastly the estimated cause if it happens. The report then will be sent to the
Safety and Health Department via Lafarge e-mail and it will be strictly checked and
recorded by the department.
To encourage members of Lafarge Cement to join this program and send more reports
monthly, a reward system has been introduced. In this reward system designed by Safety
and Health Department, members who recorded to send higher than 2 reports will be
rewarded with a voucher. This RM50 voucher can be used by members to buy any items
at Teow Soon Huat Shopping Mall located in Kuah, Langkawi.
This reward system has encourages Lafarge members to submit more reports thus
indirectly increases the awareness on the important of safety and hazards at the workplace
amongst them. With the increasing number of report submitted by members compared to
the last few years, the objective is totally achieved.
101
9.2 ENVIRONMENTAL ISSUE
9.2.1 LAFARGE GROUP POLICIES
For Lafarge Cement Group, they keep believe that they will only succeed in the long term
if their actions respect the common interest. This means they must not comply with laws
but also conduct business consistent with sustainable development principles. Thus, they
are committed to the protection of the environment, human health and well-being, to the
migration of climate change and the conservation of nature.
With objective of to ensure the continued improvement of environmental performance,
they aim to use energy and natural resources more efficiently, minimize the production of
waste, harmful air emissions, and water discharge while seeking ways to preserve
landscape and biological diversity.
In order to implement these objectives, Lafarge commits to:
1. Operations
Operate their facilities in a manner that meets local laws, standards and
regulations and the environmental management systems requirements.
Minimize the use of non-renewable resources (feasible and safe) and replace them
with substitute raw materials (alternative fuels or biomass).
Minimize the amount of hazardous and other wastes generated, reuse and recycle
materials where practicable and dispose of wastes using safe and responsible
methods.
Implement programs to prevent accidental releases like having emergency
response action programs in place at all sites.
102
2. Resources, Training, Research
Provide adequate financial and human resources, employee training and
awareness rising to facilitate continuous improvement in environmental
performance.
Take the necessary steps, including sponsoring research, to improve employee’s
knowledge of the environmental impacts of their processes and products.
3. Procurement
Evaluate the environmental values and policies of subcontractor and supplier
candidates as part of the selection process.
Require subcontractors and suppliers to respect our environmental, health and
safety values and comply with Lafarge policies and procedures when present at
plant.
4. Stakeholder relations
Provide stakeholders routinely with environmental information about Lafarge
operations and products in an open manner.
103
9.2.2 LAFARGE MALAYAN CEMENT INITIATIVES
Conserving natural resources – Biomass to energy
Objective
To reduce the cement plant’s consumption of fossil fuel and provide a disposal solution
for the organic wastes generated by palm oil production.
Context
Malaysia is the world’s leading producer of palm oil. Waste from this production (mainly
the palm kernel shells) poses a disposal problem for growers, and is commonly landfilled
or burned with no energy recovery. At the same time, the Rawang and Kanthan cement
plants use large quantities of coal which is imported and used as their primary fuel.
Figure 9.3: CO2 emissions from combustion of the biomass
are considered to be “carbon neutral”.
104
Solution
Lafarge Cement decided to use palm kernel shells as a secondary fuel in its cement kiln.
The equipment needed to receive, sort and grind the palm kernel shells, as well as the
necessary belt conveyors, was installed. The shells are now fed directly into the
precalciner.
Results
This substitution is a means of reclaiming the biomass for energy at a rate of 10% of
overall energy consumption. By reducing the amount of coal burned, the two plants have
cut their aggregate CO2 emissions by 140,000 metric tons per year, given that emissions
generated by combustion of the biomass are considered “carbon neutral”. Finally, the
reduction in imports also means less transport-related pollution.
Figure 9.4: Palm kernel shells are substituted for some
of the coal.
105
Lafarge Roofing – CoolRoof insulating roof system
Objective
To define a construction system appropriate for tropical climates which control heat
transmission from the roof to the living areas of the house.
Context
In warm climates, construction features can make a significant contribution to efforts to
control the indoor temperature of housing units. In conventional construction, the sun’s
radiation on the roof tiles causes heat to be transmitted from the roof to the attic or loft
area, and then down into the living areas. If the house is air conditioned, high
temperatures also have an impact on energy consumption, since more energy is needed to
counterbalance the higher heat load.
Solution
Lafarge developed the Monier CoolRoof, a roofing system that allows a significant
reduction in the indoor temperature of houses. The light color of the roofing tiles limits
Figure 9.5: A conventional roofing system transmits
heat from outside to inside.
106
the heat absorption. Heat is then blocked by a reflective aluminum radiant barrier foil
installed below the roof tiles. The warm air around the radiant barrier is then evacuated by
means of an arrangement consisting of a breathable ridge membrane, counter battens and
ridge tiles. Finally, an insulating material limits the transmission of the remaining heat.
Result
Compared to conventional roofing systems, Monier CoolRoof cuts heat transmission by
more than 80%, lowering the building’s indoor temperature by up to 4°C.
Figure 9.6: CoolRoof provides effective insulation and optimizes
air circulation.
107
CONCLUSION
Internship program at Lafarge Malayan Cement Langkawi Plant was successfully done.
Throughout the program, a lot of experiences, skills and knowledge had been obtained
either related with engineering or not.
While training there, I was exposed to the real working life in heavy industry. In industry
like cement manufacturer, problems and challenges come in many ways. Executives like
engineers need to think the new solutions for each of challenges come in a very short
period. In order to work in this surrounding, they need to have a strong determination for
them to overcome the working pressure.
Moreover, training at Lafarge also gives me an opportunity to understand and applies all
the things that I have learned at UNITEN. Strong foundation in theories needs to be
obtained in order to understand the working principle of each machine operating in plant.
However, it is not a big problem if our foundation is not too strong as each of Lafarge
members stand on their organization’s principle which is learning is a continuously done.
That is why Lafarge members keep learning by attending seminars and training done by
the head quarter. Helps and explanations will be well delivered to trainees if they not
understand in a particular thing.
Finally, I would like to suggest UNITEN to prolong the industrial training period in the
future as 3 months internship is not sufficient for students to well understand and adapt
things occur in an organization. For Lafarge, it is better if each of trainees there is guided
with a planned schedule so that they know what they will learn thus they can prepare
themselves first. The internship program will be more successful if these
recommendations are done in the future.
108
REFERENCES
Books
1. Standard Specification for Portland Cement. Published by the American Society
for Testing Materials. Philadelphia. Pa. USA
2. Sobolewski. 1957. Crushers, Design and Applications. Katowice
3. Der Mechanismus, 1962. Size reduction by impact – Considerations about
performance and sizing of impact crushers, Aufbereitungs-Technik ( p.437-447,
479-490 )
4. 1938. Grinding in Cement Industry Rock Products 1, Rockwood
5. Sullivan. 1927. Passage of Solid Particle Through Rotary Cylindrical Kiln.
Published by US-Bureau of Mines
6. Dersnah. 1956. Ball Coating and Grinding Aids. Published by Portland Cement
Association. Chicago: Illinois
7. Bernutat. P. (1969). Design of Modern Tube Mills and Mechanical Air Separators.
Published by Cement-Wapno-Gips, Warsaw 5 (p.131 – 134)
8. Kannewurf. (1956). Grindability Standard. Published by Portland Cement
Association Report. Chicago
9. Pearson. 1952. Fine Grinding in Tube Mills. Published by Rock Products ( p.106 )
10. Clarke. 1962. Process Engineering Calculations. Published by McGraw – Hill.
New York
11. Tonry. 1961. Heat Transfer Systems for Dry Process Kilns in Cement
Manufacturing. Published by Pit & Quarry. Chicago ( p.151 – 154 )
109
12. 1972. The Development of F.L. Smidth and Co, Published by Cement Technology.
London ( p.14 – 19 )
13. 1983. Pulse Energization of Electrostatic Precipitator of Electrostatic
Precipitators. Copenhagen: Denmark
Websites
1. United States Department of Labor. Confined Space. taken from
http://www.osha.gov/SLTC/confinedspaces/index.html
2. Canadian Centre for Occupational Health and Safety. Confined Space-
Introduction. taken from
http://www.ccohs.ca/oshanswers/hsprograms/confinedspace_intro.html
3. Wikipedia. Confined Space. April 2012. taken from
http://en.wikipedia.org/wiki/Confined_space
4. Binq Inc. Preheater and Calcining System. 2012. taken from
http://www.miningequipments.org/faq/preheater-and-calcining-system/
5. FLSmidth. October 2011. Preheating. Taken from http://www.flsmidth.com/en-
US/Products/Product+Index/All+Products/Cement+Preheating/In
Line+Calciner+Preheater+System/In-Line+Calciner+Preheater+System
6. Wikipedia. Air Preheater. March 2012. taken from
http://en.wikipedia.org/wiki/Air_preheater
7. Magotteaux. Pioneering Solutions. 2010. taken from
http://www.magotteaux.com/wiki-mag/ball-mill/
8. Wikipedia. Ball Mill. May 2012. taken from
http://en.wikipedia.org/wiki/Ball_mill
9. Vipeak. Ball Mill. 2008. taken from http://www.crushingmill.com/ball.html
110
10. ThyssenKrupp Polysius. Raw Material Preparation Brochures. 2010. taken from
http://www.polysius.com/en/publications/brochures/raw-material-preparation/
11. Manufacturing-the cement kiln. Taken from http://www.understanding-
cement.com/kiln.html
12. CIMA. Production Process. 2011. taken from
http://www.cima.com.my/cima/mainpage.php?menu=process
13. Wikipedia. Portland Cement. May 2012. taken from
http://en.wikipedia.org/wiki/Portland_cement
14. CEMBUREAU. Cement Manufacturing Process. taken from
http://www.cembureau.be/about-cement/cement-manufacturing-process
15. Essroc Italcementi Group. Engineering Graduates. 2012.
http://www.essroc.com/default.aspx?pageid=183
16. Lafarge North America. About Cement. taken from
http://www.lafargenorthamerica.com/wps/portal/na/en/2_2_1-
Manufacturing_process
17. Lafarge United Kingdom. All About Cement. 2012. taken from
http://www.lafarge.co.uk/wps/portal/uk/2_2_1-Manufacturing_process
111
Appendix A – SRS RM50 Voucher
112
Appendix B – Worker Pass
(Front)
(Back)
113
Appendix C – Near Miss Report Form
114
Appendix D – Safety Observation Report Form
115
Appendix E – Risk Assessment Form
116
Appendix F – Measurement Overview Sheet for Preheater
117
Appendix G – Cement Mill Lubrication Piping Drawing
118
Appendix H – Shell Liners Arrangement in Cement Mill
119
Appendix I – Purge Air Seal Plan for Cement Mill
120
Appendix J – Type of Shell Liners and Its Arrangement in Cement Mill
121
Appendix K – Drawing Produced for Maintenance Department in Changing New
Shell Liners
122
Appendix L – Traced Pressure Vessel Valve in Cement Mill Section