Innovation in the Comox Valley Meetings, Collaboration and Networking at the Operational Level First Wal-Mart then Home Depot Presented by Kevin Lagan, P. Eng Director of Operational Services City of Courtenay
Transcript
Page 1: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Innovation in the Comox Valley

Meetings, Collaboration and Networking at the Operational Level

First Wal-Martthen

Home Depot

Presented byKevin Lagan, P. Eng

Director of Operational ServicesCity of Courtenay

Page 2: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

City of CourtenayMonthly

Dev Op• Planning/Operations/Building

CVSTAC/CVWTAC• Courtenay/Comox/RDCS

Operations and Admin

CVSC/CVWC• Joint meeting

Bi Monthly

OpComm• Operations/Community

Services (Parks)

CHIPS• Engineering/Planning/MoT/

RCMP

CoOp Traffic/Crash Reduction• Engineering/Planning/MoT/

ICBC/RCMP

BIA/City• Operations/Planning/Building/

BIA

Page 3: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Every 3 months

Municipal Operations• Courtenay• Comox• Campbell River• Cumberland

CoOp• Operations/Parks

Crews

Every 6 months

Op Con• Operations• Consultants

City/School District 71• Senior staff meet

Annual

Courtenay/Comox/RDCS Operations, Planning and Administration

Page 4: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 5: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 6: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 7: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 8: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

How Has Courtenay Prepared For Development?

A Brief 20 year History:1988

1992

1993

• Population approximately 10,500• First qualified Building Inspector employed

• Very active residential and commercial development.

• Land Development Guidelines Provincial/Federal Government.

• Superstore application processed

• First City Engineer employed • Street Trees in Subdivisions Bylaw

Page 9: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

1994 • First Municipal Planner employed• Moratorium on development in North East

Courtenay

Studies Commissioned for 20 Year Horizons for:TransportationWater SupplySanitary SewersStorm Drainage

• DCC Bylaw• City Engineering specifications drafted• First significant rewrite of OCP including D.P.

requirements for commercial, industrial and multi-family

Page 10: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

1995

1996

1998/9

• City Hall catches fire and is demolished

• Work begins on infrastructure upgrading

• Tree Management Protection Bylaw

• 50 yr then 100 yr storms one year apart

• City expends $2.5 m on storm drainagesystem upgrades

Page 11: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

2000

2002

2003

2004

• Wal-Mart rezoning application

• Wal-Mart opens• Courtenay becomes member of

WBM for BC

• Home Depot rezoning application

• Home Depot Opens• OCP rewrite• Updated 20 year Studies for:

Water SupplySanitary SewersStorm Drainage

Page 12: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

2005

2006

2007

• Environmental D.P. requirements in OCP Bylaw

• 300 mm topsoil requirement for landscaped areas and between tree roots and 450 mm topsoil for shrub areas

• Rewrite of Soil Deposit/Removal Bylaw• Riparian Area Requirements in OCP Bylaw• Courtenay/Comox MOU on areas of

interest• Updated 20 year City Transportation Study

• RDCS, Courtenay, Comox agreement on sustainability

• Maximum building height review• Courtenay population approximately

23,000 119% increase since 1988

Page 13: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Wal-Mart Development9.3 ha site on which one old single family home located

Rezoning was required to allow the development to occur

Public hearings 16 hours of presentations

City worked with our municipal lawyers and drafted a Comprehensive Development Agreement (CDA) and Land Development Covenant (LDC)

Documentation included automatic rezoning after 60 days, amenitypackage of $600,000, advertising on site of downtown Courtenay area

Also included were all the off-site road work, municipal utilities, private utilities, and environmental monitoring

Page 14: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

As the development was adjacent to the Millard Creek any loss of precipitation to the catchments area was critical.

The precipitation falling on the roof area of Wal-mart, Winners and Staples (approx. 1.2 hectares) is captured, passed through an oil/grit interceptor and then discharged to a artificial aquifer running the length of the west side of the development.

The precipitation from the other roof areas is collected, passed through an oil/grit interceptor and discharged into an engineered wetland/detention pond (built by the developers) prior to discharging into Millard Creek.

Page 15: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

ON-SITE SERVICING PLAN

Page 16: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

ARTIFICIAL AQUIFER DETAIL

PRO

PERT

Y LI

NE

TYPICAL Ex. ELEVATION AT PROPERTY LINE 20.3 m

3.00 + /-

15.14

SLAB 21.50 m

SUB-GRADE 21.10 m

FOUNDATION STRUCTURE

FINISHED GRADE AT 22.20 m

COMPACTED GRAVEL ROAD BASE

FINISHEDASPHALT SURFACE

17.35

SWALE 4.70

TELUS 8.91

WATER 6.91GAS 7.91

HYDRO 9.91

AQUIFER CONSTRUCTION - PHASE 2

INSTALL SILT FENCE ALONG FULL LENGTH OF E & N R/W BOUNDARY TO MINISTRY OF ENVIRONMENT LANDS AND PARKS/DEPARTMENT OF FISHERIES AND OCEANS SPECIFICATIONS.

STRIPPED SURFACE

100 DIA. SCREENED PIEZOMETER c/w NELSON BOXES (3 REQUIRED)

300 mm DEEP TOPSOIL AND SEED

2:1

0.50

TOP OF SAND AQUIFER AT 20.90 m

STRUCTURAL FILL MATERIAL

PERIMETER FOOTING DRAINS TO FLOW TO FRONT OF BUILDING

NATIVE BACKFILL

INSTALL "40 MIL" THICK HIGH DENSITY POLYETHYLENE DRAINAGE CURTAIN BARRIER ALONGSIDE FULL LENGTH OF AQUIFER. MINIMUM 2.0 m ROLL WIDTH. ANY SEAMS TO BE WELDED AS PER MATERIAL SUPPLIER'S INSTRUCTIONS.

PREVIOUSLY INSTALLEDSAND AQUIFER MATERIAL BY GRADING CONTRACTOR

NON-WOVEN GEOTEXTILE FILTER FABRIC - NILEX 4551OR EQUAL BETWEEN SAND AND OVERLYING FILL FULLY COVERING ENTIRE SAND AQUIFER ZONE

375 mm PERFORATED PIPE IN DRAIN ROCK c/w FILTER FABRIC SURROUNDINVERT 20.50

PLACE COMPACTED CLEAN WASHED BEDDING SAND UP TO 20.90 m. (REMAINDER OF SAND AQUIFER)

SECTION A-A

Page 17: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 18: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 19: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 20: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 21: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 22: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 23: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 24: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 25: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 26: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 27: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 28: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Home Depot Development4.0 hectare treed lot 10,800 m² building

Roof areas and pavement cover 90% of the site

Pre planning, on site and off site works agreed with developer.

Rezoning application drafted, works, services, and amenity contribution of $300,000 detailed in LDC and CDA.

Site is at the head of the Brooklyn Creek catchment area. The creek flows through Courtenay, RDCS area ‘B’ and Comox.

Page 29: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Home Depot Development

Immediately downstream of the site is the Crown Isle development where a series of golf water hazards/storm drainage detention ponds discharge into Lake 20. All flows into and out of the system have a fixed limit for a 10 year storm event.

On-site roof drainage is controlled and piped to a oil/grit interceptor. It is then piped to an exfiltration gallery and the excess flows connected to a deep well injection system.

The east loading access road is sloped away from the building into a bio swale.

Page 30: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

Home Depot Development

The parking lot surface water is collected, passed through an oil/grit interceptor and then piped through perforated pipes which bleed water into imported sands. The excess flows are then directed to a second deep well injection system.

In addition to this on-site system is a municipal system designed to accept the entire site surface flows.

For a one in two year storm event almost no precipitation discharges into the municipal surface water system.

The CDA provides for 5 years of semi-annual independent monitoring by a geotechnical consultant for the water quality in the deep wells.

Page 31: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 32: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 33: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 34: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 35: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 36: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 37: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 38: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 39: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 40: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full
Page 41: Innovation in the Comox Valley Meetings, Collaboration and ... · swale 4.70 telus 8.91 water 6.91 gas 7.91 hydro 9.91 aquifer construction - phase 2 install silt fence along full

SITE VISITS IN COURTENAY

1. Veterans Memorial ParkwayEngineered wetland/detention pondFindley Creek Tributary storm water separationHabitat compensation for the Red Legged Frog

2. Muir Road Development Findley Creek flow augmentation and community detention ponds