+ All Categories
Home > Documents > Inspections, Tests and Safety Considerations

Inspections, Tests and Safety Considerations

Date post: 20-Jul-2016
Category:
Upload: rizviabbas2012
View: 22 times
Download: 1 times
Share this document with a friend
Description:
inspection doc
44
Published by The Plastics Pipe Institute, Inc. Inspections, Test and Safety Considerations
Transcript
Page 1: Inspections, Tests and Safety Considerations

Published by The Plastics Pipe Institute, Inc.

Inspections, Testand

Safety Considerations

Page 2: Inspections, Tests and Safety Considerations

©Copyright, The Plastics Pipe Institute, Inc. 1999

Page 3: Inspections, Tests and Safety Considerations

i

Table of Contents

Foreword iv

Scope 1

Introduction 1

Handling and Storage 2

Receiving Inspection 2

Product Packaging 3

Checking the order 4

Load Inspection 5

Receiving Report & Reporting Damage 6

Unloading Instructions 6

Unloading Site Requirements 7

Handling Equipment 7

Unloading Large Fabrications, Manhole and Tanks 8

Pre-Installation Storage 9

Pipe Stacking Heights 10

Exposure to UV and Weather 11

Cold Weather Handling 11

General Conditions During Installation 12

Joining and Connections 12

Field Joining 12

Cleaning 13

Field Fusion Joining 13

Field Handling 14

Inspection and Testing 15

Pre-Construction 15

During Construction 15

Butt Fusion Joint Quality 15

Inspections, Tests and Safety Considerations

Page 4: Inspections, Tests and Safety Considerations

ii

Table of Contents (cont’d)Soil Tests 17

Pipe surface Damage 17

Deflection Tests 18

Post Installation 20

Leak Testing 20

Pressure Test Precautions 21

References 21

Test Pressure 22

Test Duration 22

Pre-Test Inspection 22

Hydrostatic Testing 23

Monitored Make-up Water Test 23

Non-monitored Make-up Water Test 24

Pneumatic Testing 24

High Pressure Procedure 25

Low Pressure Procedure 25

Initial Service Testing 26

Test Procedure 26

Non-Testable Systems 26

Considerations for Post Start-Up and Operation 26

Disinfecting Water Mains 26

Cleaning 27

Squeeze-Off 27

Tools 28

Key Elements 29

Procedure 30

Routine or Emergency? 32

Repairs 33

Page 5: Inspections, Tests and Safety Considerations

iii

Table of Contents (cont’d)Damage Assessment 33

Permanent Repairs 34

Temporary Repairs 35

Conclusion 35

References 36

List of IllustrationsFigure Page

Figure 1 Typical Silo Pack Truckload (40' Trailer) 3

Figure 2 Typical Bulk Pack Truckload (40' Trailer) 4

Figure 3 Typical Strip Load Truckload (40' Trailer) 5

Figure 4 Forklift Load Capacity 8

Figure 5 Loose Pipe Storage 9

Figure 6 Bent Strap Test Specimen 16

Figure 7 Determining Initial Deflection 18

Figure 8 Squeeze-off Stresses 30

Figure 9 Constrained Pipe Repair 34

List of TablesTable Page

Table I Suggested Jobsite Loose Storage StackingHeights for Conventionally Extruded Pipe Lengths 9

Table II Suggested Jobsite Loose Storage StackingHeights for Extruded Profile Pipe 10

Table III Test Phase Make-up Amount 23

Table IV Squeeze Tool Bar Radius 29

Page 6: Inspections, Tests and Safety Considerations

iv

ForewordInspections, Tests and Safety Considerations is one of the chapters in the

Plastics Pipe Institute’s PPI Handbook of Polyethylene Piping. Other topicsaddressed in the handbook include design and installation of polyethylenepiping systems, joining procedures, and relevant codes and standards.

The PPI Handbook of Polyethylene Piping is produced by the PPI Municipaland Industrial (M&I) Division. M&I membership consists of major North Americanmanufacturers of polyethylene (PE) pipe and fittings, PE piping materials,machinery, and equipment used for joining and installing PE piping, relatedtest laboratories, and professional organizations.

PPI maintains additional divisions that address other applications such asgas distribution. PPI and its divisions provide technical and promotional supportfor the effective use and continued application of thermoplastics pipe andrelated products, consistent with the best public interest. PPI membershipalso includes producers of polyvinyl chloride (PVC), chlorinated polyvinyl chloride(CPVC), polybutylene (PB) and crosslinked PE (PEX) piping products andmaterials.

For a list of other publications available from PPI and/or further information,please contact:

The Plastics Pipe Institute, Inc.Toll free: 1-888-314-6774

http://www.plasticpipe.org

The information in this publication was prepared by PPI as a service toits members and the industry. While prepared in good faith and believed tobe accurate, PPI, its members, and contributors disclaim all liability for anyloss or damage arising from reliance on this information by any person. PPIdoes not endorse the proprietary products or processes of any manufacturer.Consult the product manufacturer for specific information.

October 1999

Page 7: Inspections, Tests and Safety Considerations

Inspections, Tests and SafetyConsiderations

Once a polyethylene piping system has been selected and designed foran application, the design is implemented by securing the pipe, fittings andother necessary appurtenances, installing the system, and placing it in ser-vice. Piping installation involves setting various parts, people, and machinesin motion to obtain, assemble, install, inspect and test the piping system.Whenever machinery, piping parts, and personnel are engaged in pipingsystem construction, safety must be a primary consideration.

This chapter presents some of the inspections, tests and safetyconsiderations related to installing polyethylene piping, placing an installedsystem in service, and operating a polyethylene piping system.

This chapter does not purport to address all of the productapplications, inspections, tests, or construction practicesthat could be used, nor all of the safety practices necessaryto protect persons and property. It is the responsibility ofthe users of this chapter, and the installers, inspectorsand operators of piping systems to establish appropriatesafety and health practices, and to determine theapplicability of regulatory limitations before any use,installation, inspection, test or operation.

Generally, piping system installation begins with obtaining the pipe, fittings,and other goods required for the system. Assembly and installation follow,then system testing and finally, release for operation. Throughout theinstallation process, various inspections and tests are performed to ensureinstalled system quality, and that the system when completed is capable offunctioning according to its design specifications. In the selection, design,and installation of polyethylene piping systems, professional engineeringservices, and qualified installers should be used.

Inspections, Tests and Safety ConsiderationsPage 1

Scope

Introduction

Page 8: Inspections, Tests and Safety Considerations

Polyethylene piping products are integrated pipe and fitting systems fora broad range of commercial, municipal, utility and industrial applications.They may be buried, laid on the surface, supported above grade, installedunderwater, or floated on the surface of lakes or rivers.

Polyethylene piping products are manufactured from 1/4" (6 mm) diameterthrough 120" (3050 mm) diameter under applicable industry standards(ASTM, AWWA, etc.) for pressure, non-pressure and low pressureapplications. As well, polyethylene fittings, custom fabrications, specialstructures and appurtenances are available for full pressure rated, reducedpressure rated, or non-pressure rated applications.

Conventionally extruded polyethylene pipes have homogeneous wallsand smooth interior and exterior surfaces. Profile pipes are manufacturedby extruding a profile over a mandrel. These pipes have smooth interiors,and may have a smooth or a profiled exteriors. Profile pipes are primarilyapplied to non-pressure or low pressure applications.

Fittings, fabricated structures, tanks, and manholes are constructed forpressure, low pressure and non-pressure applications. Smaller size fittingsare usually injection molded. Larger fittings, fabricated structures, tanks,and manholes are fabricated in manufacturer’s facilities. Thermal joiningtechniques used for fabrication usually limit the design pressure capacity ofthe structure. Complex structures are generally not suitable for fieldfabrication.

After the piping system has been designed and specified, the pipingsystem components must be obtained. Typically, project management andpurchasing personnel work closely together so that the necessarycomponents are available when they are needed for the upcomingconstruction work.

Receiving Inspection

Few things are more frustrating and time consuming than not havingwhat you need, when you need it. Before piping system installation begins,an important initial step is a receiving inspection of incoming products.Construction costs can be minimized, and schedules maintained by checking

Inspections, Tests and Safety ConsiderationsPage 2

Handling and Storage

Page 9: Inspections, Tests and Safety Considerations

incoming goods to be sure the parts received are the parts that were or-dered, and that they arrived in good condition and ready for installation.

Polyethylene pipe, fittings, and fabrications are shipped by commercialcarriers who are responsible for the products from the time they leave themanufacturing plant until they are accepted by the receiver. Pipe andfabricated fittings and structures are usually shipped on flatbed trailers.Smaller fittings may be shipped in enclosed vans, or on flatbed trailersdepending upon size and packaging. Molded fittings are usually boxed, andshipped by commercial parcel services.

Product Packaging

Depending on size, polyethylene piping is produced in coils or in straightlengths. Coils are stacked together into silo packs. Straight lengths arebundled together in bulk packs or loaded on the trailer in strip loads. Standardstraight lengths for conventionally extruded pipe are 40' long, however,lengths up to 60' long may be produced. Profile extruded pipes are typicallyproduced in 20' lengths. State transportation restrictions on length, heightand width usually govern allowable load configurations. Higher freight costswill apply to loads that exceed length, height, or width restrictions. Althoughpolyethylene pipe is lightweight, weight limitations may restrict load size forvery heavy wall or longer length pipe.

Inspections, Tests and Safety ConsiderationsPage 3

Pallet Silo Pack

Figure 1 Typical Silo Pack Truckload (40’ Trailer)

Page 10: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 4

Extruded profile pipe lengths are usually shipped on standard 40' flatbedtrailers. Pipes are commonly packaged in bundles or as strip loads. Pipes96" ID (2438 mm ID) and 120" ID (3048 mm ID) will exceed 8' overall width,and are subject to wide load restrictions.

Figures 1 through 3 are general illustrations of truckload and packagingconfigurations. Actual truckloads and packaging may vary from theillustrations.

Small fittings are packaged in cartons which may be shipped individuallyby package carriers. Large orders may be palletized and shipped in enclosedvans. Large fittings and custom fabrications may be packed in large boxeson pallets, or secured to pallets.

Occasionally, when coiled pipe silos and boxed fittings are shippedtogether, fitting cartons are placed in the center of the silo packs. Tanks,manholes, and large fittings and custom fabrications are usually loadeddirectly onto flatbed trailers.

Checking the Order

When a shipment is received, it should be checked to see that the correctproducts and quantities have been delivered. Several documents are used

Bulk Pack

Figure 2 Typical Bulk Pack Truckload (40’ Trailer)

Page 11: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 5

here. The Purchase Order or the Order Acknowledgment lists each item byits description, and the required quantity. The incoming load will be describedin a Packing List which is attached to the load. The descriptions and quantitieson the Packing List should match those on the Purchase Order or the OrderAcknowledgment.

The carrier will present a Bill of Lading that generally describes the loadas the number of packages the carrier received from the manufacturing plant.The Order Acknowledgment, Packing List, and Bill of Lading should all be inagreement. Any discrepancies must be reconciled among the shipper, thecarrier, and the receiver. The receiver should have a procedure for reconcilingany such discrepancies.

Load Inspection

There is no substitute for visually inspecting an incoming shipment toverify that the paperwork accurately describes the load. Products are usuallyidentified by markings on each individual product. These markings shouldbe checked against the Order Acknowledgment and the Packing List. Thenumber of packages and their descriptions should be checked against theBill of Lading.

Strip Load Pack

Layer SeperationDunnage

Figure 3 Typical Strip Load Truckload (40’ Trailer)

Page 12: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 6

This is the time to inspect for damage which may occur anytime productsare handled. Obvious damage such as cuts, abrasions, scrapes, gouges,tears, and punctures should be carefully inspected.

When pipe installation involves saddle fusion joining, diesel smoke onthe pipe’s outside surface may be a concern because it may reduce thequality of saddle fusion joints. Smoke damage is effectively prevented bycovering at least the first third of the load with tarpaulins. If smoke tarps arerequired, they should be in place covering the load when it arrives.

Receiving Report & Reporting Damage

The delivering truck driver will ask the person receiving the shipment tosign the Bill of Lading, and acknowledge that the load was received in goodcondition. Any damage, missing packages, etc., should be noted on the billof lading at that time.

Shipping problems such as damage, missing packages, documentdiscrepancies, incorrect product, etc., should be reported to the productsupplier immediately. Shipping claims must be filed within 7 days.

Unloading Instructions

Before unloading the shipment, there must be adequate, level space tounload the shipment. The truck should be on level ground with the parkingbrake set and the wheels chocked. Unloading equipment must be capableof safely lifting and moving pipe, fittings, fabrications or other components.

WARNING: Unloading and handling must be performedsafely. Unsafe handling can result in damage to propertyor equipment, and be hazardous to persons in the area.Keep unnecessary persons away from the area duringunloading.

WARNING: Only properly trained personnel should operateunloading equipment.

Page 13: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 7

Unloading Site Requirements

The unloading site must be relatively flat and level. It must be largeenough for the carrier’s truck, the load handling equipment and its move-ment, and for temporary load storage. Silo packs and other palletized pack-ages should be unloaded from the side with a forklift. Non-palletized pipe,fittings, fabrications, manholes, tanks, or other components should be un-loaded from above with lifting equipment and wide web slings, or from theside with a forklift.

Handling Equipment

Appropriate unloading and handling equipment of adequate capacity mustbe used to unload the truck. Safe handling and operating procedures mustbe observed.

Pipe must not be rolled or pushed off the truck. Pipe, fittings,fabrications, tanks, manholes, and other components must notbe pushed or dumped off the truck, or dropped.

Although polyethylene piping components are lightweight compared tosimilar components made of metal, concrete, clay, or other materials, largercomponents can be heavy. Lifting and handling equipment must haveadequate rated capacity to lift and move components from the truck totemporary storage. Equipment such as a forklift, a crane, a side boom tractor,or an extension boom crane is used for unloading.

When using a forklift, or forklift attachments on equipment such asarticulated loaders or bucket loaders, lifting capacity must be adequate atthe load center on the forks. Forklift equipment is rated for a maximumlifting capacity at a distance from the back of the forks. (See Figure 4.) If theweight-center of the load is farther out on the forks, lifting capacity is reduced.

Before lifting or transporting the load, forks should be spread as wideapart as practical, forks should extend completely under the load, and theload should be as far back on the forks as possible.

WARNING: During transport, a load on forks that are tooshort or too close together, or a load too far out on theforks, may become unstable and pitch forward or to theside, and result in damage to the load or property, orhazards to persons.

Page 14: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 8

Lifting equipment such as cranes, extension boom cranes, and side boomtractors, should be hooked to wide web choker slings that are secured aroundthe load or to lifting lugs on the component. Only wide web slings should beused. Wire rope slings and chains can damage components, and shouldnot be used. Spreader bars should be used when lifting pipe or componentslonger than 20'.

WARNING: Before use, inspect slings and liftingequipment. Equipment with wear or damage that impairsfunction or load capacity should not be used.

Unloading Large Fabrications, Manholes and Tanks

Large fabrications, manholes and tanks should be unloaded using a wideweb choker sling and lifting equipment such as an extension boom crane,crane, or lifting boom. The choker sling is fitted around the manhole riser ornear the top of the tank. Do not use stub outs, outlets, or fittings as liftingpoints, and avoid placing slings where they will bear against outlets or fittings.Larger diameter manholes and tanks are typically fitted with lifting lugs.

WARNING: ALL lifting lugs must be used. The weight ofthe manhole or tank is properly supported only when alllugs are used for lifting. Do not lift tanks or manholescontaining liquids.

Figure 4 Forklift Load Capacity

RatedLoad

Capacity

ReducedLoad

Capacity

Page 15: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 9

Pre-Installation Storage

The size and complexity of the project and the components, will determinepre-installation storage requirements. For some projects, several storageor staging sites along the right-of-way may be appropriate, while a singlestorage location may be suitable for another job.

The site and its layout should provide protection against physical damageto components. General requirements are for the area to be of sufficientsize to accommodate piping components, to allow room for handlingequipment to get around them, and to have a relatively smooth, level surfacefree of stones, debris, or other material that could damage pipe orcomponents, or interfere with handling. Pipe may be placed on 4-inch widewooden dunnage, evenly spaced at intervals of 4 feet or less.

Pipe Size Suggested Stacking Height* - Rows

DR Above 17 DR 17 & Below

4 15 125 12 106 10 88 8 6

10 6 512 5 414 5 4

Table I – Suggested Jobsite Loose Storage Stacking Heightsfor Conventionally Extruded Pipe Lengths (Ref. 1)

Figure 5 Loose Pipe Storage

Blocking prevents movement

Width to suit

# Rows per Table Ior Table II

Straight Pipes not tangled upor crossing over each other

Page 16: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 10

*Stacking heights based on 6' for level terrain and 4' for less level terrain

Pipe Size Suggested Stacking Height*Rows

18 421 324 327 230 233 236 242 148 154 160 166 172 184 196 1

120 1*Suggested stacking heights based on 6' for level terrain and 4' for less level terrain.

Pipe Size Suggested Stacking Height* - Rows

DR Above 17 DR 17 & Below

16 4 318 4 320 3 322 3 224 3 226 3 228 2 230 2 232 2 236 2 142 1 148 1 154 1 163 1 1

Pipe Stacking HeightsCoiled pipe is best stored as-received in silo packs. Individual coils may be

removed from the top of the silo pack without disturbing the stability of the remainingcoils in the silo package.

Table II – Suggested Jobsite Loose Storage Stacking Heights for Extruded Profile Pipe (Ref. 2)

Page 17: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 11

Pipe received in bulk packs or strip load packs should be stored in thesame package. If the storage site is flat and level, bulk packs or strip loadpacks may be stacked evenly upon each other to an overall height of about6'. For less flat or less level terrain, limit stacking height to about 4'.

Before removing individual pipe lengths from bulk packs or strip loadpacks, the pack must be removed from the storage stack, and placed on theground.

Individual pipes may be stacked in rows. Pipes should be laid straight,not crossing over or entangled with each other. The base row must beblocked to prevent sideways movement or shifting. (See Figure 5, Table I,and Table II.) The interior of stored pipe should be kept free of debris andother foreign matter.

Exposure to UV and Weather

Polyethylene pipe products are protected against deterioration fromexposure to ultraviolet light and weathering effects. Color and black productsare compounded with antioxidants, thermal stabilizers, and UV stabilizers.Color products use sacrificial UV stabilizers that absorb UV energy, and areeventually depleted. In general, non-black products should not remain inunprotected outdoor storage for more than 2 years, however, somemanufacturers may allow longer unprotected outside storage. Black productscontain at least 2% carbon black to protect the material from UV deterioration.Black products with and without stripes are generally suitable for unlimitedoutdoor storage and for service on the surface or above grade. (Ref. 11, 12,13, & 14)

Cold Weather Handling

Temperatures near or below freezing will affect polyethylene pipe byreducing flexibility and increasing vulnerability to impact damage. Care shouldbe taken not to drop pipe, or fabricated structures, and to keep handlingequipment and other things from hitting pipe. Ice, snow, and rain are notharmful to the material, but may make storage areas more troublesome forhandling equipment and personnel. Unsure footing and traction requiregreater care and caution to prevent damage or injury.

Walking on pipe can be dangerous. Inclement weather can make pipesurfaces especially slippery.

Page 18: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 12

WARNING: Keep safety first on the jobsite; do not walk on pipe.

Joining and Connections

For satisfactory material and product performance, system designs andinstallation methods rely on appropriate, properly made connections. Aninadequate or improperly made field joint may cause installation delays, maydisable or impair system operations, or may create hazardous conditions.

Polyethylene piping products are connected using heat fusion,electrofusion, thermal welding, and mechanical methods such as gasketedbell-and-spigot joints, flanges, and compression couplings. Joining andconnection methods will vary depending upon requirements for internal orexternal pressure, leak tightness, restraint against longitudinal movement(thrust load capacity), gasketing requirements, construction and installationrequirements, and the product.

Connection design limitations and manufacturer’s joiningprocedures must be observed. Otherwise, the connectionor products adjacent to the connection may leak or failwhich may result in property damage, or hazards topersons.

The tools and components required to construct and install joints inaccordance with manufacturer’s recommendations should always be used.However, field connections are controlled by, and are the responsibility ofthe field installer.

A complete discussion on joining and connecting polyethylene pipingproducts is presented in PPI’s Handbook of Polyethylene Pipe, chapterentitled “Polyethylene Joining Procedures”. (Ref. 3)

Field Joining

All field connection methods and procedures require that the componentends to be connected must be clean, dry, and free of detrimental surfacedefects before the connection is made. Contamination and unsuitable surfaceconditions usually produce an unsatisfactory connection. Gasketed jointsmay require appropriate lubrication.

General Considerations During Installation

Page 19: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 13

Cleaning

Before joining, and before any special surface preparation, surfaces mustbe clean and dry. General dust and light soil may be removed by wiping thesurfaces with clean, dry, lint free cloths. Heavier soil may be washed orscrubbed off with soap and water solutions, followed by thorough rinsingwith clear water, and drying with dry, clean, lint-free cloths.

WARNING: Before using chemical cleaning solvents, thepotential risks and hazards to persons should be knownby the user, and appropriate safety precautions must betaken. Chemical solvents may be hazardous substancesthat may require special handling and personal protectiveequipment.

The manufacturer’s instructions for use, and the material safety datasheet (MSDS) for the chemical should be consulted for information on risksto persons and for safe handling and use procedures. Some solvents mayleave a residue on the pipe, or may be incompatible with the material. SeePPI Technical Report TR-19, Thermoplastics Piping for the Transport ofChemicals for additional information on chemical compatibility of polyethylenematerials. (Ref. 4)

Field Fusion Joining

Heat fusion joining requires specialized equipment for socket, saddle, orbutt fusion, or electrofusion. Heat fusion joining may be performed in anyseason. During inclement weather, a temporary shelter should be set-upover the joining operation to shield heat fusion operations from rain, frozenprecipitation, and cold winds.

WARNING: Most heat fusion equipment is not explosion-proof. The fusion equipment manufacturer’s safetyinstructions must be observed at all times and especiallywhen heat fusion is to be performed in a potentially volatileatmosphere.

WARNING: When installing large diameter polyethylenepipe in a butt fusion machine, do not bend the pipe againstan open fusion machine collet or clamp. The pipe maysuddenly slip out of the open clamp, and cause injury ordamage.

Page 20: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 14

Field Handling

Polyethylene pipe is tough, lightweight, and flexible. Installation doesnot usually require high capacity lifting equipment. See Handling and Storagefor information on handling and lifting equipment.

WARNING: To prevent injury to persons or property, safehandling and construction practices must be observed atall times. The installer must observe all applicable Local,State, and Federal Safety Codes, and any safetyrequirements specified by the owner or the projectengineer.

Pipe up to about 8" (219 mm) diameter and weighing roughly 6 lbs perfoot (20 kg per m) or less can usually be handled or placed in the trenchmanually. Heavier, larger diameter pipe will require appropriate handlingequipment to lift, move and lower the pipe. Pipe must not be dumped,dropped, pushed, or rolled into a trench.

WARNING: Appropriate safety precautions must beobserved whenever persons are in or near a trench.

Coiled lengths and long strings of heat fused polyethylene pipe may becold bent in the field. Field bending usually involves sweeping or pulling thepipe string into the desired bend radius, then installing permanent restraintsuch as embedment around a buried pipe, to maintain the bend.

WARNING: Considerable force may be required to fieldbend the pipe, and the pipe may spring back forcibly ifholding devices slip or are inadvertently released whilebending. Observe appropriate safety precautions duringfield bending.

These paragraphs have attempted to convey the primary safetyand handling considerations associated with joining and connectingpolyethylene pipe. For a more thorough discussion on the joiningmethods used with polyethylene pipe, the reader is referred to PPI’sHandbook of Polyethylene Pipe, Polyethylene Joining Procedureschapter.

Page 21: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 15

Inspections and tests begin before construction. Jobsite conditions dictatehow piping may be installed and what equipment is appropriate forconstruction. Soil test borings and test excavations may be useful todetermine soil bearing stress and whether or not native soils are suitable asbackfill materials.

In slipline rehabilitation applications, the deteriorated pipeline should beinspected by remote TV camera to locate structurally deteriorated areas,obstructions, offset and separated joints, undocumented bends, and serviceconnections. In some cases, a test pull, drawing a short section of sliplinerthrough the line, may be conducted to ensure that the line is free ofobstructions.

The installer should carefully review contract specifications and plans. Itis important that the specifications and plans fit the job. Different pipingmaterials require different construction practices and procedures. Thesedifferences should be accurately reflected in the contract documents. Goodplans and specifications help protect all parties from unnecessary claimsand liabilities. Good documents also set minimum installation qualityrequirements, and the testing and inspection requirements that apply duringthe job.

All incoming materials should be inspected to be sure that sufficientquantities of the correct products for the job are at hand, and that they arrivedin good condition, ready for installation.

During Construction

Tests and inspections performed during construction include butt fusionjoint quality tests, soil compaction and density tests, pipe deflection tests,pressure tests, and other relevant inspections. Fusion joint qualification andinspection guidelines for butt, socket and saddle fusions should be obtainedfrom the pipe or fitting manufacturer.

Butt Fusion Joint Quality

Visual inspection is the most common joint evaluation method for all sizesof conventionally extruded polyethylene pipe. Visual inspection criteria forbutt fusion joints should be obtained from the pipe manufacturer. Computercontrolled ultrasonic inspection equipment is available for 12" IPS and smallerpipes with walls 1" or less in thickness. Equipment for larger diameters andwall thickness is being developed. X-ray inspection is generally unreliablebecause x-ray is a poor indicator of fusion quality.

Pre-ConstructionInspection and Testing

Page 22: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 16

Cold fusion is a poor quality joint that should be removed and re-done. Ifnot repaired, joint failure can occur.

When butt fusion is between pipe and molded fittings, the fitting-sidebead may exhibit shape irregularities which are caused by the fittingmanufacturing process. A slightly irregular fitting-side bead may not indicatean improper joint, provided that the pipe-side bead is properly shaped, andthe v-groove between the beads is correct. Contact the pipe or fittingmanufacturer if assistance is required.

Fusion joining may be destructively tested to confirm joint integrity,operator procedure, and fusion machine set-up. A field-performed destructivetest is a bent strap test.

The bent strap test specimen is prepared by making a trial butt fusion,usually the first fusion of the day, and allowing it to cool to ambienttemperature. A test strap that is at least 6" or 15 pipe wall thicknesses longon each side of the fusion, and about 1" or 1-1/2 wall thicknesses wide is cutout of the trial fusion pipe. (See Figure 6) The strap is then bent so that theends of the strap touch. Any disbondment at the fusion is unacceptable,and indicates poor fusion quality. If failure occurs, fusion procedures and/ormachine set-up should be changed, and a new trial fusion and bent straptest specimen should be prepared and tested. Field fusion should not proceeduntil a test joint has passed the bent strap test.

t

15 t or 6” min 15 t or 6” min

1 - 1/2 tor 1” min

Test Strap

Butt Fusion

Figure 6 Bent Strap Test Specimen

Page 23: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 17

WARNING: A test strap from thick wall pipe may requireconsiderable effort to bend. Further, the test strap mayspring back if the ends are inadvertently released whilebending. Appropriate personnel safety precautions shouldbe observed.

High-speed, tensile-impact testing, a destructive test of a tensile couponcut from the pipe joint, can provide a quantitative joint strength assessment.Tensile impact strength of the joint may be compared to that of the basepipe.

Soil Tests

During buried pipe installation, work should be checked throughout theconstruction period by an inspector who is thoroughly familiar with the jobsite,contract specifications, materials, and installation procedures. Inspectionsshould reasonably ensure that significant factors such as trench depth, grade,pipe foundation (if required), quality and compaction of embedment backfill,and safety are in compliance with contract specifications and otherrequirements. To evaluate soil stability, density and compaction, appropriateASTM tests may be required in the contract specifications.

Pipe Surface Damage

Surface damage may occur during construction handling and installation.Significant damage may impair the future performance of the pipeline. Thefollowing guidelines may be used to assess surface damage significance.

For polyethylene pressure pipelines, damage or butt fusion misalignmentshould not exceed 10% of the minimum wall thickness required for thepipeline’s operating pressure. (Ref. 5) Deep cuts, abrasions or groovescannot be field repaired by hot gas or extrusion welding. Excessive damagemay require removal and replacement of the damaged pipe section, orreinforcement with a full encirclement repair clamp. Misaligned butt fusionsshould be cut out and redone.

If damage is not excessive, the shape of the damage may be aconsideration. Sharp notches and cuts should be dressed smooth so thenotch is blunted. Blunt scrapes or gouges should not require attention. Minorsurface abrasion from sliding on the ground or insertion into a casing shouldnot be of concern.

Page 24: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 18

Deflection Tests

Buried flexible pipes rely on properly installed backfill to sustain earthloadsand other loads. Proper installation requires using the backfill materialsspecified by the designer, and installing the pipe as specified by the designer.

Large diameter extruded profile pipes, and larger diameter, high DRconventionally extruded pipes are inherently flexible. Pipe deflection can beused to monitor the installation quality. Improperly embedded pipe candevelop significant deflection in a short time, thus alerting the installer andthe inspector to investigate the problem. Inspection should be performed asthe job progresses, so errors in the installation procedure can be identifiedand corrected.

Initial deflection checks of extruded profile pipe may be performed afterembedment materials have been placed and compacted. The inside diameter

D1

D2

Backfill placedand compacted

Vertical diameter

Final Backfill placedand compacted

Vertical diameter

Figure 7 Determining Initial Deflection

Page 25: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 19

of the pipe is measured after backfill materials have been placed to the pipecrown, and compacted. This is D1. Then final backfill materials are placedand compacted, and the pipe inside diameter is measured again at the exactlocation where the prior measurement was taken. This is D2. (See Figure7)

Percent initial deflection is calculated using the following:

%Deflection =D1- D2

D1100

where D1 and D2 are as defined above and depicted in Figure 7.

Another method to measure deflection is to pull a pre-sized mandrel throughthe pipe. The mandrel should be sized so that if the pipe exceeds allowabledeflection, the mandrel is blocked.

To properly size the mandrel, the allowable vertical diameter of the pipemust be established. It is necessary to account for pipe ID manufacturingtolerances and any ovality that may occur during shipping. Pipe base IDdimensions and tolerances should be obtained from the manufacturer. Themaximum mandrel diameter is calculated as follows:

MD = D -Dy

100

where DM = maximum mandrel diameter, in

D = base pipe ID, in

D = D - A + Bi2 2

Di = nominal pipe ID, in

A = ID manufacturing tolerance, in

B = shipping ovality, in

B = 0.03Di

y = allowable deflection, percent

Deflection tests of conventionally extruded pipe may be performed in thesame manner. However, conventionally extruded pipe is manufactured to acontrolled outside diameter, so the inside diameter is subject to the combinedtolerances of the outside diameter and the wall thickness.

Page 26: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 20

Leak Testing

The intent of leak testing is to find unacceptable faults in a piping system.If such faults exist, they may manifest themselves by leakage or rupture.

Leakage tests may be performed if required in the Contract Specifications.Testing may be conducted in various ways. Internal pressure testing involvesfilling the test section with a nonflammable liquid or gas, then pressurizingthe medium. Hydrostatic pressure testing with water is the preferredand recommended method . Other test procedures may involve pairedinternal or end plugs to pressure test individual joints or sections, or an initialservice test. Joints may be exposed to allow inspection for leakage.

Liquids such as water are preferred as the test medium because lessenergy is released if the test section fails catastrophically. During a pres-sure test, energy (internal pressure) is applied to stress the test section. Ifthe test medium is a compressible gas, then the gas is compressed andabsorbs energy while applying stress to the pipeline. If a catastrophic fail-ure occurs, both the pipeline stress energy and the gas compression energyare suddenly released. However, with an incompressible liquid such aswater as the test medium, the energy release is only the energy required tostress the pipeline.

WARNING: Pipe system pressure testing is performed todiscover unacceptable faults in a piping system. Pressuretesting may cause such faults to fail by leaking orrupturing. This may result in catastrophic failure. Pipingsystem rupture may result in sudden, forcible, uncontrolledmovement of system piping or components, or parts ofcomponents.

WARNING: Pipe Restraint. The pipe system under testand any closures in the test section should be restrainedagainst sudden uncontrolled movement from catastrophicfailure. Test equipment should be examined beforepressure is applied to insure that it is tightly connected.All low pressure filling lines and other items not subjectto the test pressure should be disconnected or isolated.

Post Installation

Page 27: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 21

WARNING: Personal Protection. Take suitableprecautions to eliminate hazards to personnel near linesbeing tested. Keep personnel a safe distance away fromthe test section during testing.

Pressure Testing Precautions

The piping section under test and any closures in the test section shouldbe restrained or otherwise restricted against sudden uncontrolled movementin the event of rupture. Expansion joints and expansion compensators shouldbe temporarily restrained, isolated or removed during the pressure test.

Testing may be conducted on the system, or in sections. The limitingtest section size is determined by test equipment capability. If the pressurizingequipment is too small, it may not be possible to complete the test withinallowable testing time limits. If so, higher capacity test equipment, or a smallertest section may be necessary.

If possible, test medium and test section temperatures should be lessthan 1000F (380C). At temperatures above 1000F (380C), reduced testpressure is required. Before applying test pressure, time may be requiredfor the test medium and the test section to temperature equalize. Contactthe pipe manufacturer for technical assistance with elevated temperaturepressure testing.

References

The following reference publications provide pressure testing information:

ASME B31.1 Power Piping, Section 137, Pressure Tests. (Ref. 6)

PPI TR-31 Underground Installation of Polyolefin Piping, Section 7,System Testing. (Ref 1)

ASTM F 1417, Standard Test Method for Installation Acceptance ofPlastic Gravity Sewer Lines Using Low-Pressure Air. (Ref. 7)

Uni-Bell PVC Pipe Association Standard, Uni-b-6-90 RecommendedPractice for Low-Pressure Air Testing of Installed Sewer Pipe.

Page 28: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 22

The piping manufacturer should be consulted before using pressuretesting procedures other than those presented here. Other pressure testingprocedures may or may not be applicable depending upon piping productsand/or piping applications.

Test Pressure

Test pressure may be limited by valves, or other devices, or lower pressurerated components. Such components may not be able to withstand therequired test pressure, and should be either removed from, or isolated fromthe section being tested to avoid possible damage to, or failure of thesedevices. Isolated equipment should be vented.

• For continuous pressure systems where test pressure limitingcomponents or devices have been isolated, or removed, or are notpresent in the test section, the maximum allowable test pressure is1.5 Times the system design pressure at the lowest elevation in thesection under test.

• If the test pressure limiting device or component cannot be removedor isolated, then the limiting section or system test pressure is themaximum allowable test pressure for that device or component.

• For non-pressure, low pressure, or gravity flow systems, consult thepiping manufacturer for the maximum allowable test pressure.

Test Duration

For any test pressure from 1.0 to 1.5 times the system design pressure,the total test time including initial pressurization, initial expansion, and timeat test pressure, must not exceed eight (8) hours. If the pressure test is notcompleted due to leakage, equipment failure, etc., the test section shouldbe de-pressurized, and allowed to “relax” for at least eight (8) hours beforebringing the test section up to test pressure again.

Pre-Test Inspection

Test equipment and the pipeline should be examined before pressure isapplied to ensure that connections are tight, necessary restraints are in-place and secure, and components that should be isolated or disconnectedare isolated or disconnected. All low pressure filling lines and other itemsnot subject to the test pressure should be disconnected or isolated.

Page 29: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 23

Hydrostatic testing

Hydrostatic pressure testing is preferred and is strongly recommended.The preferred testing medium is clean water. The test section should becompletely filled with the test medium, taking care to bleed off any trappedair. Venting at high points may be required to purge air pockets while thetest section is filling. Venting may be provided by loosening flanges, or byusing equipment vents. Re-tighten any loosened flanges before applyingtest pressure.

Monitored Make-up Water Test

The test procedure consists of initial expansion, and test phases. Duringthe initial expansion phase, the test section is pressurized to the test pressure,and sufficient make-up water is added each hour for three (3) hours to returnto test pressure. (Ref. 1)

Nominal Pipe Size, Make-Up Water Allowancein (U.S. Gallons per 100 ft of Pipe)

1 Hour Test 2 Hour Test 3 Hour Test

1-1/4 0.06 0.10 0.161-1/2 0.07 0.10 0.17

2 0.07 0.11 0.193 0.10 0.15 0.254 0.13 0.25 0.405 0.19 0.38 0.58

5-3/8 0.21 0.41 0.626 0.3 0.6 0.9

7-1/8 0.4 0.7 1.08 0.5 1.0 1.5

10 0.8 1.3 2.112 1.1 2.3 3.4

13-3/8 1.2 2.5 3.714 1.4 2.8 4.216 1.7 3.3 5.018 2.0 4.3 6.520 2.8 5.5 8.022 3.5 7.0 10.524 4.5 8.9 13.326 5.0 10.0 15.028 5.5 11.1 16.8

Table III Test Phase Make-up Amount

Page 30: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 24

Nominal Pipe Size, Make-Up Water Allowancein (U.S. Gallons per 100 ft of Pipe)

1 Hour Test 2 Hour Test 3 Hour Test

30 6.3 12.7 19.232 7.0 14.3 21.534 8.0 16.2 24.336 9.0 18.0 27.042 12.0 23.1 35.348 15.0 27.0 43.054 18.5 31.4 51.763

After the initial expansion phase, about four (4) hours after pressuriza-tion, the test phase begins. The test phase may be one (1), two (2), or three(3) hours, after which a measured amount of make-up water is added toreturn to test pressure. If the amount of make-up water added does notexceed Table III values, leakage is not indicated.

Non-monitored Make-Up Water Test

The test procedure consists of initial expansion, and test phases. Forthe initial expansion phase, make-up water is added as required to maintainthe test pressure for four (4) hours. For the test phase, the test pressure isreduced by 10 psi. If the pressure remains steady (within 5% of the targetvalue) for an hour, no leakage is indicated.

Pneumatic Testing

WARNING: Compressed air or any pressurized gas usedas a test medium may present severe hazards to personnelin the vicinity of lines being tested. Extra personnelprotection precautions should be observed when a gasunder pressure is used as the test medium.

WARNING: Explosive Failure—Piping system ruptureduring pneumatic pressure testing may result in theexplosive, uncontrolled movement of system piping, orcomponents, or parts of components. Keep personnel asafe distance away from the test section during testing.

Page 31: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 25

Pneumatic testing should not be used unless the Owner and the respon-sible Project Engineer specify pneumatic testing or approve its use as analternative to hydrostatic testing.

Pneumatic testing (testing with a gas under pressure) should not beconsidered unless one of the following conditions exists:

• when the piping system is so designed that it cannot be filled witha liquid; or

• where the piping system service cannot tolerate traces of liquidtesting medium.

The testing medium should be non-flammable and non-toxic. The testpressure should not exceed the maximum allowable test pressure for anynon-isolated component in the test section.

Leaks may be detected using mild soap solutions (strong detergentsolutions should be avoided), or other non-deleterious leak detecting fluidsapplied to the joint. Bubbles indicate leakage. After leak testing, all soapsolutions or leak detecting fluids should be rinsed off the system with cleanwater.

High Pressure Procedure

For continuous pressure rated pipe systems, the pressure in the testsection should be gradually increased to not more than one-half of the testpressure, then increased in small increments until the required test pressureis reached. Test pressure should be maintained for ten (10) to sixty (60)minutes, then reduced to the design pressure rating, and maintained forsuch time as required to examine the system for leaks.

Low Pressure Procedure

For components rated for low pressure service the specified rated testpressure should be maintained for ten (10) minutes to one (1) hour, but notmore than one (1) hour. Test pressure ratings must not be exceeded.

Leakage inspections may be performed during this time. If the testpressure remains steady (within 5% of the target value) for the one (1) hourtest time, no leakage is indicated.

Pressure testing of gravity-flow sewer lines should be conducted inaccordance with ASTM F 1417, Standard Test Method for InstallationAcceptance of Plastic Gravity Sewer Lines Using Low-Pressure Air. (Ref. 7)

Page 32: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 26

Initial Service Testing

An initial service test may be acceptable when other types of tests arenot practical, or where leak tightness can be demonstrated by normal service,or when initial service tests of other equipment are performed. An initialservice test may apply to systems where isolation or temporary closures areimpractical, or where checking out pumps and other equipment affords theopportunity to examine the system for leakage prior to full scale operations.

Test Procedure

The piping system should be gradually brought up to normal operatingpressure, and held at operating pressure for at least ten (10) minutes. Duringthis time, joints and connections should be examined for visual evidence ofleakage.

Non-Testable Systems

Some systems may not be suitable for pressure testing. These systemsmay contain non-isolatable components, or temporary closures may not bepractical. Such systems should be carefully inspected during and afterinstallation. Inspections such as visual examination of joint appearance,mechanical checks of bolt or joint tightness, and other relevant examinationsshould be performed.

Disinfecting Water Mains

Applicable procedures for disinfecting new and repaired potable watermains are presented in standards such as ANSI/AWWA C651, DisinfectingWater Mains. (Ref. 8) ANSI/AWWA C651 uses liquid chlorine, sodiumhypochlorite, or calcium hypochlorite to chemically disinfect the main.Disinfecting solutions containing chlorine should not exceed 12% activechlorine, because greater concentration can chemically attack and degradepolyethylene.

Considerations for Post Start-Up and Operation

Page 33: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 27

Cleaning

Pipelines operating at low flow rates (around 2 ft/sec or less) may allowsolids to settle in the pipe invert. Polyethylene has a smooth, non-wettingsurface that resists the adherence of sedimentation deposits. If the pipelineis occasionally subject to higher flow rates, much of the sedimentation willbe flushed from the system during these peak flows. If cleaning is required,sedimentation deposits can usually be flushed from the system with highpressure water.

Water-jet cleaning is available from commercial services. It usuallyemploys high pressure water sprays from a nozzle that is drawn through thepipe system with a cable.

Pressure piping systems may be cleaned with the water-jet process, ormay be pigged. Pigging involves forcing a resilient plastic plug (soft pig)through the pipeline. Usually, hydrostatic or pneumatic pressure is appliedbehind the pig to move it down the pipeline. Pigging should employ a piglauncher and a pig catcher.

A pig launcher is a wye or a removable spool. In the wye, the pig is fittedinto the branch, then the branch behind the pig is pressurized to move thepig into the pipeline and downstream. In the removable pipe spool, the pigis loaded into the spool, the spool is installed into the pipeline, and then thepig is forced downstream.

WARNING: A pig may discharge from the pipeline withconsiderable velocity and force. The pig catcher is abasket or other device at the end of the line designed toreceive the pig when it discharges from the pipeline. Thepig catcher provides a means of safe pig discharge fromthe pipeline.

WARNING: Soft pigs must be used with polyethylene pipe.Scraping finger type or bucket type pigs may severelydamage a polyethylene pipe and must not be used

Commercial pigging services are available if line pigging is required.

Squeeze-Off

Squeeze-off (or pinch-off) is a means of controlling flow in smaller diameterpolyethylene pipe and tubing by flattening the pipe between parallel bars.Flow control does not imply complete flow stoppage in all cases. For larger

Page 34: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 28

pipes, particularly at higher pressures, some seepage is likely. If the situationwill not allow seepage, then it may be necessary to vent the pipe betweentwo squeeze-offs.

Polyethylene gas pipe manufactured to ASTM D 2513 is suitable forsqueeze-off; however, squeeze-off practices are not limited to gasapplications. Squeeze-off is applicable to polyethylene PE3408 and PE2406pressure pipe up to 16" IPS, and up to 100 psi internal pressure. Largersizes and higher pressures may be possible, but suitable commercialequipment is not presently available, so there is no demonstrated experiencewith larger sizes or higher pressures.

WARNING: Squeeze-off is applicable ONLY to PE2406 andPE3408 polyethylene pipe and tubing. The pipe or tubingmanufacturer should be consulted to determine if squeeze-off is applicable to his product, and for specific squeeze-off procedures.

Tools (Ref. 9)

Squeeze-off tools should have

• parallel bars that are shaped to avoid pipe damage,

• mechanical stops to prevent over-squeeze pipe damage,

• safety mechanisms to prevent accidental release, and

• a mechanism that controls the rate of closure, and the rate ofrelease.

Typical bar shapes are single round bars, twin round bars, or flat barswith rounded edges. Other bar shapes may also be suitable so long asedge radius requirements are met. See Table IV.

Positive mechanical stops between the bars are essential to prevent oversqueeze and pipe damage. The stops limit bar closure to 70% of twice themaximum wall thickness. (Ref. 9) For DR or SDR sized polyethylene pipeONLY, (not tubing or schedule sized pipe), stop distance may be determinedby

g = 1.568D

DR

where g = stop gap, inD = pipe outside diameter, inDR = pipe dimension ratio

Page 35: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 29

Table IV – Squeeze Tool Bar Radius

Consult the pipe manufacturer for stop gap dimensions for tubing sizes.

Typical squeeze-off tools use either a manual mechanical screw orhydraulic cylinders. In either case, a mechanism to prevent accidental barseparation is an essential safety feature of the tool.

Key Elements

Closing and opening rate are key elements to squeezing-off withoutdamaging the pipe. It is necessary to close slowly and release slowly, withslow release being more important. The release rate for squeeze-off shouldbe 0.50 inches/minute or less as specified in ASTM F1041 (Ref. 10) or ASTMF1563 (Ref. 9) The pipe must be allowed sufficient time to adjust to the highcompressive and tensile stresses applied to the pipe’s inside wall duringsqueeze-off.

Research work performed under contract to the Gas Research Instituteindicates that the greatest damage potential is during release, especiallywith heavier wall pipes. Flattening places high compressive stress on theinside wall at the outer edges of the squeeze. Then releasing and openingapplies high tensile stress to the same area. The material must be givenample time to accommodate these stresses. Opening too fast may causeexcessive strain, and may damage the inside wall.

Lower temperatures will reduce material flexibility and ductility, so in colderweather, closure and opening time must be slowed further.

Pipe Diameter Minimum Bar Radius

< 0.750 0.50> 0.750 < 2.375 0.63> 2.375 < 4.500 0.75> 4.500< 8.625 1.00

> 8.625 <16.000 1.50

Page 36: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 30

Testing of PE2406 and PE3408 polyethylene piping has shown that whenproper procedures and tools are used, squeeze-off can be performed withoutcompromising the expected service life of the system. However, pipe canbe damaged during squeeze-off

• if the manufacturer’s recommended procedures are not followed, or

• if the squeeze is held closed too long, or

• from static electric discharge, or

• by altering or circumventing the closure stops, or

• by squeezing-off more than once in the same location.

WARNING: Pipe damaged during squeeze-off could leakor fail at the squeeze-off point. Pipe known or suspectedto have been damaged during squeeze-off should beremoved from the system, or should be reinforced at thesqueeze-off point using a full encirclement clamp.

Procedure

From the installation of the squeeze-off tool to its removal, the total timeshould not exceed 8 hours. Excessive time may damage the pipe.

Figure 8 Squeeze-off Stresses

High Compressive Stressduring flattening, thenHigh Tensile Stress

during opening

Page 37: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 31

1. Select the correct size squeeze tool for the pipe being squeezed.Squeeze bar closure stops must be in place, and must be the correct sizefor the pipe’s diameter and wall thickness or DR.

2. Fit the tool on the pipe so the pipe is centered in the tool, and the toolis square to the pipe. The squeeze off tool must be at least 3 pipe diameters,or 12 inches, whichever is greater, away from any butt fusion, or any socket,saddle, or mechanical fitting.

WARNING: Static electricity control. When pipe conveyinga compressed gas is being flattened, the gas flow velocitythrough the flattened area increases. High velocity, drygas, especially with particles present in the flow, cangenerate a static electric charge on pipe surfaces whichcan discharge to ground. Before flattening the pipe, thetool should be grounded and procedures to control staticcharge build-up on pipe surfaces should be employed.Grounding and static control procedures should remainin place for the entire procedure.

3. Operate the bar closing mechanism, and at a controlled rate, flattenthe pipe between the bars.

3.1 For 3" IPS and larger pipe, pause at least 1 minute whenthe pipe is flattened halfway and another minute when3/4 closed. For all pipe sizes, pause 1 minute when thepipe inside walls make contact.

3.2 After pausing 1 minute when the pipe inside walls makecontact, continue closing at about half the prior closingrate until the tool bars contact the closure stops.

3.3 If temperatures are near freezing or lower, closure ratesshould be halved and pauses should be doubled.

4. If necessary, engage the accidental release prevention mechanism.

5. Perform the necessary work downstream of the squeeze off.

WARNING: Venting may be required for 100% shut-off.Squeeze-off may not stop all flow. If 100% shut-off isrequired, it may be necessary to install two squeeze-offtools at two points along the line, and vent between them.Any work performed must be downstream of the secondsqueeze-off. Do not remove or alter the closure stops, orplace anything (rags, sticks, etc.) between the bars andthe pipe.

Page 38: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 32

6. When work is complete, disengage the accidental release mechanism(if required), and open the squeeze-off tool bars at a controlled rate no fasterthan the Step 3 closure rate. Opening must include a 1 minute pause at thewall contact point, and, 1 minute pauses at 1/4 open (3/4 closed) and 1/2open points for 3" IPS and larger pipes.

7. When the squeeze-off tool has been completely opened, rotate thetool 90 degrees around the pipe, and slowly re-round the pipe.

7.1. Re-round the pipe by closing the tool part-way until the pipe iscircular. It may be necessary to close slightly past circular, sothat the pipe is round when the tool is again released. Re-rounding closure rate should not exceed the Step 3 closurerate.

7.2. Re-rounding is partial closure, sufficient to make the pipecircular again. DO NOT completely flatten the pipe.

8. Open the bars, and remove the squeeze-off tool.

9. Identify the squeezed-off area by wrapping tape around the pipe, orinstalling a full encirclement clamp over the area.

WARNING: Do not squeeze-off more than once in the sameplace. Doing so will damage the pipe.

Additional information on squeeze-off may be found in ASTM F 1041,Standard Guide for Squeeze-off of Polyolefin Gas Pressure Pipe and Tubing.

Routine or Emergency?

Squeeze-off procedures may be used for routine, scheduled changes topiping systems, or as an emergency procedure to control gasses or liquidsescaping from a damaged pipe. For scheduled piping changes, the aboveprocedure should be followed, and if followed, the pipe’s service life is notexpected to be compromised.

However, an emergency situation may require quickly flattening the pipeand controlling flow because the escaping fluid may be an immediate hazardof greater concern than damaging the pipe.

WARNING: If an emergency situation requires rapidflattening, then the pipe or tubing will probably bedamaged.

Page 39: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 33

Repairs

Repair situations may arise if a polyethylene pipe has been damaged.Damage may occur during shipping and handling, during installation, or afterinstallation. Damage may include scrapes or abrasions, breaks, punctures,kinks, or emergency squeeze-off. Permanent repair usually involvesremoving and replacing the damaged pipe or fitting. In some cases, temporaryrepairs may restore sufficient serviceability and allow time to schedulepermanent repairs in the near future.

Damage Assessment

Damaged pipe or fittings should be inspected and evaluated. Pipe, fittings,fabrications or structures with excessive damage should not be installed.Damage that occurs after installation may require that the damaged pipe orcomponent be removed and replaced.

WARNING: Scrapes or gouges in pressure pipe cannot berepaired by filling-in with extrusion or hot air welding. Thedamaged section should be removed and replaced.

WARNING: Improperly made fusion joints cannot berepaired.

Improper butt fusions must be cut-out and re-done from the beginning.Poorly joined socket or electrofusion fittings must be removed and replaced.Poorly joined saddle fittings must be removed by cutting out the main pipesection, or, if the main is undamaged, made unusable by cutting the branchoutlet or chimney off the saddle fitting, and installing a new saddle fitting ona new section of main.

WARNING: Broken or damaged fittings cannot be repairedand, as such, should be removed and replaced.

WARNING: Kinked pipe must not be installed and cannotbe repaired.

Kinked pipe must be removed and replaced.

WARNING: Pipe damaged during an emergency squeeze-off cannot be repaired.

Squeeze-off damaged pipe must be removed and replaced.

Page 40: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 34

Permanent Repairs

For buried large diameter polyethylene pipe that has been poorlybackfilled, excessive deflection may be correctable using point excavationto remove backfill, then reinstalling embedment materials in accordance withrecommended procedures.

Where replacement is required, any joining method appropriate to theproduct and service requirements is generally acceptable. Butt and socketfusion joining procedures require that one of the components movelongitudinally. However, constrained installations, such as buried pipes, maynot allow such movement.

Permanent repair of constrained pipe typically employs techniques thatdo not require longitudinal movement of one or both pipe ends. Techniquesinclude deflecting one pipe end to the side, using a mechanical orelectrofusion coupling, or installing a flanged spool. See Figure 9. Typicalmethods for joining repair pipe sections include flanges, electrofusioncouplings, and fully restrained mechanical couplings.

To repair using a flanged spool, cut out, remove and discard the damagedpipe section. Install flanges on the two pipe ends. Measure the distancebetween the flange sealing surfaces, and prepare a flanged pipe spool ofthe same length. Install the flanged spool.

Repair using an electrofusion coupling or a fully restrained mechanicalcoupling is limited to pipe sizes for which such couplings are available.Mechanical or electrofusion coupling repairs are made by deflecting onepipe end to the side for the coupling body to be slipped on. The pipe endsare then realigned, and the coupling joint fitted up. To allow lateral deflection,a length of about 10 times the pipe outside diameter is needed.

Replacement using Electrofusionor Fully Restrained Mechanical Coupling

Figure 9 Constrained Pipe Repair

Replacement with Flanged Spool

Page 41: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 35

Temporary Repair

Until permanent repairs can be effected, temporary repairs may be neededto seal leaks or punctures, to restore pressure capacity, or to reinforcedamaged areas. Temporary repair methods include but are not limited tomechanical repair couplings and welded patches.

A successful piping system installation is dependent on a number offactors. Obviously, a sound design and the specification and selection ofthe appropriate quality materials are paramount to the long term performanceof any engineered installation. The handling, inspection, testing, and safetyconsiderations that surround the placement and use of these engineeredproducts is of equal importance.

In this chapter, we have attempted to provide fundamental guidelinesregarding the receipt, inspection, handling, storage, testing, and repair ofpolyethylene piping products. While this chapter cannot address all of theproduct applications, test and inspection procedures, or constructionpractices, it does point out the need to exercise responsible care in planningout these aspects of any job site. It is the responsibility of the contractor,installer, site engineer, or other users of these materials to establishappropriate safety and health practices specific to the job site and inaccordance with the local prevailing codes that will result in a safe andeffective installation.

Conclusion

Page 42: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 36

1. Plastics Pipe Institute, TR-31, “Underground Installation of PolyolefinPipe, Washington, DC.

2. Gilroy, H.M., “Polyolefin Longevity for Telephone Service, AntecProceedings, 1985.

3. Plastics Pipe Institute, Handbook of Polyethylene Pipe, Chapter onPolyethylene Joining Procedures, Washington, DC.

4. Plastics Pipe Institute, TR-19, “Thermoplastics Piping for the Transportof Chemicals”, Washington, DC.

5. American Gas Association, AGA Plastic Pipe Manual for Gas Service,AGA, 1994.

6. American Society of Mechanical Engineers, B31.1, Section 137.

7. American Society for Testing and Materials, ASTM F1417, “StandardTest Method for Installation Acceptance of Plastic Gravity Sewer LinesUsing Low Pressure Air”, West Conshohocken, PA, 1998.

8. American Water Works Association, “AWWA Standard for DisinfectingWater Mains”, Denver, CO, 1992.

9. American Society for Testing and Materials, ASTM F1563, “StandardSpecification for Tools to Squeeze-off Polyethylene (PE) Gas Pipe orTubing”, West Conshohocken, PA, 1998.

10. American Society for Testing and Materials, ASTM F1041, “StandardGuide for Squeeze-off of Polyethylene Gas Pressure Pipe or Tubing”,West Conshohocken, PA, 1998.

11. American Society for Testing and Materials, ASTM D2104, “StandardSpecification for Polyethylene (PE) Plastic Pipe, Schedule 40”, WestConshohocken, PA, 1998.

12. American Society for Testing and Materials, ASTM D2239, “StandardSpecification for Polyethylene (PE) Plastic Pipe (SIDR-PR) Basedon Controlled Inside Diameter”, West Conshohocken, PA, 1998.

13. American Society for Testing and Materials, ASTM D2447, “StandardSpecification for Polyethylene (PE) Plastic Pipe, Schedules 40 and80, Based on Outside Diameter”, West Conshohocken, PA, 1998.

References

Page 43: Inspections, Tests and Safety Considerations

Inspections, Tests and Safety ConsiderationsPage 37

14. American Society for Testing and Materials, ASTM D3035, “StandardSpecification for Polyethylene (PE) Plastic Pipe (DR-PR) Based onControlled Outside Diameter”, West Conshohocken, PA, 1998.

Page 44: Inspections, Tests and Safety Considerations

The Plastics Pipe Institute, Inc.Toll Free: (888) 314-6774

www.plasticpipe.org


Recommended