Installation of Automatic SeismicTrip System in Existing NPPs
Prepared by: Ting ChowPresented by: Lih-Yih Liao
Institute of Nuclear Energy Research (INER)Taiwan, ROC
Third TAEC-USNRC Technical ExchanTAECtingNRC, Washington D.C., USA
May 31, 2005
11
Contents
BackgroundApproachASTS design logicMajor elements in the ASTS ASTS installationMajor dedication processConclusion
22
Background
Taiwan island is located at a complex juncture between the Eurasian plate and Philippine sea plateIt was the disastrous Ji-Ji earthquake(M=7.3) occurred on September 21, 2000 triggered TAEC to suggest TPC to install the ASTS in its 6 existing nuclear units to further ensure the safety.ASTS is mandatory in Japan, but not in US..
33
Approach
Technical requirements in the purchase specification was prepared by the TPC and approved by the TAEC.Foxboro/Invensys design/product plus INER dedication process.Use plant’s RPS trip logic
44
Trip wiring for TPC NPP1,2 (OR logic)
Wiring for NPP1 (OR Logic)
A1/ a NO/To RPS AA`1/ a
NO/To RPS B
NO/To RPS C
NO/To RPS D
A`
A
B D
C
B` D`
C`
Upper Floor
Lower Floor
Location of Accelerometers Set point and Trip Unit
B1/ a B`1/ a
C1/ a C`1/ a
D1/ a D`1/ a
66
FBA-23
BPF V/A Converter
Y
設定點跳脫次單元Foxboro SPEC 200 (Class 1E)
X
Z
訊號處理次單元0.1 to 10Hz BPF +Volt/Amp Converter
(To Be Dedicated)
測震感測器次單元
2AP-A
LM
2AP-A
LM
2AI-I2V
2AI-I2V
N-
2AX
+PS9A
N-2A
O-L
2C-R
Blank
SPEC200 NEST (N-2ANU-P)
DC 24V
Trip指示燈
DC 24V
RPS Logic
強震急停裝置跳脫邏輯測試平台架構圖
4-20 mA±2.5V
BPF V/A Converter
BPF V/A Converter
0~5V
BPF V/A Converter
Y X
Z ±2.5V
BPF V/A Converter
BPF V/A Converter
0~5V
±12V
FBA-23
±12V
N-2A
P+TIM
2AP-A
LM
2AP-A
LM
2AI-I2V
2AI-I2V N
-2A
X+P
S9A
N-2A
O-L2C
-R
Blank
SPEC200 NEST (N-2ANU-P)
DC 24V
4-20 mA
N-2A
P+TIM
Seismic sensor
ASTS design logic
77
Major elements in the ASTS
There are three sub-units in the ASTS:--Earthquake sensors:
Kinemetrices FBA23 triaxial accelerometers.
--Data process:BPF( up to10hz), B/U converter , V/A converterThese two sub units are installed in one water-proof rigid box (sensor box)
-- Trip control module:Foxboro spec200 module(with some modification),
and two spec200 are installed in one 19” control cabinet
88
ASTS installation
Install seismic sensors (FBA23) on both basematfloor and operating floor in major (reactor/auxiliary) building for BWR/PWR.The number of seismic sensors on each floor depends on plant’s RPS trip logic, i.E.,4/floor for BWR and 3/floor for PWR. Total 44 sensors installed in 6 operationg units.One control cabinet responsible for two sensor boxes. Total 22 control cabinets installed in back panel rooms in control buildings.
99
Major dedication process
NEMA4 water proof testAnti-radiation test: 8.76x100 rads over 40 yearsEMI/EMC test: follow RG 1.180 requirement
1010
Major dedication process
Seismic test: use plant specific required response spectrum, TRS envelop RRS Seismic auto-trip accuracy test: must not trip when filtered PA below set point minus 0.05g, and must trip when filtered PA exceeds set point over 0.05g.Trip signals occurred within 10 second interval are considered as same events
1111
2 3 5 2 3 5 2 3 50.1 1.0 10.0Frequency, Hz
0.00
0.40
0.80
1.20
1.60
Spec
tral A
ccel
erat
ion,
g
OBENPS I, +0.83ft Horizontal
NPS I, +0.83ft Vertical
NPS I, +56.83ft Horizontal
NPS I, +56.83ft Vertical
NPS II, -42.5ft Horizontal
NPS II, -42.5ft Vertical
NPS II, +2.17ft Horizontal
NPS II, +2.17ft Vertical
NPS III, +74&80ft Horizontal
NPS III, +74&80ft Vertical
NPS III, +126ft Horizontal
NPS III, +126ft Vertical Zone2
OBE RRS
Damping ratio = 5 %
2 3 5 2 3 5 2 3 50.1 1.0 10.0Frequency, Hz
0.00
1.00
2.00
3.00
Spec
tral A
ccel
erat
ion,
g
SSENPS I, +0.83ft Horizontal
NPS I, +0.83ft Vertical
NPS I, +56.83ft Horizontal
NPS I, +56.83ft Vertical
NPS II, -42.5ft Horizontal
NPS II, -42.5ft Vertical
NPS II, +2.17ft Horizontal
NPS II, +2.17ft Vertical
NPS III, +74&80ft Horizontal
NPS III, +74&80ft Vertical
NPS III, +126ft Horizontal
NPS III, +126ft Vertical Zone2
SSE RRSDamping ratio = 5 %
OBE RRS (envelope all floor RS) SSE RRS(envelope all floor RS)
OBE/SSE required response spectrum
1616
Conclusion
This total 2,500,000.-USD project finished in 1 year.The important features of the ASTS include: Foxboro spec200 analog system(10 seconds timer card, 20ms trespassing time needed for relay to seal-in), low pass filter, and use pa(low-pass filtered) for auto trip parameter.Independent dedication process performed by INER
1717
Historical Earthquakes
This map showed all felt earthquakes and major disastrous earthquakes ever struck Taiwan since 1900. It is noted that there are five in-land earthquakes with magnitude larger than 7.0 and these are those cause high fatalities
1818
Tectonic plates of Taiwan islandThis map showed the tectonic plates of Taiwan Island (After Angelier, 1986). Basically Taiwan is on the boundary between Eurasian Continental Plate and Philippine Sea Plate. Due to the process of collision of these two plates, eastern part of Taiwan moves toward NW at a rate about 2.5~8.0 cm/year based on actual GPS measurement starting from 1993.