1 Confidential. For internal use only. Do not distribute. HUGMN User Group Meeting St. Jude Medical The Road to Hyperion Bliss Lisa Jones – Director, Financial Systems
Transcript
Page 1: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

1Confidential. For internal use only. Do not distribute.

HUGMN User Group MeetingSt. Jude Medical

The Road to Hyperion Bliss

Lisa Jones – Director, Financial Systems

Page 2: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

2Confidential. For internal use only. Do not distribute.

Agenda Hyperion Road Map Hyperion Planning Implementation

Overview of Planning/Forecasting Process Redesign of Hyperion Planning Big Wins Lessons Learned

DRM Hyperion Planning Upgrade HFM Implementation FDM Batch Automation Application Support

Page 3: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

3Confidential. For internal use only. Do not distribute.

Hyperion Road Map

Page 4: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

4Confidential. For internal use only. Do not distribute.

STJ Forecast/Plan Cycles – No changes were made to our Planning process as a result of the Hyperion Planning Implementation

4

Cycle** February is the only month that does not have an active cycle**

Start End Cycle Length (system open to final

submission)

Forecast (4 Quarterly Forecasts)

Forecast1.1 12/19/13 01/12/14 24 days

Forecast2.1 03/01/14 04/11/14 41 days

Forecast3.1 05/31/14 07/11/14 41 days

Forecast4.1 07/27/14 10/10/14 75 days

Outlook (4 Quarterly Outlooks)

Outlook1.1 02/27/14 03/14/14 16 days

Outlook2.1 05/29/14 06/13/14 15 days

Outlook3.1 08/27/14 09/12/14 16 days

Outlook4.1 11/26/14 12/12/14 16 days

AOP (Annual Operating Plan) 07/27/14 11/14/14 110 days

STRAT (5 year Strategic Plan) 02/27/14 07/13/14 137 days

Page 5: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

5Confidential. For internal use only. Do not distribute.

Hyperion Planning – Initial Design

REVSCOGS Input of Units, Revenue,

Scogs & Ocogs

OPEXPROJ Input of Operating expenses

by cost center, by project

WRKFORCE Detailed employee

information (US employees only, workforce planning has not been rolled out for OUS employees).

Hyperion Plan Types (CVPLAN)

Essbase Cubes (All BSO Cube)

FX2RVOP FX Engine used for loading

of actual data in transactional input and converting to USD. End users do not have access this cube.

CNFX3 Currency Neutralized data.

The majority of our management reporting is out of this Essbase cube

CMFX3• Currency Modeling. Used

only by Corporate FP&A to model planning data at various FX rate assumptions.

DRM EPMA Planning Essbase Cubes

Page 6: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

6Confidential. For internal use only. Do not distribute.

Hyperion Planning – Initial Design

Reports

AcctPeriodGeoEntityYearScenarioVersion

AcctPeriodGeoEntityYearScenarioVersion

Project

ProjectEmployee

RevscogsInput/Calc/Agg

OpexprojInput/Calc/Agg

WrkforceInput/Calc/Agg

CNFX3Calc/Agg

AcctPeriodGeoEntityYearScenarioVersion

CMFX3Calc/Agg

Page 7: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

7Confidential. For internal use only. Do not distribute.

Issues with original design

Biggest complaintfrom end users

Page 8: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

8Confidential. For internal use only. Do not distribute. 88

BSOInput/Calc/Translate

Redesign - “Rocket the data”

ASOAggregate

1. Faster Aggregation2. Input/Calc and translate in BSO (CVPLN)3. Move zero level data to ASO4. Aggregate in ASO

Result: Moves the aggregation function to the ASO database

Page 9: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

9Confidential. For internal use only. Do not distribute.

Hyperion Planning Re-design Highlights

Page 10: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

10Confidential. For internal use only. Do not distribute.

Hyperion Planning – Big Wins

1. Currency Modeling – Previously we did not load plan/forecast data in local currency therefore it was very difficult to run accurate currency modeling. Now that all countries input in local dollars, we have a very accurate way to model planning data at different FX rate assumptions.

2. Currency Neutralization – All countries submit in local dollars, we are able to run currency neutral at all rates. This used to be maintained offline in Excel spreadsheets

3. One Global Planning System – We have one Planning system that is supported centrally by the EFS. This gives us transparency into the numbers since everyone is using the same system, provides more discipline in the planning process and serves as “one version of the truth”.

4. 15 Month AOP cycle – Beginning with FY12 Forecast4.1/FY13 AOP we implemented a 15 month rolling forecast. This allowed users ability to stay within one form instead of switching between cycles.

Page 11: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

11Confidential. For internal use only. Do not distribute.

Hyperion Planning – Lessons LearnedLessons Learned

1. STJ Involvement – The majority of the project was designed and led by ExternalConsultants. The EFS team was not established until November 2010. We should have had full-time

dedicated STJ resources on the project from day 1.

2. Data Reconciliation - The effort of data reconciliation was significantly underestimated and we ultimately went live with no historical data.

3. Phased Implementation – We should have gone with a phased implementation (by division or by plan type) rather than implementing all divisions, all plan types at one time.

4. Delay Workforce – We should have looked at phasing in the workforce cube after all users were comfortable with the new Planning system. Workforce is definitely the most complicated cube type and initially EFS spent majority of production support on workforce related issues.

5. Financial Reports – too much time was spent on developing F/R reports that were never used. As time has gone by, we have started to create more reports, but in the beginning, 100% of the reporting was coming out of Spreadsheet Add-in or SmartView.

6. Consistency of Metadata – It is important to set standards and naming conventions at the start of the project so that your application is clean and consistent across all the dimensions.

7. Detailed Documentation within Calc Scripts– The best place to document what a Calc script is doing is within the calc script itself. If all of your Calc Scripts have good documentation it will allow for easier knowledge transfer between external consultants and internal resources.

8. Use of Global Forms – Important to get agreement with all divisions on web form design so you can use “global” forms that apply to all divisions rather than creating customized divisional web forms as it is more objects to maintain/update on a go-forward basis.

Page 12: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

12Confidential. For internal use only. Do not distribute.

DRM – Data Relationship Manager

EFS TeamMaintains all metadata

Division FP&A users rely heavily on DRM to

view hierarchies

Page 13: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

13Confidential. For internal use only. Do not distribute.

Why did we upgrade to 11.1.2.2

Version 11.1.2.2

We struggled with EPMA in the 11.1.1.3 versionGIT was heavily pushing physical to virtual serversErroneous Data Issue in 11.1.1.3 that was fixed in version 11.1.2.2SmartView enhancements with the new version of 11.1.2.2Organization Announcement drove many changes to web forms/metadata HFM and Planning need to be on the same version because they closely aligned and share workspace and/or metadata

Page 14: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

14Confidential. For internal use only. Do not distribute.

What was included in the Upgrade

Page 15: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

15Confidential. For internal use only. Do not distribute.

Lessons Learned of Upgrade

Page 16: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

16Confidential. For internal use only. Do not distribute.

Hyperion Enterprise Overview

Page 17: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

17Confidential. For internal use only. Do not distribute.

HFM Implementation

Goals/ObjectivesApply Lessons Learned from HP & Upgrade

Ensure that project was on time, on budget with no critical issues.

Avoid recreating Enterprise

Stepped back during requirements gathering to ensure we designed HFM to meet external reporting needs and not re-create Enterprise.

Centralize Mappings We wanted to implement more control to gain consistent and more accurate mapping of actuals

Project Team Smaller project team, longer burn rate. SME’s from STJ involved from day one of the project

HFM / HP Don’t duplicate data in multiple systems. Use HFM for what it was intended for.

Page 18: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

18Confidential. For internal use only. Do not distribute.

Key Design Elements of HFM

Page 19: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

19Confidential. For internal use only. Do not distribute.

Current Hyperion Environments

Page 20: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

20Confidential. For internal use only. Do not distribute.

HFM Project Team

STJExternals

Magic of the Project Room•Project Team sat together from Day one. •Knowledge Transfer between externals & employees occurred on a daily basis•Impromptu Design / White board discussions early on and throughout project•No surprises•Team camaraderie

Page 21: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

21Confidential. For internal use only. Do not distribute.

FDM Batch Automation

Page 22: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

22Confidential. For internal use only. Do not distribute.

HFM Successes

Measure of Success

Project was on time, under budget with no defects heading into Go-live

We actually closed January quicker than we had in Enterprise for the first month under HFM

Data reconciliation was led by SME’s

We had 2 years of historical data in HFM within 2 months of having our dimensions built. By July of 2013 we were pretty much a week behind the official Hyperion Enterprise Close

Requirement Sign-off were held in person with all divisions meeting to walk through requirements

We had very little change requests or scope creep

Training was delivered by EFS TeamUser acceptance of HFM was very high and they picked up the new tool very quickly.

Unit Testing, UAT and Parallel Closes were very successfulWe completed 3 rounds of parallel testing and were able to close out all defects prior to Go-live

Knowledge Transfer occurred during project

We were able to roll off the external consultants within 1 week of closing the books for January. EFS team was ready to support the application

Page 23: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

23Confidential. For internal use only. Do not distribute.

HFM Successes (cont’d)

Measure of Success

Out of box I/C Matching Reduced many manual hours spent on reconciling I/C matching reports

HFM Supplemental Web Forms

Huge gain in efficiencies by our SEC and Tax Department by leveraging HFM web forms. They now spend time analyzing the data instead of ticking & tying the data.

Duplicate Data No longer spend time reconciling detailed data between all the systems.

Accuracy of data mappingsThe reconciliation between source G/L (primary SAP) and HFM is almost automatic

Financial ReportingWe only created minimum amount of F/R reports in HFM. Users still tend to like Excel based reports.

Cash Flow by Legal EntityUtilize the HFM supplemental web forms to roll forward assets, Liab and equity and cash flow has been 85% automated

Page 24: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

24Confidential. For internal use only. Do not distribute.

HFM – BIG WIN

Page 25: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

25Confidential. For internal use only. Do not distribute.

EFS Support Model

Page 26: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

26Confidential. For internal use only. Do not distribute.

Project ReOrg

Announced inJanuary 2014

In Production By July 2014

HFM was NOTImpacted!!!

Cutover wasSmooth &

System was stable

Page 27: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

27Confidential. For internal use only. Do not distribute.

EnterpriseFinancialSystems

Team

User Counts

Page 28: Integrated Business Plan - HUGmnhugmn.org/Downloads/STJ - HUGmn Pres… · PPT file · Web view · 2017-05-01HUGMN User Group Meeting ... Redesign of Hyperion Planning Big Wins

28Confidential. For internal use only. Do not distribute.

Our Journey over the past 4 years