+ All Categories
Home > Documents > INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors...

INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors...

Date post: 20-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
12
Appendix A INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019-20 1. INTRODUCTION 1.1 This report summarises the activity carried out during 2019-20 by the Internal Audit team of the Finance and Governance Directorate and has contributed to the Council’s Annual Governance Statement. 2. INTERNAL AUDIT 2.1 The 2019-20 Internal Audit plan was presented to the Audit and Governance Committee in June 2019. The responsibility for delivering the internal audit plan lies with the Head of Internal Audit, supported by a small in-house team of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery partners to deliver the internal audit plan. For the financial year 2019-20, this was a joint provision by PwC, Mazars and FIT Business Solutions. 2.2 As at the date of this report, 92% of our full audits were at draft or final report stage: 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 88% 98% 98% 98% 94% 92*% * There has been an impact on ability to conclude remaining jobs as a direct result of Covid-19 response efforts. 2.3 However, an audit is not fully complete until the final report is issued, which normally only happens once a formal response from the client has been received. The Head of Internal Audit is conscious that there are a few audits that are still at draft report stage and will work to finalise these. 2.4 High risk (formerly known as Priority 1) recommendations which are due have either been followed up or are in progress. 2.5 As in previous years, Internal Audit has experienced delays in achieving engagement from some managers to start internal audits, and where draft reports have been issued, to bring them to a conclusion. The Head of Internal Audit will continue to work with senior managers throughout the year to improve this. However, it should also be recognised that some expected changes to the level of engagement received have materialised in Quarter 4 2019-20, as a direct result of the Covid-19 response efforts. 2.6 The level of performance achieved during the year has largely been due to the in-house team working closely with the internal audit delivery partners to deliver an effective internal audit service. The Head of Internal Audit will be further building on this with the delivery partners, via the Apex framework and the Cross-Council Assurance Service. 2.7 The high priority main financial (fundamental) systems were examined during the year as these are regarded as high priority mainly due to the high volumes
Transcript
Page 1: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

Appendix A INTERNAL AUDIT TEAM

ANNUAL ACTIVITY REPORT FOR 2019-20

1. INTRODUCTION

1.1 This report summarises the activity carried out during 2019-20 by the Internal Audit team of the Finance and Governance Directorate and has contributed to the Council’s Annual Governance Statement.

2. INTERNAL AUDIT

2.1 The 2019-20 Internal Audit plan was presented to the Audit and Governance Committee in June 2019. The responsibility for delivering the internal audit plan lies with the Head of Internal Audit, supported by a small in-house team of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery partners to deliver the internal audit plan. For the financial year 2019-20, this was a joint provision by PwC, Mazars and FIT Business Solutions.

2.2 As at the date of this report, 92% of our full audits were at draft or final report stage:

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20

88% 98% 98% 98% 94% 92*%

* There has been an impact on ability to conclude remaining jobs as a direct result of Covid-19 response efforts.

2.3 However, an audit is not fully complete until the final report is issued, which

normally only happens once a formal response from the client has been received. The Head of Internal Audit is conscious that there are a few audits that are still at draft report stage and will work to finalise these.

2.4 High risk (formerly known as Priority 1) recommendations which are due have either been followed up or are in progress.

2.5 As in previous years, Internal Audit has experienced delays in achieving engagement from some managers to start internal audits, and where draft reports have been issued, to bring them to a conclusion. The Head of Internal Audit will continue to work with senior managers throughout the year to improve this. However, it should also be recognised that some expected changes to the level of engagement received have materialised in Quarter 4 2019-20, as a direct result of the Covid-19 response efforts.

2.6 The level of performance achieved during the year has largely been due to the in-house team working closely with the internal audit delivery partners to deliver an effective internal audit service. The Head of Internal Audit will be further building on this with the delivery partners, via the Apex framework and the Cross-Council Assurance Service.

2.7 The high priority main financial (fundamental) systems were examined during the year as these are regarded as high priority mainly due to the high volumes

Page 2: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

and values of transactions, together with other key operational and non-fundamental areas highlighted in the Audit Plan. For these audits, a level of assurance is given on the effectiveness of the internal control that are in place and any recommendations made to enhance controls or processes are graded according to the severity of the issue to be rectified.

2.8 With regard to school audits, in the 2019-20 financial year, Internal Audit re-commenced full reviews of each school; with the aim to complete the full schedule of maintained schools in the Borough by 2021-22. This entails a review of all financial and statutory areas and replaced the ‘themed approach’ which was previously in place for 2018-19. The work is non-chargeable; however, Internal Audit will receive its share of funding from the maintained schools’ budget.

2.9 For all our full audits, we issue an assurance rating, the descriptions of which for 2019-20 are as follows:

Substantial Assurance - No significant improvements are required. There is a sound control environment with risks to key service objectives being well managed. Any deficiencies identified are not cause for major concern.

Reasonable Assurance - Scope for improvement in existing arrangements has been identified and action is required to enhance the likelihood that business objectives will be achieved.

Limited Assurance - The achievement of business objectives is threatened and action to improve the adequacy and effectiveness of the risk management, control, and governance arrangements is required. Failure to act may result in error, fraud, loss or reputational damage.

No Assurance - There is a fundamental risk that business objectives will not be achieved, and urgent action is required to improve the control environment. Failure to act is likely to result in error, fraud, loss or reputational damage.

The recommendation classifications used during 2019-20 were as follows: -

Critical - Life threatening or multiple serious injuries or prolonged workplace stress. Critical impact on the reputation or brand of the organisation which could threaten its future viability. Cessation of core activities or major financial loss.

High - Major issue for the attention of senior management and the Audit & Governance Committee. Action to be effected within 1 to 3 months.

Medium - Important issues to be addressed by management in their areas of responsibility. Action to be effected within 3 – 6 months.

Low – Minor issues resolved on site for local management. Action usually to be effected within 6 months to 1 year.

2.10 The graph / tables below shows a classification of the assurance levels for the audits carried out 2019-20, then a breakdown of all assurance ratings given in

Page 3: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

2019-20 (more details of the limited and no assurance audits can be seen in Appendix 3).

Page 4: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

Internal Audit Reviews 2019-20

3. FINAL REPORTS

No Audit Directorate Assurance

Level

Action Priorities

Critical High Medium Low

1 Heathcote School Families No 0 2 13 9

2 Stoneydown Park Primary School

Families Limited 0 3 5 1

3 Assessment and Placements

Families Limited 0 2 0 3

4 Off Payroll Engagements and IR35 Rules

Cross Cutting Limited 0 2 1 0

5 Procurement Finance & Governance Limited 0 2 1 2

6 Capital Budgets & Monitoring

Cross Cutting Reasonable 0 0 2 0

7 Settlement Agreements Cross Cutting Reasonable 0 0 4 4

8 Regeneration Project - Lea Bridge

Economic Growth Reasonable 0 0 3 3

9 Regeneration Project - the Score

Economic Growth Reasonable 0 0 4 2

10 Acacia Nursery School Families Reasonable 0 0 4 2

11 Greenleaf Primary School Families Reasonable 0 0 9 4

12 Handsworth Primary School

Families Reasonable 0 0 1 4

13 Holy Family Catholic School

Families Reasonable 0 0 3 3

14 Kelmscott School Families Reasonable 0 0 4 5

15 Asylum Spend Families Reasonable 0 1 0 0

16 St Mary's Catholic Primary School

Families Reasonable 0 0 3 3

17 Cash and Bank Finance & Governance Reasonable 0 0 2 0

18 Data Protection Security Toolkit

Finance & Governance Reasonable 0 0 1 0

19 Mortuary Finance & Governance Reasonable 0 0 2 2

20 Construction Industry Scheme

Finance & Governance Reasonable 0 0 4 3

21 Budgetary Control & Reporting

Finance & Governance Reasonable 0 1 1 1

22 Accounts Payable Finance & Governance Reasonable 0 0 1 1

23 Accounts Receivable Finance & Governance Reasonable 0 0 1 1

24 Central Accounting Finance & Governance Reasonable 0 0 1 1

25 Housing Health and Safety Checks

Finance & Governance Reasonable 0 0 2 0

26 Anti-Social Behaviour Resident Services Reasonable 0 0 7 1

27 Food Safety Resident Services Reasonable 0 0 1 3

28 Blue Badge Applications Resident Services Reasonable 0 0 4 4

29 Community Ward Funding Grants

Resident Services Reasonable 0 0 5 3

30 Repairs and Maintenance Resident Services Reasonable 0 1 9 5

31 Housing Capital Programme

Resident Services Reasonable 0 0 6 0

Page 5: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

No Audit Directorate Assurance

Level

Action Priorities

Critical High Medium Low

32 Capital Receipts Resident Services Reasonable 0 0 1 3

33 Complaints Resident Services Reasonable 0 0 3 3

34 Ainslie Wood - Key Risk Audit Chargeable

Families Substantial 0 0 1 2

35 NNDR Finance & Governance Substantial 0 0 1 2

36 Risk Management (Actions N/A, as advisory in nature).

Finance & Governance Substantial N/A N/A N/A N/A

37 Council Tax Finance & Governance Substantial 0 0 2 0

38 Housing Rents Resident Services Substantial 0 0 0 2

39 Housing Service Charges & Leaseholders

Resident Services Substantial 0 0 0 0

40 ICT Audit - ICT and Digital Strategy - Review of Activity and Progress (Management Letter Only)

Corporate Development

No Opinion applicable

N/A N/A N/A N/A

41 Grants Claims: Troubled families April - July 2019

Families No Opinion applicable

N/A N/A N/A N/A

42 Grants Claims: Troubled families August - October 2019

Families No Opinion applicable

N/A N/A N/A N/A

43 Grant Claims: Troubled families Nov-19 to Mar-20

Families No Opinion applicable

N/A N/A N/A N/A

44 Grant Claims - The Rise Project 2017-18

Families No Opinion applicable

N/A N/A N/A N/A

45 Hawkswood Primary School (Follow-up)

Families No Opinion applicable

N/A N/A N/A N/A

4. DRAFT REPORTS (Final Opinions TBC)

No Audit Directorate Provisional Assurance

Level

Action Priorities

Critical High Medium Low

46 ICT Audit - Asset Management including licensing Q2/3

Corporate Development

No 0 7 7 2

47 ICT Audit - Cyber Security Q2

Corporate Development

Limited 0 4 8 1

48 Chingford CofE Infant/Junior School

Families Substantial 0 0 1 3

5. FIELDWORK ONGOING

5.1 As a result of re-deployments to front line services, for staff within the Internal Audit Team (in response to Covid-19), there has been some impact on our ability to conclude all remaining fieldwork. Equally, auditees leading on these reviews have been impacted themselves, reducing their capacity to assist and facilitate timely conclusion.

5.2 The following audits remain ongoing, at varying levels of completeness. Internal Audit Management are now considering options. For those that are advanced sufficiently to enable draft reporting, this will take place as soon as

Page 6: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

possible. Where testing has not progressed in entirety, an overall opinion may be awarded based on the evidence that was available for examination, or a decision may be taken to withhold an overall assurance opinion. Some high-level reporting may still occur to clarify the position taken.

No Audit Directorate Assurance

Level

Action Priorities

Critical High Medium Low

Adult Services Income Families

Opinion TBC (Fieldwork Ongoing)

TBC TBC TBC TBC

Managing Change Process

Corporate Development

Opinion TBC (Fieldwork Ongoing)

TBC TBC TBC TBC

Schools Traded Services Debtors

Corporate Development

Opinion TBC (Fieldwork Ongoing)

TBC TBC TBC TBC

Shared Pension Service (Note: This is an external review)

Finance & Governance

Opinion TBC (Fieldwork Ongoing)

TBC TBC TBC TBC

Page 7: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

6. FOLLOW UP OF INTERNAL AUDIT RECOMMENDATIONS

6.1 Where control or operational issues are identified during internal audits, recommendations to rectify these issues are agreed with operational managers and form part of the final audit report. It is therefore vital that management’s progress on implementing the recommendations is reviewed to identify whether improvements have been made and the control issues removed.

6.2 Table 1 below shows the follow-up reviews that have been undertaken between April 2019 and March 2020. It should be noted that no further follow-up work has been progressed since this time, to avoid putting unnecessary pressure on service areas at the time of the Covid-19 lockdown.

Table 1 - Full Follow-up Reviews Completed in 2019-20

No.

Follow-up Reviews

Year of Original

Audit Directorate

Priority 1s in

Original Audit Due

Priority 1 Implementation

Fully Partially Not

Implemented

No longer

Relevant

1 HCL Axon –

Contract Management

2017-18 Finance and Governance

2 2 - - -

2 School - Henry

Maynard 2018-19 Families 3 3 - - -

3

Tenant Management Organisations

(TMOs)

2018-19 Resident Services 1 1 - - -

4 Off Payroll

Engagements and IR35 Rules

2017-18 Neighbourhoods and Commercial

1 1 - - -

5

Disclosure & Barring Service

(DBS) and Identification

Checks

2018-19 Resident Services 2 2 - - -

6

Contract Management (Facilities –

Amey)

2017-18 Resident Services 3 - - - 3

7 Lettings Waltham

Forest – Market

2018-19 Families 1 - 1 - -

Page 8: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

No.

Follow-up Reviews

Year of Original

Audit Directorate

Priority 1s in

Original Audit Due

Priority 1 Implementation

Fully Partially Not

Implemented

No longer

Relevant

Rent Scheme

8 School -

Hawkswood Group

2018-19 Families 5 5 - - -

9 Schools -

themed - DBS checks

2018-19 Families 2 1 1 - -

10 Leavers 2017-18 Resident Services 1 - 1 - -

11

ICT - Access Rights and

System Access – High

Privileged Access

2018-19 Corporate

Development 2 - 2 - -

12

ICT - Post Implementation Review Mosaic Upgrade and

Reporting

2018-19 Corporate

Development 4 - 3 1 -

13 ICT Change Management

2017-18 Corporate

Development 4 2 2 - -

14 ICT Audits -

Mobile Computing

2016-17 Corporate

Development 8 5 3 - -

15 ICT BACS Processing

Audit 2017-18

Corporate Development

10 7 1 2 -

Totals 49 29 14 3 3

6.3 As previously reported to Committee, a further review was undertaken in November 2019 to follow up on the process of the Hawkswood Group following the audit which was undertaken in May 2018.

6.4 The Hawkswood Group follow-up report has been included at Appendix 4.

Page 9: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

6.5 Table 2 below shows the number of remaining audits where there are outstanding priority 1 recommendations that require follow-up.

(Priority 1 findings are classified as high risk from 2019-20).

Table 2 – Summary of Outstanding P1 Recommendations

No. Year of Original

Audit Title

Number raised in Original

Audit

Status of Implementation

Fully Partially Not

Implemented

No longer

relevant

1 2019/20 Budgetary Control and Reporting

1 verification planned for Summer 2020

2 2019/20 Procurement 2 verification planned in May / June 2020

3 2019/20 Stoneydown Park School

3 verification planned for Summer 2020

4 2018/19 ICT - Disaster Recovery

2 verification to be arranged

5 2018/19 Payment Cards 3 verification planned for Summer 2020

6 2018/19 Payroll 1 verification planned for Summer 2020

7 2018/19 Assessments and Placements

2 verification planned for Summer 2020

8 2018/19 Emergency Planning and Business Continuity

1 - 1 - -

9 2018/19 Kingdom Contract Management

1 verification planned for Summer 2020

19 2018/19 Recruitment 1 - 1 - -

11 2018/19 Supplier Resilience 2 verification planned for Summer 2020

12 2017/18 Homelessness 1 verification planned for Summer 2020

13 2017/18 Registrars 3 1 2 - -

14 2017/18 Traded Services 3 verification planned for Summer 2020

15 2017/18 Schools - Health and Safety

3 verification planned for Summer 2020

16 2017/18 Commercial Property 2 verification planned for Summer 2020

17 2017/18 Housing Management File Management and Data Retention

6 verification planned for Summer 2020

18 2016/17

Freedom of Information and Subject Access Requests

2 verification being carried out as part of 2020/21 FoI / SARs review

19 2016/17 ICT I-World Housing Application Review

7 6 1 - -

20 2016/17 IT Performance & 4 3 1 - -

Page 10: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

No. Year of Original

Audit Title

Number raised in Original

Audit

Status of Implementation

Fully Partially Not

Implemented

No longer

relevant

Governance

21 2015/16 Schools Construction Contracts

2 verification planned for Summer 2020

52 10 6 - -

Note: there are 52 P1 recommendations to be followed up. We have carried out some preliminary work in respect of 16 and the remaining 36 will be picked up during planned verification work.

7. AUDIT PLAN 2019-20

7.1 The Public Sector Internal Audit Standards (PSIAS) require public sector Internal Audit services to produce a plan of work that they propose to carry out during the year. The purpose of the plan is to ensure that the available audit resources are used effectively and are targeted towards the key and high-risk areas of the Council’s activities.

7.2 The previous CIPFA Code recommended that the audit plan is fixed for a period that is no longer than twelve months and is sufficiently flexible to accommodate changes in risks and priorities that arise during the period covered by the plan. This remains sound operational sense when organisations are faced with significant amounts of change as it enables the audit plan to be reviewed and revised to meet the demands of changing circumstances.

7.3 In compiling the internal audit plans, the Head of Internal Audit has taken into consideration a number of factors including, but not limited to:-

The risk registers and the risk categories used in compiling the risk registers, together with Internal Audit’s own assessment of risk in the operational areas;

The adequacy of the risk management, performance management, and other assurance processes such as internal and external reviews;

The requirements of the external auditors and their ability to place reliance on the work of Internal Audit in forming their opinion on the Council’s Financial Statements;

The extent and scope of audit activity in previous years, including the previous audit reports and recommendations made to strengthen controls or enhance systems;

Page 11: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

The requirements of regulations and legislation, and external factors such as grant conditions, and the views of senior managers in individual directorates.

7.4 The internal audit plan covers the activities of the Council that have to be audited annually, together with the areas where the Head of Internal Audit considers are in need of or are due an independent Internal Audit review. The internal audit plan is delivered by the in-house team and the Council’s internal audit delivery partner.

7.5 The draft 2019-20 internal audit plan was presented to, and agreed by, the Audit and Governance Committee in June 2019. The internal audit plan is however dynamic and subject to change during the course of the year to reflect the needs of the Authority. As predicted, some changes to the 2019-20 audit plan were made during the year and these are set out in the table at Appendix B.

8. QUALITY ASSURANCE OF INTERNAL AUDIT WORK

8.1 In relation to quality assurance, measures are in place to ensure that Internal Audit reports and fieldwork are stringently checked. This applies to in-house and delivery partner audits and following to managerial checks, all work is then reviewed by the Council’s Head of Internal Audit before being issued. In addition, the External Auditor examines internal audit reports.

9. ICT AUDIT WORK

9.1 At the beginning of 2017-18, a fully qualified consultant IT auditor was engaged to carry out the Council’s ICT audits. From 2020-21, PwC will instead provide this service.

10. COMPLIANCE WITH THE PUBLIC SECTOR INTERNAL AUDIT STANDARDS

10.1 The Public Sector Internal Audit Standards (PSIAS) came into effect on 1st April 2013 and were last updated in August 2017. As defined in the Internal Audit Charter and Internal Audit Strategy, Internal Audit always comply with the PSIAS. A peer reviewed self-assessment against the PSIAS will be undertaken during 2020-21 with our Shared Service partner at Enfield Council.

11. RISK MANAGEMENT ARRANGEMENTS

11.1 The Council has a risk management processes in place to identify, assess and manage the significant business risks to the Council’s objectives. The risk management process includes a risk management strategy and policy that are reviewed annually and agreed by the Audit and Governance Committee. Waltham Forest Council has in place strategic and operational risk registers, and the Council’s Governance Board and its Audit and Governance Committee periodically review these risk registers.

11.2 The Risk Management Strategy and Policy was last revised during 2018-19 and has been applied throughout 2019-20. Update reports and the strategic risk register have been presented to committee meetings during the year.

Page 12: INTERNAL AUDIT TEAM ANNUAL ACTIVITY REPORT FOR 2019 …€¦ · of an Audit Manager, three Auditors and one apprentice Auditor. The Head of Internal Audit also works with delivery

11.3 In preparing the 2019-20, internal audit plan, Internal Audit referred to the operational, directorate and corporate risk registers to identify key risk that would need to be audited during the year.

11.4 Risk management training is provided for staff and Members. Waltham Forest Council’s risk maturity is currently at the ‘Risk Defined’ level (level 3) on the Institute of Internal Auditors five-point risk maturity scale.

12. UPDATE ON 2020 WORK AND COVID19 RESPONSE

12.1 At the start of the financial year 2020-21, the Audit Plan work was suspended due to the Council responding to the Covid19 pandemic and Internal Audit officers were redeployed to assist with the response.

12.2 Work started on looking at Covid-19 specific risks in June 2020 being led remotely by our delivery partner PwC. This has included a review of Remote and Home Working arrangements, and a specialist Accounts Payable review using data analytics, and forms part of the Covid-19 assurance work which includes considerations of how we can deliver an effective internal audit function in the future.


Recommended