  • 8/9/2019 Introduction to Projects for Project Administrators

    1/54

    Oracle Financials

    Training Guide

    Introduction to Projects for Project Administrators

    IT Services Training Team

    The University of Manchester

    email:[email protected]

    www.itservices.manchester.ac.uk/trainingcourses/coursesforstaff

    Version:4.1

    mailto:[email protected]:[email protected]:[email protected]://www.itservices.manchester.ac.uk/trainingcourses/coursesforstaffhttp://www.itservices.manchester.ac.uk/trainingcourses/coursesforstaffhttp://www.itservices.manchester.ac.uk/trainingcourses/coursesforstaffmailto:[email protected]
  • 8/9/2019 Introduction to Projects for Project Administrators

    2/54

  • 8/9/2019 Introduction to Projects for Project Administrators

    3/54

    Table of Contents

    1 Introduction .............................................................................................................. 41.1 What is a Project? ............................................................................................................. 51.2 RMS and Oracle Projects .................................................................................................... 5

    1.3

    User Roles ........................................................................................................................ 5

    2 Interactions with Other Oracle Modules ................................................................... 63 Project Status Flows ................................................................................................. 84 Tasks ......................................................................................................................... 94.1 Additional Top Tasks ....................................................................................................... 105 Oracle Projects Terms ............................................................................................. 115.1 Key Members .................................................................................................................. 115.2 Customers ...................................................................................................................... 115.3 Agreements .................................................................................................................... 125.4

    Service Types (HESA Code) .............................................................................................. 12

    5.5 Transaction Controls ........................................................................................................ 125.6 Burden Schedules ............................................................................................................ 125.7 Project Events ................................................................................................................. 126

    Logging on to Oracle Financials .............................................................................. 13

    7 The Top Ten List ...................................................................................................... 148 Project Status Inquiry Screen ................................................................................. 159

    Data Displayed on the Main PSI Screen .................................................................. 16

    9.1 Drilling Down for More Data ............................................................................................. 179.2 Viewing Project Information ............................................................................................. 189.3 Viewing Commitments ..................................................................................................... 219.4 Viewing Commitment Details ............................................................................................ 229.5 Accessing Task Status ..................................................................................................... 239.6 Drilling Down from the Task Status Window ...................................................................... 2510 Expenditure Inquiry Screens .................................................................................. 2610.1 Searching by Project Number/Name or Task Number/Name ............................................... 26

    10.2

    Searching by Item Dates .................................................................................................. 27

    10.3 Searching by Expenditure Batch (Project Journals) ............................................................ 2710.4 Searching by Inventory Item ............................................................................................ 2810.5 Searching by Transaction Source ...................................................................................... 2810.6 Searching by Expenditure Type ........................................................................................ 2910.7 Drilling Down from the Expenditure Inquiry Screens .......................................................... 3011 My Projects ............................................................................................................. 3211.1 Searching with a Project Number ..................................................................................... 3511.2 Searching with the Project Name ...................................................................................... 3511.3 Searching by Key Member................................................................................................ 3511.4 Searching by Faculty/School Code .................................................................................... 3612 PA Reports .............................................................................................................. 37

    12.1

    Running a Report ............................................................................................................ 3712.2 Printing a Report ............................................................................................................. 38

    12.3

    Exporting a Report .......................................................................................................... 40

    13 Help and Support .................................................................................................... 4114 Document Retention Policy .................................................................................... 4215 Appendix AShortcuts and Function Keys ............................................................ 4516 Appendix BToolbars ............................................................................................ 4817 Appendix CExporting Oracle Projects Data......................................................... 4918 Appendix D - Cross Reference RMS/Oracle Projects .............................................. 5219

    Reference Glossary ................................................................................................. 54

    19.1 Accessing Documentation ................................................................................................ 5419.2 Accessing the Live System ............................................................................................... 54

  • 8/9/2019 Introduction to Projects for Project Administrators

    4/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 4

    1 Introduction

    This manual gives you an overview of Oracle Financials Projects module and introduce you to keyconcepts. You will learn how to work with a research project in Oracle Projects.

    This manual covers basic Oracle Projects terminology and the Project Status Inquiry screen, which isused to view data about projects.

    It is written for project administrators, in particular, for people who will create journals againstprojects.

    DISCLAIMERS: This course covers the centralised processes involved inproject accounting in Oracle Projects. It does not cover how to manage aresearch project, how to cost or bid for grants, or how to use RMS. It does notcover local faculty or school procedures for managing projects, nor will it trainyou to be an accounting officer, if you have no previous experience.

    The Oracle Financials system is still under development as this manual is beingwritten. Some details of the system may change in future; updated versions ofthe manual will be made available on the training web site as changes aremade.

    Training on Oracle Projects consists of several courses:

    For Research Project Managers

    Introduction to Projects for Project Managers Project Journals Project Invoicing

    For Research Project Administrators

    Introduction to Projects for Project Administrators Project Journals

  • 8/9/2019 Introduction to Projects for Project Administrators

    5/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 5

    1.1 What is a Project?

    Oracle Projects helps the University work with projects where:

    The project has a definite start and end date outside the Universitys financial year or if theproject crosses a year end.

    A specific award funds the project.

    The University needs to analyse costs differently than the General Ledger activity codes. Forexample, with Oracle Projects, computers can appear in Consumables for project accounting,but in Equipment in the GL.

    1.2 RMS and Oracle Projects

    In future, new research projects will start in the PreAward system in RMS. After award, an interface

    program will move these projects to Oracle Projects.

    NOTE: Integration - The PreAward portion of the RMS system will beintegrated with Oracle Projects. Oracle Projects will manage the post-awardfinancial aspects of a project. RMS will still handle research projects prior toaward. Research projects will start their life in the (PreAward) RMS. They willmove to Oracle Projects after award.

    Project numbers are automatically assigned by Oracle Projects. The numbers consist of a letter prefix,plus a six digit number:

    Research Projects (R)

    Other Projects (P -- non-Research, non-Estates)

    In this manual, we will consider Research projects only. R100034 is an example of a typical Researchproject number. The same number is used as the projects General Ledger code.

    1.3 User Roles

    User roles determine what menu options you can view within Oracle Projects. Three user roles havebeen defined for the Projects module: Project Manager, Project Administrator and Project

    Inquiry. Oracle Financials calls these roles responsibilities.

    This table summarises the main tasks that each user role/responsibility can perform:

    Project Manager Edit project record

    Create budgets

    Create journals

    Create invoices

    Project Administrator View project data

    Create journals

    Project Inquiry View project data

  • 8/9/2019 Introduction to Projects for Project Administrators

    6/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 6

    2 Interactions with Other Oracle Modules

    The diagram on the following page shows links between the Projects module and other modules inOracle Financials. Specifically, some processing, while affecting project accounting, doesnt occur

    within the Projects module.

    Referring to the diagram on the following page:

    Oracle Projects doesnt raise requisitions or purchase orders for projects (do this within iProc or Oracle Purchase Ordering modules)

    Oracle Projects doesnt manage supplier invoices or payments(managed within the Oracle Accounts Payable module)

    Oracle Projects does create invoices and claims for projects

    (data is passed to the Oracle Accounts Receivable module)

    Oracle Projects doesnt manage debtor/funder receipts(handled by the Oracle Accounts Receivables module)

    However, all data relevant to a project, regardless of where initiated, passes to Oracle Projects.Various screens within Projects allow you to drill down to the original transaction, even if wheninitiated outside the Projects module.

    Why is this important? One reason: Requisitions and purchase orders for projects must be enteredwith the required identifying data about the project to be charged.

  • 8/9/2019 Introduction to Projects for Project Administrators

    7/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 7

    DiagramInteractions with Other Oracle Modules

  • 8/9/2019 Introduction to Projects for Project Administrators

    8/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 8

    3 Project Status Flows

    In general, projects go through several stages. Oracle Projects calls a stage of the project its status.As an example, the status flow for grants is shown below. The status flow for contract projects is very

    similar.

    G-Award In Prep

    G-Awarded notActivated

    G-Pending Closed

    G-Awarded

    G-Closed

    Status Flow for Grants (Post Award)

    Project setupFund project from agreement

    Create budgets

    Add costsCreate invoices/revenues

    Journals

    Journals

    The project status determines the order in which activities can be undertaken on a project; the right

    column of the diagram above lists the activities occurring at each stage. Also note that it is possible tomove backwards between some stages, say from G-Pending Closedback to G-Awarded.

    You will not be able to post transactions or create journals against a project until the status is setappropriately by the Project Manager.

  • 8/9/2019 Introduction to Projects for Project Administrators

    9/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 9

    4 Tasks

    Oracle Projects organises projects into smaller units called tasks. By default, any project has at leastone task, the Top Task.

    TIP:Tasks may seem like a strange name for what you might call theprojects activities. Remember that Oracle Projects has been designed as aflexible system, capable of dealing with projects undertaken by anything fromconstruction companies to multinational corporations to universities like ours.

    Task Structure

    Tasks are organised in a hierarchy. For example, the tasks below could appear in a Research Councilproject. The projects tasks correspond to categories normally found in claims.

    Task A - Funder - Research CouncilA01 - StaffA02 - Student MaintenanceA03 - Student FeesA04 - FeesA05 - Travel & SubsistenceA06 - EquipmentA07 - ConsumablesA08 - MiscellaneousA99 - Indirect Costs

    NOTE: Research Council projects should use the numbering scheme shownabove. If a category, such as A02 Student Maintenance is not applicableto a project, it may be deleted, but the other subtasks, such as A03StudentFees will not be renumbered to close the gap. This means that similar projectswill have similar task lists, with gaps where unnecessary tasks were removed.

    NOTE:fEC projects will be transferred from the RMS with an appropriate taskstructure that differs somewhat from the one illustrated above. The principlesfor working with tasks are the same regardless of the whether the project usesfEC.

    NOTE:The latest Task list can be found at:http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/proj/

    http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/proj/http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/proj/http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/proj/
  • 8/9/2019 Introduction to Projects for Project Administrators

    10/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 10

    4.1 Additional Top Tasks

    Oracle Projects allows the University to analyse the finances of relatively complex research projects.One tool for doing this is to add a second top task to a project. Here are several examples of projects

    where it would be useful to have more than one top task:

    Example: A project with two funder/debtors, each with its own indirect cost schedule (called theburden schedule in Oracle). Each funder/debtor has its own task (A and B), and a different indirectcost schedule is assigned to each funder/debtors task. fEC Projects are always set to No IndirectCosts.

    Heres a sample list of tasks for a project:

    Task AFunder/DebtorUK Industry

    A01: StaffA04: FeesA07: ConsumablesA99: Indirect Costs

    Task B - FunderUK Central Government

    B01: StaffB04: FeesB07: ConsumablesB99: Indirect Costs

    Example:A project where another University works as a subcontractor. The project itself is assignedto Task A; the subcontracting University is assigned to Task B. Heres a sample list of tasks for aproject:

    Task AFunder/DebtorResearch Council

    A01: StaffA05: TravelA06: EquipmentA07: ConsumablesA99: Indirect Costs

    Task B - FunderOther Universities Subcontractor

    B01: StaffB05: TravelB06: Equipment

    B07: ConsumablesB99: Indirect Costs

    NOTE: The last subtask, A99, B99, etc., is always reserved for systemgenerated Indirect Costs.

  • 8/9/2019 Introduction to Projects for Project Administrators

    11/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 11

    5 Oracle Projects Terms

    Your User Role (Project Administrator/Project Inquiry) determines which menus you see when youlog in to Oracle Projects. Each project has Key Members assigned. Key Members work with the

    project accounting data, or may be the Principal Investigatoror Co-Investigatoron the project.

    5.1 Key Members

    When a Key Member is assigned to a project, that person can access information about the project inOracle. Key Members can see their own projects, but not anyone elses projects.

    TIP:Only Key Members on a project can access that projects record. Everyonewho needs to view a project needs to be added as a Key Member.

    Each project must have one Key Member called the Project Manager. In Oracle Financials, theProject Manager is the person who manages the project record, not the project itself! The systemallows only one Project Manager per project at any time. The Project Manager has complete control ofthe project record.

    Other types of Key Members include the Research Business Managerand the Research ContractManager.

    The Principal Investigatorand any Co-Investigatorswill be Key Members even though they maynot need to access the complex data stored in the system. This is because their names and affiliationsare used in credit split computations. Oracle computes indirect costs according to the faculty andschool splits entered for the PI and Co-Is.

    TIP:Staff entering purchase requisitions do not need to be Key Members of aproject. Enter purchase requisitions in the iProc module, or manually.

    5.2 Customers

    Organisations that fund research projects are called Customers in Oracle Projects. In Projects,customers have a relationship with the University. A customer can be a funder, a debtor, or afunder/debtorfor a project.

    The project debtor is the organisation from which the University will receive payment. When aproject has a single customer, the customer will be either a funder/debtor, or a debtor. If invoices orclaims are to be created, there must be a customer who is a debtor.

  • 8/9/2019 Introduction to Projects for Project Administrators

    12/54

  • 8/9/2019 Introduction to Projects for Project Administrators

    13/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 13

    6 Logging on to Oracle Financials

    Oracle is a web-based system. We use a standard web browser to run Oracle.

    Steps to Log on:1. Start your web browser. Go to the Universitys home page.

    2. Enter finance after the Universitys URL:http://www.manchester.ac.uk/finance

    3. Navigate to: Oracle Financials

    4. Select the Login to Oracle Financialslink as shown below.

    5. Type your Usernameand Password.

    6. Click on the responsibilityyou wish to use. Options appear in the right column for thisresponsibility.

    7. Click Project Status Inquiryin the right column. The Find Project Statuswindow appears.

    Conclusion:We are now ready to work with Oracle Projects.

    http://www.manchester.ac.uk/financehttp://www.manchester.ac.uk/financehttp://www.manchester.ac.uk/financehttp://www.manchester.ac.uk/financehttp://www.manchester.ac.uk/finance
  • 8/9/2019 Introduction to Projects for Project Administrators

    14/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 14

    7 The Top Ten List

    You can copy menu options that you use frequently to the Top Ten List.

    Steps to copy a menu option to the Top Ten List:1. If you wish to add a menu sub-option, double click the option to expand the menu first.

    Menus with sub options have +signs in front of them, like +Expenditures or +Billing in the listbelow. Here Billing has been expanded to display sub options. The Agreements sub option isselected.

    2. Click the option you wish to add, like Agreementsin the list above.

    3. Click the arrow. The option moves to the Top Ten List.

    Conclusion: You have copied a menu option to the Top Ten List.

  • 8/9/2019 Introduction to Projects for Project Administrators

    15/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 15

    8 Project Status Inquiry Screen

    Once a project is underway, you can use the Project Status Inquiry (PSI) screen, to viewinformation about the project. The PSI screen provides a detailed snapshot about projects. An Oracle

    process updates the data on the PSI screen.

    Navigate To: Project Status Inquiry

    Displaying a Single Project

    1. Type the Project Numberin the Number field.

    2. Click Find. The Project Status screen appears with data about your project.

    Displaying Multiple Projects

    If you dont know the project number, or would like to view several projects at once, try one of theseoptions:

    Leave all fields blank on the Find Project Statusscreen and click Find. All projects you areauthorised to view will appear on the PSI screen.

    If you know the name of a Key Memberon the project, type the surname in the Namefieldand press Tabon your keyboard. Projects you are authorised to view with this Key Memberappear on the PSI screen. Click Find. The PSI screen will appear.

  • 8/9/2019 Introduction to Projects for Project Administrators

    16/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 16

    9 Data Displayed on the Main PSI Screen

    Navigate To: Project Status Inquiry

    The table below shows the column heading abbreviations and the data that appears as you scrollacross the screen. All amounts shown in the PSI screen are in GBP.

    Heading Abbreviation Heading

    Ovr Bgt Over Budget

    TotCst Bgt TotalCost Budget

    ITDAct Cost Inception to DateActual Cost

    Commit Amt Commitment Amount

    TotRev Bgt TotalRevenue BudgetITDAct Rev Inception to DateActual Revenue

  • 8/9/2019 Introduction to Projects for Project Administrators

    17/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 17

    9.1 Drilling Down for More Data

    While on the main Project Status screen, you can drill down to view other information about theproject.

    1. Events- Events are not available through this button. Instead, select the Task Statusbutton.

    2. InvoicesNot accessible through Projects Admin or Project Inquiry access (available with high-level access only).

    3. Commitments Use this to see commitments against the project (see page 21). To limitcommitments to ones associated with a particular task, click Task Status.

    4. Project- For an overview, including classifications, customers and key members (see page18).

    5. Resource Status- Not used at University of Manchester.

    6. Task Status - For information about events (if appropriate), task level commitments, actuals,and the tasks themselves (see page23).

    1 2

    3 4 5 6

  • 8/9/2019 Introduction to Projects for Project Administrators

    18/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 18

    9.2 Viewing Project Information

    To view information about a particular project from the Main PSI screen:

    1. Select (highlight) the project you wish to view.

    2. Click the Projectbutton. The Project Informationwindow appears.

    Note these fields at the top of this screen:

    Number Oracle Projects automatically assigns a sequential number to the project. Forresearch projects, the number consists of R (Research) + 6 digits.

    TypeG (Grant) or C (Contract) and a description of the project type.

    Organization The unit within the University of Manchester that owns the project.Examples include University Administration and EPS Faculty Office.

    Trans DurationThese are the earliest and latest dates that transactions can be entered

    for the project. They are not the start and end dates of the project itself.

    StatusStage of the project, as discussed previously.

    The Classificationstab at the bottom of the screen contains two items:

    Type of Projectalways Research for research projects

    Research Programmethe type of Research Programme associated with a project, such asClinical Trials or Research Grant.

  • 8/9/2019 Introduction to Projects for Project Administrators

    19/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 19

    3. Click the Customerstab to see customer details.

    4. Click the Key Memberstab to see the list of Key Members.

  • 8/9/2019 Introduction to Projects for Project Administrators

    20/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 20

    5. Click on the Headerof the Project Informationscreen (any of the top fields).

    6. Click on the Zoomicon on the toolbar.

    7. A window appears showing youAdditional Informationabout the project.You wont be able toview the actual project but you can see the additional dates from here.

  • 8/9/2019 Introduction to Projects for Project Administrators

    21/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 21

    9.3 Viewing Commitments

    1. From the Project Statuswindow, select the project you wish to view.

    2. Click the Commitmentsbutton.

    3. The Find Commitmentswindow opens.

    You can use this screen to limit the commitments shown. If you want to see all commitments for thisproject, just click Findwithout completing any fields.

    Limit by Supplier Name- Use the wildcard %and a keyword (e.g. %lyreco% and press Tab) tofilter the list or just type %and click the []to get a full list of suppliers.

    Limit by Expenditure Type - Use the wildcard %if you know the Expenditure Type code (e.g. 2%and press Tabto see staff costs).

    Limit by Commitment Dates - Enter a start date and an end date for the commitments you wish toview.

    Limit by Commitment Type - Click the [] to get a list of Commitment Types (e.g. SupplierInvoices, Purchase Orders). Select the type desired, and click OK.

  • 8/9/2019 Introduction to Projects for Project Administrators

    22/54

  • 8/9/2019 Introduction to Projects for Project Administrators

    23/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 23

    9.5 Accessing Task Status

    This window shows the same information as the main PSI window, but broken down by task.

    1. From the Project Statuswindow, select the project you wish to view.

    2. Click the Task Statusbutton. The Task Statuswindow opens.

    3. The window opens with only the Top Taskvisible.

  • 8/9/2019 Introduction to Projects for Project Administrators

    24/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 24

    4. If there are events associated with this top task, the Eventsbutton is active.

    5. Click the Events button to see the associated events.

    6. Close the Event Detailswindow to return to the Task Statuswindow.

    7. Double click the +sign in front of the Top Taskletter to reveal the sub tasks.

  • 8/9/2019 Introduction to Projects for Project Administrators

    25/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 25

    9.6 Drilling Down from the Task Status Window

    You can view further information about a task or subtask from the Task Status window. Beforedrilling down, click the task you want more information about.

    1. Click Commitments, Actuals, or Task, as desired. These options are described below. (TheEventsbutton only displays information for the top task).

    2. Click Tasksto view Task Information(shown below).

    3. For Subtasksyou can view:

    Commitments(on the same screen as shown above).

    Task(same screen as shown above, but for this subtask).

    Actuals- This opens the Find Expenditure Itemsscreen (shown below)

    4. Enter any criteria desired to limit the items returned and click Find. The Expenditure ItemDetailsscreen appears.

    Conclusion: You have viewed detailed data about projects.

  • 8/9/2019 Introduction to Projects for Project Administrators

    26/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 26

    10 Expenditure Inquiry Screens

    Navigate To: Expenditures > Expenditure Inquiry > Project

    The Expenditure Inquiry screens let you see all expenditure on a particular project. Or you couldselect the Expenditure Inquiry > All option if you dont know the project number. There arevarious fields to use when searching, some are explained below.

    10.1Searching by Project Number/Name or Task Number/Name

    1. Enter any criteria into one of the top fields on the screen e.g. Project Number.

    2. Click Find. The Project Expenditure Itemsscreen appears.

  • 8/9/2019 Introduction to Projects for Project Administrators

    27/54

  • 8/9/2019 Introduction to Projects for Project Administrators

    28/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 28

    10.4Searching by Inventory Item

    1. Enter the Stores Item Reference.

    2. Click Find. The Project Expenditure Itemsscreen appears.

    10.5Searching by Transaction Source

    1. Enter or select a Transaction Sourcefrom the list of values [].

    2. Click Find. The Project Expenditure Itemsscreen appears.

  • 8/9/2019 Introduction to Projects for Project Administrators

    29/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 29

    10.6Searching by Expenditure Type

    1. Enter or select the Expenditure Typefrom the list of values [].

    2. Click Find. The Project Expenditure Itemsscreen appears.

  • 8/9/2019 Introduction to Projects for Project Administrators

    30/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 30

    10.7Drilling Down from the Expenditure Inquiry Screens

    Once the Project Expenditure Itemsscreen appears (shown below) you can drill further down tosee more details about transactions.

    1. Click Item Details. This window will pop-up.

    2. Select one of the following, these are explained on the next pages:

    Cost Distribution Lines

    AP Invoice

    PO Receipt

    Purchase Order Details

    PO Receipt if available, shows you the goods receipt for the purchase order e.g. quantitiesreceived and any corrections.

    Purchase Order Detailsif available, shows you the purchase order details e.g. Buyer (person who

    created the order), line details, Charge Accounts (finance codes) and supplier details.

  • 8/9/2019 Introduction to Projects for Project Administrators

    31/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 31

    Cost Distribution Lines shows you the Debit and Credit for this transaction and the PA(Project) & GL PeriodsandDatesit has been posted to.

    AP Invoiceshows you details of the Supplier Invoice from the Accounts Payable module. View theDate the invoice was paid, or the Due Date, Payment Method, Invoice Amounts, VoucherNumber.

  • 8/9/2019 Introduction to Projects for Project Administrators

    32/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 32

    11 My Projects

    Navigate To: My Projects

    Either select PA My Projectsfrom your list of responsibilities from the main E-Business Suite homepage as shown below.

    Or, if youre already in one of the Oracle screens, youll need to Switch Responsibilities. Close offall windows so that you return to the Navigator. Click the Top Haticon on your toolbar.

    A list of the responsibilities that you have been assigned appears and you can choose which one you

    want to change to. Select PA My Projectsfrom the list then click OK.

  • 8/9/2019 Introduction to Projects for Project Administrators

    33/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 33

    My Projects is a relatively new reporting tool that is designed to bring back a list of the projects thatan academic or key member is working on and then be able to drill down to the lower level detail andtransactions.

    1. Upon entering the My Projects area you will be presented with a list of the projects that you are

    assigned to.

    2. From this screen you can click on the hyperlinks (the project numbers) and this will take you to atask breakdown of the summary. It starts with the tasks rolled together so you will only see the

    top task information. Click on the button to expand the task list.

  • 8/9/2019 Introduction to Projects for Project Administrators

    34/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 34

    3. From here you can click on the task numbers to drill to the actual costs/revenue with these tasks.This is actually the information in the BH05/PA09 reports.

    4. From the home page you can search for other projects using the project number project name,key member name or using the faculty or school alpha code. These are explained in the nextsections.

    NOTE: The Budget status column is a simple calculation. If the budget amountis less than the actual costs to date amount then the status column will show ared cross, otherwise it will show a green tick.

  • 8/9/2019 Introduction to Projects for Project Administrators

    35/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 35

    11.1Searching with a Project Number

    1. Click the torch icon to bring up the search screen, or enter the project number directly.

    2. Click the Quick Select icon. This will bring back a list of projects matching your search criteriaand you can then use it in the same way as the My Projects list.

    11.2Searching with the Project Name

    1. Click the torch icon and then change the drop down to Project Name.

    2. Enter the name of the project (use the wildcard %to help with searching).

    3. Use the Quick Selecticon to then select this project.

    11.3Searching by Key Member

    1. Click the torch icon and enter the surnamein the Key Member search field.

    2. Use the Quick Selectas above.

  • 8/9/2019 Introduction to Projects for Project Administrators

    36/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 36

    11.4Searching by Faculty/School Code

    1. Click the torch icon and then change the drop down to Code.

    2. Enter the code for the school or faculty and click GO. Use the Quick Selectas before.

  • 8/9/2019 Introduction to Projects for Project Administrators

    37/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 37

    12 PA Reports

    Navigate To: PA Reports > Discoverer Viewer

    Reports in Oracle are linked to responsibilities. On the Projects Admin course we look at three Projectsreports:

    PA02 - Balances - Actuals & Budgets Report

    This report shows you similar detail to the Project Status Inquiry (PSI) screen. This is the same reportas the BH2 report. It shows the Project balances as per the PSI screen which is refreshed overnight.

    PA09 - Transactions All Report

    This report shows you similar detail to the Expenditure Inquiry screen. This is the same report as the

    BH5 report. It includes revenue and expenditure transactions.

    PA47List of Projects and Tasks

    This report provides details of tasks for selected projects.

    12.1Running a Report

    Navigate To: PA Reports (UOM) >Discoverer Viewer

    1. To open a report, youll need to use the expandor focusicons (as highlighted below).

    2. From the expanded list of worksheets, choose the worksheet you wish to open the report on.

    3. Enter the required Parametersand click Goto run the report.

  • 8/9/2019 Introduction to Projects for Project Administrators

    38/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 38

    4. The report will be shown.

    Once a Discoverer report has been run, the output can be printed or exported.

    12.2Printing a Report

    1. From theActionslist at the top-left hand side of the screen, select the option Printable Page.

    2. This link will display the Printable Page Options; Contentand Page Setup. By default theContentoption will be selected.

  • 8/9/2019 Introduction to Projects for Project Administrators

    39/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 39

    3. You can make choices as to what content you wish to have printed on the page such as titles.

    4. Once you have made your choices you can click on Preview sample.

    5. A sample PDF will be created which you can view first, and then click on the Printable PDFbutton to generate a complete PDF document.

    6. Once you have viewed the PDF, close it and click on Printable PDF.

    7. The PDF will be created. Click on the link to view, save and print as appropriate.

  • 8/9/2019 Introduction to Projects for Project Administrators

    40/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 40

    12.3Exporting a Report

    1. From theActionslist at the top-left hand side of the screen, select the option Export.

    2. The export link allows you to export to different formats. Use the drop down menu to choose theexport type.

    3. Once you have chosen the file type click on Export.

    4. The export will be ready to view. Click on the Click to view or savebutton.

    5. A File Download dialogue box opens according to the file type you have chosen. You canchoose to Open it and then save to a specified area on your computer, or choose to Save itstraight away.

  • 8/9/2019 Introduction to Projects for Project Administrators

    41/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 41

    13 Help and Support

    The support model for the Oracle Financials system is as follows:

    1. Check theOracle Financials web sitefor the answer.

    Look at theTop 10 FAQ's,and theTraining Material and FAQ'sfor the area you are havingproblems with.

    If you are not able to find the answer here, then go to step 2.

    2. Contact yourFrequent User.

    3. Raise a Support Call.

    Once your frequent user has been contacted, and agrees that the problem cannot be solvedlocally, a support call should be logged. There is a new link on the Oracle Financials Help andSupport web page to log a support call:

    http://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/Support/SupportModel.html

    As part of the process to log the support call, you will have to verify that you have checked thewebsite and spoken to a frequent user. Once you have ticked these boxes, you will have tocategorise your call from a selection in a drop down box. This will ensure that the call is directedappropriately. Any call logged which is capable of being dealt with locally will revert to the user forsolution.

    4. My password needs changing or I have forgotten my password

    A newweb page has been placed on the Oracle Financials website to direct users to an emailaddress under the control of the IT service desk, who will continue to deal with passwordchanges.

    5. Your Access

    Your Oracle access may take several days to come through. If you havent received your access after several days, you must log a support call(see section 3 above).

    New users you will receive an e-mail with your username, password & the link to the Livesystem. You will be prompted to change your password the first time you log in.

    Existing usersyou will see your new responsibility e.g. PA Projects Admin added to your list.

    NOTE: The information above can be found on the Universitys Finance

    web pages. Go to:http://manchester.ac.uk/financeand thenselect Oracle Financials.

    http://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_FAQ_top_10.pdfhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_FAQ_top_10.pdfhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_FAQ_top_10.pdfhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_super_user_network.pdfhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_super_user_network.pdfhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_super_user_network.pdfhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/Support/SupportModel.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/Support/SupportModel.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://manchester.ac.uk/financehttp://manchester.ac.uk/financehttp://manchester.ac.uk/financehttp://manchester.ac.uk/financehttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/forgottenpassword.htmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/Support/SupportModel.htmlhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_super_user_network.pdfhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.itservices.manchester.ac.uk/trainingdocumentation/staffrestricted/corpapps_ofa_FAQ_top_10.pdfhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtml
  • 8/9/2019 Introduction to Projects for Project Administrators

    42/54

  • 8/9/2019 Introduction to Projects for Project Administrators

    43/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 43

    Accounts Receivable

    Type of document Where kept? How long? Any further comments

    Sales orders Local storage inschools/departments

    Retain untilthe debt hasbeen fully

    paid, or thecontract isended.

    Keep these if they are available, asthey are required to be produced iflegal action is needed to recover a

    debt. Reference them locally by thesales invoice number generated bythe system.

    Contracts withcustomers

    Local storage inschools/departments(high valuecontracts originalpaperwork may bestored centrally)

    Life of thecontract plusthe period ofobligations

    Sales invoices Not required Please make sure all information onthe system is complete.

    Sales credit note Signed copies need

    to be retained indepartments

    2 years

    Remittance advicereceived with payment

    Centrally stored,and also storedlocally bydepartments who dotheir own banking.

    6 years pluscurrent year,or if EU grant,life of grantplus 3 years

    Bank Giro Credits Centrally stored,and also storedlocally bydepartments who dotheir own banking.

    6 years pluscurrent year,or if EU grant,life of grantplus 3 years

    This is the paper document issuedby the bank when cash/cheques arepaid in.

    Manual (paper)receipts

    These are manualreceipts given tocustomers toacknowledge receiptof cash.

    6 years pluscurrent year,or if EU grant,life of grantplus 3 years ifneeded.

    In most cases the receipt will begenerated electronically by thesystem, and no paper record isneeded. This only applies if apaper based receipting system is inoperation.

    Source direct debitinstructions (forcollections)

    These are usuallyonly kept centrally,for Accommodationoffice and SSC

    6 years

  • 8/9/2019 Introduction to Projects for Project Administrators

    44/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 44

    Projects

    Type of document Where kept? How long? Any further comments

    Project journals Not required Not requiredproviding allinformation is entered onto the

    electronic record.Claims documentation 6 years plus

    current year,or if EU grant,life of grantplus 3 years ifrequired

    General Ledger

    Type of document Where kept? How long? Any further comments

    Journals Not required Please make sure all information on

    the system is complete, and anysupporting information for the journalis attached to the electronic record asan attachment prior to the journalbeing posted.

    Petty cash imprestforms

    Kept in thecentre when thecash float isreimbursed.

    6 years

    Other

    Type of document Where kept? How long? Any further commentsBank statements Centre 6 years

  • 8/9/2019 Introduction to Projects for Project Administrators

    45/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 45

    15Appendix AShortcuts and Function Keys

    Description Shortcut Key

    Block Menu Ctrl + B

    Clear Block F7

    Clear Field F5

    Clear Form F8

    Clear Record F6

    Commit Ctrl + S

    Count Query F12

    Delete Record Ctrl + Up

    Display Error Shift + Ctrl + E

    Down Down

    Duplicate Field Shift + F5

    Duplicate Record Shift + F6

    Edit Ctrl + E

    Enter Query F11

    Execute Query Ctrl + F11

    Exit F4

    Help Ctrl + H

    Insert Record Ctrl + Down

    List of Values Ctrl + L

    List Tab Pages F2

    Next Block Shift + Page Down

    Next Field Tab

    Next Primary Key Shift + F7

    Next Record Down

    Next Set of Records Shift + F8Previous Block Shift + Page Up

    Previous Field Shift + Tab

    Previous Record Up

    Print Ctrl + P

    Return Return

    Scroll Down Page Down

    Scroll Up Page Up

    Show Keys Ctrl + K

    Up Up

    Update Record Ctrl + U

  • 8/9/2019 Introduction to Projects for Project Administrators

    46/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 46

    Menus: File Menu

    Command Description

    New Creates a new record in the active form

    Open Opens the detail screen for the selection

    Save Saves any pending changes in the active form

    Save and ProceedSaves any pending changes in the active formand advances to the next record

    Next StepUpdates the workflow in the navigator byadvancing to the next step in the process

    Export Exports information in your form to a browser

    Place on NavigatorCreates an icon in the Documents tab of theNavigator which can be used to recall the activeform

    Log on as a Different User Allows you to log on to as a different user

    Switch Responsibility Allows you to change the responsibility

    Print Prints your current window

    Close Form Closes all windows of the current form

    Exit Oracle Applications Quits Oracle Applications

    Edit Menu

    Command Description

    Undo TypingUndoes any typing done in a field before the field isexited

    Cut Cut

    Copy Copy

    Paste Paste

    Duplicate Record Above Copies all values from the prior record

    Duplicate Field Above Copies all the values of the current fieldClear Record Erases the record from the current field

    Clear Block Erases all records from the current block

    Clear Form Erases any pending changes

    Delete Deletes the current record from the database

    Select All Selects all records

    Deselect AllDeselects all selected records except for the currentrecord

    Edit Field Displays the Editor window for the current field

    Preferences Change Password Displays the Change Password dialogue box

    Preferences Profiles Displays the Profiles window

  • 8/9/2019 Introduction to Projects for Project Administrators

    47/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 47

    View Menu

    Command Description

    Show Navigator Displays the Navigator window

    Zoom Invokes custom defined zooms

    Find Displays the Find window

    Find All Retrieves all recordsQuery by Example Enter Opens Enter Query mode to enter search criteria

    Query by Example Run Runs the query

    Query by Example Cancel Cancels the query

    Query by Example Show Last Criteria Recovers the search criteria used in the previousquery

    Query by Example Count Matching Records Counts the number of records that would beretrieved if you ran the current query

    Record First Moves the cursor to the first record

    Record Last Moves the cursor to the last record

    Translations Displays the translations window

    Attachments Displays the attachments window

    Summary/Detail Switch between the summary and detail views ofa combination block

    Tools MenuMay contain up to 15 product-specific entries

    Window Menu

    Command Description

    CascadeDisplays any open windows in a cascadedfashion

    Tile HorizontallyDisplays any open windows in a horizontally tiledfashion

    Tile VerticallyDisplays any open windows in a vertically tiledfashion

    1 (Title of Open Window)Displays a list of open windows titles in the orderin which they are stacked

    Help Menu

    Command Description

    Window Help Displays help for the current window

    Oracle Applications Library Displays a window that lists all available Help text

    Keyboard HelpDisplays the current mapping of specific functionsand menu options

    Record History Displays information about who created andupdated the current record

  • 8/9/2019 Introduction to Projects for Project Administrators

    48/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 48

    16Appendix BToolbars

    New

    Find

    Show Navigator

    Save

    Next Step

    Switch Responsibility

    Print

    Close Form

    Cut

    Copy

    Paste

    Clear Record

    Delete

    Edit Field

    Zoom

    Translations

    Attachments

    Folder Options

    Window Help

    % Wildcard used in searching

  • 8/9/2019 Introduction to Projects for Project Administrators

    49/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 49

    17Appendix CExporting Oracle Projects Data

    Exporting Data

    Many screens in Oracle Projects allow you to export data. To check whether data from a particularscreen can be exported, select File> Exporton the menu. If Export is greyed out, you cannot exportfrom this screen.

    Selecting Exportbrings up the following dialogue box:

    If you select Open, the file opens in Notepad. Sample data appears below. This is fine if you justwant a quick printout of the data.

    To work with the data in Excel:

    1. Select Edit > Select Allfrom the menu (shortcut: press CTRL+A).

    2. Select Edit > Copy(shortcut: press CTRL+C).

    3. Opena blank Excel worksheet.

    4. Select Edit > Paste(shortcut: press CTRL+V) and paste the data into Excel.

    NOTE:Remember that this is a snapshot of your data. It will not update if thedata in Oracle Projects changes.

  • 8/9/2019 Introduction to Projects for Project Administrators

    50/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 50

    Shortcut: Change the File Association

    The export file has a .tsv extension, which will probably be associated with Notepad on yourcomputer. If you have sufficient rights on your computer, you can change the file association so thatthe file will automatically open with Excel.

    To do this:1. Select File > Exportwithin Oracle Projects. The File Downloaddialogue box appears.

    2. Click Save. The Save Asbox appears.

    3. Savethe file to My Documents. Note the filename (fnd_gfm.tsv).

    4. OpenMy Documents. Right click the file and select Open With.

  • 8/9/2019 Introduction to Projects for Project Administrators

    51/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 51

    5. Click Choose Program. The Open With dialogue box opens.

    6. Select Microsoft Office Excel.

    7. TickAlways use the selected program to open this type of file. Be sure to tick this option,or your computer will not remember that you want to use Excel with this type of file (see previouspage for a screen shot example of this).

    8. Click OK.

    Saving the Excel File

    If you want to work with this file again, be sure to save it as an Excel file. To do this:

    1. Select File > Save As. Give the file an appropriate name.

    2. Change Save as type to Microsoft Excel 97Excel 2003 & 5.0/95 Workbook.

    3. Click Save.

  • 8/9/2019 Introduction to Projects for Project Administrators

    52/54

    Training GuideIntroduction to Projects for Project Administrators

    Page 52

    18Appendix D - Cross Reference RMS/Oracle Projects

    Thanks to Annette Crossley for compiling the initial data on which this cross reference is based.

    RMS Screen ORACLE PROJECTS

    TO VIEW

    Basic Details Application Reference PSI Screen Project Description

    Basic Details Faculty PSI Screen Project

    Basic Details School PSI Screen Project

    Basic Details Title PSI Screen Project Long Name

    Basic Details Planned Start Date Projects Main Screen Flexfield

    Basic Details Award Date Projects Main Screen Flexfield

    Basic Details Actual Start Date Projects Main Screen Flexfield

    Basic Details Duration Projects Main Screen Flexfield

    Basic Details Expected End Date Projects Main Screen Flexfield

    Basic Details Final Accounting Date Projects Main Screen Transaction End Date

    Basic Details Starting Cert Date Projects Tasks Flexfield

    Basic Details Programme Scheme PSI Screen Project Classifications Class Code

    Basic Details Status Projects Main Screen

    Basic Details

    Approval Form (RGC10, Blue Form,

    PanMan) Projects Main Screen Flexfield

    Basic Details Res A/cs Officer PSI Screen Project Key Members

    Basic Details Currency Projects Currency

    Basic Details Award Total PSI Screen Project

    App App Appointments Approvals

    Ext Part External Participants PSI Screen Project Key Members

    Sponsors Funder PSI Screen Project Customers

    Sponsors Funder/ Debtor Ref

    Project Funding

    Enquiry

    Sponsors Funder VAT Status Where Funder is different from Debtor VAT info not needed.

    Sponsors Source of Funds PSI Screen Task Status Task

  • 8/9/2019 Introduction to Projects for Project Administrators

    53/54

    IT Services Training

    Introduction to Projects for Project Administrators

    Page 53

    RMS Screen ORACLE PROJECTS

    TO VIEW

    Sponsors Debtor PSI Screen Project Customers

    Sponsors Debtor Address Projects Customers

    Sponsors Debtor VAT Status Projects Tasks Flexfield

    Sponsors Indirect Cost Policy by Project Projects

    Burden

    Multipliers

    Costing Burden

    Schedules

    Investigator PI PSI Screen Project Key Members

    Investigator PI School Projects Zoom Icon

    Investigator PI % Credit Projects Zoom Icon

    Investigator PI RAE UoA Projects Zoom Icon

    Investigator Co-I PSI Screen Project Key Members

    Investigator Co-I School Projects Zoom Icon

    Investigator Co-I % Credit Projects Zoom Icon

    Investigator Co-I RAE UoA Projects Zoom Icon

    Cost Headings Budget PSI Screen

    Cost Headings Indirect Costs by Cost Headings Projects Tasks Options

    Burden

    Multipliers

    Costing Burden

    Schedules

    Claim Profile Claim/ Invoice Schedule Projects

    Billing

    Information Billing Setup

    Claim Profile Claim Type Projects

    Billing

    Information Billing Setup

    Claim Profile

    Profiled Amount for Installments/ Fixed

    Claims Billing Events Project

    Claim Profile Invoice Numbers & Amount PSI Screen InvoicesClaim Profile Claim Transactions

    Claim Profile Payroll Details

    Ind Cost Indirect Costs Debit Split Projects Zoom Icon

    Ind Cost Indirect Costs Credit Codes Projects Zoom Icon

    Ind Cost Indirect Costs Credit % Projects Zoom Icon

  • 8/9/2019 Introduction to Projects for Project Administrators

    54/54

    Training GuideIntroduction to Projects for Project Administrators

    19 Reference Glossary

    19.1Accessing Documentation

    All of our Training Guides and Supplementary Material can be downloaded from the IT ServicesTraining Team website at:

    http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/

    19.2Accessing the Live System

    The live system can be accessed viathe following link and then select Login to Oracle Financials:

    http://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtml

    http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/http://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/http://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.campus.manchester.ac.uk/finance/Sys/OracleSystem/SysUnityIS.shtmlhttp://www.itservices.manchester.ac.uk/trainingcourses/corporateapplications/finance/

Recommended