+ All Categories
Home > Documents > INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE...

INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE...

Date post: 21-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
122
THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2187 as follows: CONTRACTOR RFI Item No. Ref. Sheet / Spec Pg. Question/Answer Dwg No. 3-001 G-00a, G.101 Q. On G-000a, Florence Crittenton Services, 96 Zuni, is that the wrong graphic? On G101, I think the school is 55 S. Zuni and the Services building is at 96 S. Zuni. I believe we are adding the gym on to the services building at 96 S. Zuni. A. The new school is 55 S. Zuni and the gym is being added to that building. The graphics are correct. 3-002 085113 Q. Aluminum window spec 085113 call for blinds installed in the vent windows. Per drawings or details none are shown for either school. Is this spec correct for these two schools, or is this a can spec, please verify. A. The integral blinds apply to all exterior aluminum windows in 55 S. Zuni. Integral blinds are not required at 96 S. Zuni. 3-003 102239 Q. Please consider Kwik-Wall as a substitution for Folding Panel Partitions. A. The Substitution request is rejected. Kwik-Wall is not a DPS approved manufacturer. If the partition company would like to be on the approved list in the future, we encourage them to follow DPS procedures. If the product is acceptable it will be added to the DPS Construction Standards during future Standards Updates. August 31 is the deadline for the 2014 update. 3-004 105113 Q. Please consider Hadrian Emperor Lockers as a substitute for lockers. A. Hadrian Emperor Lockers is not an accepted substitute for lockers. 3-005 Q. The division 27 specs do not appear to include access systems, network cabling, security or cctv. Will specifications be provided? A. See item 3-012 below. 3-006 A-102 Q. Per floor plan A-102 Item Note 08.01 says 6’ Lx 18’’ H are these windows hollow metal? A. Yes, these are window type W20 as elevated on sheet A-621. 3-007 114000, KA2.1 Q. Please verify if they want grease filters (per the dwg) or extractors (per the specs) for the Avtec hood? A. Provide grease filters per the drawings. Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE July 23, 2014
Transcript
Page 1: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

THIS ADDENDUM MUST BE ACKNOWLEDGED.

THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2187 as follows:

CONTRACTOR RFI

Item No.

Ref. Sheet / Spec Pg.

Question/Answer Dwg No.

3-001 G-00a, G.101

Q. On G-000a, Florence Crittenton Services, 96 Zuni, is that the wrong graphic? On G101, I think the school is 55 S. Zuni and the Services building is at 96 S. Zuni. I believe we are adding the gym on to the services building at 96 S. Zuni. A. The new school is 55 S. Zuni and the gym is being added to that building. The graphics are correct.

3-002 085113 Q. Aluminum window spec 085113 call for blinds installed in the vent windows. Per drawings or details none are shown for either school. Is this spec correct for these two schools, or is this a can spec, please verify. A. The integral blinds apply to all exterior aluminum windows in 55 S. Zuni. Integral blinds are not required at 96 S. Zuni.

3-003 102239 Q. Please consider Kwik-Wall as a substitution for Folding Panel Partitions. A. The Substitution request is rejected. Kwik-Wall is not a DPS approved manufacturer. If the partition company would like to be on the approved list in the future, we encourage them to follow DPS procedures. If the product is acceptable it will be added to the DPS Construction Standards during future Standards Updates. August 31 is the deadline for the 2014 update.

3-004 105113 Q. Please consider Hadrian Emperor Lockers as a substitute for lockers. A. Hadrian Emperor Lockers is not an accepted substitute for lockers.

3-005 Q. The division 27 specs do not appear to include access systems, network cabling, security or cctv. Will specifications be provided? A. See item 3-012 below.

3-006 A-102 Q. Per floor plan A-102 Item Note 08.01 says 6’ Lx 18’’ H are these windows hollow metal? A. Yes, these are window type W20 as elevated on sheet A-621.

3-007 114000, KA2.1

Q. Please verify if they want grease filters (per the dwg) or extractors (per the specs) for the Avtec hood? A. Provide grease filters per the drawings.

Denver Public Schools Purchasing Department

1617 S. Acoma St. Denver, Colorado 80223

INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE

July 23, 2014

Page 2: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

SPECIFICATIONS

Item No.

Spec Section & Page No.

Description Dwg No.

3-008 000108-1 The email address for Denver Public Schools Contact was incorrectly spelled, the correct email address is: [email protected].

3-009 087100, pg 3 Delete line 2.1.2.c. Schlage is not an approved manufacturer for locksets, latchsets, or deadbolts.

3-010 09200, pg 5 For line 3.01.L. Revise the sentence as follows: “ Use at toilet rooms, kitchens, locker rooms, janitor rooms – except behind tile – and elsewhere as indicated.” Delete line 3.01.M.1. Impact resistant gypboard is not required on ceilings or soffits.

3-011 093200, pg 2 Delete A1.03 A. Grout sealers are not allowed.

3-012 270110, 270500, 270526, 270553, 270800, 271100, 275400.0020, 281300, 282001.0010, 272323.0010

See attached specification sections 270110 Operation and Maintenance of Communications Systems, 270500 Common Work Results for Communications, 270526 Grounding and Bonding for Communications Systems, 270553 Identification for Communications Systems, 270800 Commissioning of Communications Systems, 271100 Structured Cabling, 275400.0020 CATV, 281300 Electronic Access Control Systems, 282001.0010 Electronic Security System, and 282323.0010 CCTV that were inadvertently left out of the issued Volume 2 Project Manual.

CIVIL

Item No.

Ref. Sheet Description Dwg. No.

NONE

LANDSCAPE & IRRIGATION

Item No.

Ref. Sheet Description Dwg No.

NONE

STRUCTURAL

Item No.

Ref. Sheet Description Dwg. No.

NONE

ARCHITECTURE

Item No.

Ref. Sheet Description Dwg. No.

3-013 A-600 Revise Door Leaf Thickness column to show all door thickness at 1 ¾”.

3-014 A7.51 All detail references that refer to hardware, door pulls, and drawer pull should defer to the Project Manual section 12 32 16, paragraph 2.03.B regardless of what is graphically indicated on this page.

Page 3: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

If your proposal has been submitted and you wish to amend it, please modify your proposal on company letterhead. The amended proposal must be received prior to or included at the time and date set for the proposal opening. Each modification submitted to the District's Purchasing Office located at 1617 S. Acoma St. Denver, CO 80223. It must have Vendor’s name and return address and the applicable RFP number and title of the RFP clearly marked on the face of the envelope. If more than one modification is submitted, the modification bearing the latest date of receipt by the District's Strategic Sourcing Office will be considered the valid modification. *****This addendum must be acknowledged, whether or not you amend your proposal.*****

This Addendum must be included in your submittal or proposal, providing you do not need to amend your proposal.

PRINT OR TYPE YOUR INFORMATION

Name of Company: ____________________________________________ Fax: _____________

Address: ________________________ City/State: ________________ Zip: ______________

Contact Person: ___________________ Title: _____________________ Phone: ___________

Authorized Representative’s Signature: ____________________________ Phone: ___________

Printed Name: ____________________ Title: _____________________ Date: _____________

Approved by: ______________ Date: _____________

Reviewed by: ______________ Date: _____________

14-MC-2187 Addendum # 3

Page 4: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

OPERATION AND MAINTENANCE OF COMMUNICATIONS SYSTEMS

27 01 10 - 1

SECTION 27 01 10

OPERATION AND MAINTENANCE OF STRUCTURED CABLING AND ENCLOSURES

PART 1 - MAINTENANCE OF PATCH FIELDS

1.1 Any persons with Contractor or Denver Public Schools adding or moving copper or fiber optic patch (equipment) cords shall do so in a neat, workmanlike fashion in keeping with the original system concept and according to all industry best practices as outlined in cabling standards and applicable BICSI publications referenced previously in this document.

1.2 Persons performing such moves, adds or changes (MACs) shall further adhere to the following:

A. Contactor shall use existing cabling management pathways and take care to place cable like with like, maintaining original segregation strategies for separating fiber and copper cables as well as any separation necessary between different types of copper cables.

B. Cables shall be dressed neatly within patch management pathways with care taken to maintain minimum bend radius of not less than 1 times the cord outer diameter for copper and not less than a 1" bend radius for fiber jumpers as per ANSI/TIA 568-C.0.

C. All patch cords used shall be of same copper Category or fiber OM/OS designation or higher than the media used in the permanent links.

D. Patching in all cases shall be done using factory terminated cords manufactured for that purpose. Hand terminated patch cords will not be accepted.

E. All patch cords or jumpers must be completely contained within supplied cable management paths. Cables draped across the front of cabinets or racks will not be accepted.

F. Any persons moving fiber optic patch cords for any reason will clean the connector with lint-free wipes and 99% or higher isopropyl alcohol before replacing the connector in a port.

G. Any persons with Denver Public Schools or Installing Contractors performing moves, adds or changes within patch field will label additions to the system according to the labeling guidelines outlined in this document.

H. Any persons with Denver Public Schools or Installing Contractors performing moves, adds or changes within patch field will record the move according to documentation guidelines outlined in this document.

END OF SECTION

Page 5: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 1

SECTION 27 05 00

COMMON WORK RESULTS FOR COMMUNICATIONS

PART 1 - SUMMARY

1.1 The purpose of this document is to provide additional instructions for the planning, design and installation of an end-to-end Category 6 cabling system and associated fiber optic backbone cabling. This document will encompass the structured wiring, the system components, proper installation practices, support and management structures, cable testing, and most importantly the documentation. For specific installation, testing, grounding, bonding, and documentation guidelines please refer to the specific sections in this document. Persons performing such moves, adds or changes (MACs) shall further adhere to the following:

1.2 A structured wiring solution is only as robust as its weakest component, therefore all wires and connections should be Category 6 rated on a component level as defined in the above referenced ANSI/TIA-568-C.2 standard or its more recent revision at the time of installation. The links shall further pass a permanent link performance test as described in this document. Multi-mode fiber links within buildings shall be of OM3 armored designation or higher as indicated by the project documents.

1.3 When planning and installing a structured cabling system for DPS the Contractor must pay particular attention to ensure all components used are of the same Category or optical OM level of performance. Splicing in copper horizontal links is expressly forbidden unless part of a planned zone cabling strategy.

1.4 The DPS network infrastructure design shall in all cases be a star topology unless indicated otherwise by specific project documentation. By pre-wiring all possible locations in a new or existing building in a star topology, all administrative moves, changes and additions will be made at patch field contained in the Telecommunications Rooms.

PART 2 - REGULATORY REFERENCES

2.1 These Denver Public Schools (DPS) Department of Technology Services (DoTS) cabling standards are based on the guidelines published by the Telecommunications Industries Association (TIA) as well as the more detailed requirements of the Building Industry Consultative Services International (BICSI).

2.2 Contractor is responsible for knowledge and application of current versions of all applicable Standards and Codes. In cases where listed Standards and Codes have been updated, Contractor shall adhere to the most recent revisions, including all relevant changes or addenda at the time of installation. A list of Regulatory References current as of the time of this writing is shown below:

ANSI/TIA:

Page 6: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 2

ANSI/TIA-568-C.0 (September 2010) Generic Telecommunications Cabling for Customer Premises TIA-568-C.0-1 (September 2010) Generic Telecommunications Cabling for Customer Premises-Addendum 1, Updated Reference for Balanced Twisted-Pair Cabling ANSI/TIA-568-C.1 (February 2009) Commercial Building Telecommunications Cabling Standards TIA-568-C.1-2 (November 2011) Commercial Building Telecommunications Cabling Standard, Addendum 2 General Updates ANSI/TIA-568-C.2 (August 2009) Balance Twisted Pair Communications and Components Standards ANSI/TIA-568-C.3 (June 2008) Optical Fiber Cabling Components Standard ANSI/TIA-568-C.3-1 (December 2011) Optical Fiber Cabling Component Standard- Addendum 1, Addi-tion of OM4 Cabled Optical Fiber and array connectors ANSI/TIA-568-C.4 (July 2011) Broadband Coaxial Cabling Components Standard ANSI/TIA-942-A (August 2012) Telecommunications Infrastructure Standard for Data Centers TIA-569-B (October 2004) Commercial Building Standard for Telecommunications Pathways and Spaces TIA-569-B-1 (May 2009) Temperature and Humidity Requirements for Telecommunications Spaces ANSI/TIA-606-B (June 2012) Administration Standard for Telecommunications Infrastructure TIA-607-B (September 2011) Generic Telecommunications Grounding (Earthing) and Bonding for Cus-tomer Premises TIA-758-A (August 2004) Customer-Owned Outside Plant Telecommunication Infrastructure Standard TIA-1152 (September 2009) Requirements for Field Test Instruments and Measurements for Balanced Twisted-Pair Cabling ANSI/TIA-862-A (April 2011) Building Automation Systems Cabling Standard TIA-1005-1 (March 2010) Telecommunications Infrastructure Standard for Industrial Premises; Addendum 1 - Industrial Pathways and Spaces ISO/IEC ISO 11801 - Generic Cabling for Customer Premises National Electric Codes National Electrical Safety Code (NESC) (IEEE C2-2012) National Electrical Code (NEC) (NFPA 70) OSHA Standards and Regulations – all applicable Local Codes and Standards – all applicable BICSI Telecommunications Distribution Methods Manual, 12th Edition Information Transport Systems Installation Methods Manual (ITSIMM), 6th Edition

Page 7: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 3

ANSI/BICSI 002-2011, Data Center Design and Implementation Best Practices ANSI/NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installa-tion Methods for Commercial Buildings ANSI/BICSI 001-2009, Information Transport Systems Design Standard for K-12 Educational Institutions AV Design Reference Manual, 1st Edition Network Design Reference Manual, 7th Edition Outside Plant Design Reference Manual, 5th Edition

Wireless Design Reference Manual, 3rd Edition

2.3 Anywhere cabling standards conflict with electrical or safety codes, Contractor shall defer to NEC and any applicable local codes or ordinances, or default to the most stringent requirements listed by either.

2.4 Knowledge and execution of applicable codes is the sole responsibility of the Contractor. Any code violations committed at the time of installation shall be remedied at the Contractor’s expense.

PART 3 - STRUCTURED CABLING SYSTEMS DEFINITIONS

3.1 "Structured Wiring" is a philosophy of pre-installing necessary cabling to device locations to be available to be used as these devices come on line. Moves and changes are affected at structured patch fields with the permanently installed links being relatively unchanging. In most basic form, a structured wiring system consists of horizontal wiring and appropriate connecting hardware, with backbone cabling connecting the horizontal sub-system to the main and intermediate distribution areas.

3.2 The following terms for various sub-systems are defined within the ANSI/TIA 568-C series of standards and shall be referred to throughout this document.

A. The entrance facility (EF) is the point where the outside plant cables and associated hardware is brought into the building. The entrance facility may be used for public network services, private network customer services or both. The demarcation points between carrier and customer and over-voltage protection devices are located here.

B. The telecommunications room (TR) (often referred to in the industry as MDF/IDF) is a centralized space for telecommunications equipment (e.g. PBX, computing equipment, video switch, etc.) that serves users in the building. This room is also, where the horizontal distribution cables are terminated. All recognized types of horizontal cabling are terminated on compatible connecting hardware. Similarly, recognized backbone cables are also terminated in the closet.

Page 8: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 4

Device activation is done with jumpers or patch cables to provide flexible connectivity for extending various services to users at the telecommunications outlets.

C. The backbone cabling provides interconnections between telecommunications closets, equipment rooms and entrance facilities. It consists of the backbone cables, main and intermediate cross-connects, mechanical terminations and patch cords or jumpers used for cross-connection. The backbone may connect Telecom Rooms within a building or between buildings.

D. The horizontal cabling consists of the physical media used to connect each outlet or device to a TR. Various types of cable can be used for horizontal distribution. Each type has its own performance limitations, size, and ease-of-use.

Page 9: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 5

PART 4 - REGULATORY REFERENCES – CONCLUSION

4.1 Denver Public Schools is investing in the latest technology to increase the speed and capacity of our communications systems in order to create a network infrastructure that will support DPS into the future. New applications will allow people to share vast amounts of information in the form of voice, data and video at efficient speeds. However, investing in the latest electronics to support these applications will be an exercise in futility if the installed cable plant cannot support the technologies involved.

4.2 Structured cabling will allow us to build an infrastructure for our communication needs to last well into the future. However, the ability to run any application, to any work area, at any time comes only with the proper planning and installation of a high-performance structured cabling system. Proper planning includes examining all applications, network technologies and telecommunications outlet locations that are currently used or might be used in the future. Accounting for foreseeable scenarios allows the physical infrastructure to be installed once, yet serve our requirements not yet on the horizon. Moves, adds and changes no longer require pulling new cables – except when our physical space expands.

4.3 Choosing the proper media for a new cable installation depends on the applications and services that the network is expected to provide. However, regardless of the other UTP classifications, Category 6 will be used for all data and telephony applications. Electrically noisy areas such as HVAC equipment rooms or near motors may lend themselves more to shielded or optical fiber cable. Budgetary concerns should influence the decisions to this point. However, keep in mind that standards-based systems are designed to last a minimum of 25 years from the time of installation. Therefore, cutting corners on the foundation of the network will have ramifications for many years to come and will not be tolerated. A properly planned and installed system will allow Denver Public Schools to spend their time, attention, and limited capital resources in other areas.

PART 5 - GENERAL INSTALLATION GUIDELINES

5.1 This section emphasizes some important details and installation processes for the structured cabling system. For complete guidelines see "Regulatory References" above.

5.2 Each individual 4 pair cable will be used for one service unless the data link application is designed to do so (as in VoIP voice over Internet Protocol). Splitting of pairs from a 4 pair cable across more than one jack is forbidden.

5.3 When installing Unshielded Twisted Pair (UTP) it must be compliant with industry standards. When routing cables through walls and ceilings the Contractor must maintain all distance limitations from power cable and devices as outlined in TIA 569-B.

5.4 Pulling a cable with too much force or bending it too sharply can change the electrical characteristics of the cable and degrade its performance, so care must be taken during the installation process to prevent any undue stress on the cable. Contractor shall adhere to all manufacturer's guidelines on cable handling, as well as the recommendations in TIA 568-C.0

Page 10: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 6

5.5 The cable should move freely at all times and be protected from sharp edges while it is being pulled. When pulling around tight or multiple corners, two or more people should be used to guide the cable and prevent damage to it.

5.6 Care should be taken when using any type of cable tie. Cables should be lightly tightened to avoid any visible stress, which can change the characteristics of the UTP cable.

5.7 All Contractor installed raceways shall be installed in practical alignment with either the building or structures within the building and securely attached to the building by use of plastic anchors, toggle bolts, expansion anchors or other method appropriate for the application and approved by the DoTS Project Manager.

5.8 All Contractor installed raceways shall be installed within the building so as not to interfere with or block any existing fixture, painting, mural, or artwork presently existing in the building.

5.9 All Contractor installed raceways shall be level and plumb when run vertically or horizontally along walls or ceilings. On raceway runs under a height of 8 feet from the floor, Contractor shall glue all fittings to the raceway using PVC cement.

5.10 All service loops on cabling links shall be according to TIA guidelines with a minimum 12" copper UTP slack in the work area that should be partially pushed back into conduit and stored in the ceiling space leaving approximately 7" left in the wall box. Contractors shall under no circumstances use "accordion" folds or in any way violate cable bend radius to store service loops in the work area.

5.11 Service loops in the telecommunications rooms shall also meet TIA requirements of 3 feet for copper and a minimum 3 meters slack for fiber backbones. TR slack shall be appropriately and neatly stored in managers, on pathways or on walls as necessary for that environment using storage appliances built to that purpose.

5.12 All penetrations shall be fire stopped according to national and local codes.

5.13 All Category 6 cables will be terminated on Panduit angled standard density Patch Panels and performance verified according to test procedures located in the testing and acceptance section of this document.

5.14 Coax cables shall be installed only in maintaining legacy systems. Additions to such systems shall be terminated on eight port splitters with a minimum of 6” between rows to connect all coax within a TR. The Contractor will use T&B snap and seal connectors. The Contractor shall place a 75-Ohm terminator cap on any unused splitter output ports.

5.15 The device end of legacy coax cables will be terminated in self-terminating inserts placed in an appropriate faceplate to match the installed systems. Any conduits supplied by the electrical sub-contractor for support of installed video locations are to be 1” in size.

Page 11: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 7

5.16 The Contractor shall test any additions to legacy coax cables and provide documentation of these tests as outlined in this document.

5.17 The wiring Contractor will make the head end connection to the cable TV Vendor’s entrance termination when making additions to any legacy broadband systems.

5.18 The Contractor placed drops for Wireless Data Access Points (WAP’s) shall be terminated at the serving TR end in the Panduit patch panels, using black jacks, with the other Category 6 terminations, and labeled in the same fashion as all other cables.

5.19 The device end of access point drops will be terminated with a Panduit RJ45 Category 6 ivory Mini-com jack in 2-port surface mount box. No service loops are needed on WAP locations.

5.20 In all other applications (i.e. hard deck ceiling or wall penetration), the device end of the cable will be terminated with a Panduit RJ45 Category 6 ivory TG-style jack and installed in a two port flush mount or surface mount box.

5.21 The Contractor will be responsible for mounting the Wireless Access Points and covers in hard deck applications.

5.22 All Wireless Access Points that are placed above drop ceiling will have a 1” wide label placed on the grid below the WAP location. This label will be 1” wide and have black text on an orange label.

5.23 Any conduits provided for the communication outlets are to be 1” in diameter with no daisy chaining allowed between work areas or speakers in audio systems.

5.24 In locations using Wiremold raceway, the Contractor may match the raceway previously installed. The legacy Wiremold is type 2400 or 4000. A 1” conduit will be supplied for each 10’ of Wiremold placed. All new installations shall use raceway types as described in the project documentation.

5.25 The Panduit frame used in conjunction with Wiremold raceway is CFG2__ or CFG4__ which is a two port or four-port GFCI frame. The Contractor will select the color to match the raceway.

5.26 Non-metallic multi-channel raceway shall be Panduit T-45, T-70, TG-70 or Twin-70 as described in the raceway section of this document. Consult project documentation for specific raceway to be used on that project.

5.27 Labor and material components will include TR build-out. The Wiring Contractor may be responsible for purchasing and installing additional 4x8x3/4” fire rated plywood backboards. These backboards shall be installed with firebrand facing outwards and painted with white fire-retardant paint according to TIA and BICSI guidelines. The standard number of plywood sheets for the Main TR is two and a minimum of one sheet of ¾” plywood installed for each TR.

Page 12: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 8

5.28 The Contractor shall be responsible for placing and mounting of all equipment racks, wire management, terminating hardware (copper and fiber), ladder racks (including waterfalls), grounding of the ladder racks and Panduit frames, and all labeling as described in this document.

5.29 Other specific installation guidelines are included in sections referencing specific sub-systems within this document.

PART 6 - MANDATORY CONTRACTOR REQUIREMENTS

6.1 Any Contractor wishing to bid DPS projects must meet the following qualifications:

A. Contractor shall maintain an established, permanent local office in the Denver, Colorado metropolitan area.

B. Contractor must provide insurance and performance bond certificate for the full amount of the bid proposal.

C. Contractor must not have filed for bankruptcy within the past seven years.

D. Contractor must not have defaulted on a material or performance bond within the past seven years.

E. Background checks and drug testing must be documented for all onsite Contractor employees and available for review by DPS.

F. All work performed will be completed by employees of the Contractor. No subcontracting will be permitted without prior written approval from DPS/DoTS.

G. Contactor shall be a Panduit Certified Installer.

H. At least 30 percent of the technicians on the job must have a current Panduit Certified Copper Technicians certificate to install Panduit Copper Distribution Systems.

I. At least 30 percent of the technicians installing any Fiber Distribution Systems must have a current Panduit Certified Fiber Technicians certificate to install Fiber Distribution Systems.

J. Contractor is responsible for workmanship and installation practices in accordance with the Panduit Certified Installers Program and all recommendations of TIA and BICSI references cited above.

K. A copy of contractor company and individual certification documents must be submitted with the quote in order for such quote to be valid.

L. All projects shall be covered by the Panduit Certification PLUS Warranty as described in this document.

M. Denver Public Schools requires that the Contractor have a BICSI Certified Registered Communications Distribution Designer (RCDD) on staff for the duration of the project.

Page 13: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 9

N. Contractor shall supply detailed references of five or more recently installed sites similar in size, drop count and configuration (including backbone). Please submit the site name, contact, contact telephone number, date installed, and project size.

6.2 Contractor Personnel/Technician Requirements:

A. Contractor shall provide an organizational chart of all personnel to be involved with this project. This chart shall include names and telephone contact numbers for all corporate officers, local management staff, Project Managers, RCDD’s and technical staff. This list shall be kept current and submitted bi-weekly to the Department of Technology Services (DoTS) Project Manager for the duration of the project. Resumes should be included for the assigned Project Manager, Lead Technicians for each proposed site, and the RCDD overseeing the bid design.

B. All of the installation personnel of the Installation Contractor shall be required to wear uniforms on-site. As a minimum, these uniforms shall consist of shirt with the company's name prominently displayed and all personnel shall comply with all Denver Public Schools appearance polices.

C. Technician photo ID badges are also required to be worn on the upper part of the body at all times.

D. Each Technician must have been employed directly by the Contractor for a minimum period of six (6) continuous months, have successfully passed a background check, and drug test.

E. All Contractor employees must successfully pass a background check and drug test. Proof of this requirement can be requested by DPS at any time.

F. The Contractor may request in writing to DPS on a case-by-case basis to utilize personnel that has verifiable related work experience, but may not have been employed by the Contractor for at least six (6) months.

6.3 Project Manager Requirements:

A. Contractor shall assign a dedicated Project Manager (PM) to serve as a primary liaison with DPS both during the project and for maintenance issues after project completion.

B. Minimum five years project management experience for voice, data, and multimedia cabling infrastructure systems.

C. RCDD preferred.

D. Have current, Panduit technician certificates in both copper and fiber installation.

E. Have thorough knowledge of all applicable standards, NEC, building and NFPA codes.

F. Have working knowledge of networking equipment and topologies.

G. Possess good personal interaction and communications skills.

H. Use computer-based project management software (preferably Microsoft Project, Microsoft Excel).

I. Have experience with formalized quality assurance practices.

Page 14: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 10

6.4 Tasks required of the Contractor Project Manager:

A. Serve as single point of contact on project related issues.

B. Oversee the project and complete quality inspections

C. Have the authority to execute changes for the Contractor.

D. Project coordination (labor tasks and materials).

E. Attend all project related meetings, walk-through, etc.

F. Be on-site for critical junctures.

G. Ensure conformance with Contract Provisions.

H. Be responsible for conditions and commitments associated with the Panduit Certification PLUS Warranty.

I. The Contractor’s Project Manager will be required to attend all project meetings requested. These may be weekly scheduled meetings or as required.

PART 7 - PROJECT PROGRESS REPORTS

7.1 The Contractor’s Project Manager will be required to submit weekly progress reports to Denver Public Schools and/or its designees via electronic transmission each Monday, at the end of the business day. Each report shall contain the following:

A. Work completed for the week, work scheduled for completion the following week, unforeseen construction obstacles, other comments.

B. Daily/Weekly Work Logs: Daily - The installation Contractor shall keep a daily log to be left on the job site. At a minimum, this log is to contain the following; weekly status reports, installation-tracking forms, material-tracking forms, packing slips, injury report, etc. This log must be available for reviewing at all times.

Example

DATE: MDF-A

Operation

Total

Runs

Rough-

In

Runs

Comp.

%

Comp.

Term.

Closet

%

Comp.

Term.

Jacks

%

Comp. Tested

%

Comp.

Rough In Cat 6 Ca-

ble

Place Cat 6 Cable

Place Speaker Cable

Wireless Access

Point

Totals

Place 25pr Tie Ca-

bles Size

Rough-

In Length

Date

Placed

Date

Term.

Date

Tested

Page 15: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 11

MDF to IDF B

MDF to IDF C

Place Cat 6 Tie

Cables # of

Rough-

In Length

Date

Placed

Date

Term.

Date

Tested

MDF to IDF B

MDF to IDF C

Place RG 11 Tie

Cables # of

Rough-

In Length

Date

Placed

Date

Term.

Date

Tested

MDF to IDF B

MDF to IDF C

Place Speaker Tie

Cables # of

Rough-

In Length

Date

Placed

Date

Term.

Date

Tested

MDF to IDF B

MDF to IDF C

Place Fiber Optics

Cable Mode

Rough-

In Length

Date

Placed

Date

Term.

Date

Tested

MDF to IDF B

MDF to IDF C

Room Build Date Placed

MDF-A

IDF-B

IDF-C

On Site

MDF A

Qwest Date Placed DoTS Responsibility

IT Feed

Trunks released

Data Switch

Installation Stacks

Date

Placed

Date

Tested DoTS Responsibility

MDF-A

IDF-B

IDF-C

X-Connects &

Patch cords

Total

X-

Con

X-

Cons

Comp.

%

Comp. DoTS Responsibility

IT Feed

MDF-A

IDF-B

IDF-C

Page 16: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 12

Totals

Telephones

Total

Sets

Sets

Comp.

%

Comp.

Sets

Tested

%

Tested

DoTS Respon-

sibility

Stations

Video Feeds Date Placed Date Tested DoTS Respon-

sibility

Comcast

Productivity

Total

Hours

Prod.

Hours

%

Prod.

Non-Prod

Hours

%

Non-Prod

Lead Technician

Technicians

Roadblock Resolution Resolution Date

C. DoTS will supply an electronic copy of this form upon request.

D. The Contractor Project Manager shall send the weekly log to the DoTS Project Manager or his/her designee by either Email or fax.

E. The Contractor shall create all logs using an Excel spreadsheet. (This may require the Installation Contractor to maintain a portable computer on the job site).

Page 17: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 13

7.2 The Project Manager shall in addition to formal weekly reports, participate in a walkthrough of the site as often as required by DPS/DoTS.

PART 8 - CONTRACTOR - ADDITIONAL RESPONSIBILITIES

8.1 The Contractor is responsible for the cost to repair or replace any items that are damaged because of the Contractor’s work. These items may include, but are not limited to, ceiling grids, ceiling tiles, patch/ paint walls to match existing color, electrical, HVAC lines, etc.

8.2 When working in and around the building, extreme care shall be exercised with regard to protection of the existing structure and mechanical systems. The Contractor will be required to notify DPS/DoTS for the repair or replacement of any damaged items. DPS will arrange for the repairs or replacement and bill the Contractor as appropriate.

8.3 The Contractor shall thoroughly examine the premises and observe all conditions under which the work will be performed. The Contractor shall document all existing conditions.

8.4 Unless documented otherwise, all finishes shall be assumed undamaged. Any damage noted by Denver Public Schools and/ or its designees in the area of work performed, and not previously noted, shall be the responsibility of the Contractor.

8.5 All repairs, restoration, patching, etc. shall match existing adjacent surfaces as to material, texture, and quality.

8.6 Site Clean Up:

A. The Contractor is responsible for removing all trash and debris to outside garbage containers on a daily basis by the end of each day, or as needed during the course of the day. The Contractor shall provide their own trash containers or utilize DPS trash containers with prior written approval.

B. No trash or debris is to be left in any area where work has been performed. This includes removing trashcans or other forms of garbage collection devices at the end of each day.

C. At the completion of the installation, the Contractor shall clean all areas where work has been performed. This procedure shall include vacuuming and light mopping of floor surfaces, cleaning of racks, panels, boards, etc. The Contractor may be required to repeat this process during the acceptance period.

D. Workstation outlet location areas shall be cleaned on an on-going basis each time the Contractor completes work in the area.

Page 18: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 14

8.7 The Project Manager and Project Lead Technician shall have cell phones and be accessible at all times.

8.8 The Contractor shall have an Internet addressable Email box for communications with Denver Public Schools or its designees for the purpose of gaining or distributing current information.

8.9 All Contractors and their employees are expected to conduct themselves in a professional manner at all times while implementing any DPS cabling project. All rules and guidelines of the project site shall be followed.

8.10 No alcohol use, drug use, smoking, or inappropriate language shall be permitted on the project site.

8.11 Appropriate dress and identifications is required at all facilities and Contractor’s must follow DPS rules and regulations.

8.12 Under no circumstances shall any Contractor employee use any school or school employee’s equipment or material.

8.13 Denver Public Schools/or its designees shall have the right to immediately remove personnel without notice.

8.14 The Contractor shall provide, possess, and have proper knowledge of the appropriate tooling and equipment required to install the specified materials:

A. This includes, but is not limited to the following: safety equipment, correct power tools, personnel lifts, termination tools, field test equipment, etc.

B. Any tools that require certification (such as a power-actuated fastener), shall be only operated by individuals certified in their use.

Page 19: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 15

PART 9 - MATERIALS STORAGE

9.1 The Contractor is responsible for providing storage on the grounds of the project. As a minimum, water tight, lockable container capable of storing a two week supply of materials plus all of the Contractor's equipment is acceptable.

9.2 Outside portable storage units will need DPS approval prior to placement. The Contractor must remove any graffiti on Contractor’s equipment immediately.

PART 10 - FIELD VERIFICATION

10.1 The Contractor shall field verify all dimensions prior to installation. Field verifications shall include, but not be limited to, installing measuring tape in backbone pathways and reporting lengths to Materials Contractor.

PART 11 - SCHEDULE

11.1 For individual projects, Denver Public Schools and/or its designees will have compiled a project schedule. This schedule will be provided at the biweekly Project Managers Meeting. Each Contractor shall be responsible for reviewing the schedule and determining the necessary personnel to ensure timely task completion.

PART 12 - CHANGES TO SCHEDULE

12.1 Denver Public Schools and/or its designees may find it necessary to reduce (shorten) the schedule or lengthen the schedule of the initial allotted time. DPS shall not incur any additional cost should the schedule change. Any changes to the schedule shall be handled individually, with the concurrence of all parties.

PART 13 - DPS PROJECT CONTACT

13.1 13.01 If there are any questions or if any additional information is required pertaining to the DPS Project Coordination, please contact: Mike Hall at 720-423-3898.

PART 14 - SYSTEM COMPONENT WARRANTY

14.1 14.01 All installed communications products shall be covered by a manufacturer component warranty against any manufacturing defects for a period of 25 years.

A. The Contractor shall replace, free of charge for this period, any cable, connector, or other component installed by the Installation Contractor that fails due to such defects.

Page 20: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 16

B. The Materials Contractor shall provide a copy of this product warranty to the Installation Contractor. The Materials Contractor shall replace free of charge for this period, any cable, connector, or other passive component installed by the Installation Contractor that malfunctions.

PART 15 - CERTIFICATION PLUS SYSTEM PERFORMANCE WARRANTY

15.1 Contractor shall provide a 25 year Panduit Certification PLUS warranty on all copper and fiber permanent cabling links. This warranty guarantees the installed system shall support all current and future data link protocols designed and specified by IEEE and TIA to operate over that Category (copper) or OM designation (fiber) of cable.

15.2 The Certification Plus Warranty may be applied only if the cabling links are comprised entirely of Panduit connectivity and cable.

15.3 To offer this warranty, Contractor agrees to adhere to the requirements listed below:

A. Installation firm must be a current Panduit Certified Installer (PCI) in good standing and shall include a copy of the company PCI certification with the bid.

B. Contractor shall name a project manager to serve on site as a liaison responsible to inspect and assure all terminations are compliant to factory methods taught in Panduit Technician Certification Training and according to all Standards cited in the Regulatory References section of this document. This liaison shall have a current, up-to-date Panduit Certified Technician (PCT) certificate in both copper and fiber. Copies of the copper and fiber certificates of the Panduit liaison shall be submitted with the bid.

C. Contractor agrees all components comprising active links shall be of the same copper Category or fiber OM designation as the system being installed. Contractor shall under no circumstances mix different Categories or OM classes of cable or termination devices (connectors) within the same link or system.

D. Contractor shall install all racking and support structures according to TIA Standards in such fashion as to maintain both Standard and Manufacturer recommendations for uniform support and protection, segregation of different cable types, maintenance of maximum pulling tensions, minimum bend radius, approved termination methods as well as adhering to industry accepted practices of good workmanship.

E. Contractor is responsible for understanding and submitting to Panduit all documents required prior to project start to apply for this warranty. These include but are not limited to the project information form and SCS warranty agreement.

F. Contractor is responsible for understanding and submitting to Panduit all documents required at project end. These include completed warranty forms, passing test reports and drawings of floor plans showing locations of links tested.

G. Test results shall be delivered in the tester native format (not Excel) and represent the full test report; summaries shall not be accepted. Contact Panduit for a current list of approved testers, test leads and latest operating systems.

H. Upon acceptance of Warranty, Panduit will mail a notification letter to the Installer and a notification letter and warranty certificate to DPS.

Page 21: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMON WORK RESULTS FOR COMMUNICATIONSMEP Engineering Project No. 13464 27 05 00 - 17

PART 16 - RESTORATION/RESPONSE TIME

16.1 If the failure or malfunction of a component causes a single workstation outlet location to become inoperable, the Contractor shall correct and make serviceable the station within eight (8) business hours of being notified of the problem. The repairs may be made during normal business hours as defined herein. All repairs shall be given priority over new installation work.

16.2 If the failure or malfunction of a component causes more than a single workstation outlet location (such as a network segment or backbone cable) to become inoperable, the Contractor shall correct and make serviceable the stations within four (4) hours of being notified of the problem. The repairs shall be made regardless of time of day.

16.3 The Contractor shall maintain a method of contact for these repairs for both normal business hours and non-business hours (24x7, 365 days).

16.4 The Contractor shall stock a sufficient amount of replacement materials for the expressed purpose of restoring service. The Contractor shall follow the manufacturers’ procedures to replace any materials used from their stock for these repairs (e.g., from the Materials Contractor or from the manufacturer).

16.5 All costs for the entire warranty period (25 years) shall be included as part of the project price.

END OF SECTION

Page 22: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS MEP Engineering Project No. 13464 27 05 26 - 1

SECTION 27 05 26

GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

PART 1 - GROUNDING AND BONDING

1.1 Contractor is responsible for bonding to ground all newly placed equipment and installed racks or cabinets per the TIA 607-B Standard using Panduit bonding systems. Details of bonding are as follows:

A. All newly installed racks and cabinets shall have installed a vertical busbar mounted along one equipment rail to serve as a clean, low-resistance bonding place for any equipment not equipped with a designated grounding pad.

B. Smaller equipment without an integrated grounding pad shall be bonded to the vertical busbar through the use of a thread-forming grounding screw that is anodized green and includes serrations under the head to cut through oxidation or paint on the equipment flange.

C. Larger equipment (chassis switches) with a designated grounding terminal shall be bonded to the vertical busbar with an EBC (equipment bonding conductor) kit built to that purpose.

D. Contractor shall take care to clean (wire brush, scotchbrite pads) any metallic surface to be bonded down to bare metal and apply a film of anti-oxidation paste to the surfaces prior to effecting the bond.

E. All bonding lugs on racks and busbars shall be of two-hole irreversible compression type. Mechanical lugs and single-hole lugs will not be accepted and shall be removed and replaced at Contractor's expense.

F. Every rack or cabinet shall have an individual bonding conductor into the grounding network, serially connecting (daisy-chaining) of racks is expressly forbidden and will not be accepted.

G. Rack Bonding Conductors (RBC) may tap into an overhead or under floor aisle ground, or may run to the wall-mounted grounding busbar in smaller Telecommunications rooms containing five racks or less.

H. A minimum of every other rack or cabinet shall be outfitted with a properly installed and bonded ESD (electro-static discharge) port along with a wrist strap and lead to be used by any technicians servicing network equipment. On four post racks and cabinets, these ESD ports and straps shall be provided on front and back to be accessible and able to reach any active equipment needing servicing.

I. Armored cables shall be properly bonded to the earthing system with a kit built to that purpose.

1.2 For examples of rack and cabinet grounding refer to the illustrations below:

Page 23: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS MEP Engineering Project No. 13464 27 05 26 - 2

Properly Bonded Cabi-

net

Rack Ground Strip

(not used in retrofit

application)

Basic equipment cabinet

with the doors and side

panels removed for

clarity

Front to Back Rail Jumper

Common Bonding Network

Jumper

Mesh Common Bonding

Network

Equipment Jumper

Grounding Busbar

(can be mounted to bottom or

top of cabinet)

Electrostatic Discharge

(ESD) Port

Page 24: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS MEP Engineering Project No. 13464 27 05 26 - 3

Properly Bonded Two-post Rack

Page 25: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS MEP Engineering Project No. 13464 27 05 26 - 4

1.3 List of bonding materials:

Part Number Description

LCC series Panduit two-hole compressing lugs for code conductors in BICSI hole spacing.

HTCT series Panduit HTAPs. Must be selected according AWG size of run and tap conductors.

CLRCVR series Panduit clear covers for HTAPs. Must be selected according to HTAP being covered.

RGS134-1Y Grounding strip (vertical busbar) for newly installed racks or cabinets with screw rails.

78.65" (2m) length; .67" (17mm) width; .05" (1.27mm)thickness; provided with .16

oz. (5cc) of antioxidant, one grounding sticker and three each #12-24 x 1/2" and M6 x

12mm thread-forming screws.

RGS134B-1 Grounding strip for newly installed racks or cabinets with cage nut rails: 78.70" (2m)

length; .67" (17mm) width; .05" (1.27mm) thickness; provided with .16 oz. (5cc) of

antioxidant, one grounding sticker, three cage nut bonding studs, eight #12-24 bonding

nuts and three strip clips.

RGCBNJ660P22 Jumper kit for bonding individual racks or cabinets into grounding backbone. #6 AWG

(16mm²) jumper; 60" (1.52m) length; 45° bent lug on grounding strip side; provided

with .16 oz. (5cc) of antioxidant, two each #12-24 x 1/2", M6 x 12mm, #10-32 x 1/2"

and M5 x 12mm thread forming screws and a copper compression HTAP* for con-

necting to a #6 to #2 awg sized bonding backbone.

RGCBNJ660PY Jumper kit for bonding individual racks or cabinets into grounding backbone. #6 AWG

(16mm²) jumper; 60" (1.52m) length; 45° bent lug on grounding strip side; provided

with .16 oz. (5cc) of antioxidant, two each #12-24 x 1/2", M6 x 12mm, #10-32 x 1/2"

and M5 x 12mm thread forming screws and a copper compression HTAP* for con-

necting to a #2 awg to 250 kcmil bonding backbone.

GJ672UH Rack jumper (and cabinet) kits for smaller TR (5 bays or less) to bond individual rack

or cabinet directly back to wall mounted busbar. One 72" length #6 AWG green wire

with yellow horizontal stripe. Jumper is pre-terminated on one end with LCC6-

14JAWH-L and the other end with LCC6-14JAW-L. This rack grounding jumper is

72" long. For other lengths replace the "72" in the part number. Available lengths are

72, 96, 120, 144, 168, 192, 216, 240, 264 and 288 inches.

RGESD2-1 Two-hole ESD port with 5/8" hole spacing; provided with an ESD protection sticker,

.16 oz. (5cc) of antioxidant, and two each #12-24 x 1/2" and M6 x 12mm thread-

forming screws.

RGESDWS Adjustable fabric ESD wrist strap with 6' coil cord, banana plug, 1 megaohm resistor

and 4mm snap.

RGTBSG-C Green thread-forming bonding screws for use to mount equipment that does not have a

built-in grounding pad (terminal).

CNB4K Green bonding cage nut, includes 4 #12-24 bonding cage nuts (.06 – .11 thick panel)

and 4 #12-24 x 1/2" bonding screws with #2 Phillips/slotted combo hex head (use

5/16" or 8mm socket). Ideal for patch panel applications and bonding smaller equip-

ment not equipped with a built-in grounding terminal.

CNBK Green bonding cage nut, includes 50 #12-24 bonding cage nuts (.06 – .11 thick panel)

and 50 #12-24 x 1/2" bonding screws with #2 Phillips/slotted combo hex head (use

5/16" or 8mm socket).

RGW-100-1Y 100 paint piercing bonding washers for 3/8" (M8) stud size; .875" (22.2mm) O.D.;

provided with .16 oz. (5cc) of antioxidant. NOTE: Panduit racks come supplied with

these. This is needed to construct non-Panduit racks.

RGEJ1024PHY 24" long pre-terminated equipment grounding jumper#10 AWG (6mm²) jumper; bent

lug on grounding strip side to straight lug on equipment; provided with .16 oz. (5cc) of

antioxidant and two each #12-24 x 1/2", M6 x 12mm, #10-32 x 1/2" and M5 x 12mm

thread-forming screws.

Page 26: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS MEP Engineering Project No. 13464 27 05 26 - 5

RGEJ1036PFY 36" long pre-terminated equipment grounding jumper#10 AWG (6mm²) jumper; bent

lug on grounding strip side to straight lug on equipment; provided with .16 oz. (5cc) of

antioxidant and two each #12-24 x 1/2", M6 x 12mm, #10-32 x 1/2" and M5 x 12mm

thread-forming screws.

GB2B0514TPI-1 Wall mounted telecommunications busbar suitable for small telecom room. Pre-

assembled with BICSI/TIA-607-B hole spacing. Bar is 1/4" x 2" x 24" in size.

GB4B1028TPI-1 Wall mounted telecommunications busbar suitable for larger telecom room. Pre-

assembled with BICSI/TIA-607-B hole spacing. Bar is 1/4" x 4" x 24" in size.

ACGK Armored cable grounding kit. Contains one grounding terminal for #6 AWG ground-

ing conductor, and one #10 mechanical clamp for cable diameters in 9/16" – 1 1/16"

diameter range.

ACG24K-500 #6 AWG (16mm2) jumper for armored cable diameter 0.85" (21.3mm) to 1.03"

(26.2mm); 24" (609.6mm) length; factory terminated on one end with LCC6 two-hole

copper compression lug and the other end with grounding terminal; provided with two

each #12-24 and M6 thread-forming screws and a black polypropylene terminal cover.

ACG24K #6 AWG (16mm2) jumper for armored cable diameter up to 0.84" (21.3mm); 24"

(609.6mm) length; factory terminated on one end with LCC6 two-hole copper com-

pression lug and the other end with grounding terminal; provided with two each #12-

24 and M6 thread-forming screws and a black polypropylene terminal cover.

LTYK Wall mounted busbar label kit. Label kit includes printed tag and one flame retardant

cable tie.

END OF SECTION

Page 27: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton IDENTIFICATION FOR COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 27 05 53 - 1

SECTION 27 05 53

IDENTIFICATION FOR COMMUNICATIONS SYSTEMS

PART 1 - GENERAL REQUIREMENTS

1.1 All permanently installed cable and network infrastructure labels shall be machine generated on

labels manufactured for that purpose, and designed to outlast the elements to which they

attach.

1.2 All permanently installed cable and network infrastructure labels shall be machine generated

using Panduit Easy-Mark software, or generated on-site using a Panduit PanTher hand-held

labeler.

1.3 It is the responsibility of the Contractor to label all elements of the network cabling system with

permanent, machine-generated labels according to:

A. Circuit naming conventions already established at Denver Public Schools.

B. Guidelines established in the TIA 606-B Standard.

C. Any project-specific instructions associated with particular jobs.

1.4 On specific projects, Contractor shall bring to the attention of DoTS anywhere these standards,

guidelines and instructions may be in conflict for clarification and resolution.

1.5 The following are general points regarding how Denver Public Schools cabling shall be labeled

A. Label each cable, work area outlet location, fiber enclosure, etc. with a computer generated or

machine printed label. Each label shall be easily visible and made of materials designed to

outlast the elements to which they are attached

B. Labels shall be machine generated using Panduit Easy-Mark labeling software and laser-printed

onto Panduit sheet labels appropriate to the device to which they attach.

C. Individual labels that must be printed on-site will be printed using the Panduit "PanTher" hand-

held labeler (LS8EQ-KIT-ACS) onto labels made specifically for the elements to which they

attach.

Page 28: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton IDENTIFICATION FOR COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 27 05 53 - 2

D. Handwritten labels for anything besides temporary place-holders prior to placement of

permanent machine-generated labels will not be accepted and must be corrected at

Contractor's expense

PART 2 - CABLE LABELS

2.1 The structured cabling system is based on a structured wiring design of three (3) - UTP

Category 6 cables to each teacher/student outlet location. The cables shall be designated by

TR room, rack, row, and position (i.e. A.2.14.24, B.2.5.15).

2.2 All additions to legacy coax cables will be labeled at both ends utilizing the alpha TR

designation and a consecutive numeral designation beginning at one.

2.3 Hand-written cabling systems labels are not allowed and will not be accepted.

2.4 All cable labels shall be of the wrap around self-laminating type. It is Contractor's responsibility

to confirm the label size is appropriate for the cable installed. The following circuit designation

and labeling materials list indicates a complete list of approved labeling supplies.

Part Number Description

PROG-EM2GO Easy-Mark Labeling Software for PC, supplied on USB Flash Drive.

LS8EQ-KIT-ACS Panduit PanTher hand-held label printing system in kit. Includes LS8EQ printer with

QWERTY keypad, one cassette of S100X150VAC self-laminating labels, six AA al-

kaline batteries, LS8E-ACS, LS8-CASE, LS8-PCKIT, LS8-IB, LS8-WS, quick refer-

ence card and operator’s manual.

C195X040Y1J Faceplate label for use with Easy-Mark labeling software and laser printer.

C261X035Y1J Faceplate label for use with Easy-Mark labeling software and laser printer - horizontal

sloped faceplates.

C195X040Y1C Faceplate label for use with PanTher LS8E hand-held printer

C261X035Y1C Faceplate label for use with PanTher LS8E hand-held printer - horizontal sloped face-

plates.

C261X035Y1J Component Labels for Mini-Com® Modular Faceplate Patch Panels for use with Easy-

Mark software and laser printer.

C261X035Y1C Component Labels for Mini-Com® Modular Faceplate Patch Panels for use with Pan-

Ther LS8E hand-held printer.

S100X150YAJ Self-laminating cable labels for Category 6 cable for use with Easy-Mark software and

laser printer.

S100X150VAC Self-laminating cable labels for Category 6 cable for use with PanTher LS8E hand-

held printer.

S100X650YAJ Label for indoor armored 12 and 24 str cable - for use with Easy-Mark software and

laser printer.

S100X650VAC Label for indoor armored 12 and 24 str cable - for use with PanTher LS8E handheld

Page 29: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton IDENTIFICATION FOR COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 27 05 53 - 3

printer.

S100X400YAJ Label for outdoor armored 24 str cable - for use with Easy-Mark software and laser

printer.

S100X400VAC Label for outdoor armored 24 str cable - for use with PanTher LS8E handheld printer.

S100X160YAJ and

NWSLC-3Y

Laser printable fiber jumper self-laminating labels with rotating sleeve for FZE/FXE

multimode and singlemode fiber jumpers

S100X160VAC and

NWSLC-3Y

Fiber jumper self-laminating labels with rotating sleeve for FZE/FXE multimode and

singlemode fiber jumpers. For use with PanTher LS8E handheld printer.

S100X220YAJ and

NWSLC-7Y

Laser printable fiber jumper self-laminating labels with rotating sleeve for FZD/FXD

jumpers.

S100X220VAC and

NWSLC-7Y

Fiber jumper self-laminating labels with rotating sleeve for FZD/FXD jumpers for

PanTher LS8E handheld printer.

S100X150YAJ Label for copper patch cords for use with laser printer.

S100X150VAC Label for copper patch cords for use with PanTher hand-held labeler.

T100X000VPC-BK 1" high, continuous black on white, vinyl tape labels for labeling racks and cabinets

with PanTher LS8E handheld labeler.

C400X100YJT 1" by 4" white, polyester label for labeling racks and cabinets that prints from laser

printer using Easy-Mark software.

Page 30: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton IDENTIFICATION FOR COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 27 05 53 - 4

PART 3 - EQUIPMENT LABELS – GENERAL

3.1 All telecommunications equipment and parts furnished and installed by the Contractor shall be

equipped with a permanent numbering identification indicating its individual location within the

school.

3.2 All such identification labels shall be machine generated. Hand written designators will not be

accepted.

3.3 Label numbers shall be comprised of the TR room-rack-row-position. Equipment to be identified

shall include, but not limited to, all wiring, faceplates, jacks and connecting blocks.

3.4 All vertical and horizontal faceplates and other miscellaneous locations (e.g. master clock,

DDC/IBAS, security panel, etc.) will be identified using TR room-rack-row-position specific to the

drop location.

3.5 Faceplates shall be provided a Panduit machine printed adhesive label placed directly on

faceplate in the label area. The clear plastic label cover will then be installed over the

permanent label.

PART 4 - JACK DESIGNATORS

4.1 All jacks at both the device and patch panel locations may be identified with a permanent fine tip

Sharpie, handwritten using TR room-rack-row-position specific to the drop location on the side

of the jack. This labeling shall not be visible from the exterior face of the jack.

PART 5 - PATCH PANEL LABELING

5.1 All patch panels located in the TRs will be identified by using rack-row-position specific to the

drop location using permanent, pressure sensitive (sticky), machine generated labels designed

to fit in the plates that snap into the front of the patch panels.

PART 6 - FIBER ENCLOSURE LABELING

6.1 The black enclosures shall be labeled with "From - To" information. All ports shall be labeled

with strand numbers.

PART 7 - RACK LABELING

Page 31: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton IDENTIFICATION FOR COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 27 05 53 - 5

7.1 Racks will need to be numbered to conform to DPS/DoTS labeling requirements. For example,

rack 0 should be installed closest to the wall and allowing for outward growth. The label shall be

placed at the top and centered on the rack.

7.2 All racks will be labeled on the front and rear with 1" high continuous black on white vinyl tape.

END OF SECTION

Page 32: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 1

SECTION 27 08 00

COMMISSIONING OF COMMUNICATIONS

PART 1 - SYSTEM PERFORMANCE TESTING

1.1 All cables shall be tested in accordance with this document, the ANSI/TIA standards, the PANDUIT® Certification Plus System Warranty guidelines and best industry practice.

1.2 If any of these are in conflict, the Contractor shall bring any discrepancies to the attention of the DPS project team for clarification and resolution.

1.3 Copper Testing:

A. All twisted-pair copper cable links shall be tested for Category 6 compliance per the requirements in ANSI/TIA 1152 and ANSI/TIA 568-C.2 using a test unit meeting a minimum IEC IIIe level of accuracy.

B. All Category 6 cables shall have a minimum of +3db of headroom.

C. All testers used must have been factory calibrated by the manufacturer within one year of use or according to factory calibration recommendations, whichever is the more stringent.

D. Contractor shall set references according to manufacturer’s recommendation prior to each day’s testing and reset references anytime tester is left unused for more than two hours.

1.4 Fiber Testing:

A. All installed fiber shall be tested for link-loss in accordance with ANSI/TIA-C.0 and shall be within limits specified within ANSI/TIA-C.3. DPS may further define acceptable link loss thresholds for specific fiber links.

B. For horizontal cabling systems using multimode optical fiber, attenuation shall be measured in one direction at either 850 nanometer (nm) or 1300 nm using an LED light source and power meter.

C. Backbone multimode fiber cabling shall be tested at both 850 nm and 1300 nm (or 1310 and 1550 nm for single mode) in both directions.

D. Test set-up and performance shall be conducted in accordance with the ANSI/568-C.0 Standard, Method B. All test leads must be reference cords built specifically for fiber testing. Fiber testing performed using standard fiber jumpers will be considered invalid and must be repeated by the Contractor at no cost to DPS.

E. Where multiple links are combined to complete a circuit between devices, the Contractor shall test each individual terminated fiber link - so only basic link loss is required. The test method

Page 33: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 2

shall be the same used for the test described above. The values for calculating loss shall be those defined in the ANSI/TIA 568-C.3 Standard unless specified otherwise in by DPS.

F. Attenuation testing shall be performed with stable launch conditions, using as test leads true fiber reference cords built to that purpose. The light source shall be left in place after calibration and the power meter moved to the far end to take measurements. While an OTDR may be useful to determine exact locations of light loss, only a loss meter is required for simple link performance verification.

Page 34: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 3

PART 2 - TEST RESULTS AND DOCUMENTATION:

2.1 Upon completion of the installation and testing, the telecommunications contractor shall provide three (3) full documentation sets to the DPS/DoTS for approval within three weeks of completion of installation.

2.2 Test results must be in the tester native format, spreadsheets will not be accepted.

2.3 The media shall be clearly marked on the outside front cover with the words “Project Test Documentation”, the project name, and the date of completion (month and year).

2.4 The results shall include a complete record of test frequencies, cable type, conductor pair and cable (or outlet) I.D., measurement direction (where applicable), reference setup, and test crew member name(s).

2.5 The test equipment name, manufacturer, model number, serial number, software (OS) version, model number of test heads and leads (where applicable), and last calibration date will also be provided at the end of the document.

2.6 Unless the manufacturer specifies a more frequent calibration cycle, an annual calibration cycle is anticipated on all test equipment used for this installation.

2.7 The test document shall detail the test method used and the specific settings of the equipment.

2.8 When repairs and re-tests are performed, the problem found and corrective action taken shall be noted, and both the failed and passed test data shall be documented in the documentation.

2.9 DPS reserves the right to confirm contractor test results with random testing by a 3rd party including the right to require contractor to perform 100% retesting based upon the results of these random tests.

2.10 Mandated retests based on discovery of faulty methods/results shall be performed at Contractor's expense.

2.11 The As-Built drawings are to include cable routes and outlet locations. Their sequential number as defined elsewhere in this document shall identify outlet locations.

2.12 Numbering, icons, and drawing conventions used shall be consistent throughout all documentation provided.

Page 35: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 4

2.13 DPS will provide floor plans in paper and electronic (DWG, AutoCAD - latest version) formats on which as-built construction information can be added. These documents will be modified accordingly by the telecommunications contractor to denote as-built information as defined above and returned to the DPS in hard copy and electronic form (AutoCAD).

PART 3 - CUTOVER REQUIREMENTS

3.1 Contractor’s bid proposal shall include all labor and material necessary to cut over (migrate) the school/site communication system from the existing wiring infrastructure to the newly Contractor installed wiring infrastructure.

3.2 The system cutover timeframe for the voice, data, and video, etc. communications network will take place upon completion of the new wiring infrastructure but not in conjunction with the installation of the new system. The cutover schedule will be scheduled and coordinated by the DoTS Cut Coordinator.

3.3 The Contractor will be required to attend any walkthroughs with the DoTS Cut Coordinator, in order, to determine room/office outlet locations, phones that are defective and need to be replaced, new phone locations and any other documentation needed for a successful cut over.

3.4 DoTS Cutover Responsibilities:

A. The DoTS Cut Coordinator will be on site at the time of the cut over and work closely with the Contractor to ensure a quick and successful cut over transparent to the end user.

B. The DoTS Cut Coordinator will provide the Contractor with cut sheets that will include all information necessary for the Contractor to complete the work.

C. DoTS will provide any telephone instruments that are required.

D. The DoTS Cut Coordinator will remove all cross connects on the old terminal wall field and determine for the Contractor what wiring and material the Contractor is to remove.

3.5 Contractor Cutover Responsibilities:

A. The Contractor will assign a Cut Coordinator to the project who will work closely with the DoTS Cut Coordinator.

B. Using the floor plans provided by the Contractor, the DoTS Cut Coordinator in conjunction with the Contractor’s Cut Coordinator will conduct walkthroughs to determine room/office outlet locations, phones that are defective and need to be replaced, new phone locations and any other documentation needed for a successful cutover.

C. The Contractor will be responsible to identify and resolve any issues with the Contractor placed cables for opens, reversals, etc.

D. The Contractor will be responsible for removing and disposing of all old wiring and used material from the school as directed by the DoTS Cut Coordinator.

Page 36: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 5

E. If the existing phone and data equipment is relocated to a new location, the Contractor, using the information provided by DoTS, will remove all phone and data related equipment (Phones, Ethernet switches, routers, NIU) from the existing location and reinstall that equipment in the new location and mount that equipment in either a rack or on the wall as directed by the DoTS Cut Coordinator.

F. Using the cut sheets, the Contractor will be responsible to place all voice and data patch cords, cross connects, line cords, and Remote Access Devices.

G. In conjunction with the equipment cutover, the Contractor will visit each phone and data location within the school and move the phone and computer from the old wiring to the new wiring location as designated on the cut sheets.

H. The Contractor will change all line and patch cords to lengths specified in the project documentation and per direction of the DoTS.

I. The Contractor will replace the existing computer patch cord with a new Contractor provided Category 6 patch cord.

J. All computers will be tested by DPS personnel during the cut over.

K. Where required, the Contractor will be responsible for changing the existing wall phone to a desk set, and patch and repair all holes left in the walls. The replacement equipment for damaged telephone instruments or set bases will be provided by DPS.

L. In instances where the Contractor will be required to install or replace raceway, care shall be taken to match raceway with the legacy installation.

M. In the event certain portions of old raceway must be removed, the Contractor will be responsible to remove any raceway that has been damaged or detached from the original wall. However, painting to match the existing walls will not be required.

N. In cases where just a small amount of raceway is removed, end caps will also not be required.

O. If the existing faceplate and outlet are behind any piece of large furniture (e.g. cabinets, file cabinets, etc.) the Contractor will be responsible to move the furniture and replace the faceplate. If the Contractor feels this cannot be done in a safe manner, the Contractor should contact the DPS Cut Coordinator for instructions.

P. Situations might also arise where the existing holes cannot be patched or covered with a single or double gang outlet cover, this also should be noted and reported to the DPS Cut Coordinator for guidance.

Q. Test each set for dial tone, line access and extension number. If during the cut over of the school/site there are any wiring outlets that were missed on the initial installation of the wiring or any problems found in the new infrastructure, the Contractor will correct these problems promptly at no additional cost to DPS.

R. The Contractor will be responsible for securely mounting all wireless access points provided by DPS. These access points will be mounted as directed by the DPS Cut Coordinator.

S. The Contractor will also be required to provide a patch cable to connect the wireless access point into the Category 6 cable and jack for each wireless access point installed.

Page 37: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton COMMISSIONING OF COMMUNICATIONS SYSTEMS MEP Engineering Project No. 13464 26 05 00 - 6

T. After the cutover has been completed, the Contractor and the DoTS Cut Coordinator will conduct a final acceptance walkthrough to ensure that all problems have been resolved and the cut over has been successfully completed.

U. The Contractor should realize that each school will have different situations and circumstances that will be addressed on a case by case basis.

V. Contractor will also be responsible for resolving any structured cabling conversion related issues for 60 days after cutover.

W. If the Contractor and the DPS Cut Coordinator cannot resolve any problems that might arise then the decision of the DPS Cut Coordinator will be final and binding at no additional cost to DPS.

PART 4 - INSPECTION/ACCEPTANCE PERIOD

4.1 Denver Public Schools and/or its designees shall periodically inspect the work of the Contractor. When requested the Contractor shall, at no additional charge, supply an installation technician to accompany the individual(s) performing the inspection tasks. The Contractor shall be responsible for uncovering concealed areas in order for the work to be inspected.

4.2 Denver Public Schools requires a thirty (30) day acceptance period after the completion of any project, or a portion thereof if turned over to DPS prior to the completion of the total project. Final project completion is the conclusion of all specified work, including all labeling, testing, documentation, site cleanup, and quality inspection.

4.3 DPS and/or its designees shall utilize this acceptance period to perform workmanship evaluations and random testing. A representative of the Contractor shall be available to work with DPS and/or its designees during this acceptance period.

4.4 The Contractor shall be required to make any repairs or modifications deemed necessary by Denver Public Schools and/or designees immediately, without exception or recourse.

4.5 The required warranties shall begin at the conclusion of the acceptance period.

END OF SECTION

Page 38: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 1

SECTION 27 10 00

STRUCTURED CABLING

COMMUNICATIONS CABINETS, RACKS, FRAMES, AND ENCLOSURES

PART 1 - 19" RACKS

1.1 Standard 19” frames with vertical wire management will be utilized in all MDF and IDF locations. However, if there is concern for space or security, a locking cabinet will be required.

1.2 The Contractor shall assemble all Panduit 19" equipment racks (part number CMR19X84) and permanently mount them using the appropriate anchoring kits.

1.3 In the telecom rooms 19” Panduit racks shall have installed two-sided (front and rear) vertical managers of 12-inch width in between racks (Panduit part number PRV12) and 8-inch front and rear vertical cable managers on ends of rows (Panduit part number PRV8).

1.4 Contractor shall provide front doors for racks Panduit part number PRD8 for the 8-inch managers and PRD12 for the 12-inch managers. Refer to appendix “A” at the end of this section for part numbers.

1.5 Contractor shall confirm all cable managers are sized to have no more than 40% fill upon installation per manufacturer's fill charts, and bring to the attention of the DoTS any managers that are improperly sized for the application for resolution.

PART 2 - COMMUNICATIONS CABINETS

2.1 Large equipment rooms (data centers) and certain Telecommunications Rooms may require lockable cabinets for equipment mounting for security purposes.

2.2 Switch Cabinets shall be Panduit N series. Refer to appendix “A” at the end of this section for part numbers.

2.3 Server Cabinets shall be Panduit S series. Refer to appendix “A” at the end of this section for part numbers.

Page 39: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 2

COMMUNICATIONS PATCH PANELS

PART 1 - COPPER PATCH PANELS AND TERMINATION BLOCKS

1.1 Patch panels will be installed in all MDF, IDF and Entrance Facility locations.

1.2 All patch panels shall be standard density (48 ports per 2 RU), angled modular-jack style and designed to accommodate Panduit TG-style 8 position modular jacks.

1.3 No patch panel should be installed below row 26 except in rack zero without explicit instruction to do so from the DPS DoTS.

1.4 Smaller installations or ones with limited floor space may use wall mount distribution racks. In these instances the project documentation will so indicate and the DoTS PM will make this determination.

1.5 Multi-pair backbones shall be terminated on rack mounted 24 port angled modular panels or hardware selected to match legacy hardware for that location.

Page 40: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 3

COMMUNICATIONS RACK MOUNTED POWER PROTECTION AND POWER STRIPS

PART 1 - RACK/CABINET POWER

1.1 Racks and cabinets shall be supplied with a 10 port, 120 volt, 20 AMP POU with 20 AMP thermal breaker. Refer to appendix “A” at the end of this section for part numbers.

COMMUNICATIONS BACKBONE CABLING

PART 1 - DEFINITION

1.1 This is the cabling that provides the interconnection between various TRs and the EF whether in the same or different buildings.

PART 2 - GENERAL GUIDELINES

2.1 All armored fiber and copper backbone communications cable shall be installed in common routes but separated by classification, with cable tied to approved support hangers and segregated where they enter the TRs.

2.2 In all TRs similar cable types will be separated and grouped for termination. In NO case shall cables of a different type be intertwined.

PART 3 - TYPES AND NUMBERS OF BACKBONE CABLES

3.1 Between the main TR and each intermediate TR the Contractor will install:

A. One 25 pair 24 AWG plenum tie cable.

B. One OM3 12 strand multi-mode 50/125µm plenum armored fiber optic cable for every 288 Category 6 cables installed.

C. One RG11 and one RG6 PVC or plenum video coax tie.

D. Two 18 Ga. 2 pair shielded PVC or plenum ties.

E. Two 4 pair Category 6 PVC or plenum data backup ties terminated on yellow jacks at the end of the last patch panel.

F. A new pull string.

Page 41: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 4

COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING

PART 1 - INTRABUILDING FIBER BACKBONE CABLING

1.1 The backbone cabling between TRs contained in the same building shall be OM3 tight-buffered, plenum-rated armored cable.

1.2 Telecommunications rooms with less than 288 copper drops shall have 12 strand OM3 tight-buffered, plenum-rated armored cable.

1.3 Telecommunications rooms with more than 288 copper drops shall have 24 strand OM3 tight-buffered, plenum-rated armored cable. See project documentation for the number of 24 strand cables needed for these larger TRs.

1.4 All DPS intra-building fiber backbones must be armored whether or not routed in conduit.

1.5 All optical fiber cables shall have a minimum bend radius of 15 times the outside diameter of the cable.

1.6 All conduit runs shall contain long radius "sweeps" versus 90-degree bends.

1.7 The optical fiber cable shall have the proper strain relief installed in accordance with the manufacturer’s instructions.

1.8 All cables containing Kevlar type strength member shall have the strength members braided and secured to the mounting enclosure.

PART 2 - INTER-BUILDING FIBER BACKBONE CABLING

2.1 The backbone cabling between buildings shall be 24 strand, gel free, indoor/outdoor rated, loose-tube multi-mode OM3 fiber.

2.2 Transition to tight-buffered indoor cable shall be accomplished using fan-out kits mounted in wall mount enclosures in the entrance facility. Refer to appendix “A” at the end of this section for part numbers.

COMMUNICATIONS OPTICAL FIBER SPLICING AND TERMINATIONS

PART 1 - OPTICAL FIBER BACKBONE CABLE TERMINATIONS

Page 42: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 5

1.1 All optical fiber cables shall terminate in Panduit FRME optical fiber enclosures.

1.2 Additions to legacy optical fiber cables with SC-style terminations shall be terminated with Panduit Opticom SC-type connectors to match the installed cabling.

1.3 All green-field (new) optical backbones shall be terminated using Panduit Opticom LC-type connectors.

1.4 The Contractor shall provide all consumable materials for optical fiber connector terminations.

1.5 Outdoor single-mode/loose-tube fiber shall be terminated using fan-out kits and Panduit Opticom LC connectors.

COMMUNICATIONS HORIZONTAL CABLING

PART 1 - ROUTING OF TWISTED PAIR WORKSTATION CABLE

1.1 All twisted pair workstation cables shall be within 295 feet from patch panel to faceplate.

1.2 Where installing cabling infrastructure in the interstitial ceiling space or routing cables to a workstation location, the cables shall be installed above all other apparatus in the ceiling, as close as possible to the deck above.

1.3 These cables shall be run in bundles and supported with an approved hanging system (e.g. Panduit J-mod, J-hook system). See hangers and supports for communications systems specification section for details.

1.4 The maximum span between supports shall be five feet (5 ft.). All cables shall be loosely bundled (never tightly) with plenum cable ties every five feet or less.

1.5 Without exception, in any instance where a cable passes through a wall or other barrier, the cable must be protected with a fire caulked metallic sleeve as described elsewhere in this document.

1.6 All cables routed from the termination point to the work area outlet shall be free of splices, deformations, jacket damage, or other factors that may degrade the performance of the cables.

1.7 Refer to appendix “A” at the end of this section for UTP cabling part numbers.

PART 2 - WORK AREAS - GENERAL REQUIREMENTS

Page 43: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 6

2.1 All partition wall workstation outlet locations shall have the cables routed in the void space inside the wall whenever possible.

2.2 If conduit is provided at the location, the cables shall be routed therein to the outlet box.

2.3 If a conduit is not provided at the specified location, the Contractor shall make access to the void space above the ceiling level. The preferred method for this access is to utilize a stepper bit through the wall's top cap and insert a stud grommet.

2.4 The Contractor shall provide and install an outlet box at the standard electrical outlet height of 18” AFF. When practical the Contractor should match the orientation and height of the existing electrical outlets.

2.5 The Contractor shall provide foam or another form of approved fire stopping around the opening in the top of the wall.

2.6 DPS standards are to install two teacher stations and one student station in each classroom.

2.7 The structured cabling system is based on a structured wiring design of three (3) - UTP Category 6 cables to each teacher/student outlet location.

2.8 The cables shall be designated TR room, rack, row, and position (i.e., A.2.14.24, B.2.5.15). All teacher/student cabling shall originate from Panduit jack panels in the TRs.

2.9 All twisted pair teacher/student cables shall be terminated on Panduit sloped horizontal or vertical type outlets.

2.10 Any other exceptions will be at the discretion of the DPS/DoTS project manager. All twisted pair workstation cables shall be terminated in consecutive order utilizing the station identification number.

2.11 All teacher/student cabling shall be configured to the 568B pinout.

2.12 Teacher outlet locations will consist of a four port sloped faceplate with three Category 6 cables. RG6 coax cable will be considered in additions to legacy systems only.

2.13 Student outlets will consist of a four port sloped horizontal or vertical faceplate with three Category 6 connections and the fourth port blanked out, or configured as called out in the documentation specific to that project.

Page 44: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 7

2.14 The fixed video application is predominantly installed in new construction and remodeled schools; however, this application can be implemented in existing schools.

2.15 Contractor shall cable projector locations with low-skew, vga cable to the Teacher location. Low skew cable shall be termination on both ends with a 15 pin DB connector, Panduit part number CMD15HDEIY.

2.16 All horizontal wiring must not exceed (295 ft.). This is actual tested cable length, not the physical distance between the TR and the workstation outlet.

2.17 If any horizontal cabling run is more than the 295 feet, it must be submitted to the DoTS Project Manager for written exemption to this document prior to being installed.

PART 3 - INSTALLATION OF TWISTED PAIR STATION CABLES

3.1 The pulling tension of all twisted pair station cables shall not exceed 25 ft-lbs.

3.2 Jacketed twisted pair workstation cables shall have a minimum bend radius of four (4) times the diameter of the cable.

3.3 The jacket of the twisted pair cable for IDC type connections shall be removed as needed for termination, but jacket shall be as close as possible to insulation displacement clips as possible on installed devices as per TIA 568-C.0.

3.4 The terminated workstation cables shall have equal tension on all conductors. In addition, conductors within a pair should not be bent around the other conductor to reach its termination point (commonly referred to as knuckling).

3.5 The pairs shall be visually inspected after the conductors are punched. If a connector needs to be re-terminated, all conductors in that cable shall also be re-terminated to keep consistent length, pair twists, and equal tension on all conductors.

3.6 On Panduit TG-style jack terminations, jacket of UTP cable shall pass entirely into device and be locked in place with retaining clip per Panduit Copper Technician certification class. Jacks showing exposed twisted pairs will not be accepted and must be corrected at Contractor's expense.

3.7 The conductors of the twisted pair cable shall be untwisted a maximum of (» 0.25 in.) from the point which the conductors are connected to the IDC (insulation displacement clips) of the termination device.

Page 45: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 8

3.8 All terminations which require the use of an impact tool, shall have the insertion tool set to its lowest level. Only single conductor tools shall be permitted.

3.9 The installation technician shall visually inspect all seated conductors prior to using an insertion or impact tool to punch the conductors.

3.10 When pulling cable the cable shall not be bent around objects less than 4 inches in diameter, Contractor shall temporarily install a perpendicular, short length of 4 inch EMT or similar device to maintain cable integrity during installation.

PART 4 - MODULAR FURNITURE WORK AREAS

4.1 When modular furniture workstation outlets are required, all cables shall route through communications poles from the ceiling above the modular furniture.

4.2 Any holes drilled that expose any metal edges will be bushed to prevent damage to the wire.

4.3 In the event communication poles are filled to capacity, the Contractor will be required to install new poles (the old poles must be removed by the Contractor during the cutover).

PART 5 - SERVICE LOOPS AT WORK AREA

5.1 DPS does not want “service loops” stored in wall boxes. When terminating the device end of the cabling, Contractor shall follow this procedure:

A. Pull 12” of wire out of the outlet box, trim and terminate the cabling.

B. After termination, push the cabling back up the conduit, leaving approximately 7” of wire in the box. “Box stuffing” and kinking of cable will not be acceptable.

C. Allow the remainder to remain slack as it exits the upper end of the conduit and caulk the conduit with fire caulking.

D. This applies to all horizontal terminal equipment locations including WAP locations in dropped tile ceilings.

Page 46: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 9

PART 6 - USE OF CABLE TIES

6.1 Blue Velcro type cable ties shall be installed in TRs. Plenum tie-wraps will be installed in all other locations including the ceiling space.

6.2 Plenum cable ties must be red in color to be easily identifiable upon inspection. All cable wraps shall be loosely installed with no deformation to the cable jackets.

PART 7 - SEPARATION OF HORIZONTAL CABLE FROM EMI RFI SOURCES

7.1 All communications cabling shall be separated from sources of EMI/RFI according to by a minimum of six inches or according to guidelines in TIA 569-B, whichever is most stringent.

7.2 These EMI sources include, but are not limited to fluorescent lights/ballasts, air handling units, power risers, etc.

7.3 In any TR that is adjacent to an electrical room, mechanical room, elevator shaft, or other EMI/RFI source, the cables shall not be routed on the opposite sides of adjoining wall(s). Placement of cables in such situations shall follow guidelines in TIA 569-B and BICSI TDMM 13.

PART 8 - HORIZONTAL CABLE SEGREGATION

8.1 The Contractor shall segregate and bundle all workstation cables in the cable tray/trough as they enter the TR. All cables shall be bundled in groups of twenty-four (24) individual twisted pair workstation cables.

8.2 In horizontal TRs, the twisted pair workstation cables shall divide (right or left, top to bottom) depending upon the side of the patch panel to which the twisted pair workstation cables are terminated and from the direction the cables enter the racks.

8.3 The cables shall be grouped together for cable bundles destined for the same side of a wire management rack. This procedure shall produce an orderly installation with no crossovers for all visible cabling.

COMMUNICATIONS PATCH CORDS, STATION CORDS, AND CROSS CONNECT WIRE

PART 1 - COPPER AND FIBER PATCH CABLES

1.1 Patch cables are used to make the physical connection between the structured cabling and the network and telecommunications equipment.

Page 47: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 10

1.2 At the TR, patch cables and fiber jumpers are used to facilitate fast and easy moves, changes or additions to the network.

1.3 At the desktop, station cables enable connectivity from the communications outlet to the end user’s network device.

1.4 All copper patch cables and fiber jumpers shall be factory assemblies. Hand termination of patch cables is not allowed.

1.5 All copper patch cables will be Panduit and will be color-coded blue and white to help differentiate between various systems running on the same cabling system.

1.6 The percentages of patch cables are as follows:

Per station jack (1) White & (1) Blue %

5' 48%

7' 34%

10' 15%

14' 2%

20’ 1%

1.7 In instances where the total patch cables exceeds 10 meters, the length of the permanent horizontal channel must be de-rated per the tables contained within TIA 568-C.0. Contractor is responsible to report all such instances to the DoTS for resolution.

Page 48: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 11

APPENDIX A

COPPER CONNECTIVITY AND WORK AREA

Part Number Description

CBXJ2EI-A Surface Mount Box, 2 Port, Electric Ivory

CFG2EI GFCI Frame, 2 Port, Electric Ivory - mounts behind any GFCI electrical faceplate

CFG4EI GFCI Frame, 4 Port, Electric Ivory

CFPHS2__ Two port angled faceplate for use with Wiremold raceway - Designate color last two

blanks for color: EI (electric ivory), IW (international white), or WH (white)

CFPHSL4EI Faceplate, 4 Port, Classic, Sloped Horizontal, Electric Ivory

CFPSL2EIY Faceplate, 2 Port, Classic, Sloped, Electric Ivory

CFPSL4EIY Faceplate, 4 Port, Classic, Sloped, Electric Ivory

CFPSL6EIY Faceplate, 6 Port, Classic, Sloped, Electric Ivory

CJ688TGBL Mini-Com Module, Cat 6, UTP, 8 pos 8 wire, Universal, Black, TG Style

CJ688TGEI Mini-Com Module, Cat 6, UTP, 8 pos 8 wire, Universal, Electric Ivory, TG Style

CPPLA48WBLY Patch Panel, 48 Port, Angled, Black with front removable plates

CPPLA24WBLY Patch Panel, 24 Port, Angled, Black with front removable plates

MIWBAEI Box Adapter, In Wall, Electric Ivory - Allows installation of single gang faceplate on

double gang back box

PUP6004BU-UY Copper Cable, Enhanced Cat 6, 4-PR, 23 AWG, UTP, CMP, Blue, 1000 Feet/305m

UIT70FH2EI Ultimate ID Single Gang Horizontal Sloped Comm. Snap-on Faceplate - 2 Position

UIT70FH4EI Ultimate ID Single Gang Horizontal Sloped Comm. Snap-on Faceplate - 4 Position

UIT70FV2EI Ultimate ID Single Gang Vertical Sloped Comm. Snap-on Faceplate - 2 Position

UIT70FV4EI Ultimate ID Single Gang Vertical Sloped Comm. Snap-on Faceplate - 4 Position

UTPSP3Y 3 foot, Off White, Category 6, UTP patch cord with TX6™ PLUS Modular Plugs on

each end. For lengths 1 to 20 feet (increments of one foot) and 25, 30, 35, 40 feet

change the length designation (the "3" after the P) in the part number to the desired

length.

UTPSP3YBU 3 foot, Blue, Category 6, UTP patch cord with TX6™ PLUS Modular Plugs on each

end. For lengths 1 to 20 feet (increments of one foot) and 25, 30, 35, 40 feet change

the length designation (the "3" after the P) in the part number to the desired length.

Category 6 Patch Cords

CMD15HDEIY 2-position module supplied with one 15-pin DB connector mounted to a printed circuit

board; terminates on site to low-skew VGA cable at teacher locations. Insert occupies

two faceplate ports.

Page 49: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 12

FIBER CONNECTIVITY

Part Number Description

FRME1U Rack Mount Enclosure 1 RU, Holds up to three FAP or FMP adapter panels or FOSM

splice

modules. Bidirectional sliding drawers provides front and rear access to fibers. Dimen-

sions:

1.74"H x 17.00"W x 14.20"D (44.0mm x 432.0mm x 361.0mm)

FRME2U Rack Mount Fiber Enclosure 2 RU, Holds up to six FAP or FMP adapter panels or

FOSM splice

modules. Bidirectional sliding drawers provides front and rear access to fibers. Dimen-

sions: 3.48"H x 17.00"W x 14.20"D (88.0mm x 432.0mm x 361.0mm)

FWME4 Opticom Wall Mount Fiber Enclosure. Good for containing Fan-out transitions from

outdoor loose-tube cable to indoor-type tight-buffered cable. Holds up to four Quick-

Net™ Cassettes, FAP, or FMP panels. Dimensions: 16.11"W x 12.25"H x 3.52"D.

(409.2mm x 311.0mm x 89.4mm). For sizes holding 2 or 8 adapter panel, replace "4"

in part number with 2 or 8.

FAP6WAQDSC SC Fiber Adapter Panels for additions to legacy fiber systems – 10Gig ™ OM3/OM4

50/125µm (Aqua Adapters) loaded with six SC 10Gig™ Duplex Multimode Fiber Op-

tic Adapters (Aqua) with phosphor bronze split sleeves.

FAP6WBUDSCZ SC single-mode fiber adapter panels for additions to legacy fiber systems. SC FAP

loaded with six SC duplex singlemode fiber optic adapters (Blue) with zirconia ceram-

ic split sleeves.

FAP6WAQDLC LC 10Gig™ FAP loaded with six LC 10Gig™ Duplex Multimode Fiber Optic Adapt-

ers (Aqua) with phosphor bronze split sleeves.

FAP6WBUDLCZ LC FAP loaded with six LC duplex singlemode fiber optic adapters (Blue) with zirco-

nia ceramic split sleeves.

FAPB Blank fiber adapter panel for filling space in fiber enclosures for future use.

FXD3-3M1Y OM3 SC to SC multimode duplex patch cord for legacy systems. 3mm jacketed cable

(one duplex SC connector on each end) – 10Gig™ 50/125µm. 1 meter length. Patch

cords are available in 1 – 10 meter lengths in 1 meter increments, and 15, 20, 25 and

30 meter lengths. For other lengths, replace the "1" in part number with desired length.

F9D3-3M1Y SC to SC singlemode duplex patch cord for legacy systems. 3mm jacketed cable (two

SC connectors on each end) – 9/125µm. 1 meter length. Patch cords are available in 1

– 10 meter lengths in 1 meter increments, and 15, 20, 25 and 30 meter lengths. For

other lengths, replace the "1" in part number with desired length.

FXE10-10M1Y LC to LC multimode duplex patch cord, 1.6mm jacketed cable (two duplex LC con-

nectors on each end) – 10Gig™ 50/125µm. 1 meter length. Patch cords are available

in 1 – 10 meter lengths in 1 meter increments, and 15, 20, 25 and 30 meter lengths. For

other lengths, replace the "1" in part number with desired length.

F9E10-10M1Y LC to LC singlemode duplex patch cord, 1.6mm jacketed cable (one duplex LC con-

nector on each end) – 9/125µm. 1 meter length. Patch cords are available in 1 – 10

meter lengths in 1 meter increments, and 15, 20, 25 and 30 meter lengths. For other

lengths, replace the "1" in part number with desired length.

FSCDMCXAQ SC OptiCam® 10Gig ™ 50/125µm OM3/OM4 Multimode Duplex Fiber Optic Con-

nector for 900µm tight-buffered fiber installation. This is only for additions to DPS

legacy fiber systems using SC connectors.

FSCSCBU SC OptiCam® Singlemode Simplex Fiber Optic Connector for 900µm tight-buffered

fiber installation. This is only for additions to DPS legacy fiber systems using SC con-

nectors.

FLCDMCXAQY LC OptiCam® 10Gig™ 50/125µm Multimode Duplex Fiber Optic Connector for

Page 50: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 13

900µm tight-buffered fiber installation.

FLCDSCBUY LC OptiCam® Singlemode Duplex Fiber Optic Connector for 900µm tight-buffered

fiber installation, or for use with fan-out kits when transitioning outdoor loose-tube to

inside type tight buffered cable.

FOPPX012Y 12-fiber 10Gig ™ 50/125µm (OM3) multimode plenum rated indoor interlocking ar-

mored cable.

FOPPX24Y 24-fiber 10Gig ™ 50/125µm (OM3) multimode plenum rated indoor interlocking ar-

mored cable.

FSMR924Y Opti-Core ® Gel-Free Riser Indoor/Outdoor Interlocking Armored Cable (OFCR) –

Singlemode. 24-fiber 9/125µm (OS1/OS2) singlemode riser rated indoor/outdoor inter-

locking armored stranded cable.

FSMP924Y Opti-Core ® Gel-Free Plenum Indoor/Outdoor Interlocking Armored Cable (OFCP) –

Singlemode 24-fiber 9/125µm (OS1/OS2) singlemode plenum rated indoor/outdoor

interlocking armored stranded cable.

FO12CB Fan-Out Kits Used to build up 250µm fiber to 900µm coating size for connector termi-

nation. For transitioning outdoor loose-tube fiber cable constructions to indoor tight-

buffered type. One FO12CM for each 12 fibers.

Page 51: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton STRUCTURED CABLING MEP Engineering Project No. 13464 27 10 00 - 14

RACKS, CABINETS, MANAGERS AND POU

Part Number Description

CMR19X84 Standard Rack - 84" High (2134mm)

CMUT19 Cable Management Cable Trough - good placed at bottom of racks for interbay path-

way

MIWBAEI Box Adapter, In Wall, Electric Ivory

PRD12 PatchRunner 12" (305mm) Dual Hinge Door for 84" High (2134mm) Racks

PRD8 PatchRunner 8" (203mm) Dual Hinge Door for 84" High (2134mm) Racks

PRV12 PatchRunner Vertical Cable Manager Front and Rear 12" (305mm) for 84" High

(2134mm) Racks

PRV8 PatchRunner Vertical Cable Manager Front & Rear 8" (203mm) for 84" High

(2134mm) Racks

N8512BE Panduit N-series switch cabinet, 800mm x 1070mm x 45 RU Dimensions: 84.0"H x

31.5"W x 42.0"D. With side panels, cage nut rails, single hinge front door and perfo-

rated split rear doors

S6222BP Panduit S-Type Server Cabinet frame with top panel, Cage nut rails, Single hinge per-

forated front door, Split perforated rear doors open in the middle to minimize door

swing footprint, Solid side panels, Casters and POU brackets included, Cable man-

agement on front and rear of front posts. Includes zero RU QuickNet rails for 0 RU

patching. Dimensions: 79.8"H x 23.6"W x 48.0"D (2026mm x 600mm x 1219mm)

CMRPSH20* Horizontal power strip 20 A, 120V, ten NEMA 5-20R receptacles, one 20 A thermal

breaker, 10' power cord with NEMA 5-20P plug. UL and c-UL Listed. Dimensions:

1.7"H x 19.0"W x 3.8"D (44mm x 483mm x 95mm). *For local digital monitor add

“CM”

END OF SECTION

Page 52: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 1

SECTION 27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C2 (2007; TIA 2007-1; TIA 2007-2; TIA 2007-3; TIA 2007-4; TIA 2007-5) National Electrical Safety Code

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-

Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits

NATIONAL CABLE AND TELECOMMUNICATIONS ASSOCIATION (NCTA)

NCTA RP (2003) NCTA Recommended Practices for Measurements on

Cable Television Systems

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2008; AMD 1 2008) National Electrical Code

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

47 CFR 76.605 Technical Standards

UNDERWRITERS LABORATORIES (UL)

UL 1581 (2001; R 2003 thru Oct 2009) Reference Standard for Electrical Wires, Cables, and Flexible Cords

UL 1666 (2007) Standard for Test for Flame Propagation Height of

Electrical and Optical-Fiber Cables Installed Vertically in Shafts

UL 969 (1995; R 1998 thru 2008) Standard for Marking and Labeling

Systems 1.2 RELATED REQUIREMENTS

Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS, applies to this section with the additions and modifications specified herein.

1.3 DEFINITIONS

Page 53: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 2

1.3.1 CATV

Community antenna television (CATV) system, commonly referred to as cable television, is a network of cables, headend, electronic and passive components that process and amplify television (TV) signals for distribution from the headend equipment to the individual television outlets.

1.3.2 Headend

The connection point between CATV system equipment and equipment provided by the local CATV company.

1.3.3 Distribution System

Distribution system transports and delivers adequate signals to each receiver. Provide distortion-free signal to TV sets by isolating each receiver from the system and by providing proper amount of signal to each set.

1.3.4 Cable

Trunk and feeder cables are low-loss cables used to transport the desired signal from the headend equipment to the communications closet in the area to be served. These cables are used to transport signal from the headend equipment into close proximity to a number of user locations in excess of 200 feet from the headend equipment. Drop cables are used to transport the desired signal used from the [headend equipment to the wall outlet.

1.4 SYSTEM DESCRIPTION 1.4.1 Headend

Contractor shall provide interior equipment up to headend and including the main amplifier located at the interior CATV backboard.

1.4.2 Distribution System

Distribution system shall be star topology with each outlet connected to a communications closet with a feeder cable or a drop cable and each communications closet connected to the headend equipment with a trunk cable.

1.4.3 Cable

Provide feeder cables to transport signal from the headend equipment to user locations in excess of 200 feet from the headend equipment. Provide drop cables to transport the desired signal from the headend equipment to the outlet.

1.4.4 System Components

System shall provide high quality TV signals to all outlets with a return path for interactive television and cable modem access. Provide any combination of items specified herein to achieve required performance, subject to approvals, limitations, acceptance test, and other requirements specified herein. System shall include amplifiers, splitters, combiners, line taps, cables, outlets, tilt compensators and all other parts, components, and equipment necessary to provide a complete and usable system.

1.4.4.1 System Bandwidth

a. Downstream: 50-750 MHz minimum.

Page 54: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 3

b. Upstream 5-40 MHz minimum. 1.4.5 System Performance

System shall be in compliance with 47 CFR 76.605. 1.4.5.1 Receiver Termination Signal Level

Each termination for a TV receiver must have a minimum signal level of 0 decibel millivolts (dBmV) (1000 microvolts) at 55 MHz and of 0 dBmV (1000 microvolts) at 750 MHz and a maximum signal of 15 dBmV or a level not to overload the receiver for the entire system bandwidth.

1.4.5.2 Distribution System

a. Modulation distortion at power frequencies: 4 percent or less hum distortion;

b. Composite third order distortion for:

(1) CW carriers: 53 dB.

(2) Modulated carriers: 59 dB.

c. Subscriber terminal isolation: 18 dB or greater.

d. Carrier to second order beat ratio: 60 dB.

e. Amplitude characteristic shall be within a range of plus or minus 2 decibels from 0.75 MHz to 5.0 MHz above the lower boundary frequency of the cable television channel, referenced to the average of the highest and lowest amplitudes within these frequency boundaries.

f. Visual, aural carrier level - 24-hour variation: 47 CFR 76.605, subpart (a), rules (4), (5), and

(6).

g. Frequency determination: 47 CFR 76.605, subpart (a), rules (1),(2), and (3). 1.4.5.3 All New System Tolerance

The system shall not show a serious loss of carrier to noise when the system levels are lowered 3 dB below normal or a significant distortion when the levels are increased 3 dB above normal, as observed on a TV set located at the far end extremities of the system.

1.5 SUBMITTALS

SD-02 Shop Drawings

CATV system wiring diagrams and installation details; CATV system components;

SD-03 Product Data

Attenuators; Amplifiers, including headend, trunk, bridging, and distribution; Cables, including trunk, feeder, and drop; Terminators; Splitters/combiners; Line Taps;

Page 55: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 4

Outlets; Connectors; Tilt compensator; Grounding block; Submittals for each manufactured item shall be the current manufacturer's descriptive literature of catalog products, equipment drawings, diagrams, performance and characteristics curves, and catalog cuts.

SD-05 Design Data

CATV System Loss Calculations;

SD-06 Test Reports

Operational test plan; Operational test procedures; System pretest; Acceptance tests;

SD-08 Manufacturer's Instructions

Connector Installation;

1.6 QUALITY ASSURANCE 1.6.1 Wiring Diagrams and Installation Details

Illustrate how each item of equipment functions in the system and include an overall system schematic indicating the relationship of CATV units on one diagram. Drawings shall include wiring diagrams and installation details of equipment indicating proposed locations, layout and arrangements, and other items that must be shown to ensure coordinated installation.

1.6.2 CATV System Loss Calculations

Calculations shall verify that the system does not exceed the loss values specified in dBmV at the input of all active devices and the receiver terminations. Provide a drawing displaying all distribution network calculations. The drawing should accurately show taps, splitters, outlets, and the type and length of all trunk, feeder, and drop cables. The drawing shall show how many taps, splitters, or outlets are served by each tap or splitter.

1.6.3 Operational Test Plan

Test plan shall define tests required to ensure that the system meets technical, operational, and performance specifications. Test plan shall be based on NCTA RP and be in accordance with FCC proof of performance requirements. Test plan shall include plan for testing for signal leakage. Provide test requirements and guidelines.

1.6.4 Operational Test Procedures

Use test plan and design documents to develop test procedures. Procedures shall consist of detailed instructions for a test setup, execution, and evaluation of test results.

1.6.5 Connector Installation

Provide manufacturer's instructions for installing connectors.

Page 56: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 5

PART 2 PRODUCTS

2.1 ELECTRONIC EQUIPMENT

Electronic components of similar type shall be produced and designed by the same manufacturer as major components of the equipment and shall have the manufacturer's name and model permanently attached. Equipment shall function properly as a complete integrated system. Equipment shall be shielded. The system shall be designed to operate within 5 to 1000 MHz bandwidth using 1000 MHz passive devices and a minimum of 750 MHz active devices.

2.2 HEADEND EQUIPMENT 2.2.1 Headend Amplifiers

Provide broadband distribution amplifiers. Amplifiers shall amplify broadband signals from 40 to 750 MHz and provide an amplified return path for signals from 5 to 40 MHz for 75 ohms impedance. Amplifiers shall be bidirectional with variable slope and gain control.

2.2.2 Attenuators

Provide attenuators to equalize signal levels, when required. Variable attenuators are not permitted. 2.2.3 Power Supplies

Power supplies shall contain a current limiter circuit to protect against short circuits on the radio frequency (RF) line. Provide overvoltage protection to protect solid state equipment from line surges and induced voltages, in accordance with IEEE C62.41.1 and IEEE C62.41.2.

2.3 DISTRIBUTION EQUIPMENT 2.3.1 Distribution Amplifiers

Distribution amplifiers shall be equipped for 75 ohms input and output impedance. Electronic equipment exposed to weather shall be equipped with weatherproof housings. Amplifiers shall be bidirectional with variable slope and gain control and shall amplify broadband signals from 50 to 750 MHz and provide an amplified return path for signals from 5 to 40 MHz for 75 ohms impedance.

2.3.1.1 Trunk Amplifiers

Trunk amplifiers shall have automatic level and slope control features. 2.3.1.2 Bridging Amplifiers

Bridging amplifiers shall be used to connect feeder cables to trunk cables. 2.3.2 Cables and Associated Hardware

Cabling shall be UL listed for the application and shall comply with NFPA 70. Provide a labeling system for cabling as required by UL 969. Cabling manufactured more than 12 months prior to date of installation shall not be used.

2.3.2.1 Trunk Cable

UL 1666 Provide trunk cable with an NFPA 70 rating of CATVR.

a. Provide RG-11 coaxial cable with the following characteristics:

(1) #14 AWG copper-clad steel center conductor.

Page 57: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 6

(2) Gas injected foam polyethylene dielectric with nominal 0.28 inches outer diameter.

(3) Bonded foil inner-shield and 60 percent aluminum braid or quad shield.

(4) 75 ohms impedance.

(5) 82 to 85 percent nominal velocity of propagation.

(6) Black PVC jacket

(7) Maximum attenuation characteristics: MHz DB/100 ft MHz DB/100 ft 5 0.38 600 3.18 55 0.96 750 3.65 300 2.25 1000 4.35 350 2.42 450 2.86 500 2.90

b. Provide 625 Series cable with an NFPA 70 rating of CATVR and the following characteristics:

(1) Copper-clad aluminum center conductor

(2) Seamless aluminum tubing shield

(3) Expanded polyethylene dielectric

(4) 75 ohms impedance

(5) Nominal diameter over outer conductor: 0.625 inches.

(6) Maximum attenuation at 20 degrees C and 1000 MHz: 2.07 dB/100 feet

(7) Black medium density polyethylene jacket

(8) Nominal 87 percent velocity of propagation 2.3.2.2 Feeder Cable

UL 1581, provide RG-11 coaxial trunk cable with an NFPA 70 rating of CATV] and the following characteristics:

a. #14 AWG copper-clad steel center conductor.

b. Foam FEP dielectric with .28 inches nominal outer diameter.

c. Bonded foil inner-shield and a minimum of 60 percent aluminum braid or quad shield.

d. 75 ohms impedance.

e. 81 to 84 percent nominal velocity of propagation.

Page 58: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 7

f. PVC low smoke polymer or FEP jacket.

g. Maximum attenuation characteristics: CATV

MHz DB/100 ft

50 .95 100 1.3 200 1.9 400 2.7 700 3.9 1000 4.8

2.3.2.3 Drop Cable

UL 1581. Provide RG 6 coaxial cable with an NFPA 70 rating of CATV and with the following characteristics:

a. No. 18 AWG copper-clad steel center conductor.

b. Bonded foil inner-shield and 90 percent aluminum braid.

c. Characteristic impedance of 75 ohms.

d. Foam FEP dielectric

e. Nominal capacitance, conductor to shield, of 16.2 pf per 100 ft .

f. Maximum operating voltage of 350 V RMS.

g. Maximum attenuation:

CATV MHz DB/100 ft MHz DB/100 ft 10 0.81 700 6.0 50 1.46 1000 7.3 100 2.05 200 2.83 400 4.0 500 4.53 h. PVC low smoke polymer or FEP jacket.

i. 100 percent sweep testing from 5 MHz to a minimum of 1000 MHz. 2.3.3 Terminators

Terminators shall be rated for 75 ohms and 1/4 watt.

Page 59: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 8

2.3.4 Splitters/Combiners Use splitters/combiners with characteristics equal to or exceeding the characteristics listed in this paragraph over the entire operating band. All unused outlets must be terminated with 75-ohm terminators.

a. Peak to Valley: Not to exceed 1 dB across bandwidth of device.

b. Return loss: 18 dB minimum.

c. Bandwidth: 5-1000 Mhz

2.3.5 Line Taps

Line taps shall have 18 dB minimum isolation from each tap to the thru-line.Pressure tapoffs are not permitted. Taps shall be rated from 5 to 1000 MHz and shall have a peak to valley not to exceed 1 dB to 1 GHz.

2.3.6 Outlets

Provide flush mounted, 75-ohm, F-type connector outlets rated from 5 to 1000 MHz in standard electrical outlet boxes.

2.3.7 Connectors

Provide one piece connectors. Trunk and feeder cable connectors shall be pin type. Drop cable connectors shall be feed thru type.

2.3.8 Tilt Compensator

Provide tilt compensators as required.

2.4 GROUNDING AND BONDING

Provide ground rods and connections in accordance with Section 26 05 26, "GROUNDING". 2.4.1 Grounding Block

Provide corrosion-resistant grounding block suitable for indoor installation. 2.5 BACKBOARDS

Provide void-free, fire rated interior grade plywood, 3/4 inch thick, 4 by 8 feet. Backboards shall be painted with a gray, nonconductive fire-resistant overcoat. Do not cover the fire stamp on the backboard.

PART 3 EXECUTION 3.1 INSTALLATION 3.1.1 Distribution System

Distribution system shall conform to requirements specified herein. Installation shall be in accordance with IEEE C2 and NFPA 70.

Page 60: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton CATV MEP Engineering Project No. 13464 27 54 00.00.20 - 9

3.1.1.2 Grounding System Provide the grounding block at the main CATV backboard. Ground this device according to the requirements of IEEE C2 and NFPA 70.

3.1.1.3 Trunk, Feeder, and Drop Cable

Provide cable to grounding blocks, to line taps, and to outlets. 3.2 FIELD QUALITY CONTROL 3.2.1 System Pretest Upon completing installation of the CATV system, the Contractor shall align and balance the system and shall perform complete pretesting. During the system pretest, Contractor, utilizing the approved spectrum analyzer or signal level meter, shall verify that the system is fully operational and meets all the system performance requirements of the specification. Contractor shall test the signal loss in dBmV at 55 and 750 MHz. The signal levels shall be 0 dBmV (1000 microvolts), minimum. The signal shall not exceed 15 dBmV over the entire system bandwidth. Any deficiencies found shall be corrected and revalidated by follow up testing. Contractor shall measure and record the video and audio carrier levels at each of the frequency levels specified at each of the following points in the system:

a. Furthest outlet from each communication closet.

b. A random sampling of 25 percent of the outlets from each communication closet.

c. At each outlet.

d. Headend and Distribution amplifier inputs and outputs. 3.2.2 Acceptance Tests

Contractor shall notify the Contracting Officer of system readiness 10 days prior to the date of acceptance testing. Contractor shall also coordinate with the local CATV provider and allow them to attend witness tests. CATV system shall be tested in accordance with the approved test plan in the presence of the Contracting Officer's representative to certify acceptable performance. System test shall verify that the total system meets all the requirements of the specification and complies with the specified standards. Contractor shall verify that no signal leakage exists in conformance with NCTA RP and 47 CFR 76.605. System leakage shall also be tested at the headend location with signal applied to system. Deficiencies revealed by the testing shall be corrected on the outlets sampled as well as on the outlets not sampled and revalidated by follow-up testing. Contractor shall conduct testing at each of the following points in the system:

a. Furthest outlet from each communication closet.

b. A random sampling of 25 percent of the outlets from each communication closet as

designated by the Contracting Officer.

c. At each outlet.

d. Headend and Distribution amplifier inputs and outputs.

END OF SECTION

Page 61: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 1

SECTION 28 13 00

ELECTRONIC ACCESS CONTROL SYSTEM

PART 1 - GENERAL

1.1 DESCRIPTION

A. This specification section covers the furnishing and installation of a new and complete

enterprise- wide, low-voltage, electronic access control system (EACS).

B. Contractor shall furnish and install access control hardware devices, mounting brackets,

power supplies, switches, controls, consoles and other components of the system as

shown and specified.

C. Contractor shall furnish and install access control related software to allow this system

expansion.

Software includes required license addition for access control readers and electrified

portals, workstations and Video Management System (VMS) Integration.

D. Furnish and install outlets, junction boxes, conduit, connectors, wiring, and other

accessories necessary to complete the system installation. Requirements shall be in

accordance with Division

26 00 00, Electrical.

1.2 PRECEDENCE

A. Obtain, read and comply with General Conditions and applicable sub-sections of the

contract specifications. Where a discrepancy may exist between any applicable sub-

section and directions as contained herein, this section shall govern.

1.3 GENERAL CONDITIONS

A. In accordance with Section 28 05 00, Security System General Requirements

1.4 RELATED WORK

A. In accordance with Division 28 Security System General Requirements

1.5 APPLICABLE PUBLICATIONS

A. In accordance with Division 28 Security System General Requirements

1.6 SHOP DRAWINGS & EQUIPMENT SUBMITTAL

A. In accordance with Division 28 Security System General Requirements

1.7 OPERATING AND MAINTENANCE MANUALS

A. In accordance with Division 28 Security System General Requirements.

1.8 SERVICE AND MAINTENANCE

A. In accordance with Division 28 Security System General Requirements.

Page 62: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 2

1.9 TRAINING

A. In accordance with Division 28 Security System General Requirements.

1.10 WARRANTY

A. In accordance with Division 28 Security System General Requirements.

PART 2 - PRODUCTS

2.1 ACCESS CONTROL HARDWARE

A. Provide traditional access control system based off of Mercury Security Corp. open

platform hardware and panels.

1. The access control system shall support integrating with Video Insight as the

primary graphical user interface (GUI) at the time of bid, no exceptions.

2. System Characteristics:

a. The Access Control Panel (ACP) is used as the subcomponent to the

security management system for the purpose of initiating all decision-

making criteria as it relates to the cardholders, readers, and associated

hardware connected. Decisions are made by the ACP and uploaded to

the host computer as historical events.

b. The ACP shall be listed for Underwriters Laboratory (UL): UL294 (Access

Control System)

c. The panels shall:

i. Operate without the need for the host to be on-line. No decisions

shall be dependent on the host.

ii. Support on-board 10/100 Ethernet communications to the host

as primary communication.

iii. Include a request-to-exit and door status contact input for each

reader without the need for additional modules for future use.

iv. Detect “forced entry” and “door left open.” A separate action is

required for each. v. Allow mapping of readers to any output

address within the same controller.

vi. Support at least 50 user-selected holidays.

vii. Allow all unused door logic, such as door strike relays, request-

to-exit inputs, and door status inputs to be assigned as general-

purpose points.

viii. Support optional modules for additional customization of inputs

and outputs. The following modules shall be available:

(a) Output Point Module: A minimum of 6 additional output

Page 63: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 3

points shall be provided.

(b) Combination Module: Where inputs and outputs are

necessary within the same enclosure, a combination of

at least 6 inputs and 6 outputs shall be provided.

(c) Wireless reader module or external module.

ix. Support a minimum of 5,060 alarm input points.

x. Support a minimum of 5,060 relay output points.

xi. Maintain historical information for a minimum of three (3) months

without AC power.

xii. Automatically adjust for daylight savings time and leap year.

xiii. Be supplied with battery backup and charger for a period for a

minimum of four (4) hours.

xiv. Support a variety of reader technologies:

(a) Magnetic Stripe

(b) Proximity

(c) Biometrics

(d) Wiegand

xv. Vehicle Identification

xvi. Support multiple technologies simultaneously.

xvii. Maintain the expiration date for each cardholder. Once the date

is reached, the card will automatically be disabled. No access

shall be authorized.

xviii. Maintain three (3) access times for each door location: Standard,

Long, and Egress.

xix. Have the ability to maintain an automatic door unlock during

specific hours and days.

xx. Support a minimum of (2) “levels” of Anti-Passback: Global and

Area.

d. Panels shall have additional input modules as necessary to

accommodate devices as shown on project drawings.

3. Panels shall use Mercury EP2500 controller with MR52 interface panels.

Contractor shall provide adequate number of access control panels, controllers,

door interface panels and I/O panels for a complete turnkey system to support all

components as indicated on project drawings.

B. Contactless Smart Card Readers

1. Utilize Wiegand communication.

Page 64: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 4

2. Credentials:

a. Smart Card Model

i. Operating Frequency: 13.56 MHz (ISO 15693, 14443A &

14443B)

ii. Contactless smart card reader shall implement the following high

security 13.56 MHz applications out-of-box.

(a) Secure Identity Object on iCLASS SE

(b) Secure Identity Object on MIFARE Classic SE

(c) Secure Identity Object on MIFARE DESFire EV1 SE

3. Operating voltage range: 5-16 VDC

4. Current draw: 45mA average and 75mA peak @ 12VDC.

5. Color: Gray

6. Dimensions: 1.9” x 4.0” x 0.9”

7. IP 55 exterior rated.

8. Provide adapter plate to mount on a single-gang backbox as required.

9. Firmware upgradable via pre-programmed cards.

10. Provide the ability to transmit an alarm signal via an integrated optical tamper

switch if an attempt is made to remove the reader.

11. An audio beeper and RGB light bar shall provide various tone and light

sequences to signify:access granted, access denied, power up, and diagnostics.

12. Card readers shall be HID iCLASS SE R10 # 900NNNTEK20000, #

910NNNTEK2000 and 900NNNTEK20000

a. No HID iCLASS SE substitutions.

C. Power Supplies

1. Provide an 8 output, fused power supply located next to the access control panels

with the minimum following features:

a. 12-24 VAC or VDC.

b. UL listed sub-assembly for access control.

c. Eight (8), fuse protected, fail-safe and/or fail-secure access control

outputs

d. Eight (8) normally open and/or open collector access control trigger

inputs.

e. Fire Alarm Disconnect:

i. Fire Alarm Disconnect (latching or non-latching) is individually

Page 65: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 5

selectable for any or all of the eight (8) outputs.

ii. Normally open (NO) or normally closed (NC) dry contact input. iii.

Polarity reversal input FACP signaling circuit.

iv. LED indicates that the Fire Alarm Disconnect has been activated.

v. Fire Alarm output relay for triggering auxiliary reporting devices.

f. Provide batteries and charger to provide a minimum of four (4) hours of

backup time.

g. Power supply shall be Altronix ACM8E (or approved equal).

D. Cables

1. Cable for card reader doors shall be an ‘All-in-one’ bundled Belden #658AFS,

Convergent #725116 or General Cable #4EPL1S. Coil unused portions of cable

within enclosure.

2. Provide 6-conductor 22awg shielded cable from enclosure terminal block to card

reader.

3. Provide 2-conductor 22awg cables from enclosure terminal block to door contact

switch and request to exit device.

4. Provide a minimum of a 2-conductor 18awg cable from enclosure terminal block

or power supply to electric strike, latch or panic. The contractor shall size the

cable as required for the distance and inrush current load as required.

2.2 SYSTEM SOFTWARE

A. Supports integration with Video Insight as the primary graphical user interface (GUI).

B. Operating System Requirements: Shall operate in conjunction with and be compatible

with Microsoft Windows 7 x64 Professional operating systems.

C. Support for Microsoft Active Directory (LDAP).

1. Provide all licenses required for LDAP integration.

D. Support for virtualization.

1. System shall support Microsoft Hyper V virtualization.

a. The contractor shall provide the owner with server requirements.

E. Software shall include:

1. Graphical user interface to show pull-down menus and a menu tree format.

2. Password-protected operator login and access.

F. Access Control Application Software: Shall provide interface between the ACS Host

Workstation, IP based Reader-Controllers, inputs, and outputs in order to monitor sensors

operate displays, report alarms, generate reports and provide all other system functions

as follows:

Page 66: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 6

1. Overall Access Control System Parameters:

a. Number of access control readers per system: Unlimited

b. Number of client work stations per system: Unlimited

c. Number of cardholders: 64,000 per reader stand-alone mode, unlimited

in network mode.

d. Number of credentials per cardholders: Unlimited

e. Number of cardholder groups: Unlimited

f. Number of system inputs: Unlimited

g. Number of system outputs: Unlimited

h. Reader Inputs: Door sense, request to exit, auxiliary, optical tamper, RS-

232

i. Reader Outputs: (2) outputs; TTL1 and TTL2

Access Control Software Functions: The system software shall provide for the following features and

functions:

j. Door Programming Functions

i. Extended open alarms Individual Extended open timers per door.

ii. Personal Identification Number (PIN) Codes – Up to 9 digits.

iii. Device Support: Supports selected serial RS-232 and Wiegand

devices. iv. Number of Door Groups: Unlimited

k. Shifts

i. Number of shifts: Unlimited

ii. Interval assignments: Any day of the week.

l. Permissions

i. Number of Permissions: Unlimited

m. Holidays: The software shall provide for an unlimited number of holidays.

n. Door Control: The software shall provide the following types of area

control functions:

i. Door control based on dual-authentication rules.

(a) Support requiring credentials belonging to two people

(b) Support requiring two credentials belong to same person

ii. Cardholder use limits

(a) Elapsed Time based

(b) Number of usage based

iii. Configurable individual door strike times.

iv. Configurable extended individual door hold open times.

o. Elevator Control: The software shall provide elevator control for an

unlimited number of floors.

Page 67: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 7

p. System Graphical Tree: The software shall provide for graphical tree

displays of the configured field hardware.

q. Alarm and Event Logging: The software shall provide for logging of all

system alarms and events chronologically including time and date stamp.

r. System Scheduling: The system shall provide for scheduling of events

including:

i. Open Door, Open Door Group

ii. Deactivate Badges

s. Help Documentation: The software shall include complete documentation

on CD.

t. Alarm attributes: The software shall provide for programming of the

following alarm and monitoring attributes:

i. Display of alarm events at the ACS Host workstation, or support

networked workstation.

ii. Require the reader-controller, which generated the alarm to be

restored to its normal state before the alarm is cleared.

iii. Require acknowledgment of an alarm to clear the alarm.

iv. Support auto-clearing of network related communication alarms.

v. Trigger a programmed system actions(s) when the alarm is

acknowledged.

vi. Require a User Logon for Acknowledgment.

u. Programming Downloads: The software shall provide for downloading of

programming from the ACS Host to the Reader-controller-controllers as

follows:

i. Credential holders and authorized time zones

ii. Time zones.

iii. Alarm configurations.

iv. Latch intervals.

v. TTL output on REX, Tamper, Unauthorized.

vi. Beep on events (REX, Tamper, Reject)

vii. Complete database download of 10,000 cardholder records in

less than 15 minutes with system continuing to operate normally

during this time.

v. Reader-controller Programming Options: Provide the following minimum

reader-controller programming functions:

i. Request to exit and door position switch: Provide programming

for independent supervision of request to exit and door position

switch.

ii. Manual activation of outputs: Provide for configurable activation

of outputs from a credential presentation.

iii. User definable door strike time: Provide user definable/

programmable door strike functionality for each reader-controller.

iv. In/ out Reader-controller configuration: Reader-controller

Page 68: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 8

programmed as either an in reader or out reader for recording of

time in and time out data.

v. Program use Limits: Limiting the number of times that

cardholders may use their credential to gain access at the

Reader-controller.

vi. Input/output linking: Provide programming for linking of reader

outputs with inputs.

ACS Host Software Functions: The system ACS Host software shall provide for the following features and

functions:

a. Device Status Monitoring

i. Alarm Status Indication: Provide real time status display that

indicates the current status of all devices in the device tree.

ii. Reader-controller status: Provide display of Reader-controllers

that are off line.

b. Device Group Programming

i. Reader-controller Groups: Provide for programming of Reader-

controller groups.

ii. Input Groups: Provide for programming of input groups.

iii. Output Groups: Provide for programming of output groups.

c. Trace

i. Historical Trace: Provide for historical trace on any Reader-

controller or cardholder.

d. Test Utilities: Provide system test utilities to allow for testing of the

following functions:

i. Alarm inputs status.

ii. Output operations.

iii. Credential Presentations.

iv. LED and buzzer operations

e. Real-Time Graphical Maps: Provide graphical maps that display reader-

controller status and allow for manual operation of the reader-controller..

i. Map Device Icons: Icons shall dynamically change to reflect the

current state of the devices.

f. Map Formats: Support import of maps to include the following file

formats:

i. JPEG (.jpg).

ii. Windows Metafile (.wmf).

iii. Windows Bitmap (.bmp).

g. Web- Browser Support

i. Support commonly used ACS functions from a standard

Page 69: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 9

workstation internet browser

ii. Support commonly used ACS functions from a standard mobile

phone internet browser

Credential Management Software Functions: The system credential management software shall provide

for the following features and functions:

a. Modification of cardholder records: Add, Modify and Delete records

based upon permissions.

b. Access and Credential Management: Provide for the following credential

management functions:

i. Assignment of single or multiple active badges.

ii. Programming personnel groups.

iii. Programming of group access permissions.

iv. Programming of individual access permissions

c. Badge Design: Provide badge design software that is integral to the

access control source code with the following badge layout tools:

i. Complete Badge design and Layout.

ii. Image Import.

d. ID Printers: Provide support for industry standard printers and Microsoft

Certified Windows 7 printer drivers and the following badge print formats:

i. Double-sided full color printing.

ii. Edge to edge printing.

G. Client Software:

1. The contractor shall install the client software on one (1) workstation of the

owners choosing at each site.

2. The software at each site shall only show that site.

2.4 ELECTRIC STRIKE (ES)

A. Surface mounted rim strike.

B. Accommodates hollow metal, aluminum and solid wood door frames.

C. Accommodates exit devices with latch projections from 0.5” to 0.75”.

D. High grade stainless steel construction.

E. Dimensions: 1.75”w x 9”h x 0.75”d.

F. Field selectable voltage:

1. 12 or 24 VDC

Page 70: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 10

G. Current draw, fail secure:

1. 12 VDC continuous load – 500mA

2. 24 VDC continuous load – 240mA

3. 12 VAC intermittent load – 330mA

4. 24 VAC intermittent load – 640mA H. Provide RCI #0162.

I. Provide with one (1) RCI ICEPK for each strike and connect according to manufacturer’s

specifications.

2.5 PANIC EXIT DEVICE

A. Provide new panic hardware at locations as indicated on drawings.

B. Were the drawings call for new panic hardware, the contractor shall demolish the existing

panic hardware.

C. Provide Precision Hardware:

1. Handle only – 2102 X 1702A

2. Handle with keyed cylinder – 2103 X 1703A

D. Install panic hardware according to manufacturer’s specifications.

E. Coordinate with Owner type of the hardware (handle only or handle with keyed cylinder)

for each location.

F. Any screw holes, indentation, or damage as a result of hardware removal shall be filled,

sanded and painted with primer and finish coats.

G. Utilize appropriate filler for metal or exterior exposure.

H. Coordinate with Owner selection of color for finish coats.

2.6 DOOR CONTACT/DOOR POSITION SWITCHES

A. Sealed and potted magnetic reed switch in contact housing

B. Provide DPDT for applications with multiple security systems.

C. Provide color that matches door as close as possible.

D. Provide recessed switch whenever possible.

E. Provide GE Interlogix 1078 Series for recessed applications (or approved equal).

F. Provide GE Interlogix 1045 Series for surface mount applications oOr approved equal).

2.7 REQUEST TO EXIT (REX) DEVICES

Page 71: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 11

A. Dual technology, Passive Infrared (PIR) and Range-Controlled Radar (RCR) motion

detector.

B. Reduces false alarms by sensing both heat and physical motion.

C. Independent adjustable beam pattern and radar depth.

D. Provide with mounting plate or wall mounting plate to mount over a single-gang backbox

when required.

E. Provide color that matches door as close as possible.

F. DPDT output.

G. DC Power draw: 28mA max @ 12 VDC, 17mA max @ 24 VDC.

H. AC Power draw: 38mA max @ 12 VAC, 29mA max @ 24 VAC.

I. Dimensions: 1.76”H x 7.395”W x 1.85”D.

J. Utilize contact closure REX hardware built into the handle or crashbar whenever possible.

K. Provide GE RCR-REX (Or approved equal).

2.8 DOOR LOOPS (POWER TRANSFER LOOPS)

A. Provide new power transfer loops at the top of the doors at locations as indicated on

drawings.

B. Provide all necessary materials and labor to connect existing electrified panic hardware

with existing intercom system and new access control system where appropriate.

C. Power transfer loop shall armored stainless steel door loop with metal end caps.

D. Minimum interior diameter of 3/8” and exterior diameter of 1/2”.

E. Field verify the lengths required for each door.

F. Provide RCI #9508 (or approved equal).

G. Demolish existing door loops

H. Any screw holes, indentation, or damage as a result of hardware removal shall be filled,

sanded and painted with primer and finish coats.

I. Utilize appropriate filler for metal or exterior exposure.

J. Coordinate with Owner selection of color for finish coats.

2.9 SERVER

A. Servers will be owner provided and installed. The EACS contractor shall provide the

district with minimum server configurations, operating system requirements and required

Page 72: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 12

operating system services for the remote servers.

2.10 WORKSTATIONS

A. Workstations will be owner provided and installed. The EACS contractor shall provide the

district with minimum workstation configurations and operating system requirements for

the remote workstations and the master workstation.

B. The EACS contractor shall be responsible for installing one (1) local client at each site

allowing access to only that site. The contractor shall include an additional ten (10)

software installs to be used at the owners or consultants directions.

2.11 BADGES AND CREDENTIALS

A. Provide 15,000 badge credentials with the following features:

1. Operating Frequency: 13.56 MHz

2. 2k bit with 2 application areas.

3. Composite material printable on both sides.

4. Sequential matching internal/external numbering.

5. Provide with rubber Gripper with clear vinyl strap and bulldog clip for each badge

provided.

a. HID 10685 (Gripper) with 10650 (Clip) (or approved equal).

6. The credential shall be HID iCLASS SE #3050PGGMN (no substitutions).

B. Provide 200 fob credentials with the following features:

1. Operating Frequency: 13.56 MHz

2. 2k bit with 2 application areas

3. Sequential matching internal/external numbering

4. The credential shall be HID iCLASS SE #3250PNNMN (no substitutions).

2.12 BADGE PRINTERS AND BADGING STATIONS

A. The contractor shall provide a color badge printer and badging station at the following

locations:

1. New Administration Building (new location not yet determined).

B. Provide a color badge station with the minimum following features:

1. Resin Thermal Transfer dual sided printing at 300 dpi

2. 16.7 million colors and 256 shades per pixel

Page 73: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 13

3. 90 cards per hour @ YMCKK with transfer and dual-sided printing

4. Accepts standard CR-80 card sizes

5. Accepts card thicknesses from 0.03” – 0.05”

6. Dual 200 card capacity input card hoppers

7. USB and Ethernet with internal print server

8. Provide with 13.56 MHz contactless smart card encoding for HID iCLASS SE

9. GSA FIPS-201 approved

10. 3.2” touch screen display

11. 3 year printer warranty and lifetime print head warranty.

C. The contractor shall supply enough HDP film ribbons and other necessary supplies to be

able to print 15,000 dual sided badges. Supplies shall be certified by HID Fargo.

D. The badge printer shall be an HID Fargo HDP8500 Photo ID System (or approved equal).

E. Provide with a HD USB camera and tripod for face capture.

1. HID #041839.

F. Provide with card design and production software.

1. HID Asure ID 7 Exchange #086414.

G. Provide with backdrop and portable stand.

1. HID #086102 (stand)

2. HID #086100 (blue backdrop).

H. Provide a fully functional card reader and IP single door controller near the printer for card

functionality and verification testing.

PART 3 - EXECUTION

3.1 GENERAL

A. In accordance with Division 28 Access Control General Requirements.

3.2 SPECIAL INSTRUCTIONS

A. Access Control and Lock Configuration

1. When doors have keyed hardware replaced the contractor shall match the key

used.

Page 74: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 14

B. Sequence of Operation

1. Verify each doors sequence of operation with the Owner and consultant.

3.3 ACCESS CONTROL SYSTEM INTEGRATION

A. Provide access control system integration equipment, software and programming, in

accordance with Division 28. In addition, provide specific integration schemes noted.

1. EACS Video Integration

3.4 EQUIPMENT, RACK AND CONSOLE INSTALLATION

A. Mount equipment in rooms, consoles, equipment racks, and desktops in accordance with

Division 28 Security System General Requirements.

3.5 GROUNDING PROCEDURES

A. Provide grounding of all systems and equipment in accordance with Division 28 Security

System General Requirements

3.6 WIRE AND CABLE INSTALLATION PRACTICES

A. Provide wire and cable installation in accordance with Division 28 Security System

General Requirements

3.7 DATABASE PREPARATION, CHECKING AND ACTIVATION

A. Provide database preparation, checking and activation for systems and equipment in

accordance with Division 28 Security System General Requirements.

3.8 START-UP RESPONSIBILITY

A. Provide start-up services for all systems and equipment in accordance with Division 28

Security System General Requirements

3.9 PRELIMINARY INSPECTION AND TESTING

A. Provide preliminary inspection and testing services for systems and equipment.

3.10 SYSTEM PERFORMANCE TESTING AND ADJUSTING PROCEDURES

A. Provide performance testing and adjusting of systems and equipment.

3.11 BURN-IN PERFORMANCE PERIOD

A. Provide a burn-in performance period to demonstrate the stability of the system.

3.12 COMMISSIONING AND VALIDATION

A. Provide commissioning and validation services to prove and improve the effectiveness of

the system.

3.13 TRAINING

Page 75: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents

June 25, 2014

DENVER PUBLIC SCHOOLS

Florence Crittenton ELECTRONIC ACCESS CONTROL SYSTEM

MEP Engineering Project No. 13464 28 13 00 - 15

A. Contractor shall provide a minimum of two (2) reprogramming training sessions within

twelve (12) months of the final acceptance of the system to modify the user programming.

B. User group training shall include:

1. Building walk-through indicating locations of equipment and their usage

2. User operation of client workstations, including alarm monitoring, manual door

override, card reader reports, and along with user group special operational

request.

C. Maintenance group training shall include:

1. Building walk through indicating locations of equipment and their usage

2. Location and usage of project specific forms located in the equipment showing

relationship between devices and connectivity to the Owners network

3. Trouble shooting procedures

4. Operational usage of the equipment

5. Procedures for obtaining technical service and repair of equipment.

END OF SECTION

Page 76: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 1

SECTION 28 20 01.00 10

ELECTRONIC SECURITY SYSTEM

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI INCITS 154 (1988; R 2004) Information Technology Office Machines and

Supplies - Alphanumeric Machines-Keyboard Arrangement

ANSI X9.52 (1998) Triple Data Encryption Algorithm Modes of Operation

ASTM INTERNATIONAL (ASTM)

ASTM E 84 (2009c) Standard Test Method for Surface Burning Characteristics of Building Materials

CONSUMER ELECTRONICS ASSOCIATION (CEA)

CEA 170 (1957) Electrical Performance Standards - Monochrome

Television Studio Facilities

CEA-310-E (2005) Racks, Panels, and Associated Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 142 (2007) Recommended Practice for Grounding of Industrial and Commercial Power Systems - IEEE Green Book

IEEE C2 (2007; TIA 2007-1; TIA 2007-2; TIA 2007-3; TIA 2007-4; TIA

2007-5) National Electrical Safety Code

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges

in Low-Voltage (1000 V and Less) AC Power Circuits

INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)

ISO 7811-1 (2002) Identification Cards - Recording Technique - Part 1: Embossing

ISO 7811-2 (2001) Identification Cards - Recording Technique - Part 2:

Magnetic Stripe - Low Coercivity

ISO/IEC 7810 (2003; Amd 1 2009) Identification Cards - Physical Characteristics

Page 77: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 2

INTERNATIONAL TELECOMMUNICATION UNION (ITU)

ITU V.34 (1998) Data Communication Over the Telephone Network ITU V.42 (2002; Corrigendum 1 2003) Data Communications Over the

Telephone Network: Error-Control

ITU V.92 (2000; Am 1 2001, Am 2 2002 and Corr 1 2003) Series V: Data Communication Over the Telephone Network: Simultaneous Transmission of Data and Other Signals/Enhancements to Recommendation V.90

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2008) Enclosures for Electrical Equipment (1000 Volts

Maximum)

NEMA ICS 1 (2000; R 2005; R 2008) Standard for Industrial Control and Systems: General Requirements

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2008; AMD 1 2008) National Electrical Code

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-232-F (1997; R 2002) Interface Between Data Terminal Equipment

and Data Circuit-Terminating Equipment Employing Serial Binary Data Interchange

TIA-568-C.1 (2009) Commercial Building Telecommunications Cabling

Standard

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

21 CFR 1020 Performance Standards for Ionizing Radiation Emitting Products

47 CFR 15 Radio Frequency Devices

47 CFR 68 Connection of Terminal Equipment to the Telephone Network

UNDERWRITERS LABORATORIES (UL)

UL 1037 (1999; R 1999 thru 2009) Standard for Safety Antitheft

Alarms and Devices

UL 1076 (1995; R 1996 thru 2005) Standard for Proprietary Burglar Alarm Units and Systems

UL 294 (1999; R 2001 thru 2009) Standard Access Control System

Units

UL 639 (2007; R 2010) Standard for Intrusion Detection Units

Page 78: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 3

UL 681 (1999; R 2001) Standard for Installation and Classification of Burglar and Holdup Alarm Systems

UL 796 (2006; R 2006 thru 2009) Standard for Printed-Wiring Boards

UL 972 (2006) Standard for Burglary Resisting Glazing Material 1.2 DEFINITIONS 1.2.1 Intrusion Alarm

An alarm resulting from the detection of a specified target, attempting to intrude into the protected area or when entry into an entry-controlled area is attempted without successfully using entry control procedures.

1.2.10 Identifier

A card credential, keypad personal identification number or code, biometric characteristic or any other unique identification entered as data into the entry control database for the purpose of verifying the identity of an individual. Identifiers shall be used by the ESS for the purpose of validating passage requests for areas equipped with entry control equipment.

1.2.11 Entry Control Devices

Any equipment which gives a user the means to input identifier data into the entry control system for verification.

1.2.12 Facility Interface Device

A facility interface device shall be any type of mechanism which is controlled in response to passage requests and allows passage through a portal.

1.2.13 Portal

Specific control point, such as a door or a gate, providing entry or access from one security level to another.

1.2.14 Probability of Detection

Forty-five successful detections out of 46 tests or 98 successful detections out of 103 tests. 1.2.15 Standard Intruder

Person that weighs 100 pounds or less and is 5 ft tall or less, dressed in a long-sleeved shirt, slacks and shoes (unless environmental conditions at the site require protective clothing) and walking, running, crawling or jumping through a protected zone in the most advantageous manner for the intruder.

1.3 SYSTEM DESCRIPTION

Provide an Electronic Security System (ESS) as described and shown including installation of any Furnished Equipment. All computing devices, as defined in 47 CFR 15, shall be certified to comply with the requirements for Class A computing devices and labeled as set forth in 47 CFR 15. Electronic equipment shall comply with 47 CFR 15.

Page 79: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 4

1.3.2 Systems Networks

System networks shall interconnect all components of the system. These networks shall include communications between a central station and any peer or subordinate workstations, enrollment stations, local annunciation stations, portal control stations or redundant central stations. The systems network shall provide totally automatic communication of status changes, commands, field initiated interrupts and any other communications required for proper system operation. System communication shall not require operator initiation or response. System communication shall return to normal after any partial or total network interruption such as power loss or transient upset. The system shall automatically annunciate communication failures to the operator with identification of the communication link that has experienced a partial or total failure. A communications controller may be used as an interface between the central station display systems and the field device network. The communications controller shall provide those functions needed to attain the specified network communications performance.

1.3.2.1 Console Network

A console network, if required, shall provide communication between a central station and any subordinate or separate stations of the system. Where redundant central or parallel stations are required, the console network shall allow the configuration of stations as master and slave. The console network may be a part of the field device network or may be separate depending upon the manufacturer's system configuration.

1.3.2.2 Field Device Network

The field device network shall provide communication between a central control station and field devices of the system. The field device network shall be configured as shown in the drawings. Field devices shall consist of alarm annunciation local processors and entry control local processors. Each field device shall be interrogated during each interrogation cycle. The field device network shall provide line supervision that detects and annunciates communications interruptions or compromised communications between any field device and the central station.

1.3.3 Field Equipment

Field equipment shall include local processors, sensors and controls. Local processors shall serve as an interface between the central station and sensors and controls. Data exchange between the central station and the local processors shall include down-line transmission of commands, software and databases to local processors. The up line data exchange from the local processor to the central station shall include status data such as intrusion alarms, status reports and entry control records. Local processors are categorized as alarm annunciation or entry control or a combination thereof.

1.3.4 CCTV System Interface

Provide an interface for connection of the central station to the CCTV system as specified in Section 28 23 23.00 10 CLOSED CIRCUIT TELEVISION SYSTEMS and as shown. This shall not be accomplished by using an electro-mechanical relay assembly.

1.3.5 Intercom Interface

Provide an interface for connection of the central station to the intercommunication systems as specified and as shown. This shall not be accomplished by using an electro-mechanical relay assembly.

1.3.7 Error Detection and Retransmission

Use a cyclic code error detection method, between local processors and the central station, which will detect single and double bit errors, burst errors of 8 bits or less, and at least 99 percent of all other

Page 80: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 5

multibit and burst error conditions. Interactive or product error detection codes alone will not be acceptable. A message is in error if 1 bit is received incorrectly. The system shall retransmit messages with detected errors. A 2-digit decimal number shall be operator assignable to each communication link representing the number of retransmission attempts. When the number of consecutive retransmission attempts equals the assigned quantity, the central station shall print a communication failure alarm message. The system shall monitor the frequency of data transmission failure for display and logging.

1.3.8 Probability of Detection

Each zone shall have a continuous probability of detection greater than 90 percent and shall be demonstrated with a confidence level of 95 percent. The actual number of tests performed, per sensor, to demonstrate system performance shall be nominated by the Contractor in the performance verification test procedures submitted to the District for approval in the Group IV Technical Data package.

1.3.9 Standard Intruder

The system shall be able to detect a standard intruder moving through a protected zone. 1.3.10 False Alarm Rate 1.3.10.1 Interior

Provide a false alarm rate of no more than 1 false alarm per sensor per 30 days at the specified probability of detection.

1.3.11 Environmental Nuisance Alarm Rate

Environmental alarms during nominal conditions shall not exceed 1 per day per sensor. 1.3.12 Error and Throughput Rates

Error and throughput rates shall be single portal performance rates obtained when processing individuals one at a time.

1.3.13 System Throughput

At the specified error rates, the system throughput rate through a single portal shall be as shown. 1.3.14 Passage

Passage is ingress and/or egress past an entry control device, or through a portal. Entry control procedures and equipment shall be implemented for passage through each portal as shown.

1.3.15 Detection Resolution

The system shall have detection resolution sufficient to locate intrusions at each device and zone; and tampering at individual devices.

1.3.16 Electrical Requirements

Electrically powered ESS equipment shall operate on 120 volt 60 Hz ac sources as shown. Equipment shall be able to tolerate variations in the voltage source of plus or minus 10 percent, and variations in the line frequency of plus or minus 2 percent with no degradation of performance.

Page 81: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 6

1.3.17 System Reaction 1.3.17.1 System Response

The field device network shall provide a system end-to-end response time of 1 second or less for every device connected to the system. Alarms shall be annunciated at the central station within 3 seconds of the alarm occurring at a local processor or device controlled by a local processor, and within 100 milliseconds if the alarm occurs at the central station. Alarm and status changes shall be displayed within 100 milliseconds after receipt of data by the central station. All graphics shall be displayed, including graphics generated map displays, on the console monitor within 5 seconds of alarm receipt at the security console. This response time shall be maintained during system heavy load.

1.3.17.2 System Heavy Load Condition

For the purpose of system heavy load condition, the system shall consist of central station equipment, communication controllers and all local processors as shown. System heavy load condition is the occurrence of alarms at the rate of 10 alarms per second distributed evenly among all local processors in the system. The alarm printer shall continue to print out all occurrences, including time of occurrence, to the nearest second.

1.3.18 System Capacity

The system will be comprised of scalable central servers, regional servers, monitoring stations, administrative stations, and badging stations as shown. The system shall also monitor and control the inputs and outputs shown. The system will discriminate to the individual sensors, switches, and terminal devices and report status at the appropriate workstations as shown. Include a minimum expansion capability of 25 percent through additional software capacity.

1.3.19 Console

Console equipment, unless designated otherwise, shall be rated for continuous operation under ambient environmental conditions of 36 to 122 degrees F and a relative humidity of 20 to 80 percent.

1.4 SUBMITTAL OF TECHNICAL DATA AND COMPUTER SOFTWARE

All items of computer software and technical data (including technical data which relates to computer software) which is attached to and thereby made a part of this contract. All data delivered shall be identified by reference to the particular specification paragraph against which it is furnished.

1.4.1 Technical Data Package

The data package shall include the following as required: 1.4.1.1 System Drawings

a. Functional System block diagram, identifying communications protocols, wire type and quantity, and approximate distances.

b. Security Console installation, including block and wiring diagrams and equipment layout.

c. Local processor installation, including typical block and wiring diagrams.

d. Field equipment enclosure with local processor installation and schematics.

e. Device wiring and installation drawings.

f. Details of connections to power sources, including power supplies and grounding.

g. Details of surge protection device installation.

Page 82: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 7

h. Entry control system block diagram and layout.

i. CCTV assessment block diagram and layout.

j. Details of interconnections with Intercom system.

k. Details of interconnections with Security Lighting system.

l. Intrusion detection system block diagram and sensor layout (including exterior and interior zones) as well as sensor detection patterns.

1.4.1.2 Manufacturer's Data

The data package shall include manufacturer's data for all materials and equipment, including terminal devices, local processors and central station equipment provided under this specification.

1.4.1.3 System Description and Analyses

The data package shall include system descriptions, analyses, and calculations used in sizing equipment specified. Descriptions and calculations shall show how the equipment will operate as a system to meet the performance of this specification. The data package shall include the following:

a. On-board Random Access Memory (RAM).

b. Communication speeds and protocol descriptions.

c. Hard disk size and configuration.

d. CD-ROM/CD-RW/DVD/DVD-RW drive speed and protocol descriptions.

e. Streaming tape back-up speed and capacity.

f. Removable storage disk size and configuration.

g. Alarm response time calculations.

h. Command response time calculations.

i. Start-up operations including system and database backup operations.

j. Expansion capability and method of implementation.

k. Sample copy of each report specified.

l. Color output of typical graphics.

m. System throughput calculation.

The data package shall also include a table comparing the above information for the equipment supplied and the minimum required by the software manufacturer.

1.4.1.4 Software Data

The software data package shall consist of descriptions of the operation and capability of system, and application software as specified.

Page 83: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 8

1.4.1.5 Overall System Reliability Calculations

The overall system reliability calculations data package shall include all manufacturer's reliability data and calculations required to show compliance with the specified reliability in accordance with paragraph, OVERALL SYSTEM RELIABILITY REQUIREMENTS.

1.4.1.6 Certifications

Specified manufacturer's certifications shall be included with the data package certification. 1.4.1.7 Key Control Plan

Provide a key control plan including the following:

a. Procedures that will be used to log and positively control all keys during installation.

b. A listing of all keys and where they are used.

c. A listing of all persons allowed access to the keys. 1.4.4.1 Operation and Maintenance Manuals

Deliver draft copies of the operator's, software, hardware, functional design, and maintenance manuals, as specified below, to the District prior to beginning the performance verification test for use during the test period.

1.4.4.2 Operator's Manuals

The operator's manual shall fully explain all procedures and instructions for the operation of the system, including:

a. Computers and peripherals. b. User enrollment. c. System start-up and shutdown procedures. d. Use of system and application software. e. Recovery and restart procedures. f. Graphic alarm presentation. g. Use of report generator and generation of reports. h. Data entry. i. Operator commands. j. Alarm and system messages and printing formats. k. System entry requirements.

1.4.4.3 Software Manual

The software manual shall describe the functions of all software and shall include all other information necessary to enable proper loading, testing, and operation. The manual shall include:

a. Definition of terms and functions. b. Use of system and application software. c. Procedures for system initialization, start-up and shutdown d. Alarm reports. e. Reports generation, f. Database format and date entry requirements. g. Directory of all disk files.

Page 84: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 9

h. Description of all communication protocols, including data formats, command characters, and a sample of each type of data transfer.

i. Interface definition. 1.4.4.4 Hardware Manual

A manual describing all equipment furnished including:

a. General description and specifications. b. Installation and checkout procedures. c. Equipment electrical schematics and layout drawings. d. System schematics and layout drawings. e. Alignment and calibration procedures. f. Manufacturer's repair parts list indicating sources of supply. g. Interface definition.

1.4.4.5 Functional Design Manual

The functional design manual shall identify the operational requirements for the system and explain the theory of operation, design philosophy, and specific functions. A description of hardware and software functions, interfaces, and requirements shall be included for all system operating modes.

1.4.4.6 Data Entry

Enter all data needed to make the system operational. Deliver the data to the District on data entry forms, utilizing data from the contract documents, Contractor's field surveys, and other pertinent information in the Contractor's possession required for complete installation of the database. Identify and request from the District, any additional data needed to provide a complete and operational ESS. The completed forms shall be delivered to the District for review and approval at least 30 days prior to the Contractor's scheduled need date. When the ESS database is to be populated in whole or in part from an existing or District furnished electronic database, demonstrate the field mapping scheme to correctly input the data.

1.4.4.7 Graphics

Where graphics are required and are to be delivered with the system, create and install the graphics needed to make the system operational. Utilize data from the contract documents, Contractor's field surveys, and other pertinent information in the Contractor's possession to complete the graphics. Identify and request from the District, any additional data needed to provide a complete graphics package. Graphics shall have sufficient level of detail for the system operator to assess the alarm. Supply hard copy, color examples at least 8 x 10 inches in size, of each type of graphic to be used for the completed system. The graphics examples shall be delivered to the District for review and approval at least 30 days prior to the Contractor's scheduled need date.

1.4.5.1 Operator's Manual

A copy of the final and approved Operator's Manual. 1.4.5.2 Software Manual

A copy of the final and approved Software Manual. 1.4.5.3 Hardware Manual

A copy of the final and approved Hardware Manual. 1.4.5.4 Functional Design Manual

Page 85: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 10

A copy of the final and approved Functional Design Manual. 1.4.5.5 Maintenance Manual

A copy of the final and approved Maintenance Manual. 1.4.5.6 Final System Drawings

Maintain a separate set of drawings, elementary diagrams and wiring diagrams of the system to be used for final system drawings. This set shall be accurately kept up-to-date with all changes and additions to the ESS and shall be delivered to the District with the final endurance test report. In addition to being complete and accurate, this set of drawings shall be kept neat and shall not be used for installation purposes. Final drawings submitted with the endurance test report shall be finished drawings on CD-ROM in AutoCAD format.

1.5 QUALITY ASSURANCE 1.5.1 Pre-Delivery Testing

Perform pre-delivery testing, site performance verification testing, and adjustment of the completed ESS. Provide personnel, equipment, instrumentation, and supplies necessary to perform testing. Written notification of planned testing shall be given to the District at least 14 days prior to the test; notice shall not be given until after the Contractor has received written approval of the specific test procedures.

a. Assemble the test system as specified, and perform tests to demonstrate that performance

of the system complies with specified requirements in accordance with the approved predelivery test procedures. The tests shall take place during regular daytime working hours on weekdays. Model numbers of equipment tested shall be identical to those to be delivered to the site. Original copies of all data produced during predelivery testing, including results of each test procedure, shall be delivered to the District at the conclusion of predelivery testing, prior to District approval of the test. The test report shall be arranged so that all commands, stimuli, and responses are correlated to allow logical interpretation.

b. Test Setup: The predelivery test setup shall include the following:

1) All central station equipment.

2) At least 1 of each type DTS link, but not less than 2 links, and associated equipment to

provide a fully integrated system. 3) The number of local processors shall equal the amount required by the site design. 4) At least 1 of each type sensor used. 5) Enough sensor simulators to provide alarm signal inputs to the system equal to the

number of sensors required by the design. The alarm signals shall be manually or software generated.

6) At least 1 of each type of terminal device used. 7) At least 1 of each type of portal configuration with all facility interface devices as

specified or shown. 8) Equipment as specified in Section 28 23 23.00 10 CLOSED CIRCUIT TELEVISON

SYSTEMS when required.

Page 86: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 11

9) The Contractor shall prepare test procedures and reports for the predelivery test, and shall deliver the predelivery test procedures to the District for approval. The final predelivery test report shall be delivered after completion of the predelivery test.

1.5.2 Test Procedures and Reports

Test procedures shall explain in detail, step-by-step actions and expected results, demonstrating compliance with the requirements specified. Test reports shall be used to document results of the tests. Reports shall be delivered to the District within 7 days after completion of each test.

1.5.3 Line Supervision

1.5.3.1 Signal and Data Transmission System (DTS) Line Supervision

All signal and DTS lines shall be supervised by the system. The system shall supervise the signal lines by monitoring the circuit for changes or disturbances in the signal, and for conditions as described in UL 1076 for line security equipment. The system shall initiate an alarm in response to a current change of 10 percent or greater. The system shall also initiate an alarm in response to opening, closing, shorting, or grounding of the signal and DTS lines.

1.6 ENVIRONMENTAL REQUIREMENTS 1.6.1 Interior, Controlled Environment

System components, except the console equipment installed in interior locations, having controlled environments shall be rated for continuous operation under ambient environmental conditions of 36 to 122 degrees F dry bulb and 20 to 90 percent relative humidity, non-condensing.

1.6.3 Exterior Environment

System components that are installed in locations exposed to weather shall be rated for continuous operation under ambient environmental conditions of -30 to plus 122 degrees F dry bulb and 10 to 95 percent relative humidity, condensing. In addition, the system components shall be rated for continuous operation when exposed to performance conditions as specified in UL 294 and UL 639 for outdoor use equipment. Components shall be rated for continuous operation when exposed to rain as specified in NEMA 250, winds up to 85 mph and snow cover up to 2 feet thick, measured vertically.

1.7 MAINTENANCE AND SERVICE 1.7.1 Warranty Period

Provide all labor, equipment, and materials required to maintain the entire system in an operational state as specified, for a period of two years after formal written acceptance of the system to include scheduled and nonscheduled adjustments.

1.7.2 Description of Work

The adjustment and repair of the system includes all computer equipment, software updates, communications transmission equipment and DTS, local processors, sensors and entry control, facility interface, and support equipment. Responsibility shall be limited to Contractor installed equipment. Repair, calibration, and other work shall be provided and performed in accordance with the manufacturer's documentation and instruction. The maintenance manual shall include descriptions of maintenance for all equipment including inspection, periodic prevention maintenance, fault diagnosis, and repair or replacement of defective components.

Page 87: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 12

1.7.3 Personnel

Service personnel shall be certified in the maintenance and repair of the specific type of equipment installed and qualified to accomplish work promptly and satisfactorily. The District shall be advised in writing of the name of the designated service representative, and of any change in personnel.

1.7.4 Schedule of Work

Perform two minor inspections at 6 month intervals (or more often if required by the manufacturer), and two major inspections offset equally between the minor inspections to effect quarterly inspection of alternating magnitude.

1.7.4.1 Minor Inspections

Minor inspections shall include visual checks and operational tests of console equipment, peripheral equipment, local processors, sensors, and electrical and mechanical controls. Minor inspections shall also include mechanical adjustment of laser printers.

1.7.4.2 Major Inspections

Major inspections shall include work described under paragraph Minor Inspections and the following work:

a. Clean interior and exterior surfaces of all system equipment and local processors, including

workstation monitors, keyboards, and console equipment. b. Perform diagnostics on all equipment. c. Check, walk test, and calibrate each sensor. d. Run all system software diagnostics and correct all diagnosed problems. e. Resolve any previous outstanding problems. f. Purge and compress data bases. g. Review network configuration.

1.7.4.3 Scheduled Work

Scheduled work shall be performed during regular working hours, Monday through Friday, excluding federal holidays.

1.7.5 Emergency Service

The District will initiate service calls when the system is not functioning properly. Qualified personnel shall be available to provide service to the complete system. The District shall be furnished with a telephone number where the service supervisor can be reached at all times. Service personnel shall be at site within 4 hours after receiving a request for service. The system shall be restored to proper operating condition within 8 hours after service personnel arrive onsite and obtain access to the system.

1.7.6 Operation

Performance verification test procedures shall be used after all scheduled maintenance and repair activities to verify proper component and system operation.

Page 88: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 13

1.7.7 Records and Logs

Keep records and logs of each task, and organize cumulative records for each component, and for the complete system chronologically resulting in a continuous log to be maintained for all devices. The log shall contain all initial settings. Complete logs shall be kept and shall be available for inspection onsite, demonstrating that planned and systematic adjustments and repairs have been accomplished for the system.

1.7.8 Work Requests

Separately record each service call request, as received. The form shall include the serial number identifying the component involved, its location, date and time the call was received, specific nature of trouble, names of service personnel assigned to the task, instructions describing what has to be done, the amount and nature of the material to be used, the time and date work started, and the time and date of completion. Deliver a record of the work performed within 5 days after work is accomplished.

1.7.9 System Modifications

Make any recommendations for system modification in writing to the District. System modifications shall not be made without prior approval of the District. Any modifications made to the system shall result in the updating of the operation and maintenance manuals as well as any other documentation affected.

1.7.10 Software

Provide a description of all software updates to the District, who will then decide whether or not they are appropriate for implementation. After notification by the District, implement the designated software updates and verify operation in the system. These updates shall be accomplished in a timely manner, fully coordinated with system operators, and shall be incorporated into the operation and maintenance manuals, and software documentation. Make a system image file so the system can be restored to its original state if the software update adversely affects system performance.

PART 2 PRODUCTS

2.1 MATERIALS REQUIREMENTS 2.1.1 Materials and Equipment

Units of equipment that perform identical, specified functions shall be products of a single manufacturer. All material and equipment shall be new and currently in production. Each major component of equipment shall have the manufacturer's model and serial number in a conspicuous place. System equipment shall conform to UL 294 and UL 1076. Refer to appendix “A” of this section for a list of approved products.

2.1.2 Nameplates

Laminated plastic nameplates shall be provided for local processors. Each nameplate shall identify the local processor and its location within the system. Laminated plastic shall be 1/8 inch thick, white with black center core. Nameplates shall be a minimum of 1 x 3 inches, with minimum 1/4 inch high engraved block lettering. Nameplates shall be attached to the inside of the enclosure housing the local processor. Other major components of the system shall have the manufacturer's name, address, type or style, model or serial number, and catalog number on a corrosion resistant plate secured to the item of equipment. Nameplates will not be required for devices smaller than 1 x 3 inches.

Page 89: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 14

2.1.3 Power Line Surge Protection

Equipment connected to alternating current circuits shall be protected from power line surges. Equipment protection shall withstand surge test waveforms described in IEEE C62.41.1 and IEEE C62.41.2. Fuses shall not be used for surge protection.

2.1.4 Sensor Device Wiring and Communication Circuit Surge Protection

Inputs shall be protected against surges induced on device wiring. Outputs shall be protected against surges induced on control and device wiring installed outdoors and as shown. Communications equipment shall be protected against surges induced on any communications circuit. Cables and conductors, except fiber optics, which serve as communications circuits from console to field equipment, and between field equipment, shall have surge protection circuits installed at each end. Protection shall be furnished at equipment, and additional triple electrode gas surge protectors rated for the application on each wireline circuit shall be installed within 3 feet of the building cable entrance. Fuses shall not be used for surge protection. The inputs and outputs shall be tested in both normal mode and common mode using the following two waveforms:

a. A 10 microsecond rise time by 1000 microsecond pulse width waveform with a peak voltage

of 1500 Volts and a peak current of 60 amperes.

b. An 8 microsecond rise time by 20 microsecond pulse width waveform with a peak voltage of 1000 Volts and a peak current of 500 amperes.

2.1.5 Power Line Conditioners

A power line conditioner shall be furnished for the console equipment and each local processor. The power line conditioners shall be of the Ferro resonant design, with no moving parts and no tap switching, while electrically isolating the secondary from the power line side. The power line conditioners shall be sized for 125 percent of the actual connected kVA load. Characteristics of the power line conditioners shall be as follows:

a. At 85 percent load, the output voltage shall not deviate by more than plus or minus 1

percent of nominal when the input voltage fluctuates between minus 20 percent to plus 10 percent of nominal.

b. During load changes of zero to full load, the output voltage shall not deviate by more than

plus or minus 3 percent of nominal. Full correction of load switching disturbances shall be accomplished within 5 cycles, and 95 percent correction shall be accomplished within 2 cycles of the onset of the disturbance.

c. Total harmonic distortion shall not exceed 3.5 percent at full load. 2.1.6 Field Enclosures

2.1.6.1 Interior Sensor

Sensors to be used in an interior environment shall have a housing that provides protection against dust, falling dirt, and dripping noncorrosive liquids.

2.1.6.3 Interior Electronics

System electronics to be used in an interior environment shall be housed in enclosures which meet the requirements of NEMA 250 Type 12.

Page 90: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 15

2.1.7 Tamper Provisions 2.1.7.1 Tamper Switches

Enclosures, cabinets, housings, boxes, and fittings having hinged doors or removable covers and which contain circuits or connections of the system and its power supplies, shall be provided with cover operated, corrosion-resistant tamper switches, arranged to initiate an alarm signal when the door or cover is moved. The enclosure and the tamper switch shall function together and shall not allow direct line of sight to any internal components before the switch activates. Tamper switches shall be inaccessible until the switch is activated; have mounting hardware concealed so that the location of the switch cannot be observed from the exterior of the enclosure; be connected to circuits which are under electrical supervision at all times, irrespective of the protection mode in which the circuit is operating; shall be spring-loaded and held in the closed position by the door or cover; and shall be wired so that the circuit is broken when the door or cover is disturbed.

a. Non-sensor Enclosures: Tamper switches must be installed on all non-sensor enclosures.

b. Sensor Enclosures: Tamper switches must be installed on all sensor enclosures or

housings. 2.1.7.2 Enclosure Covers

Covers of pull and junction boxes provided to facilitate initial installation of the system need not be provided with tamper switches if they contain no splices or connections, but shall be protected by tack welding or brazing the covers in place or by tamper resistant security fasteners. Labels shall be affixed to such boxes indicating they contain no connections.

2.2 FIELD PROCESSING SOFTWARE

All Field processing software described in this specification shall be furnished as part of the complete system.

2.2.1 Operating System

Each local processor shall contain an operating system that controls and schedules that local processor's activities in real time. The local processor shall maintain a point database in its memory that includes all parameters, constraints, and the latest value or status of all points connected to that local processor. The execution of local processor application programs shall utilize the data in memory resident files. The operating system shall include a real time clock function that maintains the seconds, minutes, hours, date and month, including day of the week. Each local processor real time clock shall be automatically synchronized with the central station at least once per day to plus or minus 10 seconds (the time synchronization shall be accomplished automatically, without operator action and without requiring system shutdown).

2.2.1.1 Startup

The local processor shall have startup software that causes automatic commencement of operation without human intervention, including startup of all connected Input/Output functions. A local processor restart program based on detection of power failure at the local processor shall be included in the local processor software. The startup software shall initiate operation of self-test diagnostic routines. Upon failure of the local processor, if the database and application software are no longer resident, the local processor shall not restart and systems shall remain in the failure mode indicated until the necessary repairs are made. If the database and application programs are resident, the local processor shall immediately resume operation.

Page 91: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 16

2.2.1.2 Operating Mode

Each local processor shall control and monitor inputs and outputs as specified, independent of communications with the central station or designated workstations. Alarms, status changes and other data shall be transmitted to the central station or designated workstations when communications circuits are operable. If communications are not available, each local processor shall function in a stand-alone mode and operational data, including the status and alarm data normally transmitted to the central station or designated workstations shall be stored for later transmission to the central station or designated workstations. Storage for the latest 4000 events shall be provided at each local processor, as a minimum. Each local processor shall accept software downloaded from the central station. The panel shall support flash ROM technology to accomplish firmware downloads from a central location.

2.2.1.3 Failure Mode

Upon failure for any reason, each local processor shall perform an orderly shutdown and force all local processor outputs to a predetermined (failure mode) state, consistent with the failure modes shown and the associated control device.

2.2.2 Functions

Provide software necessary to accomplish the following functions, as appropriate, fully implemented and operational, within each local processor.

a. Monitoring of inputs.

b. Control of outputs.

c. Reporting of alarms automatically to the central station.

d. Reporting of sensor and output status to central station upon request.

e. Maintenance of real time, automatically updated by the central station at least once a day.

f. Communication with the central station.

g. Execution of local processor resident programs.

h. Diagnostics.

i. Download and upload data to and from the central station.

2.3 WIRE AND CABLE

Wiring shall meet NFPA 70 standards. 2.3.1 Above Ground Sensor Wiring

Sensor wiring shall be 20 AWG minimum, twisted and shielded, 2, 3, 4, or 6 pairs to match hardware. Multi-conductor wire shall have an outer jacket of PVC.

2.3.2 Local Area Network (LAN) Cabling

LAN cabling shall be in accordance with TIA-568-C.1, category 5. 2.3.3 Cable Construction

Page 92: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 17

All cable components shall withstand the environment in which the cable is installed for a minimum of 20 years.

2.3.4 Power Line Surge Protection

Equipment connected to alternating current circuits shall be protected from power line surges. Equipment protection shall withstand surge test waveforms described in IEEE C62.41.1 and IEEE C62.41.2. Fuses shall not be used for surge protection.

2.3.5 Sensor Device Wiring and Communication Circuit Surge Protection

Inputs shall be protected against surges induced on device wiring. Outputs shall be protected against surges induced on control and device wiring installed outdoors and as shown. Communications equipment shall be protected against surges induced on any communications circuit. Cables and conductors, except fiber optics, which serve as communications circuits from console to field equipment, and between field equipment, shall have surge protection circuits installed at each end. Protection shall be furnished at equipment, and additional triple electrode gas surge protectors rated for the application on each wireline circuit shall be installed within 3 feet of the building cable entrance. Fuses shall not be used for surge protection. The inputs and outputs shall be tested in both normal mode and common mode using the following two waveforms:

a. A 10-microsecond rise time by 1000 microsecond pulse width waveform with a peak voltage

of 1500 Volts and a peak current of 60 amperes.

b. An 8-microsecond rise time by 20-microsecond pulse width waveform with a peak voltage of 1000 Volts and a peak current of 500 amperes.

2.3.6 Power Line Conditioners

A power line conditioner shall be furnished for the console equipment. The power line conditioners shall be of the Ferro resonant design, with no moving parts and no tap switching, while electrically isolating the secondary from the power line side. The power line conditioners shall be sized for 125 percent of the actual connected kVA load. Characteristics of the power line conditioners shall be as follows:

a. At 85 percent load, the output voltage shall not deviate by more than plus or minus 1

percent of nominal when the input voltage fluctuates between minus 20 percent to plus 10 percent of nominal.

b. During load changes of zero to full load, the output voltage shall not deviate by more than plus or minus 3 percent of nominal. Full correction of load switching disturbances shall be accomplished within five cycles, and 95 percent correction shall be accomplished within two cycles of the onset of the disturbance.

c. Total harmonic distortion shall not exceed 3.5 percent at full load.

PART 3 EXECUTION

3.1 EXAMINATION

Verify that site conditions are in agreement with the design package and report any changes in the site, or conditions that will affect performance of the system to the District in a report as defined in paragraph Technical Data Package. Do not take any corrective action without written permission from the District.

Page 93: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 18

3.2 GENERAL REQUIREMENTS

Install all system components, including District furnished equipment, and appurtenances in accordance with the manufacturer's instructions, IEEE C2 and as shown. Furnish necessary interconnections, services, and adjustments required for a complete and operable system as specified and shown. Control signal, communications, and data transmission line grounding shall be installed as necessary to preclude ground loops, noise, and surges from adversely affecting system operation.

3.2.1 Installation

Install the system in accordance with the standards for safety, NFPA 70, UL 681, UL 1037 and UL 1076, and the appropriate installation manual for each equipment type. Components within the system shall be configured with appropriate service points to pinpoint system trouble in less than 20 minutes. Conduit shall be rigid galvanized steel or as shown and a minimum of 1/2 inch in diameter. DTS shall not be pulled into conduits or placed in raceways, compartments, outlet boxes, junction boxes, or similar fittings with other building wiring. Flexible cords or cord connections shall not be used to supply power to any components of the system, except where specifically noted. All other electrical work shall be as specified and as shown.

3.2.2 Enclosure Penetrations

Enclosure penetrations shall be from the bottom unless the system design requires penetrations from other directions. Penetrations of interior enclosures involving transitions of conduit from interior to exterior, and penetrations on exterior enclosures shall be sealed with rubber silicone sealant to preclude the entry of water. The conduit riser shall terminate in a hot-dipped galvanized metal cable terminator. The terminator shall be filled with an approved sealant as recommended by the cable manufacturer, and in a manner that does not damage the cable.

3.2.3 Cold Galvanizing

Field welds and/or brazing on factory galvanized boxes, enclosures, conduits, etc., shall be coated with a cold galvanized paint containing at least 95 percent zinc by weight.

3.2.4 Installation Software

Load software as specified and required for an operational system, including data bases and specified programs. Upon successful completion of the endurance test, provide original and backup copies on CD-ROM of all accepted software, including diagnostics.

3.3 SYSTEM STARTUP

Satisfaction of the requirements below does not relieve the Contractor of responsibility for incorrect installations, defective equipment items, or collateral damage as a result of Contractor work/equipment. Do not apply power to the system until after:

a. System equipment items and DTS have been set up in accordance with manufacturer's

instructions.

b. A visual inspection of the system has been conducted to ensure that defective equipment items have not been installed and that there are no loose connections.

c. System wiring has been tested and verified as correctly connected.

d. System grounding and transient protection systems have been verified as properly installed.

e. Power supplies to be connected to the system have been verified as the correct voltage, phasing, and frequency.

Page 94: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 19

3.4 SUPPLEMENTAL CONTRACTOR QUALITY CONTROL

Provide the services of technical representatives who are familiar with all components and installation procedures of the installed system; and are approved by the Contracting Officer. These representatives shall be present on the job site during the preparatory and initial phases of quality control to provide technical assistance. These representatives shall also be available on an as needed basis to provide assistance with follow-up phases of quality control. These technical representatives shall participate in the testing and validation of the system and shall provide certification that their respective system portions meet the contractual requirements.

3.5 TRAINING 3.5.1 General

Deliver lesson plans and training manuals for the training phases, including type of training to be provided, and a list of reference material, for District approval. Conduct training courses for designated personnel in the maintenance and operation of the system as specified. The training shall be oriented to the specific system being installed. Training manuals shall be delivered for each trainee with 2 additional copies delivered for archiving at the project site. The manuals shall include an agenda, defined objectives for each lesson, and a detailed description of the subject matter for each lesson. Furnish audio-visual equipment and other training materials and supplies. Where the Contractor presents portions of the course by audio-visual material, copies of the audio-visual material shall be delivered to the District either as a part of the printed training manuals or on the same media as that used during the training sessions. A training day is defined as 8 hours of classroom instruction, including 2 15-minute breaks and excluding lunchtime, Monday through Friday, during the daytime shift in effect at the training facility. For guidance in planning the required instruction, assume that attendees will have a high school education or equivalent, and are familiar with ESS. Approval of the planned training schedule shall be obtained from the District at least 30 days prior to the training.

3.5.2 Operator's Training I

The first course shall be taught at the project site for a period of up to five consecutive training days at least 3 months prior to the scheduled performance verification test. Upon completion of this course, each student, using appropriate documentation, shall be able to perform elementary operations with guidance and describe the general hardware architecture and functionality of the system. This course shall include:

a. General System hardware architecture. b. Functional operation of the system. c. Operator commands. d. Data base entry. e. Reports generation. f. Alarm reporting. g. Diagnostics.

3.5.3 Operator's Training II

The second course shall be taught at the project site for a period of up to five consecutive training days during or after the Contractor's field testing, but before commencing the performance verification test. No part of the training given during this course will be counted toward completion of the performance verification test. The course shall include instruction on the specific hardware configuration of the installed system and specific instructions for operating the installed system. Upon completion of this course, each student shall be able to start the system, operate the system, recover the system after a failure, and describe the specific hardware architecture and operation of the system. Specific

Page 95: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 20

application of the results of this course should enable the students to proficiently monitor the alarm workstations during the performance verification test.

3.5.4 Operator's Training III

The third course shall be taught while the endurance test is in progress for a total of 16 hours of instruction per student, in time blocks of 4 hours. The schedule of instruction shall allow for each student to receive individual instruction for a 4-hour period in the morning (or afternoon) of the same weekday. Schedule the activities during this period so that the specified amount of time will be available during the endurance test for instructing the students. The course shall consist of hands-on training under the constant monitoring of the instructor. The instructor shall be responsible for determining the appropriate password to be issued to the student commensurate with each student's acquired skills at the beginning of each of these individual training sessions. Upon completion of this course, the students shall be fully proficient in the operation of the system.

3.5.5 System Manager Training

System managers shall be trained for at least 3 consecutive days. The system manager training shall consist of the operator's training and the following:

a. Enrollment/deactivation. b. Assignments of identifier data. c. Assign operator password/levels. d. Change database configuration. e. System network configuration and management. f. Modify graphics. g. Print special or custom reports. h. System backup. i. Any other functions necessary to manage the system.

3.5.6 Maintenance Personnel Training

The system maintenance course shall be taught at the project site after completion of the endurance test for a period of 5 training days. The training shall include:

a. Physical layout of each piece of hardware. b. Troubleshooting and diagnostics procedures. c. Component repair and/or replacement procedures. d. Maintenance procedures and schedules to include system testing after repair. e. Calibration procedures. Upon completion of this course, the students shall be fully proficient

in the maintenance of the system. f. Review of site-specific drawing package, device location, communication, topology, and

flow. 3.6 TESTING 3.6.1 General Requirements for Testing

Provide personnel, equipment, instrumentation, and supplies necessary to perform site testing. The District will witness all performance verification and endurance testing. Written permission shall be obtained from the District before proceeding with the next phase of testing. Original copies of all data produced during predelivery, performance verification and endurance testing, shall be turned over to the District at the conclusion of each phase of testing, prior to District approval of the test.

3.6.2 Contractor's Field Testing

Page 96: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 21

Calibrate and test all equipment, verify DTS operation, place the integrated system in service, and test the integrated system. Ground rods installed by the Contractor shall be tested as specified in IEEE 142. Deliver a report describing results of functional tests, diagnostics, and calibrations, including written certification to the District that the installed complete system has been calibrated, tested, and is ready to begin performance verification testing. It is recommended that the Contractor use the approved performance verification test as a guideline when the field test is conducted.

3.6.3 Performance Verification Test

Demonstrate that the completed system complies with the contract requirements. Using approved test procedures, all physical and functional requirements of the project shall be demonstrated and shown. The performance verification test, as specified, shall not be started until after receipt by the Contractor of written permission from the District, based on the Contractor's written report. The report shall include certification of successful completion of testing as specified in paragraph Contractor's Field Testing, and upon successful completion of training as specified. The District may terminate testing at any time when the system fails to perform as specified. Upon termination of testing by the Government or by the Contractor, commence an assessment period as described for Endurance Testing Phase II. Upon successful completion of the performance verification test, deliver test reports and other documentation as specified to the District prior to commencing the endurance test.

3.6.4 Endurance Test

a. General: Demonstrate system reliability and operability at the specified throughput rates for each portal, and the Type I and Type II error rates specified for the completed system. Calculate false alarm rates and the system shall yield false alarm rates within the specified maximums at the specified probability of detection. The endurance test shall be conducted in phases as specified. The endurance test shall not be started until the District notifies the Contractor, in writing, that the performance verification test is satisfactorily completed, training as specified has been completed, and correction of all outstanding deficiencies has been satisfactorily completed. Provide 1 operator to operate the system 24 hours per day, including weekends and holidays, during Phase I and Phase III endurance testing, in addition to any District personnel that may be made available. The District may terminate testing at any time the system fails to perform as specified. Upon termination of testing by the District or by the Contractor, commence an assessment period as described for Phase II. Verify the operation of each terminal device during the last day of the test. Upon successful completion of the endurance test, deliver test reports and other documentation as specified to the District prior to acceptance of the system.

b. Phase I Testing: The test shall be conducted 24 hours per day for 15 consecutive calendar days, including holidays, and the system shall operate as specified. Make no repairs during this phase of testing unless authorized by the District in writing. If the system experiences no failures during Phase I testing, the Contractor may proceed directly to Phase III testing after receipt of written permission from the District.

c. Phase II Assessment: After the conclusion of Phase I, identify all failures, determine causes of all failures, repair all failures, and deliver a written report to the District. The report shall explain in detail the nature of each failure, corrective action taken, results of tests performed, and shall recommend the point at which testing should be resumed. After delivering the written report, convene a test review meeting at the jobsite to present the results and recommendations to the District. The meeting shall not be scheduled earlier than 5 business days after receipt of the report by the District. As a part of this test review meeting, demonstrate that all failures have been corrected by performing appropriate portions of the performance verification test. Based on the Contractor's report and the test review meeting, the District will determine the restart date, or may require that Phase I be repeated. If the retest is completed without any failures, the Contractor may proceed directly to Phase III testing after receipt of written permission from the District.

Page 97: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

ELECTRONIC SECURITY SYSTEM

28 20 01.00 10 - 22

d. Phase III Testing: The test shall be conducted 24 hours per day for 15 consecutive

calendar days, including holidays, and the system shall operate as specified. Make no repairs during this phase of testing unless authorized by the District in writing.

e. Phase IV Assessment: After the conclusion of Phase III, identify all failures, determine causes of failures, repair failures, and deliver a written report to the District. The report shall explain in detail the nature of each failure, corrective action taken, results of tests performed, and shall recommend the point at which testing should be resumed. After delivering the written report, convene a test review meeting at the jobsite to present the results and recommendations to the District. The meeting shall not be scheduled earlier than 5 business days after receipt of the report by the District. As a part of this test review meeting, demonstrate that all failures have been corrected by repeating appropriate portions of the performance verification test. Based on the Contractor's report and the test review meeting, the District will determine the restart date, and may require that Phase III be repeated. Do not commence any required retesting until after receipt of written notification by District. After the conclusion of any retesting which the District may require, the Phase IV assessment shall be repeated as if Phase III had just been completed.

APPENDIX A

INTRUSION EQUIPMENT

Manufacturer Part Number Description

Honeywell V128BP-KT1 Vista 128BPE

Vista-128BP Panel

Honeywell 6150 Keypad

Honeywell 6160 Keypad

Honeywell 985 Overhead Door Contacts

GE 1076 Steel Door Contact

Honeywell 960 Door Contacts-wide gap

Honeywell 4208U Dip switch eight zone expander

Bosch DS835i Motion detector

Bosch DS778 Motion detector – Long Range

END OF SECTION

Page 98: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 1

SECTION 28 23 23.00 10

CLOSED CIRCUIT TELEVISION SYSTEMS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

CONSUMER ELECTRONICS ASSOCIATION (CEA)

CEA 170 (1957) Electrical Performance Standards - Monochrome

Television Studio Facilities

CEA-310-E (2005) Racks, Panels, and Associated Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 142 (2007) Recommended Practice for Grounding of Industrial and Commercial Power Systems - IEEE Green Book

IEEE C2 (2007; TIA 2007-1; TIA 2007-2; TIA 2007-3; TIA 2007-4; TIA

2007-5) National Electrical Safety Code

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges

in Low-Voltage (1000 V and Less) AC Power Circuits

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2008) Enclosures for Electrical Equipment (1000 Volts Maximum)

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2008; AMD 1 2008) National Electrical Code

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-232-F (1997; R 2002) Interface Between Data Terminal Equipment

and Data Circuit-Terminating Equipment Employing Serial Binary Data Interchange

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

47 CFR 15 Radio Frequency Devices

UNDERWRITERS LABORATORIES (UL)

UL 1492 (1996; R 2001 thru 2009) Audio-Video Products and

Accessories

Page 99: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 2

1.2 SYSTEM DESCRIPTION 1.2.1 General

Configure the system as described and shown. All television equipment shall conform to CEA 170 specifications. Include in the system all connectors, adapters, and terminators necessary to interconnect all equipment. Supply all cabling necessary to interconnect the closed circuit television (CCTV) equipment installed in the Security Center, and interconnect equipment installed at remote control/monitoring stations. If the CCTV system is installed for use with an Electronic Security System (ESS) interface the CCTV system with the ESS.

1.2.2 System Overall Reliability Requirement

Configure and install the system, including all components and appurtenances, to yield a mean time between failure (MTBF) of at least 10,000 hours, calculated based on the configuration specified in paragraph "System Overall Reliability Calculations."

1.2.3 Power Line Surge Protection

Protect all equipment connected to AC power from surges. Equipment protection shall withstand surge test waveforms described in IEEE C62.41.1 and IEEE C62.41.2. Fuses shall not be used for surge protection.

1.2.4 Video and Sync Signal Transmission Line Surge Protection

All cable, except fiber optic cable, used for sync or video signal transmission shall include protective devices to safeguard the CCTV equipment against surges. The surge suppression device shall not attenuate or reduce the video or sync signal under normal conditions. The surge suppression device shall be capable of dissipating not less than 1500 watts for 1 millisecond, and the response time from zero volts to clamping shall not be greater than 5 nanoseconds. Fuses shall not be used for surge protection.

1.2.5 Control Line Surge Protection

All cables and conductors, except fiber optic cables, which serve as communication, control, or signal lines shall be protected against surges and shall have surge protection installed at each end. Protection shall be furnished at the equipment and additional triple electrode gas surge protectors rated for the application on each wireline circuit shall be installed within 3 feet of the building cable entrance. Fuses shall not be used for surge protection. Test the inputs and outputs in both normal mode and common mode using the following waveforms:

a. A 10 microsecond rise time by 1000 microsecond pulse width waveform with a peak voltage

of 1500 volts and a peak current of 60 amperes.

b. An 8 microsecond rise time by 20 microsecond pulse width waveform with a peak voltage of 1000 volts and a peak current of 500 amperes.

1.2.6 Power Line Conditioners

Furnish a power line conditioner for the security console CCTV equipment. The power line conditioner shall be of the ferro resonant design, with no moving parts and no tap switching, while electrically isolating the secondary from the power line side. The power line conditioner shall be sized for 125 percent of the actual connected kVA load. Characteristics of the power line conditioner shall be as follows:

Page 100: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 3

a. At 85 percent load, the output voltage shall not deviate by more than plus or minus 1 percent of nominal when the input voltage fluctuates between minus 20 percent to plus 10 percent of nominal.

b. During load changes of zero to full load, the output voltage shall not deviate by more than plus or minus 3 percent of nominal. Full correction of load switching disturbances shall be accomplished within 5 cycles, and 95 percent correction shall be accomplished within 2 cycles of the onset of the disturbance.

c. Total harmonic distortion shall not exceed 3.5 percent at full load. 1.2.7 Video and Control Signal Data Transmission Media

Provide a video data and control signal transmission system as specified. 1.2.8 Electrical Requirements

Electrically powered IDS equipment shall operate on 120 or 240 volt 60 Hz AC sources as shown. Equipment shall be able to tolerate variations in the voltage source of plus or minus 10 percent, and variations in the line frequency of plus or minus 2 percent with no degradation of performance.

1.2.9 Uninterruptible Power Supply

All electrical and electronic equipment in the console shall be powered from an UPS provided as specified. The UPS shall be sized to provide at least 6 hours battery back-up in the event of primary failure. Batteries shall be sealed non-outgassing type.

1.3 SUBMITTAL OF TECHNICAL DATA AND COMPUTER SOFTWARE

All items of computer software and technical data (including technical data which relates to computer software), which are specifically identified in this specification shall be delivered strictly in accordance with the CONTRACT CLAUSES, SPECIAL CONTRACT REQUIREMENTS, Section 01 33 00 SUBMITTAL PROCEDURES, and in accordance with the Contract Data Requirements List (CDRL), DD Form 1423, which is attached to and thereby made a part of this contract. All data delivered shall be identified by reference to the particular specification paragraph against which it is furnished. If the CCTV system is being installed in conjunction with an ESS, the CCTV Technical Data Packages shall be submitted as part of the Technical Data Packages for Section 28 20 01.00 10 ELECTRONIC SECURITY SYSTEM.

1.3.1 Group I Technical Data Package 1.3.1.1 System Drawings

The data package shall include the following:

a. System block diagram.

b. CCTV system console installation, block diagrams, and wiring diagrams.

c. Security center CCTV equipment installation, interconnection with console equipment, block diagrams and wiring diagrams.

d. Remote control/monitoring station installation, interconnection to security center including block diagrams and wiring diagrams.

e. Camera wiring and installation drawings. f. Interconnection with video signal transmission system, block diagrams and wiring diagrams. g. Surge protection device installation.

Page 101: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 4

h. Details of interconnection with ESS.

1.3.1.2 Manufacturers' Data

The data package shall include manufacturers' data for all materials and equipment and security center equipment provided under this specification.

1.3.1.3 System Description and Analyses

The data package shall include complete system descriptions, analyses and calculations used in sizing the equipment required by these specifications. Descriptions and calculations shall show how the equipment will operate as a system to meet the performance of this specification. The data package shall include the following:

a. Switcher matrix size.

b. Camera call-up response time.

c. System start up and shutdown operations.

d. Switcher programming instructions.

e. Switcher operating and maintenance instructions.

f. Manuals for CCTV equipment.

g. Data entry forms.

1.3.1.4 Software Data

The data package shall consist of descriptions of the operation and capability of system and application software as specified.

1.3.1.5 Overall System Reliability Calculations

The data package shall include all manufacturer's reliability data and calculations required to show compliance with the specified reliability. The calculations shall be based on all CCTV equipment associated with one camera circuit and the console CCTV equipment, excluding the data transmission media (DTM).

1.3.1.6 Certifications

All specified manufacturer's certifications shall be included with the data package. 1.3.1.7 Key Control Plan

Provide a key control plan as specified in Section 28 20 01.00 10 ELECTRONIC SECURITY SYSTEM. 1.3.4.1 Operation and Maintenance Manuals

A draft copy of the operation and maintenance manuals shall be delivered to the District prior to beginning the performance verification test for use during site testing.

Page 102: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 5

1.3.4.2 Training Documentation

Lesson plans and training manuals for the training phases, including type of training to be provided with a sample training report, and a list of reference material, shall be delivered for approval.

1.3.4.3 Data Entry

Enter all data needed to make the system operational. Deliver the data to the District on data entry forms, utilizing data from the contract documents, Contractor's field surveys, and all other pertinent information in the Contractor's possession required for complete installation of the data base. Identify and request from the District, any additional data needed to provide a complete and operational CCTV system. The completed forms shall be delivered to the District for review and approval at least 90 days prior to the Contractor's scheduled need date.

1.3.5.1 Functional Design Manual

The functional design manual shall identify the operational requirements for the system and explain the theory of operation, design philosophy, and specific functions. A description of hardware and software functions, interfaces, and requirements shall be included for all system operating modes.

1.3.5.2 Hardware Manual

A manual shall describe all equipment furnished, including:

a. General hardware description and specifications.

b. Installation and checkout procedures.

c. Equipment electrical schematics and layout drawings.

d. System schematics and wiring lists.

e. System setup procedures.

f. Manufacturer's repair parts list indicating sources of supply.

g. Interface definition. 1.3.5.3 Software Manual

The software manual shall describe the functions of all software, and shall include all other information necessary to enable proper loading, testing and operation, including:

a. Definitions of terms and functions.

b. Procedures for system boot-up.

c. Description of using the programs.

d. Description of required operational sequences.

e. Directory of all disk files.

f. Description of all communications protocols, including data formats, command characters,

and a sample of each type of data transfer.

Page 103: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 6

1.3.5.4 Operator's Manual

The operator's manual shall explain all procedures and instructions for operation of the system including:

a. Video switcher.

b. Video multiplexer.

c. Cameras and video recording equipment.

d. Use of the software.

e. Operator commands.

f. System start-up and shut-down procedures.

g. Recovery and restart procedures.

1.4 QUALITY ASSURANCE 1.4.1 Predelivery Testing

Perform predelivery testing, and adjustment of the completed CCTV system. Provide all personnel, equipment, instrumentation, and supplies necessary to perform all testing. Written notification of planned testing shall be given to the District at least 14 days prior to the test and in no case shall notice be given until after the Contractor has received written approval of the specific test procedures.

1.4.2 Test Procedures and Reports

Test procedures shall explain, in detail, step-by-step actions and expected results demonstrating compliance with the requirements of the specification. Test reports shall be used to document results of the tests. Reports shall be delivered to the District within 7 days after completion of each test.

1.4.3 As-Built Drawings

Maintain a separate set of drawings, elementary diagrams and wiring diagrams of the CCTV system to be used for as-built drawings. This set shall be accurately kept up to date with all changes and additions to the CCTV system and shall be delivered to the District with the final endurance test report. In addition to being complete and accurate, this set of drawings shall be kept neat and shall not be used for installation purposes. Upon completion of the final system drawings, a representative of the District will review the final system work with the Contractor. If the final system work is not complete, the Contractor will be so advised and shall complete the work as required. Final drawings submitted with the endurance test report shall be finished drawings on mylar or vellum, and as AutoCAD or files on CD-ROM.

1.5 ENVIRONMENTAL REQUIREMENTS 1.5.1 Field Equipment

The cameras and all other field equipment shall be rated for continuous operation under ambient environmental conditions of 14 to 120 degrees F using no auxiliary heating or cooling equipment. Equipment shall be rated for continuous operation under the ambient environmental temperature, humidity, wind loading, ice loading, and vibration conditions specified or encountered for the installed location.

Page 104: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 7

1.5.2 Security Center Equipment

Security Center and remote control/monitoring station equipment shall, unless designated otherwise, be rated for continuous operation under ambient environmental conditions of 60 to 85 degrees F and a relative humidity of 20 to 80 percent.

1.6 MAINTENANCE AND SERVICE 1.6.1 General Requirements

Provide all required services, material and equipment necessary for the work to maintain the entire CCTV system in an operational state as specified for a period of 2 years after completion of the endurance test. Impacts on facility operations shall be minimized when performing scheduled adjustments or other unscheduled work.

1.6.2 Description of Work

The adjustment and repair of the CCTV system includes all computer equipment, software updates, signal transmission equipment, and video equipment. Provide the manufacturer's required adjustments and all other work necessary.

1.6.3 Personnel

Service personnel shall be qualified to accomplish all work promptly and satisfactorily. The Government shall be advised in writing of the name of the designated service representative, and of any changes in personnel.

1.6.4 Schedule of Work

Perform two inspections at 6-month intervals or less. This work shall be performed during regular working hours, Monday through Friday, excluding legal holidays. These inspections shall include:

a. Visual checks and operational tests of the CPU, switcher, peripheral equipment, interface

panels, recording devices, monitors, video equipment electrical and mechanical controls, and a check of the picture quality from each camera.

b. Run system software and correct all diagnosed problems.

c. Resolve any previous outstanding problems. 1.6.5 Emergency Service

The District will initiate service calls when the CCTV system is not functioning properly. Qualified personnel shall be available to provide service to the complete CCTV system. The District shall be furnished with a telephone number where the service supervisor can be reached at all times. Service personnel shall be at the site within 24 hours after receiving a request for service. The CCTV system shall be restored to proper operating condition within 3 calendar days after receiving a request for service.

1.6.6 Operation

Performance of scheduled adjustments and repair shall verify operation of the CCTV system as demonstrated by the applicable portions of the performance verification test.

Page 105: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 8

1.6.7 Records and Logs

Keep records and logs of each task, and organize cumulative records for each major component, and for the complete system chronologically. Maintain a continuous log for all devices containing calibration, repair, and programming data. Keep logs available for inspection on site, demonstrating that planned and systematic adjustments and repairs have been accomplished for the CCTV system.

1.6.8 Work Requests

Separately record each service call request, as received. The form shall include the serial number identifying the component involved, its location, date and time the call was received, nature of trouble, names of the service personnel assigned to the task, instructions describing what has to be done, the amount and nature of the materials to be used, the time and date work started, and the time and date of completion. Deliver a record of the work performed within 5 days after work is completed.

1.6.9 System Modifications

Make any recommendations for system modification in writing to the District. No system modifications, including operating parameters and control settings, will be made without prior approval of the Government. Incorporate any modifications made to the systems into the operations and maintenance manuals, and other documentation affected.

1.6.10 Software

Submit all software updates to the District for approval. Upon District approval, updates shall be accomplished in a timely manner, fully coordinated with the CCTV system operators, operation in the system verified, and incorporated into the operations and maintenance manuals, and software documentation. There shall be at least one scheduled update near the end of the first year's warranty period, at which time the Contractor shall install and validate the latest released version of the manufacturer's software.

1.6.11 Maintenance Manual

The maintenance manual shall describe maintenance for all equipment including inspection, periodic preventive maintenance, fault diagnosis, and repair or replacement of defective components.

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

Provide system hardware and software components produced by manufacturers regularly engaged in the production of CCTV equipment. Units of the same type of equipment shall be products of a single manufacturer. All material and equipment shall be new and currently in production. Each major component of equipment shall have the manufacturer's name and address, and the model and serial number in a conspicuous place. Equipment located at the security center or a remote control/monitoring station shall be rack mounted as shown. Both Television and Computing devices shall comply with 47 CFR 15, Subpart B. Refer to appendix “A” of this section for a list of approved products.

2.1.1 Fungus Treatment

System components located in fungus growth inductive environments shall be completely treated for fungus resistance. Treating materials containing a mercury bearing fungicide shall not be used. Treating materials shall not increase the flammability of the component or surface being treated. Treating materials shall not cause skin irritation or other injury to personnel handling it during

Page 106: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 9

fabrication, transportation, operation, maintenance, or during the use of the finished items when used for the purpose intended.

2.1.2 Soldering

All soldering shall be done in accordance with standard industry practices. 2.2 ENCLOSURES

Provide metallic enclosures as needed for equipment not housed in racks or supplied with a housing. The enclosures shall be as specified or shown.

2.2.1 Interior

Enclosures to house equipment in an interior environment shall meet the requirements of NEMA 250 Type 12.

2.2.2 Exposed-to-Weather

Enclosures to house equipment in an outdoor environment shall meet the requirements of NEMA 250 Type 4X.

2.2.3 Corrosion-Resistant

Enclosures to house equipment in a corrosive environment shall meet the requirements of NEMA 250 Type 4X.

2.3 TAMPER PROVISIONS

Enclosures, cabinets, housings (other than environmental camera housings), boxes, raceways, conduits, and fittings of every description having hinged doors or removable covers, and which contain any part of the CCTV equipment or power supplies, shall be provided with cover operated, corrosion-resistant tamper switches, arranged to initiate an alarm signal when the door or cover is moved. Tamper switches shall be mechanically mounted to maximize the defeat time when enclosure covers are opened or removed. The enclosure and the tamper switch shall function together to not allow direct line of sight to any internal components and tampering with the switch or the circuits before the switch activates. Tamper switches shall be inaccessible until the switch is activated; have mounting hardware concealed so that the location of the switch cannot be observed from the exterior of the enclosure; be connected to circuits which are under electrical supervision at all times, irrespective of the protection mode in which the circuit is operating; shall be spring-loaded and held in the closed position by the door cover; and shall be wired so that they break the circuit when the door or cover is disturbed. Tamper switches on the doors which must be opened to make routine maintenance adjustments to the system and to service the power supplies shall be push/pull-set, automatic reset type.

2.3.1 Enclosure Covers

Covers of pull and junction boxes provided to facilitate installation of the system need not be provided with tamper switches if they contain no splices or connections, but shall be protected by tack welding or brazing the covers in place. Zinc labels shall be affixed to such boxes indicating they contain no connections. These labels shall not indicate that the box is part of the security system.

2.3.2 Conduit-Enclosure Connections

All conduit-enclosure connections shall be protected by tack welding or brazing the conduit to the enclosure. Tack welding or brazing shall be done in addition to standard conduit-enclosure connection methods as described in NFPA 70.

Page 107: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 10

2.5 SYSTEM INTEGRATION

When the CCTV system is installed in conjunction with an ESS, the CCTV system shall be interfaced to the ESS and shall provide automatic, alarm actuated call-up of the camera associated with the alarm zone. Equipment shall be supplied with all adapters, terminators, cables, main frames, card cages, power supplies, rack mounts, and appurtenances as needed.

2.6 SOLID STATE CAMERAS 2.6.1 High Resolution Monochrome Camera

All electronic components and circuits shall be solid state. Signal-to-noise ratio shall not be less than 46 dB unweighted. The camera shall exhibit no geometric distortion. The lens mount shall be a C or CS-mount, and the camera shall have a back focus adjustment. The camera shall operate from minus 4 to 131 degrees F without auxiliary heating or cooling, and with no change in picture quality or resolution. The camera shall operate on 60 Hz AC power, and shall be capable of operating at a voltage of 24 Volts.

2.6.1.1 Solid State Image Array

The camera shall have a solid state imager, and the picture produced by the camera shall be free of blemishes. The camera shall provide not less than 550 lines of horizontal resolution, and resolution shall not vary over the life of the camera.

2.6.1.2 Sensitivity

Camera shall provide full video output with the infrared cut-off filter installed, without camera automatic gain, and a scene reflectance of 75 percent using an f/1.2 lens giving a camera faceplate illumination at 2850K of 0.1 footcandle.

2.6.1.3 Camera Synchronization

The camera shall have an input for external sync, and shall automatically switch over to internal sync if external sync is not present. The camera shall also have the capability of synchronization by line-locking to the AC power 60 Hz line frequency at the zero crossing point, and shall provide not less than plus or minus 90 degrees of vertical phase adjustment.

2.6.1.4 Connectors

Cameras with lenses having auto iris, manual iris, or zoom and focus functions shall be supplied with connectors and wiring as needed to operate the lens functions. Video signal output connector shall be a BNC. Cameras with integral fiber optic video transmitters shall have straight-tip bayonet type fiber optic video output connectors. A connector shall be provided for external sync input.

2.6.1.5 Automatic Circuits

The camera shall have circuitry to establish a reference black level, and an automatic white clipper and automatic gain control circuits.

2.6.2 Low Light Monochrome Camera

All electronic components and circuits shall be solid state. Signal-to-noise ratio shall not be less than 42 dB unweighted. The camera shall exhibit no geometric distortion. The lens mount shall be a C-mount, and the camera shall have a back focus adjustment. The camera shall operate from 14 to 131

Page 108: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 11

degrees F without auxiliary heating or cooling, and with no change in picture quality or resolution. The camera shall operate on 60 Hz AC power, and shall be capable or operating at a voltage of 24 Volts.

2.6.2.1 Solid State Imager

The camera shall have a solid state imager, and the picture produced by the camera shall be free of blemishes. The camera shall provide not less than 550 lines of horizontal resolution, and resolution shall not vary over the life of the camera.

2.6.2.2 Sensitivity

Camera shall provide full video output with the infrared cut-off filter installed, and a scene reflectivity of 90 percent using an f/1.2 lens giving a camera faceplate illumination of 0.002 footcandle minimum.

2.6.2.3 Camera Synchronization

The camera shall have an input for external sync, and shall automatically switch over to internal sync if external sync is not present. The camera shall also have the capability of synchronization by line-locking to the AC power 60 Hz line frequency at the zero crossing point, and shall provide not less than plus or minus 90 degrees of vertical phase adjustment.

2.6.2.4 Connectors

Cameras with lenses having auto iris, manual iris, or zoom and focus functions shall be supplied with connectors and wiring as needed to operate the lens functions. Video signal output connector shall be a BNC. Cameras with integral fiber optic video transmitters shall have straight-tip bayonet type fiber optic video output connectors. A connector shall be provided for external sync input.

2.6.2.5 Automatic Circuits

The camera shall have circuitry to establish a reference black level, and an automatic white clipper and automatic gain control circuits.

2.6.3 High Resolution Color Camera

All electronic components and circuits shall be solid state. Signal-to-noise ratio shall not be less than 50 dB unweighted. The camera shall exhibit no geometric distortion. The lens mount shall be a C-mount, and the camera shall have a back focus adjustment. The camera shall operate from 14 to 131 degrees F without auxiliary heating or cooling, and with no change in picture quality or resolution. The camera shall operate on 60 Hz AC power, and shall be capable of operating at a voltage of 24 Volts.

2.6.3.1 Solid State Image Array

The camera shall have a solid state imaging array, and the picture produced by the camera shall be free of blemishes. The camera shall provide not less than 460 lines of horizontal resolution, and resolution shall not vary over the life of the camera. The imager shall have at least 768 horizontal x 494 vertical active picture elements.

2.6.3.2 Sensitivity

Camera shall provide full video output with the infrared cut-off filter installed, without camera automatic gain, and a scene reflectivity of 75 percent using an f/1.2 lens given a camera faceplate illumination at 3200K of 0.2 footcandle minimum.

2.6.3.3 Camera Synchronization

Page 109: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 12

The camera shall have an input for external sync, and shall automatically switch over to internal sync if external sync is not present. The camera shall also have the capability of synchronization by line-locking to the AC power line frequency at the zero crossing point, and shall provide not less than plus or minus 90 degrees of vertical phase adjustment.

2.6.3.4 Connectors

Cameras with lenses having auto iris, manual iris, or zoom and focus functions shall be supplied with connectors and wiring as needed to operate the lens functions. Video signal output connector shall be a BNC. Cameras with integral fiber optic video transmitters shall have straight-tip bayonet type fiber optic video output connectors. A connector shall be provided for external sync input.

2.6.3.5 Automatic Circuits

The camera shall have circuitry for through the lens (TTL) white balancing, fixed white balancing, and automatic gain control.

2.6.4 DOME CAMERAS 2.6.4.1 Interior Dome Camera System

An interior dome camera system shall be provided with integral camera installed and integrated into the dome housing. The camera shall meet the requirements of Paragraph: High Resolution Monochrome Camera or Paragraph: High Resolution Color Camera as shown or specified. The dome housing shall be nominally 6 inches and shall be furnished in a pendant mount or ceiling mount as shown. The lower dome shall be tinted acrylic and shall have a light attenuation factor of not more that 1 f-stop. The dome system shall withstand temperature ranges from minus 22 to 122 degrees F over a humidity range of 0 to 90 percent, non-condensing.

2.6.4.2 Exterior Dome Camera System

An exterior dome camera system shall be provided with integral camera installed and integrated into the dome housing. The camera shall have a minimum horizontal resolution of 425 lines (color) or 500 lines (monochrome). The dome housing shall be nominally 6 inches and shall be furnished in a NEMA 4 pendant mount, pole mount, ceiling mount, surface mount, or corner mount as shown. The housing shall be constructed to be dust and water tight, and fully operational in 100 percent condensing humidity. The housing shall be equipped with supplementary camera mounting blocks or supports as needed to position the specified camera and lens to maintain the proper optical centerline. All electrical and signal connections required for operation of the camera and lens shall be supplied. The housing shall protect the internal drives, positioners, and camera from the environment encountered for camera operation. The lower dome shall be tinted acrylic and shall have a light attenuation factor of not more that 1 f-stop. An integral heater, sized to maintain the lower dome above the dew point, shall be part of the camera system. The dome system shall withstand temperature ranges from minus 40 to 122 degrees F over a humidity range of 0 to 90 percent, non-condensing.

2.7 CAMERA LENSES

Camera lenses shall be all glass with coated optics. The lens mount shall be a C or CS mount, compatible with the cameras selected. The lens shall be supplied with the camera, and shall have a maximum f-stop opening of f/1.2 or the maximum available for the focal length specified. The lens shall be equipped with an auto-iris mechanism unless otherwise specified. Lenses having auto iris, manual iris, or zoom and focus functions shall be supplied with connectors, wiring, receiver/drivers, and controls as needed to operate the lens functions. Lenses shall have sufficient circle of illumination to cover the image sensor evenly. Lenses shall not be used on a camera with an image format larger than the lens is designed to cover. Lens focal lengths shall be as shown or specified in the manufacturer's lens selection tables.

Page 110: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 13

2.8 CAMERA HOUSINGS AND MOUNTS The camera and lens shall be enclosed in a tamper resistant housing as specified below. Any ancillary housing mounting hardware needed to install the housing at the camera location shall be provided as part of the housing. The camera and lens contained in a camera housing shall be installed on a camera support as shown. Any ancillary mounting hardware needed to install the support and to install the camera on the support shall be provided as part of the support. The camera support shall be capable of supporting the equipment to be mounted on it including wind and ice loading normally encountered at the site.

2.8.1 Environmentally Sealed Camera Housing

The housing shall be designed to provide a condensation free environment for camera operation. The housing shall be constructed to be dust and water tight, and fully operational in 100 percent condensing humidity. The housing shall be purged of atmospheric air and pressurized with dry nitrogen, shall be equipped with a fill valve, overpressure valve, and shall have a humidity indicator visible from the exterior. Housing shall not have a leak rate greater than 2 psi at sea level within a 90 day period. The housing shall be equipped with supplementary camera mounting blocks or supports as needed to position the specified camera and lens to maintain the proper optical centerline. All electrical and signal connections required for operation of the camera and lens shall be supplied. The housing shall provide the environment needed for camera operation, and shall keep the viewing window free of fog, snow, and ice. The housing shall be equipped with a sunshield, and both the housing and the sunshield shall be white. A mounting bracket which can be adjusted to center the weight of the housing and camera assembly shall be provided as part of the housing.

2.8.2 Indoor Camera Housing

The housing shall be designed to provide a tamper resistant enclosure for indoor camera operation. The housing shall be equipped with tamper proof latches, and shall be supplied with the proper mounting brackets for the specified camera and lens. The housing and appurtenances shall be a color that does not conflict with the building interior color scheme.

2.8.3 Interior Mount

The camera mount shall be suitable for either wall or ceiling mounting and shall have an adjustable head for mounting the camera. The wall mount and head shall be constructed of aluminum or steel with a corrosion-resistant finish. The head shall be adjustable for 360 degrees of pan, and not less than 90 degrees of tilt.

2.8.4 Low Profile Ceiling Mount

A tamperproof ceiling housing shall be provided for the camera. The housing shall be low profile and shall be suitable for replacement of 2 by 2 foot ceiling tiles. The housing shall be equipped with a camera mounting bracket and shall allow a 360 degree viewing setup.

2.8.5 Interior Dome Housing

Interior dome housing shall be provided for each camera as shown. The dome housing shall be a pendant mount, pole mount, ceiling mount, surface mount, or corner mount as shown. The lower dome shall be black opaque acrylic and shall have a light attenuation factor of not more that 1 f-stop.

2.8.6 Exterior Dome Housing

Exterior dome housing shall be provided for each camera as shown. The dome housing shall be a pendant mount, pole mount, ceiling mount, surface mount, or corner mount as shown. The housing shall be constructed to be dust and water tight, and fully operational in 100 percent condensing

Page 111: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 14

humidity. The housing shall be purged of atmospheric air and pressurized with dry nitrogen, shall be equipped with a fill valve and overpressure valve, and shall have a pressure indicator visible from the exterior. The housing shall be equipped with supplementary camera mounting blocks or supports as needed to position the specified camera and lens to maintain the proper optical centerline. All electrical and signal connections required for operation of the camera and lens shall be supplied. The housing shall provide the environment needed for camera operation. The lower dome shall be black opaque acrylic and shall have a light attenuation factor of not more that 1 f-stop.

2.8.7 Exterior Wall Mount

The exterior camera wall mount shall have an adjustable head for mounting the camera. The wall mount and head shall be constructed of aluminum, stainless steel, or steel with a corrosion-resistant finish. The head shall be adjustable for not less than plus and minus 90 degrees of pan, and not less than plus and minus 45 degrees of tilt. If the bracket is to be used in conjunction with a pan/tilt, the bracket shall be supplied without the adjustable mounting head, and shall have a bolt hole pattern to match the base.

2.9 VIDEO MONITOR 2.9.2 Color Video Monitor

All electronic components and circuits shall be solid state except for the picture tube. The monitor shall have a stabilized high voltage power supply, and regulated low voltage power supplies. The monitor shall have automatic frequency control (AFC) and horizontal resolution not less than 280 lines at the center of the picture tube. The video input shall allow switchable loop-through or 75 ohm termination. The monitor shall have circuitry for automatic degaussing. The monitor shall operate on 60 Hz AC power, and shall be capable of operating at a voltage of 24 Volts.

2.9.3 Picture Tube

The monitor shall have a 15 inch picture LED flat screen diagonally. 2.9.4 Configuration

Monitors shall not interfere with each other when rack mounted or operated next to each other. 2.9.5 Controls

Front panel controls shall be provided for power on/off, horizontal hold, vertical hold, contrast, and brightness. The monitor shall have switchable DC restoration.

2.9.6 Connectors for Video Monitor

Video signal input and output shall be by BNC connectors. 2.10 VIDEO SWITCHER

The switcher shall conform to CEA 170 specifications, and shall be a vertical interval switcher. Electronic components, subassemblies, and circuits of the switcher shall be solid state. The switcher shall be microprocessor based and software programmable. The switcher shall be a modular system that shall allow for expansion or modification of inputs, outputs, alarm interfaces, and secondary control stations by addition of the appropriate modules. Switcher components shall operate on 120 volts 60 Hz AC power. The switcher central processor unit shall be capable of being interfaced to a master security computer for integrated operation and control. The video switcher central processing unit (CPU) shall have the capability of accepting time from a master clock supplied in ASCII format through a TIA-232-F input. All components, modules, cables, power supplies, software, and other items

Page 112: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 15

needed for a complete and operable CCTV switching system shall be provided. Switcher equipment shall be rack mounted unless otherwise specified. Rack mount hardware shall be supplied to mount the switcher components in a standard 19 inch rack as described in CEA-310-E.

2.10.1 Switcher Software

The switcher shall be software programmable, and the software shall be supplied as part of the switcher. The software shall be installed in the switcher CPU, and shall be configured as required by the site design. Changes or alterations of features under software control shall be accomplished through software programming without changes in hardware or system configuration. The switcher shall retain the current program for at least 6 hours in the event of power loss, and shall not require reprogramming in order to restart the system.

2.10.2 Switcher Matrix

The switcher shall be a programmable crosspoint switcher capable of switching any video input to any video output. The switcher to be installed at the site shall be configured to switch cameras on drawings to monitors, and shall have an expansion capability of not less than 20 percent.

2.10.3 Switcher Modular Expansion

The switcher shall be expandable in minimum increments as specified below. 2.10.3.1 Input Module

Hardware expansion modules shall be provided to expand the switcher matrix configuration in increments of at least 8 camera inputs.

2.10.3.2 Output Module

Hardware expansion modules shall be provided to expand the switcher matrix configuration in increments of at least 4 video outputs.

2.10.7 Accessory Control Equipment

The video switcher shall be equipped with signal distribution units, preposition cards, expansion units, cables, software or any other equipment needed to ensure that the CCTV system is complete and fully operational.

2.10.8 Connectors for Video Switcher

Video signal input and output shall be by BNC connectors. 2.10.9 Video Annotation

Video annotation equipment shall be provided for the video switcher. The annotation shall be alphanumeric and programmable for each video source. Annotation to be generated shall include, but not be limited to: individual video source identification number, time (hour, minute, second) in a 24 hour format, date (month, day, year), and a unique, user-defined title with at least 8 characters. The annotation shall be inserted onto the source video so that both shall appear on a monitor or recording. The lines of annotation shall be movable for horizontal and vertical placement on the video picture. The annotation shall be automatically adjusted for date. Programmed annotation information shall be retained in memory for at least 4 hours in the event of power loss.

Page 113: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 16

2.11 VIDEO MULTIPLEXER The video multiplexer shall be a multi-channel record and playback system with the capability of monochrome and color real time multi-screen viewing. Electronic components, sub assemblies, and circuits of the multiplexer shall be solid state. The multiplexer, using time division multiplexing, shall permit up to 16 camera inputs to be recorded simultaneously on a single video cassette recorder (VCR). All 16 camera inputs shall be capable of being viewed on a video monitor either live or recorded. The multiplexer shall allow for viewing of either live video or input from the VCR (Simplex Operation). The inputs shall be capable of simultaneous viewing on the monitor or full screen individually and in other multi-screen modes such as 2x2, 3x3, 4x4 or other configurations. The viewing format shall also permit 2x dynamic zoom capability, full screen. The multiplexer shall be compatible with EIA/NTSC video cameras and standard or super VHS VCRs. External camera synchronization shall not be required for proper operation of the video multiplexer. Control of all functions of the multiplexer shall be provided either by a full function keyboard or by pushbutton selection with on-screen menu driven set-up. The multiplexer shall retain the current program for at east 6 hours in the event of power loss.

2.12 DIGITAL VIDEO RECORDER (DVR) 2.12.1 Recording and Playback

The DVR shall be capable of recording for 168 hours or more on a single cassette tape with at least 6 user selectable time-lapse record speeds. The DVR shall have a contact closure alarm signal input which shall automatically switch the recorder into standard play, record mode when an alarm is initiated. The recorder shall reach stabilized record speed in 1 second or less. The DVR shall put a cue mark on the tape at the beginning of an alarm event recording. The alarm event record time shall be selectable for up to 3 minutes of automatic recording as a minimum. A record-lock feature shall be provided which shall protect the DVR against tampering with the tape transport controls and power control once recording has started. Playback functions shall include: alarm search, fast forward search, fast rewind search, rewind/fast forward, play, slow motion or step field/frame, and pause/still.

2.12.2 Connectors for DVR

Video signal input and output shall be by BNC connectors. The recorder shall provide connectors for alarm trigger signal input and output.

2.13 VIDEO SIGNAL EQUIPMENT

The following video signal equipment shall conform to CEA 170. Electrically powered equipment shall operate on 120 Volts 60 Hz AC power. All video signal inputs and outputs shall be by BNC connectors.

2.13.1 Ground Loop Corrector

The ground loop corrector shall eliminate the measured ground loop interference (common mode voltage) in wireline or coaxial video transmission lines. The ground loop corrector shall pass the full transmitted video bandwidth with no signal attenuation or loss. Clamping ground loop correctors shall be capable of rejecting at least an 8 volt peak-to-peak 60 Hz common mode signal. Ground isolation transformers shall be capable of rejecting at least a 10 volt peak-to-peak 60 Hz common mode signal. Ground isolation amplifiers shall be capable of rejecting at least a 30 volt peak-to-peak 60 Hz common mode signal. Differential ground loop correctors shall be capable of rejecting at least a 100 volt peak-to-peak 60 Hz common mode signal.

2.13.2 Video Loss/Presence Detector

The video loss/presence detector shall monitor video transmission lines for presence of the video signal. The detector shall annunciate an alarm when the video signal drops below a pre-set threshold level. A threshold level adjustment shall be provided for each video channel, and the threshold level

Page 114: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 17

shall be continuously adjustable through a lockable front panel control. A front panel reset control shall be provided for each video channel, which shall reset the detector after an alarm. The video loss alarm shall be annunciated through a front panel LED and a contact closure as a minimum. Video input shall be loop-through, and the video shall be unaffected when the detector is turned off. The detector shall not attenuate or reduce the level of the video signal passing through it.

2.13.3 Video Equalizing Amplifier

The video equalizing amplifier shall be designed to correct loss in video signal level and high frequency attenuation caused by long distance video signal transmission over wireline DTM. The amplifier shall have independent signal gain and equalization controls. The amplifier shall be capable of equalizing at least 3000 feet of RG-11/U coaxial cable conforming to paragraph CCTV Equipment Video Signal Wiring. The amplifier shall provide a minimum of plus or minus 6 dB of video gain and 12 dB of high frequency compensation. At least one video output shall be provided for each video input. Bandwidth shall be 10 MHz or greater, and frequency response to 8 MHz shall be plus or minus 1 dB or less. Hum and noise shall be 50 dB below 1 volt peak-to-peak or better. Video inputs shall be 75 ohm unbalanced, terminating, differential grounded. Video outputs shall be 75 ohm, differential, source terminated, 1 volt peak-to-peak. Output isolation shall be 40 dB or greater at 5 MHz.

2.13.4 Video Distribution Amplifier

The video distribution amplifier shall be designed to distribute a single, 75 ohm, unbalanced video input signal to a minimum of 4, 75 ohm, source terminated video outputs. The distribution amplifier shall have not less than plus or minus 3 dB of gain adjustment for the video output. Output isolation shall be 40 dB or greater at 5 MHz. Bandwidth shall be 10 MHz or greater, and frequency response to 8 MHz shall be plus or minus 0.5 dB or less. Hum and noise shall be 55 dB below 1 volt peak-to-peak or better.

2.13.5 Master Video Sync Generator

The master video sync generator shall generate horizontal drive, vertical drive, blanking, and sync signals as a minimum, with at least one 75 ohm output provided for each signal. The master oscillator crystal shall be pre-aged, and temperature stabilized, ovenized or temperature compensated. The sync generator shall have a composite video input and shall lock to the incoming video signal. If no video is present at the video input, the sync generator shall switch to internal crystal control. Not less than 2.5 microseconds advance and 2.5 microseconds delay of horizontal phase shall be provided. Vertical blanking width adjustment shall be provided. Vertical blanking width adjustment shall have a minimum selection range of 19, 20, and 21 lines.

2.13.6 Video Sync Distribution Amplifier

The sync distribution amplifier shall be a regenerative amplifier designed to distribute a sync signal input to not less than 6, 75 ohm outputs. Output level shall remain constant and shall not be affected by input level variations. Output isolation shall be greater than 35 dB at 5 MHz. A high impedance loop through shall be provided in addition to the 6 outputs. The distribution amplifier shall have continuously variable delay range of at least 250 nanoseconds to 2.2 microseconds. The delay shall be adjustable through a front panel control.

2.14 CCTV CAMERA POLES 2.14.1 Straight Camera Pole

The camera mounting pole shall be a hinged straight aluminum pole with counterweights and mounting base. All fittings shall be stainless steel. The camera mounting plate shall locate the camera 180 inches vertically from the base, and 20 inches horizontally from the centerline of the pole to the centerline of the camera. The camera mount shall be adjustable with a minimum of 40 degrees pan away from the pole and 6 degrees pan toward the pole, and plus and minus 90 degrees of tilt. The

Page 115: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 18

pole shall have an internal wiring harness that routes video, sync, and power between the pole base and the camera mount. The wiring harness shall be compatible with the camera to be mounted on the pole and the video DTM. Surge protection shall be provided at the pole between the wiring harness, and the incoming electronic signal lines and AC power line. The pole shall have a weatherproof, AC power service outlet that is surge protected and has a ground fault interruption device. Separate circuit breakers shall be provided for camera AC power and service outlet AC power.

2.15 ACCESSORIES

Standard 19 inch electronic rack cabinets conforming to CEA-310-E shall be provided for the CCTV system at the security center and remote control/monitoring sites as shown.

2.16 WIRE AND CABLE

All wire and cable components shall be able to withstand the environment the wire or cable is installed in for a minimum of 20 years.

2.16.1 CCTV Equipment Video Signal Wiring

The coaxial cable shall have a characteristic impedance of 75 ohms plus or minus 3 ohms. RG 59/U coaxial signal cable shall have shielding which provides a minimum of 95 percent coverage, a solid copper center conductor of not less than 23 AWG, polyethylene insulation, and a black non-contaminating polyvinylchloride (PVC) jacket. RG 6/U coaxial cable shall have shielding which provides a minimum of 95 percent coverage, with center conductor of 18 AWG or larger polyethylene insulation, and a black non-contaminating polyvinylchloride (PVC) jacket.

2.16.2 Low Voltage Control Wiring

Twisted pair low voltage control wiring to be used above ground or as direct burial cable shall be provided as described. Plenum or riser cables shall be IEEE C2 CL2P certified.

2.16.3 Digital Data Interconnection Wiring

Interconnecting cables carrying digital data between equipment located at the security center or at a secondary control/monitoring site shall be not less than 20 AWG and shall be stranded copper wire for each conductor. The cable or each individual conductor within the cable shall have a shield that provides 100 percent coverage. Cables with a single overall shield shall have a tinned copper shield drain wire. Plenum or riser cables shall be IEEE C2 CL2P certified.

2.17 PREDELIVERY TESTING 2.17.1 General

Assemble the test CCTV system as specified, and perform tests to demonstrate that the performance of the system complies with the contract requirements in accordance with the approved predelivery test procedures. The tests shall take place during regular daytime working hours on weekdays. Model numbers of equipment tested shall be identical to those to be delivered to the site. Original copies of all data produced during predelivery testing, including results of each test procedure, shall be delivered to the District at the conclusion of predelivery testing prior to District approval of the test. The test report shall be arranged so that all commands, stimuli, and responses are correlated to allow logical interpretation.

2.17.2 Test Setup

Provide the equipment needed for the test setup and shall configure it to provide alarm actuated camera call-up and alarm recording as required to emulate the installed system. The test setup shall

Page 116: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 19

consist of at least 4 complete camera circuits. The alarm signal input to the CCTV test setup shall be by the same method that is used in the installed system. The video switcher shall be capable of switching any camera to any monitor and any combination of cameras to any combination of monitors. The minimum test setup shall include:

a. Four video cameras and lenses, including dome cameras if required for the installed system.

b. Three video monitors.

c. Video recorder if it is required for the installed system.

d. Video switcher including video input modules, video output modules, and control and applications software.

e. Video multiplexer, if required for the installed system.

f. Alarm input panel if required for the installed system.

h. Any ancillary equipment associated with a camera circuit such as equalizing amplifiers, video loss/presence detectors, terminators, ground loop correctors, surge protectors or other in-line video devices.

i. Cabling for all components. PART 3 EXECUTION

3.1 INSTALLATION

Install all system components, including District furnished equipment, and appurtenances in accordance with the manufacturer's instructions, IEEE C2 and as shown, and furnish all necessary connectors, terminators, interconnections, services, and adjustments required for a complete and operable system. DTM shall not be pulled into conduits or placed in raceways, compartments, outlet boxes, junction boxes, or similar fittings with other building wiring. All other electrical work shall be as specified in the above sections including grounding to preclude ground loops, noise, and surges from adversely affecting system operation.

3.1.2 Enclosure Penetrations

All enclosure penetrations shall be from the bottom unless the system design requires penetrations from other directions. Penetrations of interior enclosures involving transitions of conduit from interior to exterior, and all penetrations on exterior enclosures shall be sealed with rubber silicone sealant to preclude the entry of water. The conduit riser shall terminate in a hot-dipped galvanized metal cable terminator. The terminator shall be filled with an approved sealant as recommended by the cable manufacturer and in such a manner that the cable is not damaged.

3.1.3 Cold Galvanizing

All field welds and brazing on factory galvanized boxes, enclosures, and conduits shall be coated with a cold galvanized paint containing at least 95 percent zinc by weight.

3.1.4 Interconnection of Console Video Equipment

Connect signal paths between video equipment with RG-6/U coaxial cable. Cables shall be as short as practicable for each signal path without causing strain at the connectors. Rack mounted equipment on slide mounts shall have cables of sufficient length to allow full extension of the slide rails from the rack.

Page 117: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 20

3.1.5 Cameras

Install the cameras with the proper focal length lens as indicated for each zone; connect power and signal lines to the camera; set cameras with fixed iris lenses to the proper f-stop to give full video level; aim camera to give field of view as needed to cover the alarm zone; aim fixed mount cameras installed outdoors facing the rising or setting sun sufficiently below the horizon to preclude the camera looking directly at the sun; focus the lens to give a sharp picture over the entire field of view; and synchronize all cameras so the picture does not roll on the monitor when cameras are selected. Dome cameras shall have all preset positions defined and installed.

3.1.6 Monitors

Install the monitors as shown and specified; connect all signal inputs and outputs as shown and specified; terminate video input signals as required; and connect the monitor to AC power.

3.1.7 Switcher

Install the switcher as shown and according to manufacturer's instructions; connect all subassemblies as specified by the manufacturer and as shown; connect video signal inputs and outputs as shown and specified; terminate video inputs as required; connect alarm signal inputs and outputs as shown and specified; connect control signal inputs and outputs for ancillary equipment or secondary control/monitoring sites as specified by the manufacturer and as shown; connect the switcher CPU and switcher subassemblies to AC power; load all software as specified and required for an operational CCTV system configured for the site requirements, including data bases, operational parameters, and system, command, and application programs; provide the original and 2 backup copies for all accepted software upon successful completion of the endurance test; and program the video annotation for each camera.

3.1.8 Video Recording Equipment

Install the video recording equipment as shown and as specified by the manufacturer; connect video signal inputs and outputs as shown and specified; connect alarm signal inputs and outputs as shown and specified; and connect video recording equipment to AC power.

3.1.9 Video Signal Equipment

Install the video signal equipment as specified by the manufacturer and as shown; connect video or signal inputs and outputs as shown and specified; terminate video inputs as required; connect alarm signal inputs and outputs as required; connect control signal inputs and outputs as required; and connect electrically powered equipment to AC power.

3.1.10 Camera Housings, Mounts, and Poles

Install the camera housings and mounts as specified by the manufacturer and as shown, provide mounting hardware sized appropriately to secure each camera, housing and mount with maximum wind and ice loading encountered at the site; provide a foundation for each camera pole as specified and shown; provide a ground rod for each camera pole and connect the camera pole to the ground rod as specified; provide electrical and signal transmission cabling to the mount location as specified; connect signal lines and AC power to mount interfaces; and connect pole wiring harness to camera.

3.2 SYSTEM STARTUP

Do not apply power to the CCTV system until the following items have been completed:

a. CCTV system equipment items and DTM have been set up in accordance with manufacturer's instructions.

Page 118: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 21

b. A visual inspection of the CCTV system has been conducted to ensure that defective

equipment items have not been installed and that there are no loose connections.

c. System wiring has been tested and verified as correctly connected as indicated.

d. All system grounding and transient protection systems have been verified as properly installed and connected as indicated.

e. Power supplies to be connected to the CCTV system have been verified as the correct voltage, phasing, and frequency as indicated.

f. Satisfaction of the above requirements shall not relieve the Contractor of responsibility for incorrect installation, defective equipment items, or collateral damage as a result of Contractor work/equipment.

3.3 SUPPLEMENTAL CONTRACTOR QUALITY CONTROL

The following requirements supplement the Contractor quality control requirements specified elsewhere in the contract. Provide the services of technical representatives who are thoroughly familiar with all components and installation procedures of the installed IDS; and are approved by the Contracting Officer. These representatives will be present on the job site during the preparatory and initial phases of quality control to provide technical assistance. These representatives shall also be available on an as needed basis to provide assistance with follow-up phases of quality control. These technical representatives shall participate in the testing and validation of the system and shall provide certification that their respective system portions meet its contractual requirements.

3.4 TRAINING 3.4.1 General

Conduct training courses for designated personnel in the maintenance and operation of the CCTV system as specified. If the CCTV system is being installed in conjunction with an ESS, the CCTV training shall be concurrent and part of the ESS training. The training shall be oriented to the specific system being installed under this contract. Training manuals shall be delivered for each trainee with two additional manuals delivered for archiving at the project site. The manuals shall include an agenda, defined objectives for each lesson, and a detailed description of the subject matter for each lesson. The Contractor is responsible for furnishing all audio-visual equipment and all other training materials and supplies. Where the Contractor presents portions of the course through the use of audio-visual material, copies of the audio-visual materials shall be delivered to the District, either as a part of the printed training manuals or on the same media as that used during the training sessions. A training day is 8 hours of instruction, including two 15 minute breaks and excluding lunchtime, Monday through Friday, during the daytime shift in effect at the facility. For guidance in planning the required instruction, assume the attendees will have a high school education or equivalent. Approval of the planned training schedule shall be obtained from the District at least 30 days prior to the training.

3.4.2 Operator's Training

The course shall be taught at the project site for five consecutive training days during or after the Contractor's field testing. No part of the training given during this course will be counted toward completion of the performance verification test. The course shall consist of classroom instruction, hands-on training, instruction on the specific hardware configuration of the installed system, and specific instructions for operating the installed system. The course shall demonstrate system start up, system operation, system shutdown, system recovery after a failure, the specific hardware configuration, and operation of the system and its software. The students should have no unanswered questions regarding operation of the installed CCTV system. Prepare and insert additional training

Page 119: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 22

material in the training manuals when the need for additional material becomes apparent during instruction. Prepare a written report after the completion of the course. List in the report the times, dates, attendees and material covered at each training session. Describe the skill level of each student at the end of this course. Submit the report before the end of the performance verification test. The course shall include:

a. General CCTV hardware, installed system architecture and configuration.

b. Functional operation of the installed system and software.

c. Operator commands.

d. Alarm interfaces.

e. Alarm reporting.

f. Fault diagnostics and correction.

g. General system maintenance.

h. Replacement of failed components and integration of replacement components into the

operating CCTV system. 3.5 SITE TESTING 3.5.1 General

Provide all personnel, equipment, instrumentation, and supplies necessary to perform all site testing. The District will witness all performance verification and endurance testing. Written permission shall be obtained from the District before proceeding with the next phase of testing. Original copies of all data produced during performance verification and endurance testing shall be turned over to the District at the conclusion of each phase of testing prior to District approval of the test.

3.5.2 Contractor's Field Testing

Calibrate and test all equipment, verify DTM operation, place the integrated system in service, and test the integrated system. Ground rods installed by the Contractor shall be tested as specified in IEEE 142. Deliver a report describing results of functional tests, diagnostics, and calibrations including written certification to the District that the installed complete system has been calibrated, tested, and is ready to begin performance verification testing. The report shall also include a copy of the approved performance verification test procedure. In addition, make a master video tape recording showing typical day and night views of each camera in the system and shall deliver the tape with the report. Note any objects in the field of view that might produce highlights that could cause camera blinding. Note any objects in the field of view or anomalies in the terrain which may cause blind spots. Note if a camera cannot be aimed to cover the zone and exclude the rising or setting sun from the picture. Note night assessment capabilities and whether lights or vehicle headlights cause blooming or picture degradation. If any of the above conditions or other conditions exist that cause picture degradation or interfere with the camera field of view, inform the Contracting Officer. The tape shall be recorded using the video recorder installed as part of the CCTV system. If a recorder is not part of the CCTV system, provide the tape in Video Home System (VHS) format. Provide the District with the original tape as part of the documentation of the system and shall submit a letter certifying that the CCTV system is ready for performance verification testing. The field testing shall, as a minimum, include:

a. Verification that the video transmission system and any signal or control cabling have been

installed, tested, and approved as specified.

Page 120: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 23

b. When the system includes remote control/monitoring stations or remote switch panels, verification that the remote devices are functional, communicate with the security center, and perform all functions as specified.

c. Verification that the switcher is fully functional and that the switcher software has been programmed as needed for the site configuration.

d. Verification that switcher software is functioning correctly. All software functions shall be exercised.

e. Verification that video multiplexers are functioning correctly.

f. Operation of all electrical and mechanical switcher controls and verification that the control performs the designed function.

g. Verification that all video sources and video outputs provide a full bandwidth signal that complies with CEA 170 at all video inputs.

h. Verification that all video signals are terminated properly.

i. Verification that all cameras are aimed and focused properly. Conduct a walk test of the area covered by each camera to verify the field of view.

j. Verification that cameras facing the direction of rising or setting sun are aimed sufficiently below the horizon so that the camera does not view the sun directly.

k. If vehicles are used in proximity of the assessment areas, verification of night assessment capabilities and determination if headlights cause blooming or picture degradation.

l. Verification that all cameras are synchronized and that the picture does not roll when cameras are switched.

o. When dome camera mounts are used in the system, verify that all preset positions are correct and that the dome also operates correctly in a manual control mode.

Deliver a report describing results of functional tests, diagnostics, and calibrations including written certification to the District that the installed complete system has been calibrated, tested, and is ready to begin performance verification testing. The report shall also include a copy of the approved performance verification test procedure.

3.5.3 Performance Verification Test

Demonstrate that the completed CCTV system complies with the contract requirements. Using approved test procedures, all physical and functional requirements of the project shall be demonstrated and shown. The performance verification test, as specified, shall not be started until receipt by the Contractor of written permission from the District, based on the Contractor's written report. This shall include certification of successful completion of Contractor Field Testing as specified in paragraph "Contractor's Field Testing," and upon successful completion of training as specified. If the CCTV system is being installed in conjunction with an ESS, the CCTV performance verification test shall be run simultaneously with the ESS performance verification test. The District may terminate testing at any time when the system fails to perform as specified. Upon termination of testing by the District or by the Contractor, commence an assessment period as described for Endurance Testing Phase II. Upon successful completion of the performance verification test, deliver test reports and other documentation as specified to the District prior to commencing the endurance test.

Page 121: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 24

3.5.4 Endurance Test

a. Demonstrate the specified requirements of the completed system. The endurance test shall be conducted in phases as specified. The endurance test shall not be started until the District notifies the Contractor, in writing, that the performance verification test is satisfactorily completed, training as specified has been completed, and correction of all outstanding deficiencies has been satisfactorily completed. If the CCTV system is being installed in conjunction with an ESS, the CCTV performance verification test shall be run simultaneously with the ESS performance verification test. Provide one operator to operate the system 24 hours per day, including weekends and holidays, during Phase I and Phase III endurance testing, in addition to any government personnel that may be made available. The District may terminate testing at any time the system fails to perform as specified. Upon termination of testing by the District or by the Contractor, commence an assessment period as described for Phase II. During the last day of the test verify the operation of each camera. Upon successful completion of the endurance test, deliver test reports and other documentation as specified to the District prior to acceptance of the system.

b. Phase I (Testing): The test shall be conducted 24 hours per day for 15 consecutive calendar days, including holidays, and the system shall operate as specified. Make no repairs during this phase of testing unless authorized by the District in writing. If the system experiences no failures during Phase I testing, the Contractor may proceed directly to Phase III testing after receipt of written permission from the District.

c. Phase II (Assessment): After the conclusion of Phase I, identify all failures, determine causes of all failures, repair all failures, and deliver a written report to the District. The report shall explain in detail the nature of each failure, corrective action taken, results of tests performed, and shall recommend the point at which testing should be resumed. After delivering the written report, convene a test review meeting at the job site to present the results and recommendations to the District. The meeting shall not be scheduled earlier than 5 business days after receipt of the report by the District. As a part of this test review meeting, demonstrate that all failures have been corrected by performing appropriate portions of the performance verification test. Based on the Contractor's report and the test review meeting, the District will determine the restart date, or may require that Phase I be repeated. If the retest is completed without any failures, the Contractor may proceed directly to Phase III testing after receipt of written permission from the District.

d. Phase III (Testing): The test shall be conducted 24 hours per day for 15 consecutive calendar days, including holidays, and the system shall operate as specified. Make no repairs during this phase of testing unless authorized by the District in writing.

e. Phase IV (Assessment): After the conclusion of Phase III, identify all failures, determine causes of all failures, repair all failures, and deliver a written report to the District. The report shall explain in detail the nature of each failure, corrective action taken, results of tests performed, and shall recommend the point at which testing should be resumed. After delivering the written report, convene a test review meeting at the job site to present the results and recommendations to the District. The meeting shall not be scheduled earlier than 5 business days after receipt of the report by the District. As a part of this test review meeting, demonstrate that all failures have been corrected by repeating appropriate portions of the performance verification test. Based on the Contractor's report and the test review meeting, the District will determine the restart date, and may require that Phase III be repeated. Do not commence any required retesting until after receipt of written notification by District. After the conclusion of any retesting which the District may require, the Phase IV assessment shall be repeated as if Phase III had just been completed.

APPENDIX A

Page 122: INVITATION TO BID 14-MC-2187 ADDENDUM NUMBER THREE …purchasingts.dpsk12.org/bids/openbids/14-MC-2187 Addendum 3.pdf · 270553 Identification for Communications Systems, 270800 Commissioning

100% Construction Documents June 25, 2014

DENVER PUBLIC SCHOOLS Florence Crittenton MEP Engineering Project No. 13464

CLOSED CIRCUIT TELEVISION SYSTEMS

28 23 23.00 10 - 25

CAMERAS

Manufacturer Part Number Description

Sony SNC-DH180 Interior 1.3MP Dome Camera w/IR

Sony SNC-DH160 Exterior 1.3MP Dome Camera w/IR

Sony SNC-DH260 Exterior 3MP Dome Camera w/IR

ACTi KCM-5211E Exterior 4MP D/N IR Box Camera

ACTi PMAX-1101 Housing Bracket

ACTi PMAX-0503 Pole Mount Adapter

Pelco PP451 Roof Top Sled “Gravity” Mount w/weight material

Pelco PP450 Parapet Mount

Sony UNI WMB3 Wall Mount

Sony UNI PMA1 Pole Mount Adapter

Sony UNIC MA1 Corner Mount Adapter

Rohn FRM238SP5 Gravity Sled

Rohn FRMPAD Gravity Sled Mat

Rohn FY253 Mast

DVR AND ACCESSORIES

Manufacturer Part Number Description

Video Insight IP License One IP camera license

Panasonic TC-L32U22 32” 1080P Monitor

Pelco PMCL-WM2A Tilt/swivel dual-arm wall mount

Peerless JMW2640D Monitor Mount

Peerless PLCK-UNL 32 “ LCD Adapter

Peerless PLCK-1 23” LCD Adapter

Panduit Panduit Orange 5e Patch Cords, sub* for length, 7’,10’,14’,20’

MinuteMan E1500RM2U 1500 VA UPS

YUASA NP7-12 7.2 Ah Replacement Battery

END OF SECTION


Recommended