+ All Categories
Home > Documents > ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM)...

ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM)...

Date post: 01-Apr-2015
Category:
Upload: yazmin-yelvington
View: 212 times
Download: 0 times
Share this document with a friend
Popular Tags:
25
ISEN 315 Spring 2011 Dr. Gary Gaukler
Transcript
Page 1: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

ISEN 315Spring 2011

Dr. Gary Gaukler

Page 2: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

1. Master production schedule2. Bill of material (BOM)3. Inventory availability4. Purchase orders outstanding5. Lead times

Effective use of dependent demand inventory models requires the following

Dependent Demand

Page 3: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

| | | | | | | |

1 2 3 4 5 6 7 8Time in weeks

F

2 weeks

3 weeks

1 week

A

2 weeks

1 weekD

E

2 weeks

D

G

1 week

1 week

2 weeks to produce

B

C

E

Start production of DMust have D and E completed here so

production can begin on B

Time-phased Product Structure

Page 4: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Lot Sizing For MRP Systems

Assumptions:• Consider only one item• Demand known and deterministic• Finite horizon• No shortages• No capacity constraints

Page 5: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Lot Sizing For MRP Systems

Problem formulation:

Page 6: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Lot Sizing: Silver-Meal Heuristic

In any given period, produce to cover demand in a future period as long as the average cost per period is reduced by doing so

Algorithm:1. Start in period 1. Calculate C(t): average per-period

cost if all units for next t periods produced in period 1.

2. Select lowest t such that C(t)<C(t+1): t*3. Produce enough in period 1 to cover t*4. Repeat, starting from period t*+1

Page 7: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Silver-Meal Example

Assume net requirements are 18, 30, 42, 5, 20Setup cost for production is $80Holding cost $2 per unit per period

Page 8: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.
Page 9: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Production Schedule Changes

• So far, the MRP examples we discussed were static• In reality, we need to update our production plans

as time passes, thus MRP plans become dynamic• The widest-used technique involves “rolling

horizons”:

Page 10: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Production Schedule Changes

• Using rolling horizons can lead to fluctuations in the production schedule

• As we include more and updated information (e.g., demand forecasts) in each period, our production schedule can change

• This is called “system nervousness”

Page 11: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Production Schedule Changes

• Results of fluctuations:– Planning for capacity utilization becomes difficult

• Fluctuations become larger when we re-run MRP more often

• But: re-running MRP is our only way of incorporating more information!

Page 12: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Shortcomings of MRP

Page 13: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Shortcomings of MRP

Page 14: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

MRP II

Page 15: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Goal of Lean production: Supply the customer with their exact wants

when the customer wants it without waste

Method: JIT JIT is a philosophy of continuous and forced

problem solving JIT: continual improvement, pull system

Just-in-time and Lean Production

Page 16: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Waste is anything that does not add value from the customer point of view

Storage, inspection, delay, waiting in queues, and defective products do not add value and are 100% waste

Waste Reduction

Page 17: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Faster delivery, reduced work-in-process, and faster throughput all reduce waste

Reduced waste reduces room for errors emphasizing quality

Reduced inventory releases assets for other, productive purposes

Waste Reduction

Page 18: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

JIT systems require managers to reduce variability

Variability is any deviation from the optimum process

Less variability = less waste Inventory hides variability

Variability Reduction

Page 19: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Inventory level

Process downtimeScrap

Setup time

Late deliveries

Quality problems

Reduce Variability

Page 20: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Inventory level

Scrap

Setup time

Late deliveries

Quality problems

Process downtime

Reduce Variability

Page 21: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

A pull system uses signals to request production and delivery from upstream stations

Upstream stations only produce when signaled

System is used within the immediate production process and with suppliers

Enabling JIT: Pull System

Page 22: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Experiment

Page 23: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

200 –

100 –

Inve

ntor

y

Time

Q2 When average order size = 100

average inventory is 50

Q1 When average order size = 200

average inventory is 100

Reduce Lot Sizes

Page 24: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

High setup costs encourage large lot sizes Reducing setup costs reduces lot size and

reduces average inventory Setup time can be reduced through preparation

prior to shutdown and changeover

Reduce Setup Costs

Page 25: ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.

Reduced space and inventory With reduced space, inventory must be in

very small lots Units are always moving because there is

no storage

Implications for Manufacturing


Recommended