+ All Categories
Home > Documents > J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO...

J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO...

Date post: 27-Apr-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
19
J-POWER’s CCT Activities Hiroto Shimizu Senior Advisor, International Business Management Department 2013. 9.6
Transcript
Page 1: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

J-POWER’s CCT Activities

Hiroto Shimizu Senior Advisor, International Business Management Department

2013. 9.6

Page 2: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

3E + S Philosophy*

*) Basis of Energy Policy

Page 3: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Who is J‐POWER?

Wholesale Electric Power FacilitiesHydro power (59 stations,  8,565,500 kW)Thermal power (7 stations,  8,412,000 kW)Geothermal (1 station, 15,000 kW)Substation  (frequency converter, switching station)Transmission lines (2,407.7 km)Hydro power (under construction, preparation)Nuclear (under construction)Transmission lines (under construction)

New businesses (Capacity)Wind power (18 station, 352,860 kW)Others (8 stations, 877,300 kW)Research Institutes

(As of March 31, 2012)

020,000

40,00060,000

80,000

Tokyo

Kansai

Chubu

Kyushu

Tohoku

J‐POWER

Chugoku

Hokuriku

Shikoku

Hokkaido

Okinawa

HydroThermalNuclear

Handbook of Electric Industries (FY2011)

[MW]

• Established as Government‐owned Electric Power Utility in 1952.

• Privatization through IPO in 2004• Japan’s biggest wholesale power 

company.

Page 4: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

4

Takasago1# 250MW(1968)2# 250MW(1969)

IsogoNew 1# 600MW(2002)New 2# 600MW(2009)Tachibanawan

1# 1,050MW(2000)2# 1,050MW(2000)

Takehara1# 250MW(1967)2# 350MW(1995)3# 700MW(1983)

Ishikawa1# 156MW(1986)2# 156MW(1987)

Matsushima1# 500MW(1981)2# 500MW(1981)

Green : Sub-Critical< 22.1MPa

Blue : Super Critical≧22.1MPa, ≦566℃

Red : Ultra Super Critical≧22.1MPa, >566℃

Matsuura1# 1,000MW(1990)2# 1,000MW(1997)

J‐POWER’s Coal Fired Power Stations

Page 5: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

5

• Rated Output: 2×1,050MW• COD: #1 July 2000

#2 Dec 2000• Steam Condition: 25MPa, 600/610deg.C

The Biggest USC Power Unit in Japan

The First Unit achieves 600/610 deg.C in the world

• Emission Regulation SOx : 50 ppm

Wet Limestone-GypsumNOx : 45 ppm

Two Stage Combustion,Low NOx Burner, SCR

Dust : 10 mg/m3NLow Low Temp ESP, FGD

Tachibanawan Power Station

Page 6: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

6

• Rated Output: 1×600MW• COD: New #1 Apr 2002• Steam Condition: 25MPa, 600/610deg.C

Cleanest Emission of Coal Fired Power Plant in the World

Isogo Power Station New #1

• Emission Regulation SOx : 20 ppm

ReACT (Dry Type FGD)NOx : 20 ppm

Two Stage Combustion,Low NOx Burner, SCR

Dust : 10 mg/m3NESP, ReACT

Page 7: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

7

New #2

Isogo Power Station New #2

• Rated Output: 1×600MW• COD: New #2 July 2009• Steam Condition: 25MPa, 600/620deg.C

• Emission Regulation SOx : 10 ppm

ReACTNOx : 13 ppm

Two Stage Combustion,Low NOx Burner, SCR

Dust : 5 mg/m3NESP, ReACT

Higher Efficiency and Cleaner Emission than New #1

Page 8: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

8

610600

593

566

538

510

482

450

25.024.524.1

18.616.6

12.5

108.65.95.8

4.1

400

450

500

550

600

650

700

1945 1955 1965 1975 1985 1995 20050

10

20

30

40

50St

eam

Tem

pera

ture

(℃

)

Stea

m P

ress

ure

(MPa

)

Year

steam pressure

steam temperature

Tachibanawan #1&2(25.0,600/ 610)

Matsuura #2(24.1,593/ 593)

620

2010

Isogo New#2(25.0,600/ 620)

Isogo New#1(25.0,600/ 610)

Development of Ultra Super Critical Steam Condition

Page 9: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

(Source : Ministry of Economic, Trade and Industory Japan, 2012.2)

CCT Roadmap of Japan

30

35

40

45

50

55

60

1960 1970 1980 1990 2000 2010 2020 2030

IGCC demo. w/ 1,200℃ GT

IGCC w/ 1,300℃ GT

IGCC  w/ 1,500℃GT

IGCC w/ 1,700℃ GT

A‐USC(Steam temp.: 700℃,pressure : 35MPa)

USC(Stem temp. : >593℃, pressure : 22.1MPa)

SC(Steam temp.: <566℃,Pressure : 22.1MPa)

Sub‐SC(Steam pressure : <22.1MPa)

Efficiency (net %, H

HV)

IGFC

Combined cycle

Single cycle

Triple combined cycle

IGCC , IGFC and A‐USC are promising CCTs in medium and long‐term.  

Page 10: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Natural Gas Combined Cycle

Fuel Cell

:Coal

:LNG

Note : Net Efficiency HHV basis、J-POWER’s R&D activities shown in red

1300℃ GT 1500℃ GT

1300℃ IGCC43 ~ 44%

1500℃ IGCC46 ~ 48%

MCFCSOFC

> 55%

IGFCIntegrated Coal Gasification Fuel Cell Combined Cycle

Coal Gasification

1700℃ GT

1700℃ IGCC50%~

▲13% CO2 ▲25%~ CO2

Pulverized Coal Firing

USC(Ultra-SC)

41%

SC(Super Critical)

38%

A-USC(Advanced USC)

46%~ @700℃

▲17% CO2

▲11% CO2

Note

(High Temperature FC)

Sub-C(Sub Critical)

34 ~ 36%

Major KeyTechnology Development

Page 11: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

1) CO2 capture (physical absorption) - suitable for higher pressure* 2) Survey of innovative CO2 capture technology

1) CO2 capture from coal gas (chemical absorption)2) Coal type diversification (high ash fusion temp. coal) 3) Research for trace elements behavior

1) Development of oxygen-blown entrained-flow gasifier 2) Establishment of gas cleanup technology

EAGLE (coal Energy Application for Gas, Liquid, and Electricity)* In collaboration with NEDO funded by METI

Establishment the technology of

EAGLE system

STEP1: Development of EAGLE gasifier 1995 - 2006FY

STEP3: For Next Generation IGCC (+CCS) 2010 - 2013FY

STEP2: Multiple Utilization and Coal Diversification 2007 - 2009FY

Overview of the EAGLE Project

Page 12: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

N2

O2

GComp GT

N2

G

(not installed)

ST

HRSG

Coal

Gasifier Syngas Cooler

Char Filter

CharSlag

Air

Air FeedCompressor Rectifying

ColumnAir

Gas Turbine

Incinerator

Air Separation Unit

Waste HeatRecovery Boiler

WaterScrubber

MDEAAbsorber

GGH

Fine Desulfurizer

MDEAStripper Limestone

Scrubber

Gypsum

Stack

Coal GasificationCold Gas Cleanup

WaterScrubber

PhysicalCO2 Capture

ChemicalCO2 Capture

Flow Diagram of the EAGLE Pilot Plant

SourShift

SweetShift

Page 13: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

CO2 Capture unit(Chemical)

Coal gasification unit

Gas clean-up unit

Air separation unit

13

Bird’s-eye View of EAGLE Pilot Plant Facilities

GT

CO2 Capture Unit(Physical)

Page 14: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Scale-Up Step for Commercialization

Oxygen-blown IGCC/CCS commercial plant(300‐600MW class)

EAGLE Project (J-POWER)Coal Feed Rate : 150 t/dTest Run : StepⅠ’02~’06, StepⅡ ‘07~’09, StepⅢ ‘10~’13 Objectives : Pilot test of Oxygen-blown Gasification and

Carbon Capture Technology

Osaki CoolGen Project (OCG)

Coal Feed Rate : 1,180 t/d (Output 166MW class)

Commissioning : March 2017

Objectives : Large scale IGCC test of Oxygen blown

Gasification and Carbon Capture Technology

J-POWER Wakamatsu

EnerGia Osaki P/S

Page 15: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

年   度 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

EnvironmentalImpact Assessment

Optimization Research & Study

[Phase1]  IGCC

TestOperation

[Phase2]IGCC with CO2 Capture

Test Operation

Design, Manufacturing and Construction

[Phase3]IGFC with CO2Capture

Test Operation

Design, Manufacturing and Construction

Fiscal Year 2010 2011 2012 20192013 2021 20222015 20162014 2017 20202018

Schedule of Osaki CoolGen Project

▲2013/3/1  Groundbreaking

Design, Manufacturing and Construction

NEDO joint research projects

Page 16: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

OCG Project Plan

1st Step 2nd Step 3rd Step

IGCC demo IGCC+CO2 capture IGFC+CO2 capture

Coal

GTAC

N2O2

FC

ASU

CO2

Gasifier Clean-up

H2 rich gas

CO2 capture

CO H2

ST G

System Flows of each steps in OCG Large Demonstration Test Program

Page 17: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Limit of Efficiency Increase

○BAT PCF < 0.8kg-CO2/kWh○Next Gen. IGCC

≒ 0.7kg-CO2/kWh○IGFC

≒ 0.6 kg-CO2/kWh

Latest Discussion

Ex.) USA EPA’s NSPS= 1 lb-CO2/kWh≒ 0.45kg-CO2/kWh

This criterion is approximately equivalent to the performance of NGCC

Responding for Global Warming Issue -Limit of Efficiency Increase-

Page 18: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Pre-combustion

EAGLE Project

Post-combustion

Matsushima Pilot. Test

Oxy-fuel combustion

Australia / JapanProject

COH2

H2O

CO+H2O->CO2+H2

CO2(30-40%) H2

O2

H2 rich gas

Air

Air

O2Air

(70-80%)CO2

Compression/Cooling

ASUGas

ifier

Flue gastreatment

Shiftreactor

CO2

separation Use of H2

Boi

ler

Boi

ler

Flue gastreatment

CO2(12-15%) H2O CO2

separation

Coal

Coal

Flue gastreatment

ASUCoal

CO2 storage

Compression/Cooling CO2 storage

Compression/Cooling CO2 storage

H2O Non-condensable gas

Flue gas recirculation

N2,H2O,O2

Category of CO2 Capture Technologies and J-POWER’s Experience

Page 19: J-POWER’s CCT Activities · Sub-C (Sub Critical) 34 ~ 36% Major KeyTechnology Development. 1) CO 2 capture (physical absorption) - suitable for higher pressure* ... Boiler Boiler

Thank you for your attention.

【Acknowledgment】EAGLE project has been managed by J-POWER in collaboration with NEDO,funded by METI


Recommended