+ All Categories
Home > Documents > Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

Date post: 02-Mar-2018
Category:
Upload: sofyan-shah
View: 227 times
Download: 0 times
Share this document with a friend

of 28

Transcript
  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    1/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-1 November 2010

    6 PROJECT DESCRIPTION: TEMPORARY JETTY DEVELOPMENT

    6.1 Introduction

    6.1.1 This Chapter describes the proposed temporary jetty development and includes

    descriptions of its on-shore and off-shore infrastructure components (see Section 6.2)

    and its phases, as follows:

    construction (see Section 6.3);

    operation (including maintenance) (see Section 6.4); and

    dismantling and restoration (see Section 6.5); or

    removal and site reinstatement, following construction, should a DCO for the

    Hinkley Point C Project not be granted (see Section 6.6).

    6.2 Temporary Jetty Infrastructure

    6.2.1 The proposed temporary jetty development would be located within the HEO application

    site shown in Figure 1-1, Volume 3 and would include the works shown inFigure 1-2,Volume 3.

    6.2.2 The jetty is proposed as a two-staged structure that can be constructed in a manner that

    accommodates the emerging transport demands of the Hinkley Point C Project, so that

    the first stage could operate alone without the second stage. However, it is expected

    that the two stages would in fact be built as one structure under one construction

    programme (i.e. stage two would be constructed once stage one is in place without any

    interval). This is reflected in the HEO application, which proposes the jetty development

    in its entirety. Accordingly, this ES describes the jetty development in its entirety.

    a) On-shore Infrastructure

    6.2.3 The following paragraphs describe the on-shore infrastructure associated with the jetty

    development.

    Rock Extraction Area

    6.2.4 A rock extraction area (see Figure 1-2, Volume 3 and Section B-B, Figure 6-1,

    Volume 3) would be created in the south-east corner of the application site to provide

    suitable granular fill material for construction of the development platform for the

    aggregates storage area (at a finished level of 20m AOD) and service road.

    6.2.5 At present, the land at the rock extraction site varies between approximately 16m and25m AOD. Following extraction, the rock extraction area would have a level of around

    14m AOD.

    6.2.6 A crushing plant would be used to process the extracted rock to the required

    specification. This plant would have tracks, screens, conveyors, a hopper / feeder unit,

    a crushing chamber and a power unit.

    Service Road

    6.2.7 The service road (see Figure 1-2, Volume 3 and Typical Section E-E, Figure 6-1,

    Volume 3) would be aligned approximately in an east-west direction between the

    aggregates storage area and the existing Hinkley Point Power Station Complex accessroad. The route would follow, in part, an existing farm track and would cross the Hinkley

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    2/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-2 November 2010

    Point C Drainage Ditch and a number of existing Public Rights of Way (PRoWs). It

    would also branch off to the north to provide a means for limited temporary access to the

    foreshore to facilitate construction of the initial jetty bridge spans using land based plant

    on the upper foreshore. In addition, the service road would be aligned in a north-south

    direction from the existing internal road to provide access to the rock extraction area

    (see Figure 1-2,Volume 3).

    6.2.8 The service road would be 8m wide to allow two-way vehicular access. Its surface

    would comprise 500mm of compacted granular fill. Approximately 5000m3 of

    compacted granular fill would be sourced from the rock extraction area and crushed to

    the correct size before being used for the service roads construction. Surface water

    run-off would fall into a soakaway running along each side the service road.

    6.2.9 Where the service road crosses the Hinkley Point C Drainage Ditch, it is proposed to

    locally culvert the ditch at the position of an existing crossing using a 1.25m diameter

    concrete pipe approximately 16m in length.

    6.2.10 Where the service road branches north to the foreshore, it would be constructed usingcompacted granular material, slope at 1 in 10 maximum and be 4.5m wide. It is

    anticipated that this would be a short-term, temporary structure, that would be built (c.1

    week), operated (c.3 months) and dismantled (c.1 week) within the overall programme

    for the jetty developments construction phase.

    Aggregates Storage Area

    6.2.11 The aggregates storage area (see Figure 1-2,Volume 3and Section A-A, Figure 6-1,

    Volume 3) would be positioned close to the landward limit of the jetty in order to

    minimise conveyor/pipeline distances required for materials transfer to the stockpiles (for

    stone and sand) and silos (for cement), and to facilitate future concreting operations for

    the Hinkley Point C Project.

    6.2.12 The aggregates storage area would comprise a concrete hardstanding area at a level of

    approximately 20m AOD, on which the storage facilities would be laid out. Eight

    uncovered aggregate stockpiles (including gravels) and six covered sand stockpiles

    (including sand and stone dust) would be situated beneath an inclined conveyor and

    tippers (that would extend from the jetty bridge) (see Figure 1-2,Volume 3and Section

    A-A, Figure 6-1, Volume 3). An inclined conveyor would rise from the jetty to an

    elevated horizontal position above the stockpiles and discharge into the individual

    stockpiles. The stockpiles would be separated by low walls / bunds to avoid cross

    contamination. The sand stockpiles, as noted above, would be enclosed within a canopy

    structure to control fugitive dust emissions.

    6.2.13 Cement would be stored in up to eight silos (see Figure 1-2,Volume 3and Section A-

    A, Figure 6-1, Volume 3). The silos would have a maximum height of 20m and a

    maximum diameter of 12m. The current design seeks to minimise height by assuming

    fluidised discharge and indicates that the silos themselves (c.15m) would have flat

    bottoms and tops, would be supported on the ground by structural steelwork (c.3m), and

    have a dust extractor (2m) on top (i.e. 20m high in total). The design also shows the

    silos being c.7m in diameter and closely spaced at 8m intervals (centre to centre). It is

    anticipated that the storage would include both ordinary Portland cement and cement

    replacement products (e.g. pulverized fuel ash (PFA)).

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    3/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-3 November 2010

    6.2.14 It is envisaged that two additional silos would be required to store the volumes of

    cement required during the peak concrete production periods during the construction of

    Hinkley Point C. These silos are expected to be larger (e.g. c.35m in height and c.12m

    in diameter) and would form part of EDF Energys application for a DCO for the Hinkley

    Point C Project. They are, therefore, not included in the HEO application and are not

    covered by this ES.

    6.2.15 The storage area would incorporate a drainage capture system which would comprise

    open drainage ditches and underground pipes, and feed into an oil water separator (see

    Figure 1-2,Volume 3). This system would discharge into a water management zone

    (WMZ; see Figure 1-2,Volume 3), which would regulate the flow into the Hinkley Point

    C Drainage Ditch (and, ultimately, Bridgwater Bay) to greenfield rates. The WMZ would

    cover an area of approximately 50m by 30m and would be approximately 3m deep.

    Contractors Site Compound

    6.2.16 To aid construction, a dedicated facility would be established adjacent to the aggregates

    storage area (see Figure 1-2,Volume 3). This facility would be sized to accommodateup to 60 construction workers and include temporary offices, mess facilities and a toilet

    block. These facilities are expected to take the form of Portakabin type structures.

    6.2.17 The facilities would be connected to services such as water supply, electrical power and

    sewage facilities, all of which would be temporary services for the duration of the

    construction works only. The water supply would comprise a bowser which would be

    filled from the existing water supply located in the area of the site entrance. The

    electrical supply would be provided by a diesel powered electrical generator. The

    generator and its fuel supply would be bunded to prevent the discharge of spillages into

    the adjacent watercourse (i.e. the Hinkley Point C Drainage Ditch). The sewage

    treatment facility would be an underground cess pool or similar, suitably sized for the

    number of staff and duration of the works. This would not be connected and, therefore,

    would not discharge into the adjacent watercourse.

    Fencing

    6.2.18 The aggregates storage area would have its own security fence (see Figure 1-2,

    Volume 3). Initially, this fence would comprise a 1.8m tall chain link fence. The line and

    level of the fence would follow the existing topography and surround the confines of the

    aggregates storage area. The fence would be moveable to allow potential re-positioning

    during the works. Once fixed in position, barbed wire protection would be added to the

    top of the fence, which would increase its height to approximately 2.14m.

    Soil Storage Areas

    6.2.19 Two soil storage areas (see Figure 1-2, Volume 3) would be created to store the topsoil

    and subsoil arising from the cleared sites for the aggregates storage area and the rock

    extraction area. The soil storage areas would be created on land situated to the east of

    the aggregates storage area and to the north of the service road.

    6.2.20 The western topsoil storage area would have an approximate 100m x 110m footprint

    and be 2m in height, while the eastern subsoil storage area would have an approximate

    100m x 50m footprint and 3m height (sized to accommodate the estimated volumes of

    soil to be stored).

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    4/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-4 November 2010

    b) Off-shore Infrastructure

    6.2.21 Plans and cross-sections of the jettys off-shore infrastructure are shown in Figure 6-2,

    Volume 3. Photomontages of the jettys off-shore infrastructure are provided in Figure

    6-3,Volume 3.

    Stage 1 Summary

    6.2.22 Stage 1 of the jettys development includes most of its main elements, including the jetty

    bridge, jetty head, berthing pocket, materials handling and conveyance equipment (see

    Figure 6-2,Volume 3).

    6.2.23 The jetty would extend into the Ministry of Defences (MoD) Lilstock Range Danger Area

    (D119), which includes a target area for military helicopter gunnery training. Ongoing

    discussions between EDF Energy and the MoD indicate that the target area would be

    moved westwards (i.e. away from the jetty) by the repositioning of its marker buoys.

    Jetty Bridge

    6.2.24 The jetty bridge would extend landwards from the jetty head to the aggregates storage

    area (see Figure 1-2, Volume 3). It would be approximately 490m long and 11.5m

    wide. Based on a review of maximum wave heights and a 5m wave on mean high water

    springs (MHWS), the bridges deck level is positioned so as to provide a minimum 1m

    air gap between the wave crest and the underside of deck beams. The deck level at its

    seaward end would be +16.5m CD (i.e. 16.5 metres above Chart Datum), which equates

    to 10.6m AOD (i.e. 10.6 metres above Ordnance Datum) (see Section C-C,Figure 6-2,

    Volume 3). From this point, the bridge would rise on a constant grade to meet the

    ground level on land which would be at +25.9m CD (i.e. 20m AOD) (see Section A-A,

    Figure 6-1,Volume 3).

    6.2.25 The bridge comprises a steel box truss structure supported on concrete cross-heads,

    which in turn are supported on raking steel tubular piles driven into the bedrock (see

    Section C-C, Figure 6-2, Volume 3). The box truss structure is of consistent form

    along the whole bridge up to the last span to the jetty head, where two smaller trusses

    accommodate the aggregates conveyor and cement pipeline. A typical crosshead

    would have two raking piles but at main bridge joints there would be four raking piles. A

    special cross head would be required at the location of the transfer hopper which would

    be larger than the other cross heads. The box truss structure provides stability to the

    bridge and the opportunity for large spans between the supporting cross heads of

    between 25 and 35m, thereby reducing the number of piles and the construction

    programme. The number of bridge piles in the arrangement is between 45 and 55depending on the final detailed design of the maximum possible span.

    6.2.26 The truss structure would incorporate a pipeline for transporting cement on its western

    side, a conveyor for aggregates on its eastern side and service ducts along its internal

    western face (see Section C-C,Figure 6-2,Volume 3). These, along with the open

    steel mesh flooring, would be supported on longitudinal steel deck beams which, in turn,

    would sit on transverse deck beams which are integral with the box truss structure.

    6.2.27 Maintenance walkways would be provided on either side of the pipeline and conveyor,

    with the primary walkway being centrally located. Hand-railing would be provided on

    both sides of the structure for the full length of the bridge. The central walkway, which is

    1.5m wide, would be used primarily for pedestrian access to the jetty head, as a central

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    5/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-5 November 2010

    maintenance (and emergency) route, and for the transportation of small equipment and

    materials by using, for example, a wide wheel based trolley.

    6.2.28 Where the jetty bridge connects to the land, it would be necessary to cross over the

    coastal footpath and, therefore, minor works may be required to ensure that all health

    and safety requirements would be met. For example, the footpath may need to be

    lowered slightly to create headroom of some 4m, and a protective cover may need to be

    constructed under the approach bridge to ensure that any spillage from above does not

    pose a risk to the public using the footpath. Cover could comprise either a self-

    supporting structure (e.g. an arch culvert tunnel) or a structure suspended from the

    longitudinal beams.

    6.2.29 The jetty bridge would not include a dedicated surface water drainage system. Rainfall

    run-off would drain directly into the sea.

    Jetty Head

    6.2.30 The jetty head would comprise a concrete head sized to accommodate 5000 deadweight tonnage (dwt) self-discharging aggregates vessels (e.g. barges) and 2500 to

    5000 dwt cement carriers (see Plan, Figure 6-2, Volume 3). This arrangement

    assumes that dredgers would discharge from port aft (i.e. from the back of the vessel on

    the left-hand side facing the bow).

    6.2.31 The size of the main jetty head is expected to be in the order of 60m by 15m, and is

    primarily based on providing a suitable berthing face and the requirement to

    accommodate cement handling equipment. It is anticipated that the jetty deck would be

    a 1.5m thick reinforced concrete slab supported by a combination of both vertical and

    raking piles (70-90 in total). Some piles would need to be anchored to withstand the

    berthing loads.

    6.2.32 The jetty head would have a fendered face to accommodate the berthing energy from

    the laden vessels over a range of tides. Emergency access ladders and associated

    equipment would be provided on the jetty deck.

    6.2.33 It is anticipated that the jetty head would have a mooring dolphin at its eastern and

    western ends. The dolphins would consist of a concrete cap supported by raking steel

    piles (although, at detailed design stage, consideration could be given to using

    monopole construction for the dolphins). The dolphins would be accessed via steel

    walkway bridges and would take the vessel mooring ropes.

    6.2.34 The berthing face of the jetty head would be parallel to the prevailing dominant east-west tidal current direction and generally parallel to the prevailing west through to south-

    west winds. This approach to the berths design should assist vessel manoeuvring

    because, for example, berthing with the ship heading into the prevailing conditions is

    preferable as it allows greater control of the vessel.

    6.2.35 The jetty head would not include a dedicated surface water drainage system. Rainfall

    run-off would drain directly into the sea.

    6.2.36 Some basic welfare facilities would be accommodated on the jetty head. A welfare

    cabin (see Plan, Figure 6-2,Volume 3) would include a self-contained portable toilet

    which would be regularly emptied (i.e. it would not discharge to sea or into a foul

    drainage connection).

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    6/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-6 November 2010

    Berthing Pocket

    6.2.37 It is considered necessary for the berth to operate with vessels afloat rather than on the

    seabed (i.e. not using a Not Always Afloat But Safely Aground (NAABSA) berth) due to

    the exposed nature of the berth. Aggregates vessels would operate within tidal access

    windows which are estimated to be 7 hours on spring tides (giving 5.5 hours for off-loading) and 7.5 hours on neap tides (giving 6 hours for off-loading). Cement carriers

    would need some 15 hours to off-load and would have to remain at the berth during low

    water; hence there would be a preference to deliver cement on neap tides, when there is

    least difference between high and low water levels.

    6.2.38 In order to increase the tidal window available for off-loading the cement carriers without

    going aground, a berthing pocket would be dredged seaward of the jetty heads berthing

    face (see Figure 6-2, Volume 3). The berthing pockets dimensions would be

    approximately 160m long by 27m wide by up to 3m deep. The sides of the berthing

    pocket would have slopes of 1 in 5. An additional depth allowance of up to 0.5m could

    be dredged due to over-dredging of the berthing pocket, making a total depth of up to

    3.5m. This is because it is assumed that the appointed dredging contractor would over-dredge by up to 0.5m to ensure that the required 3m depth is provided across the

    berthing pocket.

    6.2.39 Given the berthing pockets dimensions and side slopes, approximately 22,725m3 of

    dredged material is expected to arise from the berthing pocket. The maximum potential

    for over-dredging (i.e. by 0.5m) would add up to 2,160m3dredged material. Therefore,

    the total volume of dredged material that would arise from the berthing pocket would be

    approximately 24,885m3.

    Disposal of Dredged Material

    6.2.40 It is anticipated that the dredged material would be disposed of at an existing off-shore

    disposal site known as the Cardiff Grounds (see Plate 6.1and Chapter 7).

    6.2.41 The Cardiff Grounds is one of a number of existing off-shore disposal sites located

    within the Bristol Channel that are established to receive dredged material. For

    example, there are various sites off Cardiff, Swansea Bay Outer and Newport along the

    Welsh Coast, off Portishead and Avonmouth along the English coast, and in the middle

    of the Bristol Channel at a site known as the Merkur Buoy.

    6.2.42 It is anticipated that a degree of in-filling of the berth pocket could occur over time and,

    hence, maintenance dredging of the pocket could be required over the operational

    period for the jetty.

    Materials Handling and Conveyance Equipment

    6.2.43 The jetty development would incorporate materials handling and conveyance equipment

    for imported aggregates and cement.

    6.2.44 For importing aggregates, there would be a height adjustable aggregate receiving

    hopper to the east of the jetty head, which would be connected to an articulated

    conveyor arm (see Plan, Figure 6-2, Volume 3). The supporting structure for the

    hopper is provided by the jetty head and the adjacent mooring dolphin. This adjustable

    hopper is necessary to allow discharge from a self-discharging dredgers conveyor over

    various states of the tide. When not in use, it can be stowed at jetty deck level so as to

    prevent damage from wind and waves. Aggregate deposited in the receiving hopper

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    7/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-7 November 2010

    would be transported along an articulated conveyor arm and deposited into a transfer

    hopper on the jetty bridge and, thereafter, along the jetty bridge via the conveyor to

    stockpiles at the aggregates storage area.

    Plate 6.1 Location Map of the Cardiff Grounds Off-shore Disposal Site

    6.2.45 For importing cement, there would be a loading arm and cement receiver and booster

    on the jetty head (see Plan and Section D-D,Figure 6-2,Volume 3). The loading arm

    would be used to connect a vessels onboard cement discharge pipe to the jettys

    cement receiver and booster for the pipeline to shore.

    Aids to Navigation

    6.2.46 New navigation aids are proposed to provide safe navigation for vessels using and

    passing the jetty (see Plate 6.2; source Eagle Lyon Pope, 2009 (Ref 6.1)).

    6.2.47 It is expected that the western end of the jetty head and the eastern mooring dolphin

    would be each marked with two fixed green lights in a vertical line with a range of three

    nautical miles (nm). Since it is estimated that there could be some 15 days a year with

    fog, it is expected that there would be a fog signal to alert any passing small craft of the

    jetty position, especially as the jetty is proposed to extend into Bridgwater Bay.

    6.2.48 It is also expected that the 2m bathymetric contour is marked by lit green marker buoys

    situated to the west and east of the jetty to indicate the limits of the shallow water duringvessels approaching and departing manoeuvres (see Figure 1-2,Volume 3).

    Hinkley Point

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    8/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-8 November 2010

    Plate 6.2 Indicative Aids to Navigation for the Jetty

    Stage 2 Summary

    6.2.49 Stage 2 of the jettys development includes provision of a roadway along the jetty bridge

    and extension of the jetty head to accommodate a turning circle (for trucks) and

    deployment of a mobile crane (see Figure 6-2,Volume 3).

    Roadway along the Jetty Bridge

    6.2.50 It is anticipated that a roadway would be built along the jetty bridge as an independent

    structure adjacent to the truss bridge already in place, but supported by the existing

    concrete cross heads and raking piles (see Section C-C,Figure 6-2,Volume 3). The

    roads deck arrangement would comprise pre-cast concrete deck units on steel beams

    and provide a road that would be 5m wide.

    6.2.51 The roadway would not include a dedicated surface water drainage system. Rainfallrun-off would drain directly into the sea.

    Jetty Head Extension

    6.2.52 It is expected that the jetty head would be extended to accommodate a mobile crane at

    the jetty head in order to offload various construction materials and their transportation

    to the aggregates storage area (see Plan,Figure 6-2, Volume 3). The jetty head would

    be sized to allow vehicles to turn on the deck (and return along the jetty bridges

    roadway) and to facilitate the anticipated movement of a mobile crane at this location.

    6.2.53 The jetty head extension would not include a dedicated surface water drainage system.

    Rainfall run-off would drain directly into the sea.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    9/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-9 November 2010

    d) Lighting Strategy

    6.2.54 Appropriate lighting would be installed across the site during the jetty developments

    construction. The lighting strategy for the site would:

    provide a safe working environment;

    avoid over illumination;

    minimise upwards lighting;

    minimise light spill to neighbouring areas; and

    minimise energy consumption.

    6.2.55 On-shore lighting has been designed in accordance with British Standard (BS) 12464-2

    (2007) and the Bat Conservation Trust Bats and Lighting in the UK version 3 May

    2009. Hence temporary works areas, in particular those adjacent to the foreshore and

    bat corridors, would be provided with lamps with low UV content such as controllable

    LED lighting, metal halide lamps and high pressure sodium (white light) lamps;

    minimising the potential for light spill on bat corridors and flora and fauna associated

    with foreshore, as well as minimising the UV content.

    6.2.56 Off-shore lighting of the jetty needs to meet a number of regulations and standards. For

    example, the Docks Regulations 1988, which contain safety requirements for general

    dock work applicable to the jetty, require:

    average illumination of 20 lux in all working areas;

    average illumination of 5 lux in all means of access to working areas;

    lighting to be uniform; and

    lighting to be suitable for safe working (this may require the lighting to allow

    operators to detect spillage / leaks, read labels and correctly distinguish different

    colours).

    6.2.57 British Standard EN 12464-2 covers shipyards and docks, and would be applicable to

    the jetty development. It requires an illumination level of 20 lux and also has

    requirements for diversity (uniformity of lighting), glare and colour rendering.

    6.2.58 The planned operation of the jetty development would influence the lighting control

    scheme and associated light spill. Operation after dark is a certainty, particularly during

    the Hinkley Point C Projects peak construction and during shorter winter days, because

    delivery to the jetty would be when the tide and weather conditions permit. Providing the

    jetty and aggregates storage area can be operated safely, they would be lit so unloading

    and other operations can take place. If the jetty and stockpiles are not in use and it is

    dark, lighting could be switched off, although some minimal lighting for safe movementaround site might still be necessary.

    6.2.59 Navigational lighting would be on all of the time during the jettys operation.

    6.3 Jetty Construction

    6.3.1 The following paragraphs are intended to provide an indication of the construction

    methodology for the proposed temporary jetty development. This description is based

    upon the concept design and provides an indicative approach to construction subject to

    detailed design and the appointed contractors preferred approach. However,

    construction of this type of jetty would be substantially undertaken from sea (e.g. from

    jack-up platforms) and, to a lesser extent, from the foreshore (i.e. using land based plantthe first three or four spans). In addition, there would be a construction base located on-

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    10/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-10 November 2010

    shore (e.g. for accommodation, concrete casting, advanced fabrication, etc.) and this is

    reflected in the text which follows.

    a) On-shore Works

    6.3.2 The construction methods to be used for the on-shore works would be traditional civil

    engineering techniques.

    Soil Stripping

    6.3.3 Topsoil and subsoil would be stripped from the rock extraction area and the aggregates

    storage area and placed at the respective soil storage areas. This activity would leave

    the site ready for the works described in the following paragraphs.

    Rock Extraction Area

    6.3.4 Rock would be excavated from an area of land that is currently at between 16m and

    25m AOD. It is envisaged that the appointed contractor would work from the north in asoutherly direction, removing the topsoil, overburden, weathered rock and then fresh

    rock, until sufficient material (approximately 107,000m3) is available to use as fill. After

    excavation, the rock extraction areas floor would be at a level around 14m AOD and its

    sides are likely to be at a slope of 1 in 2. The area would be excavated using tracked

    excavators. The resulting materials would be crushed to the size required by a crusher

    plant and then distributed around the site by articulated bulk material transport trucks for

    use in constructing the service road and platform for the aggregates storage area.

    Service Road

    6.3.5 Initially, crushed rock would used to create the subgrade of the service road. The

    ground would be tested to determine its strength and then, where appropriate, a layer of

    woven fabric or plastic ground reinforcement would be laid. The road would then be

    made up with a minimum of 500mm of well compacted granular fill. The road would be

    laid to shed run-off into soakaways running alongside the road. The service road would

    be constructed using traditional earth moving equipment and plant, including tracked

    excavators, tracked bulldozers and articulated trucks for the transport of materials on

    site. Heavy duty rolling equipment would be used to compact the road and a small

    crane used intermittently to offload some bulk materials. Service road construction

    could require some excavation works of soft spots along the alignment.

    6.3.6 The culvert for the Hinkley Point C Drainage Ditch would be constructed by laying a

    1.25m diameter concrete pipe on the bed of the existing channel. Initially, the existingbridge and some vegetation around the ditch would be removed to allow access and

    temporary measures made to allow the ditch to flow during the construction of these

    works. The bed of the ditch would then be excavated to remove any soft material and

    provide a suitable bed for the new pipework. The pipework would be placed at an invert

    level that corresponds to the existing ditch and concrete placed up to the mid point of

    the pipe. The service road construction would then be made good with well compacted

    granular material up to the required level and with a natural slope down into the existing

    ditch. The roads top surface would be blinded with fines as necessary and the face of

    the slope would be protected using stones of a greater single size grading so as to

    protect the face from scour.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    11/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-11 November 2010

    6.3.7 As for the service road, the temporary access to the foreshore would be constructed by

    the placement of compacted granular material, but at a slope of 1 in 10 and a width of

    4.5m. Its slopes would be graded to allow safe access between the different levels.

    Aggregates Storage Area: Platform Construction

    6.3.8 The area would be cleared of vegetation, soil stripped (with soil taken to the storage

    areas) and excavated as necessary to reach the formation level (i.e. c.20m AOD). Soft

    spots would be replaced with well compacted granular material and, where required,

    woven or plastic grid soil reinforcement laid onto the formation level. Additional

    excavation would take place to accommodate drainage to capture surface water and

    discharge it into the existing natural surface water drainage (i.e. the small watercourse

    known as the Hinkley Point C Drainage Ditch, which currently discharges onto the

    foreshore). The drainage excavation would be backfilled with imported bedding and

    granular material up to formation level. Finally, the granular sub-base material would be

    sourced from the rock extraction area, crushed, laid and compacted in layers to

    complete the formation. These earthworks would be undertaken using traditional earth

    moving plant, such as mechanical scrapers, mechanical shovels, excavators andarticulated trucks.

    Aggregates Storage Area: Storage Facilities

    6.3.9 The stockpile areas would be set out and a layer of plastic damp proof membrane

    sheeting would be laid across the formation. Steel reinforcement would be laid onto the

    sheeting and then the concrete floor slab would be cast, in bays, and laid to falls for

    drainage. The external and intermediate segregation walls would then be installed using

    pre-cast concrete.

    6.3.10 For the cement silos, appropriately designed foundations would be constructed. This

    would involve excavation works, installation of steel reinforcement cages, and casting of

    the new concrete foundation. The steel silos are expected to be fabricated off site and

    then transported on low loader to the site and erected onto the foundations. The

    surrounding area would then be completed, with concrete paving laid to falls to allow

    vehicular access to the storage areas.

    6.3.11 Minor piping, conveying and offloading equipment would also be erected in place to link

    with the main conveyor and pipeline from the jetty bridge.

    Contractors Site Compound

    6.3.12 To construct the contractors compound, concrete footings would be cast in the groundand then Portakabin type facilities erected and founded on them. The ground area

    below these facilities would comprise gravel. The facilities would be connected to

    temporary services. Water would be supplied from a bowser, which would require no

    construction works. Electricity would be supplied from a diesel powered generator,

    which would require the construction of a concrete walled bund around the generator

    and its fuel supply. Sewage treatment would be provided by an underground cess pool

    or similar, which would require small-scale excavation works to install it.

    Fencing

    6.3.13 To construct the fence, firstly lines would be established and holes excavated for the

    posts and concrete threshold. Vertical plastic coated, galvanised steel posts would then

    be erected in place with wire straining posts. Once a number of posts are erected and

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    12/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-12 November 2010

    the fence line is fixed, the concrete thresholds would be cast between the straining

    posts. The plastic coated chain link fencing would be fixed in place using non-

    accessible fittings and the wires tensioned between the straining posts. Barbed wire

    protection would then be added to the top of the fence. The security fence would be

    constructed using traditional fencing equipment and plant including tracked excavators,

    dumper trucks, flatbed delivery vehicles, a small crane for offloading materials, andconcrete delivery lorries.

    b) Off-shore Works

    Site Demarcation

    6.3.14 The appointed contractor would demarcate the main working area for the jetty and the

    access routes from the cliff across the foreshore. The actual demarcation method would

    be elected by the appointed contractor, however, it is expected that demarcation would

    entail the installation of marker posts around the working areas as appropriate. Buoys

    could be attached to the marker posts to identify the location when submerged. The

    appointed contractor would be required to demarcate the foreshore access routes fromthe cliff to the working area, and this may be undertaken using portable markers

    installed during tidal working windows. In addition, the contractor might maintain guards

    to ensure that the public are warned and excluded from these areas. It is envisaged that

    signage would be installed around the site perimeter.

    Jetty Bridge including Materials Handling and Conveyance Equipment

    6.3.15 In constructing the jetty bridge, 45 to 55 steel tubular piles in the order of 860mm

    diameter would be installed 4m to 5m into the bedrock layer. The depth of pile

    penetration could vary since the ground investigation data available to date suggests

    that there might be a weathered layer or weaker layer within the rock mass which may

    necessitate additional penetration. It might not be feasible to drive the piles directly into

    the rock mass; hence the installation method is anticipated to be either by drilling and

    driving or by pre-drilling and concreting the pile into the socket, subject to further ground

    investigation data.

    6.3.16 With the drill and drive method, the pile is seated onto the rock head, a drill is inserted

    down the pile shaft and a hole drilled into the rock mass; the pile is then driven into the

    hole, the hole is extended and the pile is driven further into the hole until the required

    penetration is achieved. This technique would generate a degree of piling noise but is

    not anticipated to create much in the way of bed disturbance.

    6.3.17 The alternative pile installation method is for the pile to be placed into a concrete filledrock socket. The pile is firstly driven to rock head, a drill is inserted down the pile and

    the rock socket is drilled and then enlarged using the under-reaming blades to a

    diameter greater than the pile. Concrete is placed into the rock socket and the pile is

    driven into the wet concrete. Shear rings on the pile provide a degree of tension

    capacity.

    6.3.18 Preliminary calculations indicate that the steel piles for the bridge would need to be able

    to resist uplifting forces. This could be achieved by using concrete fill within the pile,

    anchors or by concreting the pile into a socket.

    6.3.19 Once the piles are driven, concrete cross heads would be placed over the pile bents. It

    is anticipated that the cross head units would be pre-cast with in situ stitching to the pile,

    thus minimising over water concrete works.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    13/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-13 November 2010

    6.3.20 The steel box truss structure units would be prefabricated in lengths that span between

    cross head supports. The prefabricated units would incorporate the steel longitudinal

    and transverse deck beams. It is also anticipated that the cement pipeline, aggregate

    conveyor and open mesh flooring would be installed within the units whilst on-shore.

    6.3.21 The inshore end of the jetty bridge, including the first few spans across the upper

    foreshore, would be installed using land based plant. For the drilling and placing of the

    tubular piles it is anticipated that various plant would be required for the installation of

    approximately one pile per day, including a 120t crawler crane, 30t excavator with drill

    attachment, piling hammer, 20t excavator to load spoil and 25t dump truck to remove

    spoil (4-6 loads per day). It is envisaged that this would result in approximately 10

    vehicles per day, including 3-4 concrete deliveries. In addition, piles would be brought

    to site by barge and tug, at a rate of one delivery per week.

    6.3.22 To place the concrete cross heads and deck steelwork it is anticipated that various plant

    would be required on a daily basis, including a 120t crawler crane and a 25t excavator.

    Crossheads and truss units would be brought to site by barge and tug at an expected

    delivery rate of one delivery per week.

    6.3.23 In addition to the above, there would be support plant and equipment such as tractor

    and trailer, small dumper trucks, lighting towers, welding sets, etc. required on an ad-

    hoc basis. There would also be miscellaneous deliveries each day; these items would

    be transported on the tractor and trailer.

    6.3.24 All plant would be required to drive on the foreshore via the temporary service road and

    move out of the tidal zone at the end of each shift. The typical speed of tracked plant is

    5mph over this type of terrain.

    6.3.25 The piles beyond the upper foreshore would be installed from sea-based plant in the

    form of piling equipment operated from jack-up barges.

    6.3.26 These complete units would then be lifted by crane provided off a jack-up barge and

    installed over the cross heads.

    Jetty Head including Materials Handling and Conveyance Equipment

    6.3.27 To support the jetty head, dolphin and fendering, 70-90 steel tubular piles in the order of

    910mm diameter would be driven in a similar manner to those installed for the jetty

    bridge. Pile installation would be undertaken from a jack-up barge. Tension anchors

    would be installed in selective piles or the piles could be concreted into rock sockets.

    6.3.28 The jetty head deck and dolphins are anticipated to be cast in situ reinforced concrete,

    with construction activities being undertaken from a jack-up barge. The use of pre-cast

    concrete elements could be considered during detail design.

    6.3.29 Once the jetty head is constructed, the installation of the materials handling and

    conveyance equipment (i.e. receiving cement silo and booster, loading arm and crane,

    conveyors, pipeline, receiving aggregate hopper, etc.) would take place. It is envisaged

    that the equipment to be installed on the jetty head would be delivered by sea and off-

    loaded using a crane barge.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    14/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-14 November 2010

    Berthing Pocket and Disposal of Dredged Material

    6.3.30 Existing ground investigation information indicates 4m of superficial deposits over rock

    head at the proposed position of the berthing pocket. It is proposed to dredge up to

    3.5m of this material to create a berth pocket (including up to 0.5m of over-dredge), thus

    improving tidal access windows for off-loading of cement. The actual dredging methodwould depend on the dredging equipment available to the contractor appointed to

    undertake the works. However, it is expected that dredging would take place using one

    of the two dredging methods described below.

    6.3.31 One method would be to use a small trailing suction hopper dredger (i.e. hopper

    capacity in the range of 2,000m3 to 5,000m3). This type of dredger is a self-propelled

    vessel. It has a draghead that extends to the seabed and agitates the sediment as it

    moves forward. The agitated sediment along with some of the surrounding water is

    sucked into the draghead and up a suction pipe by a centrifugal pump. The mix of

    sediment and water is discharged into the dredgers onboard hopper. The hopper filling

    process may entail over-flowing (and/or diverting) excess water and some of the finer-

    grained sediment overboard. Once the hopper is full, the draghead is retracted and thedredger sails to the disposal ground, releases the dredged material through the hoppers

    bottom doors, and returns to the dredging location.

    6.3.32 An alternative method would be to use a mechanical dredger, such as a backhoe

    dredger. This type of dredger typically works from a jack-up pontoon (i.e. it is a static

    piece of equipment) and is supported by a self-propelled transport barge with a built in

    hopper (hopper capacity in the range of 1,000m3). This type of dredger is, in essence, a

    hydraulic excavator that uses a bucket on the end of a boom and dipper crane arm to

    remove the seabed sediment and then bring it above the water surface and place it into

    a barge moored alongside. Once the barge is full, it sails to the disposal ground,

    releases the dredged material through its bottom doors, and returns to the dredging

    location.

    Aids to Navigation

    6.3.33 The appropriate aids to navigation (e.g. lights) would be attached to the jetty head

    and/or its associated structures (e.g. the mooring dolphins) and to marker buoys

    deployed at sea at the locations indicated on Plate 6.2. It is anticipated that the marker

    buoys (including their lights) and the anchoring system would be pre-fabricated and

    brought to site on a barge and deployed by a crane mounted on the barge. The anchors

    are likely to take the form of pre-cast concrete blocks, which would be sized to remain in

    place given the hydrodynamic regime (e.g. c.5m3). The chains are likely to take the

    form of steel link chains. The anchors, chains and buoys are likely to be connected anddeployed by the crane placing the anchor on the seabed.

    Roadway along the Jetty Bridge

    6.3.34 It is envisaged that the roadway would be constructed from cross-head to cross-head

    using a crane on a jack-up barge or land based plant to lift the materials into place. The

    pair of steel beams would be placed on bearings and then the pre-cast deck units would

    be placed on the steel beams. Pockets within the deck units would be positioned over

    shear connectors on the steel beams and the pockets subsequently concreted in situ.

    The lighting columns would be supported on the concrete cross heads and installed

    from the completed roadway.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    15/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-15 November 2010

    Jetty Head Extension

    6.3.35 The jetty head extension would be constructed in a similar manner to the jetty head. It is

    anticipated that 25 to 35 steel tubular piles in the order of 910mm diameter would be

    driven using a similar methods to that described for the jetty bridge. Pile installation

    would be undertaken from a jack-up barge. Tension anchors would be installed inselective piles or the piles could be concreted into rock sockets. The jetty head

    extensions deck is expected to comprise in situ cast reinforced concrete, with

    construction activities being undertaken from a jack-up barge. The use of pre-cast

    concrete elements could be considered during detail design.

    6.3.36 It is anticipated that a mobile crane would be transported to site by road, either directly

    or on the back of a transporter, and driven along the roadway to the jetty head

    extension.

    d) Construction Working Hours

    On-shore Works

    6.3.37 Working hours for construction of the on-shore components of the jetty, including the

    initial spans of the jetty bridge and the service road to the foreshore would be:

    from 07:00 to 18:00 on weekdays;

    from 07:00 to 13:00 on Saturdays; and

    no working on Sundays, bank holidays or public holidays.

    Off-shore Works

    6.3.38 It is anticipated that construction of the jetty would require working hours of 24 hours a

    day and seven days a week. Construction would take place with one or two shifts a day

    with variable start and finish times as dictated by the state of the tide. These hours are

    needed to expedite the jettys construction in relation to the restrictions imposed on

    working due to tidal conditions, and relate to both stages of the jetty infrastructure.

    e) Construction Programme

    6.3.39 An indicative construction programme for the jetty development is provided in Plate 6.3.

    6.3.40 Subject to the appropriate consents being granted and other tasks being completed (e.g.

    detailed design, contract procurement, etc.), the first stage of the jetty developments

    construction is anticipated to take place from Q2 2011. The construction works for stageone is expected to be completed within Q2 2012 and stage two by Q4 2012, assuming

    both stages of the jetty are constructed.

    f) Construction Personnel

    6.3.41 Up to 60 construction workers are estimated to be required during the construction of

    the jetty development at any one time.

    6.4 Jetty Operation

    6.4.1 The jetty would be available to import aggregates (gravel and sand) and cement once

    the stage one infrastructure and on-shore works are in place and available to importother construction materials once the stage two infrastructure is in place.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    16/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-16 November 2010

    Plate 6.3 Indicative Construction Programme

    Year 2011 2012

    Quarter Q2 Q3 Q4 Q1 Q2 Q3 Q4

    On-shore Works

    Mobilisation and site set upService road / hardstanding / drainage

    Stockpiles and silos

    Jetty Works Stage 1

    Mobilisation and site set up

    Install piles for jetty bridge

    Cast / install pile caps and crossheads

    Install bridge trusses

    Install finishing works to jetty bridge

    Install piles for jetty head

    Cast jetty deck

    Install piles for mooring dolphins

    Cast dolphin heads

    Install linkspans / finishing to jetty head

    Install jetty services (lighting, power)

    Dredging of berthing pocket

    Jetty Works Stage 2

    Install piles for jetty head extension

    Cast jetty head extension

    Install roadway deck on crossheads

    a) Jetty Import of Aggregates and Cement

    Materials Import: Types and Volumes of Materials

    6.4.2 The peak concrete production for the Hinkley Point C Project is anticipated to be in the

    region of 30,000m3per month, which would occur during placing of the concrete for the

    reactor buildings together with other site works. It is anticipated that there would be two

    production peaks each lasting in the region of six months. Concrete production would

    require the various imported materials, including cement (or cement replacement

    products), sands, stone dust and aggregates.

    6.4.3 Under the peak demand scenario, the following volumes of materials would need to beimported via the jetty:

    cement: 10,500 tonnes / month;

    sand: 21,000 tonnes / month; and

    stone: 36,000 tonnes / month.

    6.4.4 The normal concrete production for the Hinkley Point C Project is anticipated to be in the

    region of 12,000m3 per month. Under the normal demand scenario, the following

    volumes of materials would need to be imported via the jetty:

    cement: 4,200 tonnes / month;

    sand: 8,400 tonnes / month; and stone: 14,400 tonnes / month.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    17/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-17 November 2010

    Materials Import: Vessel Types and Numbers

    6.4.5 It is anticipated that vessels would include aggregate barges and cement carriers.

    Whilst the selection of operational vessels would be made by the appointed contractor,

    indicative vessel dimensions can be determined (see Table 6.1).

    Table 6.1 Indicative Vessel Dimensions

    Parameter Aggregate Barges Cement Carrier Cement Carrier

    Weight (dwt) 5,000 2,500 4,300

    Length (m) 100 78 92

    Beam (m) Up to 17.5 12 14

    Loaded draught (m) 6.0-6.7 5.3 6.3

    6.4.6 Based upon the dimensions identified in Table 6.1, the anticipated peak numbers of

    vessels visiting the jetty per month would be:

    cement carriers: 5 / month (2,500 dwt) or 3 / month (4,300 dwt);

    aggregates vessels (sand): 5 / month; and

    aggregates vessels (stone): 8 / month.

    6.4.7 Based upon the dimensions identified in Table 6.1, the anticipated normal numbers of

    vessels visiting the jetty per month would be:

    cement carriers: 1 / month (4300 dwt);

    aggregates vessels (sand): 2 / month; and aggregates vessels (stone): 4 / month.

    Materials Import: Vessel Manoeuvres

    6.4.8 It is assumed that vessels would berth on a rising tide and approach the berth as soon

    as there is sufficient depth of water for the required under keel clearance. Vessels

    would always try to approach the berth with the bow facing into the wind and / or current

    (whichever is the stronger), as this enables greater vessel control and manoeuvrability.

    A rising (or flood tide) would mean that the tidal current is flowing from west to east and

    would, therefore, require the vessel to head in a westerly direction when berthing and

    thus be port side alongside the jetty for unloading materials (hence the jetty head isdesigned for port aft discharge of materials).

    6.4.9 It is not envisaged that a pilot would be required to berth vessels but, should one be

    required, then the pilot would board a vessel at a designated position (probably between

    one to two nautical miles from the jetty) and would steer it to approach the berth at slow

    speed from a north-easterly direction. Once the vessel is 10m to 20m off the berth, the

    mooring lines would start to be run from the ship to shore. These lines would then be

    tensioned and used together with the engines (and bow thruster if fitted) to assist in

    bringing the vessel alongside the berth.

    6.4.10 Assuming that vessels would not be taking the ground while at the jettys berth, the

    vessel would depart the berth during an ebb tide with the current in an east to west

    direction from astern. This current direction would not be preferred, but should be

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    18/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-18 November 2010

    tolerable for a departure manoeuvre. For departure, a vessel would firstly reduce the

    number of mooring lines to the jetty whilst maintaining position alongside the berth. This

    would allow the final lines to be released relatively quickly before using the engines to

    clear the berth in a north-westerly direction. The pilot would then disembark (if a pilot

    has been engaged) before the vessel proceeds on passage to the next port or standing

    off waiting for the next tide. There is expected to be some water disturbance due topropeller and thruster wash during these manoeuvres.

    Materials Import: Vessel Movements

    6.4.11 To supply 30,000m3per month of aggregates and cement to meet the peak periods of

    demand for concrete production during the Hinkley Point C Project, 16 to 18 vessels (i.e.

    13 aggregates vessels and 3-5 cement carriers) would need to use the jetty. Taking

    berthing and departure manoeuvres into account, during peak months there would be 32

    to 36 vessel movements.

    6.4.12 To supply 12,000m3 per month of sand, aggregates and cement to meet the normal

    periods of demand for concrete production during the Hinkley Point C Project, 7 vessels(i.e. 6 aggregate barges and 1 cement carrier) would need to use the jetty. Taking

    berthing and departure manoeuvres into account, during normal months there would be

    14 vessel movements.

    Materials Import: Materials Unloading and Handling

    6.4.13 Aggregate vessels would unload via their on-board unloading equipment, which typically

    takes the form of a conveyor. Aggregate discharge rates would vary depending on the

    vessels onboard unloading equipment. Although self-discharging dredgers have a

    quoted discharge rate of some 2,000 tonnes per hour, an average discharge rate of

    1,000 tonnes per hour is considered much more achievable and has been

    accommodated by the jettys design. From the vessels conveyor, aggregate would be

    discharged into the articulated hopper on the jetty head and onto an articulated

    conveyor which spans the distance to the transfer hopper on the jetty bridge. The

    transfer hopper would discharge aggregate onto the conveyor along the jetty bridge,

    which would transport aggregate via a distribution conveyor, feeding the stockpiles at

    the aggregates storage area.

    6.4.14 The stockpiles would be contained and divided by low bund walls and open on at least

    one side so that aggregate can be gained by front loading shovel and transported to a

    concrete batching plant during construction of Hinkley Point C. The batching plant does

    not form part of the jetty development covered by this ES. It is anticipated that the

    stockpiles would contain about one months supply of aggregate to help mitigate berthdowntime due to adverse weather and sea conditions. Surface water run-off due to

    rainfall would be managed as part of the aggregates storage areas drainage system

    including, as necessary, sand and/or silt separation using catch pits or separators.

    6.4.15 The aggregates to be brought to the jetty could be sourced from a number of locations

    including quarries on land (e.g. South Wales) and extraction sites in the sea (i.e.

    licensed aggregate dredging areas). It is anticipated that on-shore quarries would be

    the most likely source because a marine source could necessitate processing (i.e.

    washing) to reduce the chloride content of aggregates prior to use. Since no provision is

    made for aggregate washing on site, it is not considered in this ES.

    6.4.16 Cement carriers discharge using an onboard pneumatic system for blowing the cement

    through a pipeline. The cement vessel would discharge to a receiving silo on the jetty

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    19/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-19 November 2010

    head. The silo would incorporate a booster pump to pump the cement through the

    cement pipeline along the jetty bridge to the silos at the aggregates storage area. The

    pipeline joints would be flanged and sealed with gaskets, as appropriate, in order to

    mitigate cement dust escaping from the pipeline.

    6.4.17 The achievable pumping rates depend on the number of manifolds, diameter of the

    pipeline or hose, the distance from the pump to the shore silo, and the difference in

    height between the vessel and the silo. In the case of the jetty development, the

    distance from the vessel to the silo would be relatively long and it could be necessary to

    incorporate a booster pump in the pipeline to increase the discharge rate. For example,

    it is most likely that an additional booster pump could be required on-shore to lift the

    cement into the silos. This would effectively mean that the vessel would be only

    required to pump to the jetty head, because the shore pump would transfer the cement

    to the silos on-shore. In these conditions, it is estimated that a discharge rate of some

    100 to 250 tonnes per hour could be achieved.

    Materials Import: Timing of Materials Unloading

    6.4.18 At present, it is assumed that vessels would be able to berth 24 hours a day, subject to

    the tide and weather limits.

    6.4.19 As identified on Table 6.1, 5,000 dwt aggregates vessels have an indicative loaded draft

    of 6.0 to 6.7m. With a tide level of +5.8m CD and seabed level of -2.0mCD, the vessel

    would approach the berth with 1.1m to 1.8m under keel clearance. The vessel would

    remain at the berth through high water and discharge its cargo. The vessel would then

    depart by the time the tide drops to +5.8mCD, although departure could take place on a

    slightly lower tidal level if the draft was reduced after off-loading and subsequent

    ballasting.

    6.4.20 Accordingly, the aggregate unloading is expected to take some 5.5 to 6.0 hours which

    would necessitate a discharge rate of some 1,000 tonnes per hour. Therefore, it is

    considered that aggregate barges can gain access to the jetty on virtually all tides, using

    the upper half of the tidal cycle each time. However, there could be other operational

    restrictions, such as weather down time, plant breakdowns, etc. which would need to be

    taken into account.

    6.4.21 Cement carriers have a lower indicative loaded draft and a slower discharge rate than

    aggregate barges, which means they would remain berthed for longer to unload their

    contents. Since 2,500dwt vessels would need 15 hours to unload and 4,300dwt vessels

    would need 30 hours to unload, cement carriers would remain berthed throughout onefull tidal cycle, including at low tide, and hence the need for the dredged berthing pocket

    to provide an additional 2m water depth.

    b) Jetty Import of Other Construction Materials

    Materials Import: Types and Volumes of Materials

    6.4.22 The jettys second stage would be used to import other materials needed for the

    construction of Hinkley Point C. It is anticipated that these imported materials would

    include unitised and/or pre-fabricated items such as pre-cast concrete pipeline units

    (e.g. for the intake and outfall structures), steel reinforcement bars (e.g. for concrete),

    brickwork, cabling, piping, ducting, etc.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    20/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-20 November 2010

    6.4.23 The jetty would not be used to offset the import of abnormal indivisible loads (AILs) via

    EDF Energys dedicated wharf at Combwich because its design cannot accommodate

    the types of vessels used to import AILs and its equipment cannot unload and convey

    the AILs.

    Materials Import: Vessel Types, Numbers, Manoeuvres and Movements

    6.4.24 Since there is no definitive information on the exact types and volumes of materials that

    would be imported during its operation, the vessel types, numbers, manoeuvres and

    movements associated with the second stage of the jetty development are not known

    with precision at the current time. However, some indicative scenarios for the second

    stage of the jetty development can be anticipated based on the types of materials likely

    to be imported and the availability of the jetty (i.e. the spare tides during which a vessel

    could be berthed at the jetty).

    6.4.25 As for the import of aggregates, it is anticipated that the jetty would receive vessels of

    sizes up to 5,000dwt due to the limitations of the berth (e.g. the water depth available at

    the berth).

    6.4.26 It is anticipated that vessels would make best use of the tidal windows available to them.

    Therefore, the potential operational capacity of the jetty (i.e. the number of vessels

    potentially using the jetty) would depend on the availability of jettys berth over spare

    tides. Spare tides are those tides when the berth is not occupied by a vessel delivering

    aggregate or cement for concrete production during the construction of Hinkley Point C,

    or when the berth cannot be occupied due to adverse weather.

    6.4.27 Assuming an average of 60 tides per month, a preliminary analysis of spare tides has

    been made (see Table 6.2). This analysis identifies the indicative number of tides

    available per month, over winter and summer, during periods of peak and normal

    concrete demand, and both including and excluding tides in between aggregate and

    cement deliveries. As would be expected, there would be more opportunity to import

    materials during normal concrete production compared to peak concrete production.

    Table 6.2 Indicative Available Tides

    Available Tides (including tides in betweenaggregate and cement deliveries)

    Available Tides (excluding tides inbetween aggregate and cement deliveries)

    Peak ConcreteProduction

    Normal ConcreteProduction

    Peak ConcreteProduction

    Normal ConcreteProduction

    Winter Summer Winter Summer Winter Summer Winter Summer

    26 32 38 (25*) 44 4 11 29 (2*) 36

    Note: * if aggregates supplied by smaller vessels of 1,200dwt

    6.4.28 The tides available when aggregate and cement deliveries are excluded represent the

    most realistic scenario of spare tides for the jetty. Under this scenario, there would be

    between 4 and 29 spare tides during winter months and between 11 and 36 spare tides

    per month during summer months.

    6.4.29 During the months of peak demand for aggregates and cement for concrete production

    during construction of Hinkley Point C, there would be between 4 and 11 spare tides permonth. Assuming one vessel per every spare tide and taking berthing and departure

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    21/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-21 November 2010

    manoeuvres into account, there would be a monthly maximum of between 8 and 22

    vessel movements to add to the 32 to 36 vessel movements associated with the import

    of aggregates and cement.

    6.4.30 During the months of normal demand for aggregates and cement for concrete

    production during construction of Hinkley Point C, there would be between 29 and 36

    spare tides per month. Assuming one vessel per every spare tide and taking berthing

    and departure manoeuvres into account, there would be a monthly maximum of

    between 58 and 72 vessel movements to add to the 14 vessel movements associated

    with the import of aggregates and cement.

    6.4.31 It is anticipated that vessels would access and depart the jetty with similar manoeuvres

    to those described for aggregate dredgers and cement vessels.

    Materials Import: Materials Unloading and Handling

    6.4.32 Although precise information is not currently available on all the types and volumes of

    materials that would be imported at stage two, it is assumed that vessels would beunloaded using the mobile crane situated on the extended jetty head. The crane would

    load materials onto trucks, which would then transport the materials along the jetty

    bridge and on-shore to the construction site for Hinkley Point C.

    6.4.33 The timing of unloading operations would have to fit around the times when the jetty is

    not being used for importing aggregates and cement, and around the tidal cycle as

    relevant to the vessel (e.g. in terms of draught available across the tidal cycle).

    c) Jetty Maintenance

    Maintenance of Handling and Conveyance Equipment

    6.4.34 During the operational life of the jetty, a degree of maintenance would be required.

    Given that the import of aggregates and cement would be within discrete timeframes

    related to demand and tides, and that EDF Energy might want to import other materials

    via the jetty, it is important that downtime due to equipment failure is limited as far as

    reasonably practicable.

    6.4.35 It is considered that the main area of maintenance would be mechanical and electrical

    maintenance associated with the receiving aggregates hopper and articulated conveyor

    and the cement booster pumps and pipeline. Maintenance and minor replacement of

    items would be undertaken locally unless significant replacement of equipment is

    required. Maintenance walkways are to be provided along the jetty bridge on eithersides of the aggregates conveyor and cement pipeline via the 1.5m wide central

    walkway.

    6.4.36 Should it be necessary to replace significant pieces of equipment, which would be very

    unlikely, delivery could be achieved by a vessel berthing at the jetty and using its

    onboard unloading equipment to unload items. Alternatively, if the stage two jetty

    infrastructure is in place, delivery could be achieved either by a vessel berthing at the

    jetty and using the crane on the jetty head, or by truck driving along the jettys roadway

    with items being off-loaded and craned into position.

    6.4.37 During routine maintenance operations, regular inspection of hydraulic equipment would

    be undertaken in order to ensure that pollution associated with hydraulic oils is avoided.It is expected that this would include inspection of the crane located on the jetty head.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    22/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-22 November 2010

    Maintenance of the Berthing Pocket

    6.4.38 It is anticipated that a degree of sediment infilling would occur over time and, hence,

    maintenance dredging of the berthing pocket might be required to ensure sufficient

    water depth for vessel berthing and unloading operations. A maintenance dredging

    regime has not been determined for the berthing pocket, but it is anticipated that themethod for maintenance dredging and the dredged material disposal site would be

    similar to capital dredging.

    6.4.39 Accordingly, it is anticipated that a small trailer hopper suction dredger or a backhoe on

    a jack-up platform would be used to carry out the dredge, and that the dredged material

    would be disposed of at the Cardiff Grounds.

    Maintenance of Aids to Navigation

    6.4.40 It is expected that the aids to navigation would be inspected every 6 or 12 months to

    ensure that the lights and systems are working correctly and the marker buoys are in the

    correct position (i.e. that they have not been dragged out of position by currents).

    d) Aggregates Storage Area

    6.4.41 The aggregates storage area would receive and store the imported aggregates and

    cement in the stockpiles and silos. The area provides storage for approximately one

    months typical demand for materials in the eight aggregate stockpiles, four sand

    stockpiles, two stone dust stockpiles and up to eight cement silos. This level of storage

    would provide contingency against disruption to supply via the jetty primarily due to

    weather downtime, but also from other supply issues.

    6.4.42 Given the aggregate storage areas arrangement (see Figure 1-2, Volume 3), it has

    been considered that transfer of aggregates and cement to the concrete batching plant

    would be by trucks or tankers, respectively. However, it is conceivable that, depending

    on the location of the batching plant, transfer of aggregates and cement could be made

    by an arrangement of conveyors and pipelines, respectively.

    e) Lighting

    6.4.43 The jetty and the on-shore area would be designed to operate in periods 24 hours a day,

    7 days a week. These areas would need to be lit at relevant times to provide a safe

    working environment. The jetty developments lighting strategy is described in Section

    6.2. The following paragraphs describe operations for which lighting might be required.

    Jetty Operations

    6.4.44 When unloading aggregates, the vessel would discharge during a specific tidal window

    on the upper half of the tidal cycle and if this occurs during dusk / darkness, operational

    lighting would be required during the unloading period and for a short time either side of

    the window. When unloading cement the vessel would remain at the berth for up to 30

    hours and the operational lighting would be required throughout this time during periods

    of dusk / darkness. In addition, operational lighting would be required during any

    maintenance work on the jetty.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    23/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-23 November 2010

    On-shore Operations

    6.4.45 The on-shore area may be lit for longer periods than the jetty, as on-shore distribution of

    aggregates and cement may occur a 24 hours a day, 7 days a week at periods of peak

    concrete production during the construction of Hinkley Point C. During non-operational

    periods, a lower level of lighting would be maintained throughout the facility for securityand safety reasons.

    f) Working Hours

    6.4.46 It is anticipated that operation of the jetty and the aggregates storage area would require

    working over 24 hours a day, 7 days a week. Operation would take place with one or

    two shifts a day with variable start and finish times as dictated by the state of the tide.

    These hours are needed to operate the jetty development in relation to the restrictions

    imposed on operations (e.g. berthing and unloading of vessels) due to tidal conditions,

    and relate to both stages of the jetty infrastructure.

    g) Operation Programme

    6.4.47 The jetty development is proposed as a temporary feature to facilitate construction of the

    Hinkley Point C Project and, therefore, it is expected to be operational for up to eight

    years.

    6.4.48 Use of the jetty would be related to the demand for aggregates and cement for concrete

    production during the construction of Hinkley Point C. It is anticipated that there would

    be two periods, each of six months, during which the jetty would be operating at its

    maximum potential in terms of berth occupancy by aggregate barges (over high tides on

    all tidal ranges) and cement carriers (over all states of the tide during neap tidal ranges).

    6.4.49 The jettys usage would reduce as Hinkley Point Cs first reactor unit becomes

    operational and would cease in advance of Hinkley Point Cs second reactor unit

    becoming operational. It is expected at this point, the jetty would be no longer required

    and dismantling would be initiated (see Section 6.5).

    h) Operation Personnel

    6.4.50 Up to 10 operation workers are estimated to be required during the operation of the jetty

    development at any one time. It is estimated that four to six linesmen would be required

    for berthing the vessels and a further two to four workers would be required for the

    unloading operation (this would depend on the shore discharging arrangement).

    6.5 Jetty Dismantling and Restoration

    6.5.1 The temporary jetty would be dismantled at the end of its operational life. It is

    anticipated that reuse of materials handling equipment would be feasible along with

    reuse and/or recycling of some of the jettys structural items.

    6.5.2 Once the jettys infrastructure has been dismantled and taken off-site, the land affected

    by the platform for the aggregates storage area would be restored to its former use for

    agriculture.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    24/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-24 November 2010

    a) On-shore Works Dismantling

    6.5.3 The hardstanding platform area created for the aggregates stockpiles and cement silos

    would be broken out. The resulting rubble would be crushed for on- or off-site re-use.

    b) Off-shore Works Dismantling

    6.5.4 The following paragraphs set out the dismantling and restoration activities for the jetty in

    the order that they are expected to take place and assuming that both stages of the jetty

    development would be in place.

    Materials Handling and Conveyance Equipment at the Jetty Head

    6.5.5 The materials unloading and handling equipment at the jetty head (e.g. articulated

    conveyor, silo, booster, hoppers and crane) would be dismantled and shipped away

    from the jetty. It is anticipated that many of these items could be reused by EDF Energy

    or sold on for use by others.

    Materials Handling and Conveyance Equipment along the Jetty Bridge

    6.5.6 It is anticipated that following some local dismantling work the steel truss inclusive of the

    cement pipeline and aggregate conveyor would be removed in units in a similar manner

    to that in which it was installed. This would require a crane barge to transport the units.

    Roadway along the Jetty Bridge

    6.5.7 The roadway deck would be systematically dismantled in a linear manner. Firstly, the

    pre-cast concrete deck sections would be removed from the steel beams. This would

    involve local breaking out of the in situ concrete surrounding the shear studs; hydro-

    demolition could be used in order to minimise damage to reinforcement. The steel

    beams would then be disconnected from the cross heads and removed. It should be

    feasible to re-use the steel beams and pre-cast concrete deck sections at another

    location.

    Jetty Bridge

    6.5.8 The concrete cross heads would be dismantled from the piles by cutting of the piles

    immediately below the cross head. The concrete could be recycled, subject to the

    degree of reinforcement.

    6.5.9 It is not considered feasible to pull out the steel tubular piles, hence cutting of the pilesat rock head / seabed level would be used to remove the main section of pile shaft. On

    the foreshore, where the pile locations could pose a risk to people walking and falling

    into holes, the remaining section of pile and internal void would be in-filled with grout. At

    locations on the foreshore where the holes / restoration are visible, a natural stone slab

    would be placed into the concrete plug. The voids left within the seabed beyond the

    foreshore would not be plugged with concrete but allowed to infill naturally with seabed

    deposits.

    6.5.10 A barge with craneage would be necessary to support, dismantle and transport these

    units for recycling as reuse is considered impractical. If tension anchors are used in

    place of concrete infill, the piles could be re-used.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    25/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-25 November 2010

    Jetty Head

    6.5.11 The dismantling of the jetty head structure and dolphin caps (including an extended jetty

    head) would involve demolition of the in situ reinforced concrete into sections, which

    would then be cut from the pile heads and lifted onto a barge for subsequent removal

    from the site. The dismantling of the tubular piles would be undertaken in a similarmanner to those of the jetty bridge.

    6.5.12 The voids left within the seabed would not be plugged with concrete but allowed to infill

    naturally with seabed deposits.

    Aids to Navigation

    6.5.13 Dismantling of the marker buoys would entail the recovery of the anchors, chains and

    buoys by crane. They are expected to be placed on a barge and taken off-site for re-

    use, recycling and, if necessary, disposal.

    c) Restoration

    6.5.14 Following infrastructure dismantling, the western area affected by the jetty

    developments on-shore works (e.g. the aggregates storage area, WMZ) would be

    restored. The eastern area of the jetty developments on-shore works (e.g. service road,

    rock extraction area) would become part of the Hinkley Point C Projects permanent

    works (e.g. the nuclear power station) and, therefore, would not be restored.

    6.5.15 Restoration would seek to restore and enhance the landscape character, improve

    biodiversity, and provide improved public access. The western part of the site would be

    restored for predominantly agriculture use, with some woodland and hedgerow planting.

    All proposed planting is to be of native species of local provenance where possible,

    selected to fit with existing local landscape character and to suit site conditions. The

    stripped topsoil and subsoil to be retained and stored on site would be used for the

    restoration works.

    6.5.16 In addition, the existing PRoWs would be reinstated and Green Lane upgraded to a

    bridleway. Footpaths and bridleways would be clearly defined and signposted, and

    maintained to a high standard. Access would take into account the needs of less able

    people. For example, self-closing bridle gates would be proposed, rather than stiles, to

    avoid creating barriers to the less able.

    6.5.17 The restoration strategy for the jetty development would form part of the overall land

    restoration strategy associated with the completion of construction of Hinkley Point C,and is described in more detail in Section 21.6and shown in Figure 21-27,Volume 3.

    d) Working Hours

    6.5.18 Dismantling and restoration of all components of the jetty development is anticipated to

    require the following working hours:

    from 07:00 to 18:00 on weekdays;

    from 07:00 to 13:00 on Saturdays; and

    no working on Sundays, bank holidays or public holidays.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    26/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-26 November 2010

    e) Dismantling and Restoration Programme

    6.5.19 It is expected that dismantling and restoration would take approximately two years,

    including dismantling of the jetty, earthworks to reprofile the site and planting.

    f) Dismantling and Restoration Personnel

    6.5.20 Up to 25 workers are estimated to be required for dismantling and restoration of the jetty

    development at any one time.

    6.6 Jetty Removal and Reinstatement

    6.6.1 The jetty development would be removed and the site reinstated if it is not required

    because the Hinkley Point C Project is not granted its consent. This would comprise two

    key activities: infrastructure removal and site reinstatement.

    a) Infrastructure Removal

    6.6.2 To physically remove the jetty developments on-shore and off-shore infrastructure, the

    same process would be adopted as that described for dismantling in Section 6.5.

    b) Site Reinstatement

    6.6.3 Following removal, the on-shore area affected by the jetty development would be

    reinstated to the extent that is practical and practicable.

    6.6.4 Reinstatement would seek to reinstate and enhance the landscape character (including

    the landform and the coastal cliff), improve biodiversity, and provide improved public

    access. The majority of the area affected by the jetty development would be returned to

    agriculture use. All proposed planting is to be of native species of local provenancewhere possible, selected to fit with existing local landscape character and to suit site

    conditions. The stripped topsoil and subsoil to be retained and stored on-site is

    expected to be used for the landscape reinstatement. The reinstated landform, soil

    structure and hedgerow framework would support the agricultural end use.

    6.6.5 In addition, as for site restoration, existing PRoWs would be reinstated across the entire

    application site and Green Lane would be upgraded to a bridleway. Footpaths and

    bridleways would be clearly defined and signposted, and maintained to a high standard.

    Access would take into account the needs of less able people. For example, self-

    closing bridle gates would be proposed, rather than stiles, to avoid creating barriers to

    the less able.

    6.6.6 The reinstatement strategy for the jetty development is described in Section 21.6and

    shown in Figure 21-26, Volume 3.

    c) Working Hours

    6.6.7 Removal and reinstatement of the jetty and the on-shore components of the jetty

    development is anticipated to require the following working hours:

    from 07:00 to 18:00 on weekdays;

    from 07:00 to 13:00 on Saturdays; and

    no working on Sundays, bank holidays or public holidays.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    27/28

    Hinkley Point C Preliminary Works Environmental Statement

    Temporary Jetty Development 6-27 November 2010

    d) Removal and Reinstatement Programme

    6.6.8 No programme is set for removal and reinstatement because this component of the jetty

    development may not be required, unless circumstances dictate otherwise. However,

    the timescales for infrastructure removal would be similar to that described for

    dismantling (see Section 6.5) and the timescales for removal and reinstatement areestimated to be up to one year for removal and two years for reinstatement.

    e) Removal and Reinstatement Personnel

    6.6.9 It is estimated that up to 25 construction workers would be required, at any one time,

    during the removal of the jetty and reinstatement of the site in the development area.

    6.7 References

    6.1 Eagle Lyon Pope (2009). Combwich Marine Impact Assessment. Eagle Lyon Pope.

  • 7/26/2019 Jetty Environmental Standard Chapter 6 - Project Description- Temporary Jetty Development

    28/28

    [This page is intentionally left blank].


Recommended