Date post: | 11-Apr-2015 |
Category: |
Documents |
Upload: | vivecpatel |
View: | 221 times |
Download: | 0 times |
John Player store replenishmentBibekananda Patel
Inventory
An inventory system is the set of policies and controls that monitor levels of inventory and determine
– what level should be maintained, – when stock should be replenished and – how large order should be.
Effective Inventory ManagementA system to keep track of inventoryA reliable forecast of demandKnowledge of lead timesReasonable estimates of
Holding costs Ordering costs Shortage costs
Key Inventory Terms Lead time: time interval between ordering and receiving the
order
Holding (carrying) costs: cost to carry an item in inventory for a length of time
Ordering costs: costs of ordering and receiving inventory
Shortage costs: costs when demand exceeds supply
Product
• Formal Shirts
Boundary Conditions
• As the storage capacity of this item is 750 units we can’t have a EOQ > 750 units.
• And, as the lead time is 10 days we should have a stock of 10 days while ordering.
Month-wise sales Estimates for 2008Yr 2008 DemandJanuary 238
February 242
March 227
April 230
May 162
June 156
July 137
August 172
September 319
October 388
November 286
December 300
Total Demand 2857
Average Demand per month 239
Standard Deviation 72.16
SD/Mean = 0.301
i.e. we can’t apply EOQ model (SD/mean > 0.01)
Formula for EOQ
EOQ 595.04
EOQ ApproachOC 200
HC 0.27Yr 2008 Demand Order Number Quantity Holding CostJanuary 238 1 707 February 242 - 65.34March 227 - 122.58April 230 2 685 May 162 - 43.74June 156 - 84.24July 137 - 110.97August 172 3 879 September 319 - 86.13October 388 - 209.52November 286 4 586 December 300 - 81Total Demand 2857 2857 803.52
Total Order Cost (4x200) = 800.00Total of
Cost 1603.52
EOQ ApproachOC 200
HC 0.27Yr 2008 Demand Order Number Quantity Holding CostJanuary 238 1 707 February 242 - 65.34March 227 - 122.58April 230 2 685 May 162 - 43.74June 156 - 84.24July 137 - 110.97August 172 3 491 September 319 - 86.13October 388 4 674 November 286 - 77.22December 300 5 300 Total Demand 2857 2857 590.22
Total Order Cost (4x200) = 1000.00 Total 1590.22
Factors Affecting Replenishment
Replenishment of merchandise is dependent on:
1. Storage capacity of the store - 750 units2. Lead times for supply of goods – 10 Days3. Rate of sales – 10% growth4. Relative stock positions across the chain – Assumed as Zero5. Ensuing events like seasonality – Sale pattern shows 3
clusters for this product.6. Holding cost – Rs. 0.27
Depending upon the sales pattern there are three seasons;
• Jan-Apr• May-Aug• Sept-Deci.e. we have three EOQ model
Table showing calculated total cost (according to days of stock)
120 days demand = 937
per day demand = 937/120 = 7.8
Total OC = OC * No of Orders
Total Cost = Total OC + Total HC
Days of Stock Order Quantity in units
Demand in units HC in Rs. OC in Rs. No of
ordersTotal OC
in Rs.Total HC
in Rs.Total Cost
in Rs.
120 937 937 0.27 200 1 200.00 379.485 579.49
105 820 937 0.27 200 2 400.00 284.6138 684.61
90 703 937 0.27 200 2 400.00 189.7425 589.74
75 586 937 0.27 200 2 400.00 126.495 526.50
60 469 937 0.27 200 2 400.00 63.2475 463.25
45 351 937 0.27 200 3 600.00 31.62375 631.62
40 312 937 0.27 200 3 600.00 21.0825 621.08
35 273 937 0.27 200 4 800.00 10.54125 810.54
30 234 937 0.27 200 4 800.00 0 800.00
25 195 937 0.27 200 5 1000.00 0 1000.00
15 117 937 0.27 200 8 1600.00 0 1600.00
10 78 937 0.27 200 12 2400.00 0 2400.00
Table showing calculated total cost (according to days of stock)
120 days demand = 627
per day demand = 627/120 = 5.05
Total OC = OC * No of Orders
Total Cost = Total OC + Total HC
Days of Stock Order Quantity in units
Demand in units HC in Rs. OC in Rs. No of
ordersTotal OC
in Rs.Total HC
in Rs.Total Cost
in Rs.
120 627 627 0.27 200 1 200.00 253.8675 453.87105 549 627 0.27 200 2 400.00 190.3838 590.3890 470 627 0.27 200 2 400.00 126.9 526.9075 392 627 0.27 200 2 400.00 84.5775 484.5860 314 627 0.27 200 2 400.00 42.3225 442.3245 235 627 0.27 200 3 600.00 21.16125 621.1640 209 627 0.27 200 3 600.00 14.1075 614.1135 183 627 0.27 200 4 800.00 7.05375 807.0530 157 627 0.27 200 4 800.00 0 800.0025 131 627 0.27 200 5 1000.00 0 1000.0015 78 627 0.27 200 8 1600.00 0 1600.0010 52 627 0.27 200 12 2400.00 0 2400.00
Table showing calculated total cost (according to days of stock)
120 days demand = 1293
per day demand = 1293/120 = 10.78
Total OC = OC * No of Orders
Total HC = HC * Order quantity
Total Cost = Total OC + Total HC
Days of Stock Order Quantity in units
Demand in units HC in Rs. OC in Rs. No of
ordersTotal OC
in Rs.Total HC
in Rs.Total Cost
in Rs.
120 1,293 1293 0.27 200 1 200.00 523.46 723.46105 1,131 1293 0.27 200 2 400.00 392.55 792.5590 970 1293 0.27 200 2 400.00 261.77 661.7775 808 1293 0.27 200 2 400.00 174.49 574.4960 647 1293 0.27 200 2 400.00 87.28 487.2845 485 1293 0.27 200 3 600.00 43.64 643.6440 431 1293 0.27 200 3 600.00 29.09 629.0935 377 1293 0.27 200 4 800.00 14.55 814.5530 323 1293 0.27 200 4 800.00 0 800.0025 269 1293 0.27 200 5 1000.00 0 1000.0015 162 1293 0.27 200 8 1600.00 0 1600.0010 108 1293 0.27 200 12 2400.00 0 2400.00
Graph of Stock Replenishment for a single season
Total cost incurred in the year 2008
• Total Cost;= 463.25 + 442.32 + 487.28= 1392.85
Conclusion
• From the EOQ model approach the total cost is found to be Rs.1590.22
• And the from the model John Player follows is found to be Rs. 1392.85
• So comparing both the model the letter one is cost effective.