+ All Categories
Home > Documents > Jon Chiglo , PE Project Director

Jon Chiglo , PE Project Director

Date post: 25-Feb-2016
Category:
Upload: simeon
View: 22 times
Download: 2 times
Share this document with a friend
Description:
2014 Construction Plans. Jon Chiglo , PE Project Director. Tentative 2014 Construction Timeline. Access to businesses and residences. Local access will remain during business hours and at all times to residences. Business signage Detour signage Temporary gravel roads . - PowerPoint PPT Presentation
Popular Tags:
88
Jon Chiglo, PE Project Director 2014 Construction Plans
Transcript
Page 2: Jon  Chiglo ,  PE Project  Director

Tentative 2014 Construction Timeline

Page 3: Jon  Chiglo ,  PE Project  Director

Access to businesses and residences

Local access will remain during business hours and at all times to residences.

- Business signage- Detour signage- Temporary gravel roads

Page 4: Jon  Chiglo ,  PE Project  Director

2014 Minn. Approach Work Contracted Maximum Impacts

• North Frontage Road—50 calendar days

• Osgood Avenue—40 calendar days

• Greeley Street—40 calendar days

• Oakgreen Avenue—25 calendar days

• South Frontage Road—70 calendar days

Page 5: Jon  Chiglo ,  PE Project  Director

Highway 36

• Single-lane in each direction – Open AT ALL TIMES• Work: Resurface road

• Westbound: Spring to mid-summer 2014(red)• Eastbound: Mid-summer to fall 2014(green)

Page 6: Jon  Chiglo ,  PE Project  Director

South Frontage Road – East of Osgood

• Closed to through traffic • Local access to businesses and residences • Work: Resurface road, replace public utilities • Spring to mid-summer 2014 (red)

Page 7: Jon  Chiglo ,  PE Project  Director

Hwy 95 / Lookout Trail / Sunnyside

• Hwy 95• Single-lane in each direction • Work: Construct 4-lane road • Spring to mid-summer 2014 (red)

• Lookout Trail• Work: Reconstruct access to Hwy 95

to right in/out intersection• Spring to mid-summer 2014

• Sunnyside Marina• Work: Reconstruct driveway• Spring to mid-summer 2014

Page 8: Jon  Chiglo ,  PE Project  Director

North Frontage Road

• North Frontage Road – Northwestern to Greeley• Possible detours to access

North Frontage Road.

• Work: Resurface road, add turn lane, add curb & gutter

• Spring to mid-summer 2014 (red)

Page 9: Jon  Chiglo ,  PE Project  Director

North Frontage Road

• North Frontage Road – Greeley to Osgood• Possible detours to access North Frontage Road, either from

Greeley St. or Osgood Ave.• Permanent closure of right in/out connection to Hwy 36• Work: Resurface road, add turn lane, add curb & gutter • Spring to mid-summer 2014 (red)

Page 10: Jon  Chiglo ,  PE Project  Director

Greeley St./Oakgreen Ave. Intersection

• North/south traffic closed for 2 periods of 6 calendar days each

• Oakgreen—Closed between S. Frontage Road and 58th St./Oak Park Blvd. for 25 days. Local residential access only. (green)

• Work: Build new frontage road system further away from Hwy 36; shift intersection to the east; install three traffic signal systems; add double left turn lanes

Page 11: Jon  Chiglo ,  PE Project  Director

Osgood Ave. Intersection

• North/south traffic closed for 2 periods of 6 calendar days each

• Work: Add double left turn lanes, resurface intersection

• Osgood intersection and Greeley-Oakgreen intersection WILL NOT close at the same time

Page 12: Jon  Chiglo ,  PE Project  Director

Final Hwy 36 Intersections Looking East

Page 13: Jon  Chiglo ,  PE Project  Director

S. Frontage Road – Oakgreen to Osgood

• Possible detours/temporary roads to access businesses/residences

• Work: Resurface road, add turn lane, add curb & gutter, replace public utilities

• Late summer to fall 2014 (blue)

Page 14: Jon  Chiglo ,  PE Project  Director

Trail Construction

• Work: Construct pedestrian/bicycle trails • Occurs as time allows, complete in fall 2014

Page 15: Jon  Chiglo ,  PE Project  Director

Other area county/city projects

Page 16: Jon  Chiglo ,  PE Project  Director

Wisconsin Approach Work

Work occurs: March 2014-late summer 2016

Goal: Open WIS 64 at the same time as the new bridge

Page 17: Jon  Chiglo ,  PE Project  Director

2014 Wisc. Approach Work

• Grade from the bluff to County Road E

• Build the WIS 35 overpass over the new WIS 64

Page 18: Jon  Chiglo ,  PE Project  Director

2014-2017 Wisc. Approach Schedule

Page 19: Jon  Chiglo ,  PE Project  Director

The New St. Croix Crossing

Page 20: Jon  Chiglo ,  PE Project  Director

Bridge Superstructure

• Timeline: Dec. 2013 to late-summer/early fall 2016

• Winter/Spring 2014 Impacts: Pile driving on the Minnesota shoreline and work on Pier 8 • Through May• 6 days per week -- 7 a.m.-7 p.m. • Goal: As much work done as possible while

windows are closed

Page 21: Jon  Chiglo ,  PE Project  Director

Minnesota Land Piers Work Progress

Page 22: Jon  Chiglo ,  PE Project  Director

2014 Bridge Construction

• Build all river piers and land piers vertically (Piers 1-13)

Page 23: Jon  Chiglo ,  PE Project  Director

2014 Bridge Construction

• Begin casting segments – Approx. 1,000 • 656 extradosed segments• 330 approach segments

• Two casting yard locations -- Gray Cloud Island and at the Hwy 36/95 interchange

• Place first segment in fall 2014

Page 24: Jon  Chiglo ,  PE Project  Director

River Bridge Construction Staging

Page 25: Jon  Chiglo ,  PE Project  Director

Segment Lifter Example

Page 26: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 27: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 28: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 29: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 30: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 31: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 32: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 33: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 34: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 35: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 36: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 37: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 38: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 39: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 40: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 41: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 42: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 43: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 44: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 45: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 46: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 47: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 48: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 49: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 50: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 51: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 52: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 53: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 54: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 55: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 56: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 57: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 58: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 59: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 60: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 61: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 62: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 63: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 64: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 65: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 66: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 67: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 68: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 69: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 70: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 71: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 72: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 73: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 74: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 75: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 76: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 77: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 78: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 79: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 80: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 81: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 82: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 83: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 84: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 85: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 86: Jon  Chiglo ,  PE Project  Director

Construction Sequence

Page 87: Jon  Chiglo ,  PE Project  Director

Contact Information

Hotline1-855-GO-CROIX (462-7649)

[email protected]

Website/Regular project updateswww.mndot.gov/stcroixcrossing

Facebook www.facebook.com/saintcroixcrossingmndot

Twitter @stcroixcrossing

Page 88: Jon  Chiglo ,  PE Project  Director

Questions?


Recommended