SU TU NAU FIELD DEVELOPMENT SU TU NAU PROJECT KICK OFF MEETING FOR VIETSOVPETRO Vietsovpetro, 20 May 2014
Transcript
Page 1: KOM Presentation STN-N Conductor_rev 2

SU TU NAU FIELD DEVELOPMENT – SU TU NAU PROJECT

KICK OFF MEETING FOR

VIETSOVPETRO

Vietsovpetro, 20 May 2014

Page 2: KOM Presentation STN-N Conductor_rev 2

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

AGENDA

A. SAFETY INSTRUCTION

B. ATTENDANCE INTRODUCTION

C. PROJECT OVERVIEW

D. PROJECT PROGRESS

E. PROJECT EXECUTION PLAN

F. AOB

Page 3: KOM Presentation STN-N Conductor_rev 2

A. SAFETY INSTRUCTION

VSP/OCD & PSD Building

EMERGENCY EVACUATION PLAN

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 4: KOM Presentation STN-N Conductor_rev 2

A. SAFETY INSTRUCTION

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 5: KOM Presentation STN-N Conductor_rev 2

SƠ ĐỒ THOÁT HIỂM TẦNG TRỆT – TÒA NHÀ XNXL-XNDVEMERGENCY ESCAPE PLAN GROUND FLOOR OF OCD-PSD BUILDING.

MUSTER STATION

Page 6: KOM Presentation STN-N Conductor_rev 2

*WHEN YOU ESCAPED FROM THE BUILDING

*Go and report to your designated Muster Station Location.

Page 7: KOM Presentation STN-N Conductor_rev 2

B. ATTENDANCE INTRODUCTION

CUU LONG JOC (Client)

PTSC MC (EPCI Contractor)

VIETSOVPETRO (T&I Contractor)

MWS

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 8: KOM Presentation STN-N Conductor_rev 2

• 1. GENERAL

• 2. SCOPE OF WORK

PROJECT OVERVIEW

C. PROJECT OVERVIEW

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 9: KOM Presentation STN-N Conductor_rev 2

C. PROJECT OVERVIEW >>

The Su Tu Nau field is located

at the northern part of Block

15-1, Offshore Vietnam and

located approximately 200 km

Southeast of Ho Chi Minh City.

The Su Tu Nau Field consist of two

platforms, one located in the south

area of the field (STN-S) and one in

the northern area of the field (STN-N).

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 10: KOM Presentation STN-N Conductor_rev 2

C. PROJECT OVERVIEW >>

PICTURE OF STN – N JACKET AT FIELD

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 11: KOM Presentation STN-N Conductor_rev 2

C. PROJECT OVERVIEW >>

No. Description Detail

1 Platform STN-N

2 Water depth 39.89m

3 Platform Type 4 legged wellhead

4 Conductor slots 6

5 Pre-installed Conductors (By other contractor) 2 (slot 1 & 3)

6 Conductor to be installed by VSP 4 (slot 2,4,5 & 6)

7 Conductor Diameter / Wall Thickness 914mm (36’’) /25mm (1’’)

8 Target Penetration 90.0m

9 Spider Deck Elevation (+) 6.339m

10 Drill Deck Elevation (+) 18.828m

11 Final Conductor Cut-off Elevation (+) 20.328m

12 Top of Wellhead (+) 22.613m

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 12: KOM Presentation STN-N Conductor_rev 2

C. PROJECT OVERVIEW >>

Segment QTY

Diameter

(m)

Wall

Thickness

(mm)

Length

(m)

Weight

(T)

Cut-off

Allowance

(m)

C1 04 914 25 56 30.68 0

C2 04 914 25 49.524 27.13 1.524

C3 04 914 25 34.524 18.91 1.524

C4 04 914 25 21.768 12.65 9.889

CONDUCTORs SEGMENT

Conductor will be divided into 04 segments in accordance with conductor pipes

installation by using Truong Sa Crane Vessel as below:

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 13: KOM Presentation STN-N Conductor_rev 2

C. PROJECT OVERVIEW >>

Supplying Material and Fabricating the temporary frame for

installation 04 Conductors.

Pre-installation survey and Post – survey by ROV

Transportation and offshore Installation of 04 conductors

(slot 2,4,5 & 6).

Detail Scope of works, refer to the Split Scope for Conductor Installation

as per link attached file.

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 14: KOM Presentation STN-N Conductor_rev 2

D. PROJECT PROGRESS

• 1. ORGANIZATION CHART

• 2. PROJECT SCHEDULE

PROJECT PROGRESS

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 15: KOM Presentation STN-N Conductor_rev 2

D. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 16: KOM Presentation STN-N Conductor_rev 2

D. PROJECT PROGRESS >>

PROJECT KEY MILESTONE

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 17: KOM Presentation STN-N Conductor_rev 2

D. PROJECT PROGRESS >>

WINDOW FOR OFFSHORE INSTALLATION CAMPAIGN OF TRUONG SA 2014

From 15/07 – 30/07: Thien Ưng SS Template Installation

From 05/08 – 15/08: STN-N Jacket 04 Conductor pipe driving

(Window for offshore installation campaign from 05/08 to 26/08)

From 27/08 – 11/09: NCS2 11.85KM from BK4A to KP.212

PLANNING AND SECURE FOR OFFSHORE CONSTRUCTION OF TRUONG

SA DERRICK BARGE & IHC S280/750 HAMMER 2014

Refer to link Attached file

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 18: KOM Presentation STN-N Conductor_rev 2

E. PROJECT EXECUTION PLAN

• 1. Engineering Plan

• 2. Procurement Plan of VSP

• 3. Marine spread

• 4. Equipment List

• 5. Onshore fabrication & preparation

• 6. Load-out & Transportation

• 7. Offshore Installation

PR

OJE

CT

EX

EC

UT

ION

P

LA

N

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 19: KOM Presentation STN-N Conductor_rev 2

VSP will utilize in-house and out-source for engineering scope. The main offshore

installation analysis shall be:

No. ITEMs In-house Out-source

1 Engineering and procedures for offshore installation x

2 Transportation and sea-fastening design x

3 Installation Engineering support to offshore Installation x

4 Answer technical site queries x

5 Drivability / Stick-up analysis of conductors x

6 Load-out Procedure and Analysis documentation. x

7 Barge Strength Check for Load-out x

8 Sea-fastening & Grillage design x

9 Liaison and coordination with MWS x

E. PROJECT EXECUTION PLAN >>

Refer to the STN North T&I Master Document Register

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Refer to the STN North T&I Procedure list

Page 20: KOM Presentation STN-N Conductor_rev 2

E. PROJECT EXECUTION PLAN >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 21: KOM Presentation STN-N Conductor_rev 2

E. PROJECT EXECUTION PLAN >>

ID No. NAME OF VESSEL SCOPE

1. Derrick Barge spreads

Truong Sa - install/ remove temporary frame

- STN-N Conductor pipe installation

3. Anchor Handling Tugs

Vung Tau 02 - Anchor Handling

- Assist Transportation Barge

- Approach to Truong Sa

4. Transportation Barge

Class 250 Transportation Barge

c/w towing tug (4000–4500 BHP)

- Transportation for Conductor pipes

and Temporary frame.

5. ROV

Ky Van 01 (Inc. ROV) - Pre and Post installation survey

- Assist during Conductor Pipe

Driving

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 22: KOM Presentation STN-N Conductor_rev 2

E. PROJECT EXECUTION PLAN >>

No. DISCRIPTION Q’TY

(pcs)

SCOPE

I Hydraulic Hammer

1.1 S750 1 Conductor Driving

1.2 S280 1 Conductor Driving

II Equipment Other

2.1 Centralizer Equipment 02 The Keep Conductor to Fit-up

and Weld

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 23: KOM Presentation STN-N Conductor_rev 2

TEMPORARY FRAME ONSHORE FABRICATION

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 24: KOM Presentation STN-N Conductor_rev 2

E. PROJECT PROGRESS >>

STN-N JACKET CONDUCTOR PIPE DRIVING STN PROJECTKICK OFF MEETING

Page 25: KOM Presentation STN-N Conductor_rev 2

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Temporary Frame will be load-out by Truong Sa crane

vessel at VSP’s port.

Conductors pipe will be load-out by Crawler Crane at

PTSC’s port.

LOADOUT METHODOLOGY

Page 26: KOM Presentation STN-N Conductor_rev 2

LAYOUT TEMPORARY FRAME ON TRUONG SA VESSEL

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 27: KOM Presentation STN-N Conductor_rev 2

LAYOUT CONDUCTORs PIPE ON BARGE

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 28: KOM Presentation STN-N Conductor_rev 2

TRUONG SA ANCHOR PATTERN FOR PIPE DRIVING

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 29: KOM Presentation STN-N Conductor_rev 2

CONDUCTOR PIPE DRIVING SEQUENCE

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 30: KOM Presentation STN-N Conductor_rev 2

E. PROJECT PROGRESS >>

CONDUCTOR PIPE DRIVING SEQUENCE

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 31: KOM Presentation STN-N Conductor_rev 2

CONDUCTOR PIPE DRIVING SEQUENCE

E. PROJECT PROGRESS >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 32: KOM Presentation STN-N Conductor_rev 2

E. PROJECT PROGRESS >>

CONDUCTOR PIPE DRIVING SEQUENCE

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 33: KOM Presentation STN-N Conductor_rev 2

F. AOB >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 34: KOM Presentation STN-N Conductor_rev 2

F. AOB >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

MARINE WARRANTY SURVEYOR PRESENTATIVE

TBA

Page 35: KOM Presentation STN-N Conductor_rev 2

F. AOB >>

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 36: KOM Presentation STN-N Conductor_rev 2

F. AOB

Weekly Meeting

Weekly report, Monthly report cut off date.

Engineering Documents check, review and approval

flow chart

Weather forecast provides

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING

Page 37: KOM Presentation STN-N Conductor_rev 2

Thank you for your attention!

T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING