Date post: | 14-Apr-2017 |
Category: |
Documents |
Upload: | quan-duy-minh |
View: | 56 times |
Download: | 2 times |
SU TU NAU FIELD DEVELOPMENT – SU TU NAU PROJECT
KICK OFF MEETING FOR
VIETSOVPETRO
Vietsovpetro, 20 May 2014
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
AGENDA
A. SAFETY INSTRUCTION
B. ATTENDANCE INTRODUCTION
C. PROJECT OVERVIEW
D. PROJECT PROGRESS
E. PROJECT EXECUTION PLAN
F. AOB
A. SAFETY INSTRUCTION
VSP/OCD & PSD Building
EMERGENCY EVACUATION PLAN
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
A. SAFETY INSTRUCTION
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
SƠ ĐỒ THOÁT HIỂM TẦNG TRỆT – TÒA NHÀ XNXL-XNDVEMERGENCY ESCAPE PLAN GROUND FLOOR OF OCD-PSD BUILDING.
MUSTER STATION
*WHEN YOU ESCAPED FROM THE BUILDING
*Go and report to your designated Muster Station Location.
B. ATTENDANCE INTRODUCTION
CUU LONG JOC (Client)
PTSC MC (EPCI Contractor)
VIETSOVPETRO (T&I Contractor)
MWS
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
• 1. GENERAL
• 2. SCOPE OF WORK
PROJECT OVERVIEW
C. PROJECT OVERVIEW
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
C. PROJECT OVERVIEW >>
The Su Tu Nau field is located
at the northern part of Block
15-1, Offshore Vietnam and
located approximately 200 km
Southeast of Ho Chi Minh City.
The Su Tu Nau Field consist of two
platforms, one located in the south
area of the field (STN-S) and one in
the northern area of the field (STN-N).
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
C. PROJECT OVERVIEW >>
PICTURE OF STN – N JACKET AT FIELD
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
C. PROJECT OVERVIEW >>
No. Description Detail
1 Platform STN-N
2 Water depth 39.89m
3 Platform Type 4 legged wellhead
4 Conductor slots 6
5 Pre-installed Conductors (By other contractor) 2 (slot 1 & 3)
6 Conductor to be installed by VSP 4 (slot 2,4,5 & 6)
7 Conductor Diameter / Wall Thickness 914mm (36’’) /25mm (1’’)
8 Target Penetration 90.0m
9 Spider Deck Elevation (+) 6.339m
10 Drill Deck Elevation (+) 18.828m
11 Final Conductor Cut-off Elevation (+) 20.328m
12 Top of Wellhead (+) 22.613m
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
C. PROJECT OVERVIEW >>
Segment QTY
Diameter
(m)
Wall
Thickness
(mm)
Length
(m)
Weight
(T)
Cut-off
Allowance
(m)
C1 04 914 25 56 30.68 0
C2 04 914 25 49.524 27.13 1.524
C3 04 914 25 34.524 18.91 1.524
C4 04 914 25 21.768 12.65 9.889
CONDUCTORs SEGMENT
Conductor will be divided into 04 segments in accordance with conductor pipes
installation by using Truong Sa Crane Vessel as below:
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
C. PROJECT OVERVIEW >>
Supplying Material and Fabricating the temporary frame for
installation 04 Conductors.
Pre-installation survey and Post – survey by ROV
Transportation and offshore Installation of 04 conductors
(slot 2,4,5 & 6).
Detail Scope of works, refer to the Split Scope for Conductor Installation
as per link attached file.
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
D. PROJECT PROGRESS
• 1. ORGANIZATION CHART
• 2. PROJECT SCHEDULE
PROJECT PROGRESS
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
D. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
D. PROJECT PROGRESS >>
PROJECT KEY MILESTONE
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
D. PROJECT PROGRESS >>
WINDOW FOR OFFSHORE INSTALLATION CAMPAIGN OF TRUONG SA 2014
From 15/07 – 30/07: Thien Ưng SS Template Installation
From 05/08 – 15/08: STN-N Jacket 04 Conductor pipe driving
(Window for offshore installation campaign from 05/08 to 26/08)
From 27/08 – 11/09: NCS2 11.85KM from BK4A to KP.212
PLANNING AND SECURE FOR OFFSHORE CONSTRUCTION OF TRUONG
SA DERRICK BARGE & IHC S280/750 HAMMER 2014
Refer to link Attached file
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT EXECUTION PLAN
• 1. Engineering Plan
• 2. Procurement Plan of VSP
• 3. Marine spread
• 4. Equipment List
• 5. Onshore fabrication & preparation
• 6. Load-out & Transportation
• 7. Offshore Installation
PR
OJE
CT
EX
EC
UT
ION
P
LA
N
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
VSP will utilize in-house and out-source for engineering scope. The main offshore
installation analysis shall be:
No. ITEMs In-house Out-source
1 Engineering and procedures for offshore installation x
2 Transportation and sea-fastening design x
3 Installation Engineering support to offshore Installation x
4 Answer technical site queries x
5 Drivability / Stick-up analysis of conductors x
6 Load-out Procedure and Analysis documentation. x
7 Barge Strength Check for Load-out x
8 Sea-fastening & Grillage design x
9 Liaison and coordination with MWS x
E. PROJECT EXECUTION PLAN >>
Refer to the STN North T&I Master Document Register
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
Refer to the STN North T&I Procedure list
E. PROJECT EXECUTION PLAN >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT EXECUTION PLAN >>
ID No. NAME OF VESSEL SCOPE
1. Derrick Barge spreads
Truong Sa - install/ remove temporary frame
- STN-N Conductor pipe installation
3. Anchor Handling Tugs
Vung Tau 02 - Anchor Handling
- Assist Transportation Barge
- Approach to Truong Sa
4. Transportation Barge
Class 250 Transportation Barge
c/w towing tug (4000–4500 BHP)
- Transportation for Conductor pipes
and Temporary frame.
5. ROV
Ky Van 01 (Inc. ROV) - Pre and Post installation survey
- Assist during Conductor Pipe
Driving
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT EXECUTION PLAN >>
No. DISCRIPTION Q’TY
(pcs)
SCOPE
I Hydraulic Hammer
1.1 S750 1 Conductor Driving
1.2 S280 1 Conductor Driving
II Equipment Other
2.1 Centralizer Equipment 02 The Keep Conductor to Fit-up
and Weld
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
TEMPORARY FRAME ONSHORE FABRICATION
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT PROGRESS >>
STN-N JACKET CONDUCTOR PIPE DRIVING STN PROJECTKICK OFF MEETING
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
Temporary Frame will be load-out by Truong Sa crane
vessel at VSP’s port.
Conductors pipe will be load-out by Crawler Crane at
PTSC’s port.
LOADOUT METHODOLOGY
LAYOUT TEMPORARY FRAME ON TRUONG SA VESSEL
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
LAYOUT CONDUCTORs PIPE ON BARGE
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
TRUONG SA ANCHOR PATTERN FOR PIPE DRIVING
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
CONDUCTOR PIPE DRIVING SEQUENCE
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT PROGRESS >>
CONDUCTOR PIPE DRIVING SEQUENCE
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
CONDUCTOR PIPE DRIVING SEQUENCE
E. PROJECT PROGRESS >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
E. PROJECT PROGRESS >>
CONDUCTOR PIPE DRIVING SEQUENCE
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
F. AOB >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
F. AOB >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
MARINE WARRANTY SURVEYOR PRESENTATIVE
TBA
F. AOB >>
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
F. AOB
Weekly Meeting
Weekly report, Monthly report cut off date.
Engineering Documents check, review and approval
flow chart
Weather forecast provides
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING
Thank you for your attention!
T&I SERVICES FOR STN-N CONDUCTORSKICK OFF MEETING