Republic of the PhilippinesDEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS
LAGUINDINGAN AIRPORT DEVELOPMENTPROJECT
Our Northern Gateway to Mindanao
PROJECT STATUS AND UPDATES AS OF 30 APRIL 2012
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
2/23
CIVIL WORKS(As of 30 April 2012)
PROJECT STATUS ANDPICTURES
Original ContractAmount : PhP 4,991,771,319.67
Revised Contract
Amount : PhP 5,484,657,799.78
Contractor : Hanjin Heavy Industries & Const. Co., Ltd. (HHIC)
Scope of Works : Runway 2100 m x 45 mTaxiways 23 m x 260 m (A & B)Main Apron 130 m x 355 m (5 Aircraft Parking Bays)Passenger Terminal Bldg. 7184 sq.m.Operation and Control Tower Bldg., Power House Bldg.,Cargo Terminal Bldg., CFR (CAT-1) Bldg.,Maintenance Bldg., Cold Water Receiving StationAdministration Bldg., Waste Water Treatment Plant,Other Airport Support Facilities
Start Date : 18 January 2008Target Date of
Completion : 17 January 2012 (original) Delay is due to the interfacingof civil works & ANSSF
Status : Actual Physical Accomplishment is 95.45% ,Slippage (-) 4.55%
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
3/23
CIVIL WORKS(Ongoing Activities at AirsideArea)
CONSTRUCTION AT RUNWAY AREA
PROJECT STATUS ANDPICTURES
Length Completed:2,100 m (W @ 45 m)
out of 2,100 m
Accomplishment
as of 30 April 2012Actual
(Over-All)91.93%
Description
ICAO Code 4E
2,100 m x 45 m SingleRunway
PCCP Construction, 101,303sq.m. out of the 103,088 sq.m.
(98.26%)
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
4/23
CIVIL WORKS(Ongoing Activities at AirsideArea)
PASSENGER TERMINAL APRON
PCCP Construction46,207 sq.m. out of the 46,207 sq.m.
(100.00%)
PROJECT STATUS ANDPICTURES
Accomplishmentas of 30 April 2012
Actual 94.61%
Description
Max. No.of ParkingBays 5
Area 46,207 sq.m.(355 m x 130 m)
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
5/23
CIVIL WORKS(Ongoing Activities at AirsideArea)
TAXIWAY A CONSTRUCTION
PROJECT STATUS ANDPICTURES
Accomplishmentas of 30 April 2012
Actual 82.22%
Description
No.2 Perpendicular
Dimension (23 m x 260 m)
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
6/23
CIVIL WORKS(Ongoing Activities at AirsideArea)
PROJECT STATUS ANDPICTURES
Sodding
72.71% Complete
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
7/23
CIVIL WORKS(Ongoing Activities at AirsideArea)
AIRSIDE PERIMETER FENCINGWORKS
PROJECT STATUS ANDPICTURES
100% Complete
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
8/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
PASSENGER TERMINALBUILDING
Accomplishmentas of 30 April 2012
Actual 95.00%Description
Design AnnualPassenger
1.6 Million
Design DayPassenger
5,303
PROJECT STATUS ANDPICTURES
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
9/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
PROJECT STATUS ANDPICTURES
Installed (2) PassengerBoarding Bridges (PBB)
PASSENGER TERMINALBUILDING
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
10/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
PROJECT STATUS ANDPICTURES
PTB Roads and Car ParkingArea
99.71% Complete
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
11/23
CIVIL WORKS(Ongoing Activitiesat Landside Area)
OPERATION ANDCONTROL TOWER
BUILDING
Accomplishment
as of 30 April 2012Actual 92.81%
PROJECT STATUS ANDPICTURES
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
12/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
CARGO TERMINAL BUILDING
Accomplishmentas of 30 April 2012
Actual 90.54%
Description
Floor Area 736 m2
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
13/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
CRASH FIRE AND RESCUE BUILDING
Accomplishmentas of 30 April 2012
Actual 90.78%
Description
FloorArea
599 m2
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
14/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
POWER HOUSE BUILDING
Accomplishmentas of 30 April 2012
Actual 86.92%
Description
Floor Area 519 m2
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
15/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
ADMINISTRATION BUILDING
Accomplishmentas of 30 April 2012
Actual 90.16%
Description
Floor Area 730 m2
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
16/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
MAINTENANCE BUILDING
Accomplishmentas of 30 April 2012
Actual 92.31%
Description
Floor Area 739 m2
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
17/23
CIVIL WORKS(Ongoing Activities at LandsideArea)
COLD WATER RECEIVING
STATION
30 April 2012
Actual 94.85%
Description
Floor Area 317 m2Fire WaterSupply
227.50 m3
Cold WaterSupply
227.50 m3
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
18/23
CIVIL WORKS(Ongoing Activities at AccessRoad
ROAD SIGNS
PROJECT STATUS ANDPICTURES
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
19/23
CROSSING - DIAMONDVILLAGE
(As of 05 May 2012)
BEFORE
AFTER
LEFT SIDE (going to the
airport)
RIGHT SIDE (going to the
airport)
PROJECT STATUS ANDPICTURES CONCRETING OF ROAD CROSSINGS AT AIRPORT ACCESS ROAD
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
20/23
CROSSING BARANGAYGASI
(As of 05 May 2012)
BEFORE
AFTER
LEFT SIDE (going to the
airport)
RIGHT SIDE (going to the
airport)
PROJECT STATUS ANDPICTURES CONCRETING OF ROAD CROSSINGS AT AIRPORT ACCESS ROAD
PROJECT STATUS AND
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
21/23
AIR NAVIGATION SYSTEM AND SUPPORTFACILITIES
PROJECT STATUS ANDPICTURES
Estimated Project Cost : US $ 16.07 Million (PhP 755.24 Million)
Source of Funds : EDCF-Republic of Korea - US $ 13.38 MGovernment of the Philippines - US $
2.69 M
Scope of Works : Navigation Aids Facilities-Instrument Landing System (ILS) composed of Localizer
(LLZ),Glide Path Equipment (GP), and Distance Measuring
Equipment (DME)-DVOR/DME-Air Meteorological Observation System (AMOS)-VHF and HF System for Air Traffic Communication-Testing of Equipment, Special Tools, and Spare Part Supply
-Commissioning Flight Test and Operational Test RunAeronautical Ground Lighting System-Underground Conduits and Cables-Airfield Lighting System-Electrical Equipment composed of High and Low Voltage
Electrical Equipment with Cables-Special Tools and Spare Part Supply-Commissionin Fli ht Test and O erational Test Run
PROJECT OVER ALL PHYSICAL AND FINANCIAL PROGRESS (A f 30 A il
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
22/23
PROJECT OVER-ALL PHYSICAL AND FINANCIAL PROGRESS (As of 30 April2012)
8/2/2019 LADP Project Presentation (as of 30 April 2012)_NEDA InfraCom
23/23
THANK
YOU!
Manila Office:#71 Judge Juan LunaSt.San Francisco DelMonteQuezon CityTelefax (02) 411-9161
Project Site Office:LADP Engineers/PMOCompoundBrgy. San Isidro,LaguindinganMisamis OrientalTelefax (088) 858-7626Tel. No. (088) 853-5203
Contact Us:
LADP ProjectManagement Office
LAGUINDINGAN AIRPORTDEVELOPMENT PROJECT
Our Northern Gateway toMindanao