+ All Categories
Home > Documents > Lake Worth Dredging Project Update July 18,...

Lake Worth Dredging Project Update July 18,...

Date post: 28-May-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
21
1 Lake Worth Dredging Project Update July 18, 2012 Paul Bounds, Regulatory and Environmental Coordinator Fort Worth Water Department
Transcript
Page 1: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

1

Lake Worth Dredging Project Update July 18, 2012

Paul Bounds, Regulatory and Environmental Coordinator Fort Worth Water Department

Page 2: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

2

Lake Worth CIP January 2008

• 20” Northside III Water $2,200,000 • Woodvale Sewer System 2,200,000 • Boat Ramps 1,654,000 • Dredging 30,706,000 • Nature Trails/Parks Imp. 18,636,000 • Love Cir./Casino Beach W/S 9,058,000 • Watercress West W/S 4,428,000 • Comanche Creek Drainage 1,300,000 • Access Control/Cable Fencing 1,715,000 • Silver Creek Road Widening 9,073,000 • Maintenance Endowment Fund 9,550,000 • Northside II Water 26,554,000 • Total $117,075,000

Page 3: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

3

Dredging Objectives • Candidate dredge areas from CIIP Study • Recreation enhancement • Safety improvement • Water quality • Boat access to lake • Target elevation of 584 ft-msl

– 6 feet below minimum normal pool • Avoid areas of known PCB contamination

3

Page 4: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

4

Page 5: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

5

Bathymetric Survey

5

Page 6: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

6

Bathymetric Survey Results

6

Page 7: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

7

Geotechnical Investigations

7

Page 8: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

8

Sediment Characterization

8

Page 9: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

9

Sediment Characterization • Phase 1 – 64 samples • Phase 2 – 18 samples • TCEQ waste disposal limits • No PCBs issues • No VOCs (volatile organic compounds) issues • No SVOCs (semivolatile organic compounds) issues • Limited detection of pesticides/herbicides • No in-lake or out-of-lake disposal restrictions

9

Page 10: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

10

Disposal Pre-purchase • Locate a disposal facility early to allow

environmental permitting • Three local bids solicited

– Silver Creek Materials – HJG – Dickey Carr

• Transmission cost estimates added for comparison

• Pre-purchase awarded to Silver Creek Materials

10

Page 11: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

11

Disposal Pre-purchase

11

Page 12: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

12

Final Design • Phase I Design

– Areas to match available funding – Areas easily permitted – Pipeline to Silver Creek Materials – Letter of Permission (LOP) from Corps

• Phase II Design – Remaining dredge areas – Minimal boat channels for access – Allowance for dock owners to “sweep into the hall” – Avoid wetlands and shallow water habitat – LOP amendment for Phase II areas

Page 13: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

13

Boat Dock Dredging Zone (Dock Adjacent to General Recreational Use Dredging Zone)

Shoreline 594’

General Recreational Use Dredging Zone Line

100 FT. Boat Dock Dredging Zone

Distance Varies

Boat Dock

Page 14: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

14

Final Design

14

Page 15: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

15

Project Status • Phase I construction awarded to Great Lakes

– 1.8 million cubic yards – $12.5 million

• Phase II – LOP amendment approved April 10, 2012 – Approx 400,000 cubic yards – Includes boat channels

15

Page 16: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

16

Final Design

16

Page 17: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

17

Moving In

Page 18: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

18

Moving In

Page 19: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

19

Dredging

Page 20: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

20

Remaining Work

• Begin Phase I dredging –Mid July 2012 • Dredging ground breaking ceremony –

July 31, 2012 • Complete Phase II Design –July 2012 • Phase II change order approval – Based

on available funding • Complete Phase 1 dredging – April 2013

20

Page 21: Lake Worth Dredging Project Update July 18, 2012fortworthtexas.gov/uploadedFiles/Water/Drinking_Water... · 2012-09-26 · • Phase II Design – Remaining dredge areas ... 14 Final

21

Questions?

21


Recommended