Date post: | 13-Apr-2017 |
Category: |
Documents |
Upload: | karthik-s-nair |
View: | 147 times |
Download: | 3 times |
PROJECT REPORT
LEAN MANUFACTURING: AN APPLICATION IN
AUTOMOBILE SERVICE SECTOR
DEPARTMENT OF MECHANICAL ENGINEERING
KARTHIK KRISHNA (10409025)
KARTHIK S NAIR (10409027)
NIKHIL J S (10409036)
NIRMAL H (10409038)
MOHANDAS COLLEGE OF ENGINEERING
AND TECHNOLOGY, ANAD, NEDUMANGAD,
THIRUVANANTHAPURAM – 695544
DEPARTMENT OF MECHANICAL ENGINEERING
CERTIFICATE
This is to certify that the bonafide report of project work done by
KARTHIK KRISHNA (REG. NO: 10409025), KARTHIK S NAIR
(REG. NO: 10409027), NIKHIL J S (REG. NO: 10409036),
NIRMAL H (REG. NO: 10409038) of Mechanical Engineering is in
partial fulfillment of the requirement for the award of the degree of
B.Tech in Mechanical Engineering of University of Kerala.
Guide: H.O.D:
Place: Anad
Date:
ACKNOWLEDGEMENT
This work would not have been possible without the support from a large group of people.
We would like to take this opportunity to thank Dr. Ashalatha Thampuran, director of
the institution, for the successful completion of our project phase-2.
We would also like to extend our sincere gratitude to our head of the department and our
project guide, Sreerag R S for providing all the necessary help involving the project work.
We are also thankful to the staff members of the department for their encouragement
and suggestions.
Lean Techniques – An Application in Automobile Service Industry
4
CONTENTS
SL NO: TITLE PAGE NO:
1 INTRODUCTION 5
2 LITERATURE REVIEW- I 10
3 PROBLEM DEFINITION 14
4 OBJECTIVE 16
5 LITERATURE REVIEW - II 17
6 DATA COLLECTION 23
7 DATA ANALYSIS 36
8 INTERPRETATION & IMPLEMENTATION 44
9 SUGGESTIONS 52
10 CONCLUSION 53
Lean Techniques – An Application in Automobile Service Industry
5
1. INTRODUCTION
Lean Manufacturing is a production practice that increases efficiency and profitability
by focusing on speed of output by waste elimination. Waste is anything that does not
add value to end product. Essentially, lean is centered on preserving value with less
work. Lean manufacturing is a management philosophy derived mostly from
the Toyota Production System (TPS) (hence the term Toyot-ism is also
prevalent). TPS is renowned for its focus on reduction of the original Toyota seven
wastes to improve overall customer value, but there are varying perspectives on how
this is best achieved. The steady growth of Toyota, from a small company to the
world's largest automaker, has focused attention on how it has achieved this success.
These are the seven wastes that Toyota had identified.
Transport (moving products that are not actually required to perform the
processing)
Inventory (all components, work in process and finished product not being
processed)
Motion (people or equipment moving or walking more than is required to
perform the processing)
Waiting (waiting for the next production step, interruptions of production during
shift change)
Overproduction (production ahead of demand)
Over Processing (resulting from poor tool or product design creating activity)
Defects (the effort involved in inspecting for and fixing defects)
Lean Manufacturing is a logical collection of practices, methodologies and tools that
focuses on reducing the above mentioned wastes or any other wastes.
As the world gets more competitive and more demanding the old work principles
have become obsolete. Many manufacturing industries have devised lean principles to
increase their profits and reduce their lead times. Even in other spheres of activity
lean has captured attention as a brand or as a concept. Many other fields including the
service sector have started implementing lean techniques. Examples of these from
many sectors are listed below.
Lean Techniques – An Application in Automobile Service Industry
6
Lean principles have been successfully applied to call center services to improve live
agent call handling. By combining Agent-assisted Automation and lean's waste
reduction practices, a company reduced handle time, reduced between agent
variability, reduced accent barriers, and attained near perfect process adherence.
Lean principles have also found application in software application development and
maintenance and other areas of information technology (IT). More generally, the use
of lean in information technology has become known as Lean IT.
A study conducted on behalf of the Scottish Executive, by Warwick University, in
2005/06 found that lean methods were applicable to the public sector, but that most
results had been achieved using a much more restricted range of techniques than lean
provides.
A study completed in 2010 identified that lean was beginning to embed in Higher
Education in the UK.
The challenge in moving lean to services is the lack of widely available reference
implementations to allow people to see how directly applying lean manufacturing
tools and practices can work and the impact it does have. This makes it more difficult
to build the level of belief seen as necessary for strong implementation. it remains the
case that the direct manufacturing examples of 'techniques' or 'tools' need to be better
'translated' into a service context to support the more prominent approaches of
implementation, which has not yet received the level of work or publicity that would
give starting points for implementers.
Due to the above mentioned difficulties there is an absence of lean techniques in the
automobile service industry. Even though the automobile service industry is closely
related to the automobile manufacturing industry lean techniques have skipped
attention.
This project aspires to implement lean techniques in the automobile service industry.
The main focus is on collecting data from an automobile service station.
Lean Techniques – An Application in Automobile Service Industry
7
The subject of our case study
Sarathy auto cars Trivandrum seemed to be the best choice for the project purpose.
Sarathy has been in the automobile industry since 1987. They have been one of the
major dealerships associated with Maruti Suzuki. Sarathy auto cars are an
organization with a turnover of Rs 300 crore. They have been recognized with many
awards like “Excellence in sales award from Maruthi Suzuki limited” in 2000-2001.
Sarathy auto cars does regular service. running repairs, accident works and body shop
works of all Maruthi cars.
Lean Techniques – An Application in Automobile Service Industry
8
FLOOR LAYOUT
Lean Techniques – An Application in Automobile Service Industry
9
ORGANISATIONAL STRUCTURE
Lean Techniques – An Application in Automobile Service Industry
10
2. LITERATURE REVIEW
As a prelude to the project the important tools used in lean are mentioned below.
2.1 LEAN TOOLS
2.1.1 5S
Fig.3.1 (a) – The 5S’s Fig.3.1 (b) 5S applied in a tool shop.
5S was developed by Hiroyuki Hirano within his overall approach to production
systems. 5S is the name of a workplace organization method that uses a list of
five Japanese words: seiri, seiton, seiso, seiketsu, and shitsuke. These 5 words, which
are often termed as the 5-pillars of the visual workplace, is a systematic process of
workplace organization. The 5 pillars are:
Sort (seiri) - Sort, the first S, focuses on eliminating unnecessary items from the
workplace that are not needed for current production operations
Set In Order ( seiton) - Set In Order focuses on creating efficient and effective storage
methods to arrange items so that they are easy to use and to label them so that they are
easy to find and put away.
Lean Techniques – An Application in Automobile Service Industry
11
Shine or systematic cleaning (seiso) - Once the clutter that has been clogging the work
areas is eliminated and remaining items are organized, the next step is to thoroughly
clean the work area.
Standardize (seiketsu) - Once the first three 5S's have been implemented, the next
pillar is to standardize the best practices in the work area.
Sustain (shitsuke) - Sustain, making a habit of properly maintaining correct
procedures, is often the most difficult S to implement and achieve. Changing
entrenched behaviors can be difficult, and the tendency is often to return to the status
quo and the comfort zone of the "old way" of doing things.
2.1.2. BOTTLENECK ANALYSIS
Fig 3.3 Steps in Bottleneck Analysis
This analysis identifies the part of the manufacturing processes that, limits the overall
throughput and improve the performance of that part of the process. It improves the
whole process by strengthening the weakest link in the manufacturing process.
2.1.3. JUST-IN-TIME (JIT)
JIT sets out to cut costs by reducing the amount of goods and materials a firm holds in
stock. JIT involves:
producing and delivering finished goods ‘just in time’ to be sold
Lean Techniques – An Application in Automobile Service Industry
12
partly finished goods ‘just in time’ to be assembled into finished goods
parts ‘just in time’ to go into partly finished goods
Materials ‘just in time’ to be made into parts.
2.4. KAIZEN (Continuous Improvement)
Kaizen is a Japanese business philosophy focused on making constant improvements.
Its underlying concept stresses there will always be room for improvement.
Fundamentally, kaizen aims to improve all activities and processes and eliminate
waste and excess.
2.1.5. KANBAN (Pull System)
Fig 3.11 Example for Kanban Board
It is derived from the combination of two Japanese words, kan ("visual") and ban
("card" or "board"), kanban roughly translates to sign board or signal board.
Kanban is a scheduling system for lean and just-in-time (JIT) production.
2.2 INDIAN SCENARIO
Lean manufacturing in India is still in infancy stage and the Indian firms are far away
from enjoying its complete benefits. The awareness level of Indian firms on lean
manufacturing is very low. The concept is largely adopted only by the big firms. One
such example is Tata Motors which has created a success story by launching Nano
implementing lean manufacturing. Tata has managed to reduce the cost of the product
Lean Techniques – An Application in Automobile Service Industry
13
by lean manufacturing processes without compromising on space and comfort, which
are the Nano’s biggest USPs. Japanese are known to be Pundits of Lean
manufacturing techniques. Indian automotive market is not new to Japanese
manufacturers; they have been here for good number of years. But till today they have
not been able to implement even 20% of their work lean techniques. Reasons behind
it are mainly corruption, poor infrastructure, and social excursion within Indian
economy.
The case of automobile service industry which is closely related to the automobile
manufacturing industry is no different. India is the largest growing automobile market
in the world. India stands 5th when it comes to the sales figures of automobiles and
will climb to second spot with an year overtaking developed countries like Germany.
The amount of cars in India have increased manifold on the Indian roads. The number
of cars to be serviced daily has increased considerably. Still the same old work
practices are followed in India.
Lean Techniques – An Application in Automobile Service Industry
14
3. PROBLEM DEFINITION
As mentioned before lean techniques were inspired from Toyota Production System
(TPS). Toyota's development of ideas that later became Lean may have started at the
turn of the 20th century with Sakichi Toyoda, in a textile factory with looms that
stopped themselves when a thread broke. This became the seed of autonomation
and Jidoka. Toyota's journey with JIT may have started back in 1934 when it moved
from textiles to produce its first car. Kiichiro Toyoda, founder of Toyota Motor
Corporation, directed the engine casting work and discovered many problems in their
manufacture. He decided he must stop the repairing of poor quality by intense study
of each stage of the process. Having visited and seen supermarkets in the USA,
Taiichi Ohno recognized the scheduling of work should not be driven by sales or
production targets but by actual sales. Given the financial situation during this period,
over-production had to be avoided and thus the notion of Pull (build to order rather
than target driven Push) came to underpin production scheduling.
It was with Taiichi Ohno at Toyota that these themes came together. He built on the
already existing internal schools of thought and spread their breadth and use into what
has now become the Toyota Production System (TPS).
Problems faced in Sarathy.
The issues faced in Sarathy are very much similar to what Toyota or any other major
industry had been facing. The cars required to be serviced per day has increased
considerably. Due to the limitations that the company faces regarding lead time the
company is not able to uptake more orders.
A fishbone diagram representing the various factors that add to increase of lead time
is shown below.
Lean Techniques – An Application in Automobile Service Industry
15
FISH BONE DIAGRAM
Lean Techniques – An Application in Automobile Service Industry
16
4. OBJECTIVE OF PROJECT
From the data collected it was found that increased delay in lead time was the major
problem faced in Sarathy. The purpose of this project is as follows.
To reduce the lead time in delivering of vehicles by using lean techniques.
To increase the efficiency of the service department.
To improve the profit and increase customer satisfaction.
To identify and eliminate existing bottlenecks.
To improve worker morale by eliminating unnecessary work (muda).
Lean Techniques – An Application in Automobile Service Industry
17
5. LITERATURE REVEW
There are so many tools used for the analysis of the data collected. A Brief description
of each tool is being to be discussed below.
5.1 HISTOGRAM
In statistics, a histogram is a graphical representation of the distribution of data. It is
an estimate of the probability distribution of a continuous variable and was first
introduced by Karl Pearson. A histogram is a representation of tabulated frequencies,
shown as adjacent rectangles, erected over discrete intervals (bins), with an area
proportional to the frequency of the observations in the interval. The height of a
rectangle is also equal to the frequency density of the interval, i.e., the frequency
divided by the width of the interval. The total area of the histogram is equal to the
number of data. A histogram may also be normalized displaying relative frequencies.
Histograms are used to plot the density of data, and often for density estimation:
estimating the probability density function of the underlying variable. The total area
of a histogram used for probability density is always normalized to 1. If the length of
the intervals on the x-axis is all 1, then a histogram is identical to a relative
frequency plot. Example for histogram is shown below.
Lean Techniques – An Application in Automobile Service Industry
18
5.2 PARETO CHART
A Pareto chart, named after Vilfredo Pareto, is a type of chart that contains
both bars and a line graph, where individual values are represented in descending
order by bars, and the cumulative total is represented by the line. The left vertical axis
is the frequency of occurrence, but it can alternatively represent cost or another
important unit of measure. The right vertical axis is the cumulative percentage of the
total number of occurrences, total cost, or total of the particular unit of measure.
Because the reasons are in decreasing order, the cumulative function is a concave
function. The purpose of the Pareto chart is to highlight the most important among a
(typically large) set of factors. In quality control, it often represents the most common
sources of defects, the highest occurring type of defect, or the most frequent reasons
for customer complaints, and so on.
5.3 SCATTER DIAGRAM
A scatter plot, scatter plot, or scatter graph is a type of mathematical
diagram using Cartesian coordinates to display values for two variables for a set of
data. The data is displayed as a collection of points, each having the value of one
variable determining the position on the horizontal axis and the value of the other
variable determining the position on the vertical axis. A scatter plot is used when a
Lean Techniques – An Application in Automobile Service Industry
19
variable exists that is below the control of the experimenter. If a parameter exists that
is systematically incremented and/or decremented by the other, it is called the control
parameter or independent variable and is customarily plotted along the horizontal
axis. The measured or dependent variable is customarily plotted along the vertical
axis. If no dependent variable exists, either type of variable can be plotted on either
axis or a scatter plot will illustrate only the degree of correlation (not causation)
between two variables.
5.4 BOX PLOT
A box plot or box plot is a convenient way of graphically depicting groups of
numerical data through their quartiles. Box plots may also have lines extending
vertically from the boxes (whiskers) indicating variability outside the upper and lower
quartiles, hence the terms box-and-whisker plot and box-and-whisker diagram.
Outliers may be plotted as individual points. Box plots display differences
between populations without making any assumptions of the underlying statistical
distribution: they are non-parametric. The spacings between the different parts of the
box help indicate the degree of dispersion (spread) and skewness in the data, and
identify outliers. In addition to the points themselves, they allow one to visually
Lean Techniques – An Application in Automobile Service Industry
20
estimate various L-estimators, notably the inter quartile range, midhinge, range, mid-
range, and trimean. Box plots can be drawn either horizontally or vertically.
5.5 CONTROL CHART
Control charts, also known as Shewhart charts (after Walter A. Shewhart) or process-
behaviour charts, in statistical process control are tools used to determine if a
manufacturing or business process is in a state of statistical control. The control chart
is one of the seven basic tools of quality control.[3] Typically control charts are used
for time-series data, though they can be used for data that have logical comparability
If analysis of the control chart indicates that the process is currently under control
(i.e., is stable, with variation only coming from sources common to the process), then
no corrections or changes to process control parameters are needed or desired. In
addition, data from the process can be used to predict the future performance of the
process. If the chart indicates that the monitored process is not in control, analysis of
the chart can help determine the sources of variation, as this will result in degraded
process performance.[1] A process that is stable but operating outside of desired
(specification) limits (e.g., scrap rates may be in statistical control but above desired
limits) needs to be improved through a deliberate effort to understand the causes of
current performance and fundamentally improve the process.
Lean Techniques – An Application in Automobile Service Industry
21
5.6 SPAGHETTI CHART
A spaghetti chart is a graphical aid used in lean manufacturing activities. It is used to
detail the actual physical flow and distances involved in a work process. A spaghetti
chart often traces the walking patterns of workers in a process, ranging from
manufacturing settings to healthcare. It mostly serves as an illustration of a system's
inefficiency. To create a spaghetti chart you first create a scale map of a work station
or work process. The next step is to draw a line from the initial point of work to the
next step, then the third step, and so on until the work/product exits the work area.
Examination of this resulting chart will show where improvements are to be made. To
create a spaghetti chart you first create a scale map of a work station or work process.
The next step is to draw a line from the initial point of work to the next step, then the
third step, and so on until the work/product exits the work area. Examination of this
resulting chart will show where improvements are to be made. This chart can be made
in 4 different detail levels. Which route the product takes where the operator walks,
where the hands of the operator are needed and where the eyes of the operator are
watching. Every single detail level can be analyzed. Spaghetti charts can be used to
improve the quality of processes in various fields.
Lean Techniques – An Application in Automobile Service Industry
22
Lean Techniques – An Application in Automobile Service Industry
23
6. DATA COLLECTION
DAY 1
The first day observations were made on a much broader perspective. The main idea
was to get a general picture of the whole organization and its work practices. Sarathy
has divided its work into namely three sections. The first section deals with free and
paid services.it also include running repairs. The second section deals concerned with
accident works. The third is body shop area which does all paint jobs and dent
removals. The main focus on this project is on the workshop floors which deal with
services and accident works. The floor layout was observed and a sketch was made.
The shifts of the workers were also noted. The shifts are as follows:
SHIFT TIME
1st SHIFT
8:00-12:00
2nd SHIFT
12:45-16:45
Observations were made regarding the methodologies the company followed when a
car enters the service station.
As a car enters the bay a service advisor attends the customer. Prepares a job card
based on the complaints and does a test drive to determine existing as well as
potential problems. The car then enters the bay. The work is assigned to a particular
mechanic by the floor manager. Major works are serviced in the first come first serve
order. Minor works were the customer has to be delivered within a short span of time
are given more priority than major works. First the customer must be attended, then
his complaints should be taken down and his car should be test driven. All this must
be completed within 15 minutes. The car must enter the work floor within the next 10
minutes.
But as we observed on the first day test drives are rarely taken for any vehicle. There
is even delay in attending the customer and the 15 min time frame was lapsed in most
Lean Techniques – An Application in Automobile Service Industry
24
cases. We also observed the lack of space to accommodate cars and this restricts the
free movement of cars within the work floor.
Tools are arranged in some of the bays but that’s not the case in every bay. Water for
refilling the radiator or wiper fluid or for other related works was not available within
the bays. The mechanic had to walk around 150 meters to get to the water outlet.
DAY 1 OVERVIEW
Customer not attended and cars not test driven within 15 minutes
Unavailability of space leading to congestion within the floor
Lack of water outlet within the bay
Lack of arrangement of tools.
DAY 2
On day two observations are made in detail to find out wastes (muda) that tend to
increase the lead time. The observations we made on the second day was striking. It
was found that most of the time was lost in the store. Another major muda was in the
wheel alignment bay. On an average wheel alignment takes only 20 minutes if there
are no major overhauls. But in Sarathy we found that wheel alignment was taking
more than 40 minutes. When we did a detailed study and observed the whole
procedure step by step we could infer that the system had faulty sensor. Since the
sensor was faulty it took more time to calibrate the tires with respect to the computer
system.
As mentioned above it was found that major time lose was observed in the store.so it
was decided that we concentrate more on the store. We observed the store and found
some important revelations. The store had only one computer and a staff was assigned
with the computer related works.as it can be seen in the hierarchy the spare manager
is the head of the spares department. There are other four staffs - three for spares and
one for accessories. All the spares have part IDs. The part IDs are already entered on
the computer. Sarathy uses a dedicated server devised by maruti Suzuki. All the part
IDs are loaded within the server. The number of stock available its position and the
next arrival date of stock are all mentioned. If a part is unavailable, its nearest location
Lean Techniques – An Application in Automobile Service Industry
25
be it in a branch of Sarathy or any other dealer network is shown in the server. The
data of each part is updated on the server as parts are consumed. The data includes
how many parts are left, when the next stock will arrive and in which car was the part
replaced. According to maruti policy there should be a minimum amount of stock of
every part. Depending on the data being updated orders are placed automatically to
maruti who produces the right amount of parts and delivers it to the dealerships. Parts
that are not consumed within 3 months are called dead and the dealership is
answerable to maruti for each and every dead part. The workers seem to know by
heart the part IDs of frequently consumed spares.
The delay that occurred in the store was mainly due to the procedure that was flowed
in the spares department. The worker has to get a slip from the spares department
right a formal request for the part. The person attending the computer has to go
through part manual of each car to find the part ID of the spare requested in case he
doesn’t know the ID. Searching through the manuals usually takes a lot of time.
During all these process work is halted and the worker has to wait patiently for spare
dispatch. If there is another worker in front of the queue there is additional time
wasted for the one behind. Sometimes time is wasted in silly things like going around
the whole floor space in search of a pen.
We could find that the man power in Sarathy seemed to fluctuate. Many mechanics
we saw on the first day were missing on the second day. Three bays were totally
handled by trainees as the main mechanics were on leave. Absenteeism can be one of
the factors for larger lead times.
Lean Techniques – An Application in Automobile Service Industry
26
DETAILS COLLECTED FROM ALIGNMENT BAY
CAR DETAILS
TIME TAKEN (min)
MARUTI ERTIGA
MARUTI 800
ALTO 800
A-STAR
SWIFT DZIRE LDi
25
28
30
35
35
DAY 2 OVERVIEW
Store procedure investigated
Inconsistent man power
Data related to wheel alignment bay taken down
DAY 3
On day 3 our main aim was to prepare a check sheet of issues by which delay was
created. The main purpose of this check sheet is to find out the major cause of delay.
10 cars were observed. The check sheet is as follows
Lean Techniques – An Application in Automobile Service Industry
27
A Maruti Ertiga with complaint with rear axle had entered the bay and was delayed
due to following reasons.
The rear axle is heavy part and is a major work. There was only one worker in the
bay he had to take the help of mechanics from other bays to help him replace the axle.
Hence lack of manpower contributed to the loss of time. Wheel alignment after the re
fixing of tires was delayed because of the faulty sensors which delayed the delivery of
the vehicle.
A Maruti Ertiga with noise from the rear.
The maruti ertiga had noise from the rear because of a worn out bush in the window
near to the c-pillar. The new part was dispatched late causing delay. Since it was a
minor work it was not allotted a particular bay so the worker had to move around to
another bay in order to get appropriate tools causing delay.
Wagon R for front right suspension strut replacement.
REASONS
FOR DELAY
CAR
1
CAR
2
CAR
3
CAR
4
CAR
5
CAR
6
CAR
7
CAR
8
CAR
9
CAR
10
LACK OF
SPACE
LACK OF
MANPOWER
FAULTY
SENSORS
LACK OF
TOOLS
DELAY IN
SPARE
DESPATCH
Lean Techniques – An Application in Automobile Service Industry
28
Maruti uses mac-phearsons strut for its suspension. The strut has to be replaced with
the springs compressed.so they removed the strut and took it to the engine room
where they have a vice to compress the springs. The engine room didn’t have a tool
box so the worker had to keep moving out to get tools required. The strut was also
delivered late. The wheel alignment after the suspension replacement also took more
time.
Alto LPG gas fitted for general service.
Since the above work took lot of there was no space available in the workshop floor.
The alto had to wait to get in. lack of space contributed to the delay. Wheel alignment
which is a standard practice for general service was delayed due to the faulty sensors.
Maruti Esteem for service.
Wheel alignment for the esteem took more time.
Swift diesel for winding assembly replacement.
Winding assembly that they took from the store had to go back to the store many
times as a proper fit was not obtained. The new part was not seating as it was not
suitable for the swift. After many try outs a suitable match was found out. Lot of time
was lost. There was lack of man power as well. The glass window needs to be held by
another worker. Since the mechanic was alone he had to call out or the help for
another person. Hence the work got delayed.
Swift Dzire for spark plug replacement and general service.
The above work was delayed hence lack of space prevented this car from entering the
bay. Wheel alignment for the vehicle as part of general service was delayed due to the
faulty sensors.
Alto K10 for general service.
Lack of space and delay in wheel alignment contributed to the delay in lead time.
Baleno diesel for turbo charger replacement
Lean Techniques – An Application in Automobile Service Industry
29
The part was dispatched late. The lack of tools leads to the worker searching for tools
in another bay.
Zen Estilo for general service
Wheel alignment as part of service was delayed due to the fault with the sensor. Lack
of space because many works were delayed hence no lift was free. The Estilo had to
wait causing waste of time.
Part of our time we spent on collecting time for wheel alignment.
DETAILS COLLECTED FROM ALIGNMENT BAY
CAR DETAILS
TIME TAKEN (min)
WAGON R
ALTO LPG
ESTEEM
ZEN ESTILO
35
39
40
29
DAY 3 OVERVIEW
Check list prepared
Data required for wheel alignment bay acquired.
DAY 4
On day 4 the main focus was on getting data to strengthen our findings about the
faulty sensor and to prove that lead time was increased due to it. We collected data
about 6 other vehicle ranging from hatchbacks to MPVs. The data is as given below.
Lean Techniques – An Application in Automobile Service Industry
30
DETAILS COLLECTED FROM ALIGNMENT BAY
CARS
TIME (min)
SWIFT DZIRE LDi
SWIFT ZXi
RITZ VDI
ALTO LX
ERTIGA
OMNI
31
35
27
28
29
32
As we noticed the times required for alignment was too long for all the six cars and
alto lx took the longest of time for wheel alignment. There was no specialized worker
for wheel alignment. Workers who did wheel alignment kept changing for each car.
Alto lx a model with no power steering took the most time for this day’s observations.
This could be because of the large number of kilometers the old car has cloaked or
because of the lack of expertise of the worker.
We also made it a point to analyze the worker movement by drawing spaghetti chart
by observing the worker on bay 9.
DAY 4 OVERVIEW
Data from wheel alignment was taken
The first spaghetti chart was drawn
Lean Techniques – An Application in Automobile Service Industry
31
DAY 5
On day two we had spoken with the service manager about the faulty sensor of the
wheel alignment equipment. He responded by saying that the sensors were faulty but
they had overlooked its replacement because of the large amount of capital involved
in its replacement. We had to convince him about the time lost and made him aware
of the fact that lost time affects efficiency as well as cars serviced per day. Lesser the
amount of cars serviced translates to lesser profit.so we said changing the sensors
would be the best thing to do and would help in increasing the profit in the long run.
So on our fifth visit to sarathy the sensors had been replaced and the computer system
Lean Techniques – An Application in Automobile Service Industry
32
was functioning as good as new. We took the wheel alignment data of cars that come
for wheel alignment.
DETAILS COLLECTED FROM ALIGNMENT BAY
CARS
TIME (min)
GYPSY
ALTO LXI
ALTO K10 VXI
STING RAY
ERTIGA
MARUTHI 800
BALENO
15
16
16
17
17
17
17
It was found that the time had considerably reduced after the sensor replacement.
DAY 5 OVERVIEW
Spaghetti chart was drawn
The data after sensor replacement was taken
Lean Techniques – An Application in Automobile Service Industry
33
DAY 6
For collecting more data from the wheel alignment bay and for confirming the
elimination of muda we made a final visit to Sarathy. We took more set of values .the
values are as follows
Lean Techniques – An Application in Automobile Service Industry
34
DETAILS COLLECTED FROM ALIGNMENT BAY
CARS
TIME (min)
ERTIGA
RITZ
MARUTHI 800
SX4
SWIFT DIESEL
MARUTHI 800
OMNI
SWIFT
18
20
18
16
16
18
19
18
The time required for wheel balancing has reduced considerably. Spaghetti
chart was also drawn.
DAY 6 OVERVIEW
Elimination of muda confirmed by taking more data from wheel
alignment bay.
Spaghetti chart is drawn.
Lean Techniques – An Application in Automobile Service Industry
35
Lean Techniques – An Application in Automobile Service Industry
36
7. DATA ANALYSIS
The analysis of the data collected is going to be done with the help of the lean tools
mentioned in the literature review namely histogram, pareto chart, gantt chart, scatter
diagram, box plot etc.
On day 3, servicing time for ten vehicles was recorded and the places where
excessive delay occurred were noted. This data was then plotted into check sheet as
shown below.
CHECKSHEET
Based on the check sheet the frequency of various reasons causing delay was
established and are plotted in a histogram.
REASONS
FOR DELAY
1
2
3
4
5
6
7
8
9
10
LACK OF
SPACE
LACK OF
MANPOWER
FAULTY
SENSORS
LACK OF
TOOLS
DELAY IN
SPARE
DESPATCH
Lean Techniques – An Application in Automobile Service Industry
37
DATA SET FOR HISTOGRAM
REASON
FREQUENCY
LACK OF SPACE
4
LACK OF MANPOWER
2
FAULTY SENSORS
7
LACK OF TOOLS
3
DELAY IN SPARE DESPATCH
4
From the histogram the frequency of the main reasons in causing delay was recorded.
Now to get a clear idea of what the prominent problem is, this histogram is converted
into a pareto chart.
DATA SET FOR PARETO CHART
Lean Techniques – An Application in Automobile Service Industry
38
DATA SET FOR PARETO CHART
REASON
FREQUENCY
PERCENT
CUMULATIVEPERCENT
FAULTY SENSORS
7
35
35
LACK OF SPACE
2
20
55
DESPATCH DELAY
7
20
75
LACK OF TOOLS
3
15
90
MANPOWER
4
10
100
Lean Techniques – An Application in Automobile Service Industry
39
From the above data and charts, the details regarding the reasons for delay are all
plotted. Sarathy undertakes regular service, repairs, accident works and body shop
works. Our project primarily focuses on regular service. The works done in regular
service includes removing tyre and cleaning brake dust, clutch adjustment, wheel
alignment etc. The time taken for regular service activities were recorded for a
number of cars. Many of the activities were completed as per standard time and many
were delayed beyond a certain limit. Using the data which represents the most delayed
operation scatter diagram is plotted, which depicts efficiency in carrying out that
operation.
DATA SET FOR SCATTER DIAGRAM
SL.NO ACTIVITY STANDARD TIME
(min)
ACTUAL TIME
(min)
01 ATTENDING THE VEHICLE 15 30
02 SHIFTING TO BAY 10 25
03 LIFTING OF VEHICLE 01 01
04 REMOVING TYRES AND
CLEANING BRAKE DUST
20 20
05 CLEANING/REPLACEMENT
OF AIR/OIL FILTER
20 28
06 TOPPING OF
OIL,COOLANT,WIPER AND
BRAKE FLUID
15 25
07 CLUTCH ADJUSTMENT 10 10
08 WHEEL BALANCING 15 20
09 WHEEL ALLIGNMENT 15 40
10 FINAL INSPECTION AND
ROAD TEST
10 12
Lean Techniques – An Application in Automobile Service Industry
40
SCATTER DIAGRAM
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 1 2 3 4 5 6 7 8 9 10
Y-Values
From the scatter diagram the efficiency of all activities done was calculated. The
activity and efficiency table is shown below:
SL.NO ACTIVITY EFFICIENCY
01 ATTENDING THE VEHICLE 50
02 SHIFTING TO BAY 40
03 LIFTING OF VEHICLE 100
04 REMOVING TYRES AND
CLEANING BRAKE DUST
100
05 CLEANING/REPLACEMENT
OF AIR/OIL FILTER
71
06 TOPPING OF
OIL,COOLANT,WIPER AND
BRAKE FLUID
60
07 CLUTCH ADJUSTMENT 100
08 WHEEL BALANCING 75
09 WHEEL ALLIGNMENT 37.5
10 FINAL INSPECTION AND
ROAD TEST
83.3
Lean Techniques – An Application in Automobile Service Industry
41
From the above data, a box plot is created using the activity times, which got
efficiency less than 75%.
DATA SET FOR BOXPLOT
OBSERVATIONS IN ATTENDING THE VEHICLE
NO TIME (min)
1 20
2 25
3 28
4 20
5 17
6 10
7 30
8 15
OBSERVATIONS IN BAY ENTERING
NO TIME (min) MINIMUM 8
1 10 LOWER
QUARTILE
12.5
2 8 MEDIAN 16
3 15 UPPER
QUARTILE
21
4 20 MAXIMUM 25
5 25
6 15
7 22
8 17
MINIMUM 10
LOWER QUARTILE 16
MEDIAN 20
UPPER QUARTILE 26.5
MAXIMUM 30
Lean Techniques – An Application in Automobile Service Industry
42
OBSERVATIONS IN TOPPING
NO TIME
1 15
2 21
3 18
4 17
5 25
6 25
7 21
8 23
OBSERVATIONS IN WHEEL ALIGNMENT
MINIMUM 15
LOWER QUARTILE 16
MEDIAN 20.5
UPPER QUARTILE 22
MAXIMUM 25
NO TIME
MINIMUM 25
1 25 LOWER
QUARTILE
29
2 28 MEDIAN 35
3 39 UPPER
QUARTILE
37
4 35 MAXIMUM 40
5 40
6 30
7 35
8 35
Lean Techniques – An Application in Automobile Service Industry
43
TIMING IN BOXPLOT
0 5 10 15 20 25 30 35 40 45
AC
TIV
ITIE
S
TIME
Alignment
Topping
Bay Entering
Attending
Lean Techniques – An Application in Automobile Service Industry
44
8. INTERPRETATION AND IMPLEMENTATION
The main problem that we noted which delayed service time was due to excessive
delay in wheel alignment bay. The usual time that wheel alignment should take ranges
from 15-20 minutes. But in Sarathy we noticed that this extends even up to 40
minutes. This was due to a fault in the sensor. So we recorded time taken by some
more vehicles in alignment and it really worried us as there was so much wastage in
time here. We talked about this with the manager. But, since there was no particular
worker for wheel alignment, it was not noticed clearly and a loss of 10 to 15 minutes
was not that much concerning compared to the expense needed in replacing the
sensor. The cost for replacing the sensor amounts to Rs 1, 15,000.
Service cost for a normal service is:
For a petrol car = Rs 1200
For a diesel car = Rs 4000
The time recorded for 15 vehicles are:
Car
no
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Time
(min)
25
28
30
35
35
35
39
40
29
31
35
27
28
29
32
Considering the actual time that a worker will take for alignment to be 20 minutes,
If the fault is repaired and actually 20 minutes is taken for alignment, then it would
mean 10-12 other cars could also be aligned.
Total Time Lost = 168 minutes (approx. 3 hours)
Lean Techniques – An Application in Automobile Service Industry
45
If we talk in terms of cars called for normal service, this time would represent
servicing time needed for one more car, perhaps two. If it’s a petrol car each day for a
month, then,
And they will be able to recover the capital invested for replacing the sensor in just 4
months. And if it’s a diesel car, then,
They will be able to recover the amount in just 1 month.
We showed this analysis to the manager and he was convinced and took
corresponding measures, i.e., sensor was replaced. The following days we observed
the time taken for alignment. The time took was significantly reduced. The time
recorded for 15 vehicles after sensor replacement was:
Car
no
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Time
15
16
16
17
17
17
17
16
20
18
16
16
18
19
18
The variations can be easily observed with the help of a control chart, which is shown
below:
Total Amount received in a month = 1200*26 = Rs 31,200
Total Amount received in a month = 4000*26 = Rs 1,04,000
Lean Techniques – An Application in Automobile Service Industry
46
CONTROL CHART
0
5
10
15
20
25
30
35
40
45
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Vehicle No:
Tim
e
Control Chart
New UCL
Improved Mean
New LCL
The improvement was recorded using a box plot also. It is shown below:
EFFICIENCY VARIATION
0 5 10 15 20 25 30 35 40 45
AL
IGN
ME
NT
TIME
After
Before
Lean Techniques – An Application in Automobile Service Industry
47
SPAGHETTI CHART ANALYSIS
1st CHART
Lean Techniques – An Application in Automobile Service Industry
48
The first spaghetti chart with the red lines indicates the actual movement of the
worker. The one below it shows only the necessary movements. The work was on Bay
8.
MOVEMENT TIME TAKEN ( in seconds)
NECESSARY 145
FOR ANOTHER CAR 56
UNWANTED 142
In the necessary movement itself 112 seconds was spent for fetching water. This
essentially shows the need for a water outlet in the bay. Since the worker is not
concentrating on one particular car, it takes more than what is actually needed for its
delivery.
2nd CHART
Lean Techniques – An Application in Automobile Service Industry
49
Here, the work was on Bay 13.
MOVEMENT TIME TAKEN ( in seconds)
NECESSARY 76
FOR ANOTHER CAR 655
UNWANTED 387
In this case the work on Bay 13 could have been finished much earlier, if not for the
delay in despatch delivery. This made the mechanic to move onto another car. The
necessary movement was mainly for fetching water. In this case too many visits to the
spare store show the need for a spare runner and also the much time consuming spare
dispatch procedure.
Lean Techniques – An Application in Automobile Service Industry
50
3rd CHART
Here the work was on 2 Tech Bay II. The mechanic was concentrating on just one car
in this case. But from the chart itself we can understand that there were so many
unwanted movements.
Lean Techniques – An Application in Automobile Service Industry
51
MOVEMENT TIME TAKEN ( in seconds)
NECESSARY 420
FOR ANOTHER CAR 0
UNWANTED 2160
The unwanted movements took 2160 seconds or 36 minutes. The main reasons for
these were unavailability of water in bay, waiting time in spare store etc. In this case
the mechanic had to move so many times to 2 Tech Bay I and Wheel Balancing Bay,
as some tools needed for his work was kept in the tool boxes in these bays. In the
necessary movement itself, he had to visit spare store frequently, which again shows
the need for a spare runner.
Lean Techniques – An Application in Automobile Service Industry
52
9. SUGGESTIONS
Based on the observations suggestions were made as solutions to the existing
problems in Sarathy.
The main thing we proposed was a water outlet in proximity with all the bays.
This was to avoid unnecessary worker movements and reduce wastage of time.
Tool box was not present in every bay. Since there was no tool box in every
bay the mechanic had to move to other bays were tool box was present to find
the necessary tools. It is essential to provide tool box in every bay including
one in the engine room.
The tool boxes were of different types in different bays. This created a
difficulty for workers who at times had to change bays. Each worker gets used
to his tool box in his bay. So it takes time for him to adapt to the new
arrangement. So we propose that there must be standardization of the tool box
used in Sarathy.
Since tools were not arranged in every bay it is ideal to have shadow boards so
that each tool will be placed only in the right slot.
There is delay in spare despatch and the worker has to wait. To avoid the
unnecessary delay, we advise to employ a spare runner to assist the delivery of
spare to each bay avoiding the movement of worker. The unwanted
movement of the worker can also be avoided if a spare part runner is present.
In the wheel alignment bay worker keeps changing for every car, there is no
specialized worker for wheel alignment. It is advisable to have specifically
trained worker for wheel alignment. The more experienced a worker is for a
particular job the lesser time he needs to do it.
Lean Techniques – An Application in Automobile Service Industry
53
10. CONCLUSION
There were many suggestions made to sarathy based on the observations made.
Sarathy immediately acknowledged our findings by replacing the faulty sensors.
Sarathy also said they will think about the other suggestions and would take the steps
needed after studying the feasibility of the suggestions made.
It’s a pleasure to mention that we have gained knowledge of lean techniques and
principles. There were limitations of time and knowledge which prevented us from
making Sarathy more efficient. It is planned that these improvements in sarathy can
be brought in the future development of this project.
FUTURE IMPROVEMENTS IN PROJECT
We have been concentrating only in the workshop floor for implementing lean
techniques. We wish to expand these principles to other departments of sarathy like
accounts, managerial section and to the body shop department.
Lean techniques are better implemented if we bring automation. We wish to bring
more automation of works. According to the lean techniques, there is no end to
improvements. It is a continuous process.