+ All Categories
Home > Documents > Lecture 4 - Project Planning

Lecture 4 - Project Planning

Date post: 09-Nov-2015
Category:
Upload: nen-tran-ngoc
View: 222 times
Download: 3 times
Share this document with a friend
Description:
Lecture 4 - Project Planning
32
LECTURE 4 Project Planning
Transcript
  • LECTURE 4

    Project Planning

  • Introduction

    The most important responsibilities of a project manager are planning, integrating and executing plans

    Planning: Selecting the company objectives and establishing the policies, procedures and programs necessary

    The project manager is the key to successful project planning

    2

  • Introduction

    Project planning is determining what need to be done, by whom and by when

    Project planning must be systematic, flexible and disciplined (thru reviews & control)

    Project planning is an iterative and continuous process and must performed throughout the life of the project

    3

  • Reasons for project planning

    4

    1. To eliminate or reduce uncertainty

    2. To improve efficiency of the operation

    3. To obtain a better understanding of the objectives

    4. To provide a basis for monitoring and controlling work

  • Steps for Project Planning

    5

  • Project Objectives

    6

    Project objectives must be known to all project personnel and all managers, at all level of company

    SMART rules:

    SpecificS

    MeasurableM

    AttainableA

    Realistic or RelevantR

    Tangible or TimeboundT

  • Project Planning and Control System

    7

    Planning activities

    Monitoring activities

  • The Line Manager(s) ?

    The Project Manager ?

    Both Parties ?

    Who plans the project?

    Who executes the project?

    Who is responsible for monitoring work and controlling work?

    Who is responsible for providing feedback regarding the planning and execution phases of a project?

    Planning questions often asked

    8

  • Project Managers Responsibility

    Project Manager will define:

    Goals and objectives

    Major milestones

    Requirements

    Ground rules and assumptions

    Time, cost, and performance constraints

    Operating procedures

    Administrative policy

    Reporting requirements

    9

  • Line Managers Responsibility

    Line manager will define:

    Detailed task descriptions to implement objectives, requirements, and milestones

    Detailed schedules and manpower allocations to support budget and schedule

    Identification of areas of risk, uncertainty, and conflict

    10

  • Senior Managements Responsibility

    Senior management (project sponsor) will:

    Act as the negotiator for disagreements between project and line management

    Provide clarification of critical issues

    Provide communication link with customers senior management

    11

  • 12

    Problems with developing Objectives

    Project objectives are not agreeable to all party

    Project objectives are too rigid to change

    Unsufficient time to define objectives well

    Objectives are not adequately quantified

    Objectives are not documented well enough

    Personnel turnover is high

  • 13

    Information needed at project initiation

    The statement of work - SOW

    Narrative description of work to be accomplished Objectives, brief description of work, schedule

    The project specifications

    Statement of work Man-hour, equipment, materlals

    The Milestone schedule

    Start date, end date Other milestones: review meeitngs, procurement, testing

    The Work Breakdown Structure

    Structure the work into smaller elements It can be manageable, independent, integratable and measurable

    Planning /Scheduling tools

  • Statement of Work - SOW

    14

  • Points to Address When Developing a Statement-Of-Work

    Purpose - objectives

    Exclusions - what should not be done

    Quantities - how many

    Schedule - when the work will be started/completed

    Deliverables (i.e... work done)

    Acceptance criteria - what method will be used to accept deliverables

    Responsibility - department, office or person responsible

    15

  • Statement of Work Elements

    General scope of the work

    Objectives and related background

    Contractors tasks

    Contractor end-item performance requirements

    Reference to related studies, documentation, and specifications

    Data items (documentation)

    Support equipment for contract end-item

    16

  • Customer-furnished property, facilities, equipment, and services

    Customer-furnished documentation

    Schedule of performance

    Exhibits, attachments, and appendices

    (Continued)

    Statement of Work Elements

    17

  • Work Breakdown Structure - WBS

    18

    WBS: A product- oriented family tree which shows a subdivision of effort required to achieve an objective; for example a program, project, and contract

    A Work Breakdown Structure (WBS) defines the work to be completed in a project.

    The WBS is the basis for time estimating, resource allocation, and cost estimating and collection.

    WBS is the tool for breaking down a project into its component parts most important techniques used in project management

  • Detailed planning can be performed

    Costs and budgets can be established

    Objectives can be linked to available resources in a logical manner

    Specific authority and responsibility can be assigned

    IT IS TO STRUCTURE AN ASSIGNED PROJECT INTO VARIOUS ACTIVITIES IN ORDER THAT:

    PURPOSE OF WBS

    19

  • Work Breakdown Structure - WBS

    20

    Six-level structure

    Level Description

    Managerial Levels

    123

    Total programProject

    Task

    TechnicalLevels

    456

    SubtaskWork package

    Level of effort

    Most common type: Six-Level Indentured Structure

  • Can be developed using a top-down or bottom-up approach

    Can be hardware-related, function-related, or a combination

    Depth of WBS must balance out management effort against planning accuracy (influences technical and cost control)

    For accuracy purposes the WBS should be taken down several levels

    The WBS must be structured for objective control & evaluation

    Work Breakdown Structure - WBS

    21

  • The total program can be described as a summation of subdivided elements.

    Planning can be performed.

    Costs and budgets can be established.

    Time, cost, and performance can be tracked.

    Objectives can be linked to company resources in a logical manner.

    Schedules and status-reporting procedures can be established.

    Work Breakdown Structure - WBS

    22

  • Network construction and control planning can be initiated.

    The responsibility assignments for each element can be established.

    Work Breakdown Structure - WBS

    (Continued)

    23

  • Have clearly defined start dates

    Have clearly defined end dates

    Must be able to be used as a communicative tool in which you can communicate the expected results

    Be estimated on a total time duration not when the individual activities start or end

    Be structured so that a minimum of project office control and documentation (i.e. forms) are necessary

    In setting up a WBS the activities must:

    24

  • WBS Tasks

    Have clearly defined start and end dates

    Be usable as a communications tool in which results can be compared with expectations

    Be estimate on a total time duration, not when the task must start or end

    Be structured so that a minimum of project office control and documentation (i.e., forms) is necessary

    25

  • WBS Building House

    26

  • New Restaurant

    Specification of needs

    Conduct surveyStudy competition

    Possible foodPossible service

    Product design

    Menu designCold dishes

    Warm dishes

    Service designServing styleDinning room

    PurchasingKitchen equipment

    FixtureFurniture

    PerishablesStaples

    Process designCold dishes

    Warm dishesOutside food

    AdvertisingOn campusOff campus

    Local preparationConstruction

    ElectricityPlumbing

    Equip. installationFurniture

    Start upPreparation

    Pilot runAnalysis

    Labor force

    ServiceReqts

    Training

    CleaningReqts

    Training

    KitchenReqts

    TrainingManagementAll functions

    Coordination withUniversity

    WBS for Restaurant

    1527

  • WBS Controls

    WORKBREAKDOWNSTRUCTURE

    MGT.COORDIN.

    ORGANIZ.CHARTS

    COSTSACCOUNT-ABILITY

    DECISIONTREES

    SCHEDULES

    `

    28

  • WBS for objective control and evalution

    29

  • Corporate goals not understood lower

    down in the organization/company

    Plans encompass too much in too little time

    Poor financial estimates

    Plans based upon insufficient data

    Poor staff requirements

    Insufficient time allocated for project estimating

    REASONS WHY PLANS FAIL

    30

  • Classroom Activity 4a

    What planning steps should precede total program scheduling? What steps are necessary?

    Create a WBS for your current project.

    Why should the entire project team be involved in creating the WBS?

    31

  • 32

    Questions?


Recommended