+ All Categories
Home > Documents > LH2 Infrastructure

LH2 Infrastructure

Date post: 02-Jan-2016
Category:
Upload: belicia-romero
View: 35 times
Download: 3 times
Share this document with a friend
Description:
LH2 Infrastructure. M Hills M Courthold T Bradshaw I Mullacrane P Warburton. Outline. R&D System Manufacture Cryostat Instrumentation selection Ventilation System Safety Next Steps Controls (PW). Cryostat modifications (1). - PowerPoint PPT Presentation
20
1 CM24 – 2 nd June 2009 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton
Transcript

1

CM24 – 2nd June 2009

LH2 Infrastructure

M HillsM CourtholdT BradshawI MullacraneP Warburton

2

CM24 – 2nd June 2009

Outline

1. R&D System Manufacturea) Cryostat b) Instrumentation selection

2. Ventilation System3. Safety 4. Next Steps5. Controls (PW)

3

CM24 – 2nd June 2009

Cryostat modifications (1)

Increased heat exchange with 1st stage of cryocooler to utilise the cooling power available at ~50K

4

CM24 – 2nd June 2009

Cryostat modifications (2)

Condensing pot

Dummy absorber pot

Radiation shield

Upper radiation shield/1st stage heat exchange

Pre-cooling loops

5

CM24 – 2nd June 2009

Cryostat Instrumentation

o Level sensorso ATEX approved gauges either not available commercially or

prohibitively expensiveo Therefore chosen to use a chain of resistors

o Heaterso Cartridge heaters on condensing pot (50W + 20W)o Absorber pot – 3 x cartridge heaters to boil off liquid

o Thermometryo PRTs on condensing pot and absorbero Cernox on cryocooler 2nd stage

6

CM24 – 2nd June 2009

Gas Panel Instrumentation

o All valves identifiedo Suppliers identified for

instrumentation and discussions on exact specification underway

7

CM24 – 2nd June 2009

Ventilation System

H2 vented during operation of relief valves is separate form ventilation system

8

CM24 – 2nd June 2009

Ventilation System (2)

Ducts routed to avoid drain

9

CM24 – 2nd June 2009

Ventilation System (3)

o Case for standard ducting has been made to ISIS safety representatives and accepted

o Initial quotation received for ductwork and negotiations ongoing with contractor.

o Decision still to be made on fanso DSEAR complianceo What is a safe ‘time of persistence’ for an explosive

mixture?

10

CM24 – 2nd June 2009

Safety Issues

o Specification of ventilation system fanso Approval of ventilation system design against DSEAR

requirementso Design of safety functions in control systemo Production of documentation to demonstrate compliance with

both DSEAR and IEC61508 – this is not insignificant.o Timing and scope of safety reviews

o Internal MICE project reviewo External review before full operation

11

CM24 – 2nd June 2009

Next Steps/Priorities

1. Complete manufacture of the components of the R&D system that are being produced at AS Scientific.

2. Produce a prototype control system that, as a minimum, will allow the cryostat and gas panel to be tested.

3. Test system with Helium.

4. Produce the documentation required for a full safety case (including the controls).

5. Complete preparation of Hydrogen Control Room

6. Place contract and install the ventilation system in the hall.

7. Install bottle store along with N2 and He supply infrastructure

8. Integrate the hydride bed with the system and test with H2.

12

CM24 – 2nd June 2009

MICE Hydrogen Control System

MICE Collaboration Meeting 24June 2, 2009PJ Warburton - Daresbury Lab

13

CM24 – 2nd June 2009

Control System TasksSafety Functions - HardwiredValve Control - PLCH2 Control Room LayoutSIL Rating (BS EN 61508)

14

CM24 – 2nd June 2009

Safety Functions

Operation Of The Ventilation System On Detection Of A Hydrogen Leak

Shut PV20 If There Is Pressure Rise In The Cryostat During Operation

Gas Panel Enclosure Interlocked to Prevent Access When Hydrogen Present

15

CM24 – 2nd June 2009

Other Interlocks

A Shut-off Facility For The Hydride Bed Heater/Chiller On Detection Of Bed Overpressure

Cryocooler Shut-off If Temperature Drops Below Hydrogen Freezing Point (14k) or Heaters Faulty

16

CM24 – 2nd June 2009

Control PLCOmron CJ1M Modular PLC with EthernetExisting Software for Link to EPICSNS8 Programmable Terminal (HMI),

8.4 inch Touch Screen with EthernetFeedback From Devices in Hazardous

Areas Using Intrinsic Safety (Ex i) Key Switches on Selected Functions

17

CM24 – 2nd June 2009

Control SequencesHelium PurgeCryostat EvacuationHelium FillHelium EmptyHydrogen FillHydrogen EmptyDiagnostic

18

CM24 – 2nd June 2009

Hydrogen Control Room Layout

•Room Cleaned Out

•New Door

•Pipe Work to be Removed

•Cabinet Support Frames

•Cable Routes Established

19

CM24 – 2nd June 2009

SIL Rating

Tolerable Risk 10-5 Fatalities per Year From RAL Safety

How Safe is H2 System

Work In Progress

10-4 10-3 10-2

SIL 1 SIL 2 SIL 3

20

CM24 – 2nd June 2009

Questions


Recommended