24 October 2006 Sylvain Weisz - LEMIC
LHC Installation Status & Master Schedule
Content Global Installation Status Tour of the LHC: detailed status and plans Summary
24 October 2006 Sylvain Weisz - LEMIC
Global Installation Status
Sector QRL Magnet Interconnection Straight sections Closure
7-8 Cold tested 100% in place In progress In progress November 06
8-1 Cold tested 100% in place In progress In progress January 07
4-5 Pressure tested 99% in place In progress In progress January 07
3-4 Pressure tested 97% in place In progress
5-6 Pressure tested 95% in place Starts November 06
6-7 Pressure tested In progress
2-3 Pressure tested In progress
1-2 Installed
24 October 2006 Sylvain Weisz - LEMIC
Sector 7-8
All cold elements in place, including DFBAN(7R) & DFBAO (8L) Interconnections in progress: 8 sub-sectors (out of 14) are completed Line N cables inserted in Dispersion Suppressor 7R: ELQA Ok LSS8L
Cold parts Interconnection DFBAO-HCM/LCM in progress Interconnections done for low-β/DFBX/D1, Q4-D2/DFBMA, Q5/DFBMC
Warm parts All components in place (except large beam pipe between D1-D2) NEG activated in Q4.L8-Q5.L8 sub-sector 10-11 mbar
24 October 2006 Sylvain Weisz - LEMIC
LSS8 Left
24 October 2006 Sylvain Weisz - LEMIC
Interconnection ends week 45
3 weeks: global leakand pressure test
ELQA and flushing
Start cool-down week 51
Let 7-8 floating toConnect 8-1 to QUI
Start power testsmid-March 2007
DFBLA on critical path for Sector 8-1
~2 Wk delay on DFBAP
24 October 2006 Sylvain Weisz - LEMIC
LSS4R RF installation in progress: cavities (ACS), damper (ADT) and pick-up (APWL) in place RF wave guides in place, connection to cavities in progress Klystron installation in progress Interconnection D4-Q5/DFBML and Q6/DFBMG in progress
Arc 4-5 and DS All cryo-magnets (except SSS184) are in place:
SSS184 was reloaded and is now in SMI2 for repair (expected back in place on 29/10) Interconnections in progress, nominal rate consolidated
Cryostat closed by mid-January
LSS5L Short circuit tests done in RR53 and USC55 Low-β, DFBX, D1(6 MBXW), TAN and D2 in place
Sector 4-5
24 October 2006 Sylvain Weisz - LEMIC
DFBLD is latefor Sector 4-5
Interconnection ends week 02
DFBLD connectedfor pressure test
Start cool-down late March 2007
Start power testsearly June 2007
24 October 2006 Sylvain Weisz - LEMIC
LSS5R Low-β, DFBX, D1(6 MBXW) and TAN in place UJ56-RR57: power converters & energy extraction systems (DQR/DQS) in place
short circuit tests start mid-November Arc 5-6 and DS
Cryo-magnet transport in progress: 153 MB and 49 SSS in place LSS6L/LSS6R
UA63: short circuit tests in progress (8th zone out of 15) US/UX65: installation of QULA in progress UA67: power converters in place, cabling (AC, DC, Control & Water cooled) in progress
Arc 6-7 and DS Cryo-magnet installation: 52 dipoles and 26 SSS in place (24/10/2006)
No passage through 7-8 & 8-1 from Monday to Thursday due to interconnection work transport of cryo-dipoles and special SSS during week-ends, arc SSS via UX65
LSS7L/R Straight section: all services completed UJ73 & UJ76: power converters and energy extraction systems in place
short circuit tests start mid-December
Sector 5-6 & 6-7
24 October 2006 Sylvain Weisz - LEMIC
No dipole transport frommid-December to January:Cool-down of sector 7-8(ambiant temp. to 80 K)
No time to perform nominalHardware Commissioning
in 2007
4 weeks for cool-down:crude calibration & tuning of cryo. loops
4 weeks for power tests: restrict to injection energy
24 October 2006 Sylvain Weisz - LEMIC
Sector 1-2 QRL installation completed: pressure tests scheduled October 28th
QRL work behind us! Installation of support jacks in progress
LSS2L/LSS2R Water cooled cables installation in progress in UA23, done in UA27 Air treatment and cooling units installation close to completion in UA23/27 Installation of power converters in progress in UA23, done in UA27
Arc 2-3 and DS Cryo-magnet installation in progress: 40 dipoles and 6 SSS in place QRL jumper preparation done
LSS3L/R Installation of Power Converters in UJ33 completed, PC cabling just started DSLC (cryogenic power line) installation in progress
Sector 1-2 & 2-3
24 October 2006 Sylvain Weisz - LEMIC
Last DFB’s in May 07
Delays installation of low-β in LSS2L
Other cryo-magnets in place by March 07
Closure of LHC by end of August 07
(incl. leak & pressure tests)
Global operation tests with 7 Sectors in //
Preparation for beam 1 week for Sector 1-2
24 October 2006 Sylvain Weisz - LEMIC
Main Installation Milestones
End of interconnect in Sector 7-8: week 45 (mid-November)
Start of cool-down of Sector 7-8: week 51 (mid-December)
Start of power tests in Sector 7-8: mid-March 07
End installation of cryo-magnets (except LSS2L low-β):end of March 07
LHC Closure (including leak & pressure tests): end of August 07
End of power tests up to injection energy: mid-November 07
Ready for beam commissioning at 450 GeV: end of November 07
EDMS document #102509
24 October 2006 Sylvain Weisz - LEMIC
Summary
QRL: all sectors ready, pressure test of last sector on October 28th Magnet transport: on track to install most LHC magnets by March 07
(861 MB, 249 Arc SSS and 58 Special SSS in place today) Interconnection: on-going at nominal rate in 4 sectors
Sector 7-8 closed by mid-November Installation of power converters (>80%) and short-circuit test (>50%)
DFB delivery: DFBA (4/16), DFBM (10/23), DBX (5/8) Warm beam-pipe installation in progress in LSS8L/R, LSS1L & LSS4R
2006 objective: cool-down Sector 7-8 by the end of the year LHC Master Schedule very challenging and without contingency Time allocated to cool-down and power tests is too short to achieve a
complete hardware commissioning in 2007