LHC Installation Status & Master Schedule. Content Global Installation Status Tour of the LHC: detailed status and plans Summary. Global Installation Status. Sector 7-8. All cold elements in place, including DFBAN(7R) & DFBAO (8L) - PowerPoint PPT Presentation
Popular Tags:
13
24 October 2006 Sylvain Weisz - LEMIC LHC Installation Status & Master Schedule Content Global Installation Status Tour of the LHC: detailed status and plans Summary
Transcript
Page 1: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

LHC Installation Status & Master Schedule

Content Global Installation Status Tour of the LHC: detailed status and plans Summary

Page 2: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Global Installation Status

Sector QRL Magnet Interconnection Straight sections Closure

7-8 Cold tested 100% in place In progress In progress November 06

8-1 Cold tested 100% in place In progress In progress January 07

4-5 Pressure tested 99% in place In progress In progress January 07

3-4 Pressure tested 97% in place In progress

5-6 Pressure tested 95% in place Starts November 06

6-7 Pressure tested In progress

2-3 Pressure tested In progress

1-2 Installed

Page 3: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Sector 7-8

All cold elements in place, including DFBAN(7R) & DFBAO (8L) Interconnections in progress: 8 sub-sectors (out of 14) are completed Line N cables inserted in Dispersion Suppressor 7R: ELQA Ok LSS8L

Cold parts Interconnection DFBAO-HCM/LCM in progress Interconnections done for low-β/DFBX/D1, Q4-D2/DFBMA, Q5/DFBMC

Warm parts All components in place (except large beam pipe between D1-D2) NEG activated in Q4.L8-Q5.L8 sub-sector 10-11 mbar

Page 4: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

LSS8 Left

Page 5: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Interconnection ends week 45

3 weeks: global leakand pressure test

ELQA and flushing

Start cool-down week 51

Let 7-8 floating toConnect 8-1 to QUI

Start power testsmid-March 2007

DFBLA on critical path for Sector 8-1

~2 Wk delay on DFBAP

Page 6: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

LSS4R RF installation in progress: cavities (ACS), damper (ADT) and pick-up (APWL) in place RF wave guides in place, connection to cavities in progress Klystron installation in progress Interconnection D4-Q5/DFBML and Q6/DFBMG in progress

Arc 4-5 and DS All cryo-magnets (except SSS184) are in place:

SSS184 was reloaded and is now in SMI2 for repair (expected back in place on 29/10) Interconnections in progress, nominal rate consolidated

Cryostat closed by mid-January

LSS5L Short circuit tests done in RR53 and USC55 Low-β, DFBX, D1(6 MBXW), TAN and D2 in place

Sector 4-5

Page 7: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

DFBLD is latefor Sector 4-5

Interconnection ends week 02

DFBLD connectedfor pressure test

Start cool-down late March 2007

Start power testsearly June 2007

Page 8: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

LSS5R Low-β, DFBX, D1(6 MBXW) and TAN in place UJ56-RR57: power converters & energy extraction systems (DQR/DQS) in place

short circuit tests start mid-November Arc 5-6 and DS

Cryo-magnet transport in progress: 153 MB and 49 SSS in place LSS6L/LSS6R

UA63: short circuit tests in progress (8th zone out of 15) US/UX65: installation of QULA in progress UA67: power converters in place, cabling (AC, DC, Control & Water cooled) in progress

Arc 6-7 and DS Cryo-magnet installation: 52 dipoles and 26 SSS in place (24/10/2006)

No passage through 7-8 & 8-1 from Monday to Thursday due to interconnection work transport of cryo-dipoles and special SSS during week-ends, arc SSS via UX65

LSS7L/R Straight section: all services completed UJ73 & UJ76: power converters and energy extraction systems in place

short circuit tests start mid-December

Sector 5-6 & 6-7

Page 9: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

No dipole transport frommid-December to January:Cool-down of sector 7-8(ambiant temp. to 80 K)

No time to perform nominalHardware Commissioning

in 2007

4 weeks for cool-down:crude calibration & tuning of cryo. loops

4 weeks for power tests: restrict to injection energy

Page 10: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Sector 1-2 QRL installation completed: pressure tests scheduled October 28th

QRL work behind us! Installation of support jacks in progress

LSS2L/LSS2R Water cooled cables installation in progress in UA23, done in UA27 Air treatment and cooling units installation close to completion in UA23/27 Installation of power converters in progress in UA23, done in UA27

Arc 2-3 and DS Cryo-magnet installation in progress: 40 dipoles and 6 SSS in place QRL jumper preparation done

LSS3L/R Installation of Power Converters in UJ33 completed, PC cabling just started DSLC (cryogenic power line) installation in progress

Sector 1-2 & 2-3

Page 11: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Last DFB’s in May 07

Delays installation of low-β in LSS2L

Other cryo-magnets in place by March 07

Closure of LHC by end of August 07

(incl. leak & pressure tests)

Global operation tests with 7 Sectors in //

Preparation for beam 1 week for Sector 1-2

Page 12: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Main Installation Milestones

End of interconnect in Sector 7-8: week 45 (mid-November)

Start of cool-down of Sector 7-8: week 51 (mid-December)

Start of power tests in Sector 7-8: mid-March 07

End installation of cryo-magnets (except LSS2L low-β):end of March 07

LHC Closure (including leak & pressure tests): end of August 07

End of power tests up to injection energy: mid-November 07

Ready for beam commissioning at 450 GeV: end of November 07

EDMS document #102509

Page 13: LHC Installation Status  & Master Schedule

24 October 2006 Sylvain Weisz - LEMIC

Summary

QRL: all sectors ready, pressure test of last sector on October 28th Magnet transport: on track to install most LHC magnets by March 07

(861 MB, 249 Arc SSS and 58 Special SSS in place today) Interconnection: on-going at nominal rate in 4 sectors

Sector 7-8 closed by mid-November Installation of power converters (>80%) and short-circuit test (>50%)

DFB delivery: DFBA (4/16), DFBM (10/23), DBX (5/8) Warm beam-pipe installation in progress in LSS8L/R, LSS1L & LSS4R

2006 objective: cool-down Sector 7-8 by the end of the year LHC Master Schedule very challenging and without contingency Time allocated to cool-down and power tests is too short to achieve a

complete hardware commissioning in 2007