+ All Categories
Home > Documents > LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space...

LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space...

Date post: 19-Jan-2016
Category:
Upload: ellen-dixon
View: 217 times
Download: 1 times
Share this document with a friend
Popular Tags:
10
LIU–PLI report LIU Project Team meeting
Transcript
Page 1: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU–PLI reportLIU Project Team meeting

Page 2: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU PLI meeting - J.Coupard 2

LIU - Planning & Installation Coordination MeetingSpace Reservation & Engineering Change Request - Guideline

22 January 2015

All changes (beam line or services) which might impact other equipment or space volume (survey, transport…) have to be declared in an ECR

The integration studies have to be done before the ECRs (at least preliminary studies)

The ECRs have to be presented in the LIU-PLI coordination meeting before circulating EDMS

The ECRs have to be RELEASED before the execution of the work (the sooner the better)

Objective 2015 : All upgrade works for LIU have to be declared in a Space Reservation if the ECR cannot be yet submitted during the course of 2015

Contacts: T.Birtwistle for PS-Complex & S.Bartolome for SPS

EDMS 1465008

• Templates: https://quality.web.cern.ch/templates • Space Reservation Request (SRR)• Engineering Change Request (ECR)

• MS Word older than 2013: MS Word New My Template PS Complex or SPS

• MS Word 2013: MS Word New Shared template PS Complex or SPS

• Templates and Guidelines for Engineering Change Requests : https://edms.cern.ch/document/1271880

Page 3: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 3

Follow-up of SRR and ECR to be producedPSB

18-Jun-2015

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Beam instrumentation New tank for screen at injection (BI.BTV30) End 2016 Delphine Gerard Yes Yes

Beam instrumentation Turn-by-turn transverse profile monitor for ring 3 (matching monitor): section 4L1

Earliest possible date: YETS 2017/2018 (but not absolutely essential for operation with Linac 4)

Federico Roncarolo Yes Yes

Beam instrumentation Install new Beam Loss Monitors at injection, injection section, ring, extraction and transfer (3 different types) End 2016 (cabling!) Christos Zamantzas no Yes

Beam instrumentation New tanks and cameras for screens at extraction: BT.MTV30 LS2 Delphine Gerard Yes Yes

Beam instrumentation Provide additional wire scanners (new design):sections 11L1 and maybe 4L1

LS2 – on critical path (but: current system as redundancy) Bernd Dehning Yes Yes

Beam Intercepting Devices PSB collimator/scraper Study started; to be installed during LS2 Francois-Xavier Nuiry Yes Yes

Magnets Deliver operational main INJ/EXT bending magnets (2 yokes, 4 coil sets) Assembled by Q1 2018 A. Newborough no YES

Magnets Modify main magnet cooling, shimming and saturation layout During LS2 A.A. Newborough YES YES

Magnets Deliver magnets for BT, BTP, BTM transfer lines To be installed during LS2 A.A. Newborough YES YES

Magnets Deliver new B-train system Prototype built and tested by end 2017, final system installed during LS2 Marco Buzio Yes Yes

Power Converters PSB injection septa Power Converters Delivery date currently 2018, end-2016 deadline being reviewed Serge pittet no Yes

Power Converters PSB injection chicane PC + chicane compensation trim PC

Delivery date currently 2018, end-2016 deadline being reviewed Serge pittet no Yes

Power Converters Provide new PSB Main Power Supply (MPS) + Trims + control electronics

By mid-2018 installed in new building; commissioning during LS2 Serge pittet no Yes

PSB Extraction and Transfer Provide extraction kicker (BE.KFA14L1) and recombination kicker (BT1/4.KFA10)

Magnets manufactured end 2016, to be installed during LS2 luc sermeus no Yes

RF Systems Transverse Feedback: 800 W power amplifier, new PU head amplifiers and new (digital) electronics All to be delivered by summer 2016 Alfred Blas yes Yes

RF Systems 2/4/16 MHz (C02/C04/C16) cavity consolidation studies and Finemet cavity beam studies

Current baseline: Finemet Upgrade.Decision process in place: end 2015

Mauro PaoluzziMatthias Haase no yes

Space Reservation Requests

Engineering Change Requests

Page 4: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 4

Follow-up of SRR and ECR to be producedPSB

Not defined

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Beam Intercepting Devices Provide head- and tail dumps Ready summer 2015; to be installed in BI.SMV10 Damien Grenier

Beam Intercepting Devices Provide H0/H- dumps Ready end summer 2015; to be installed in chicane magnets Damien Grenier

Cooling and Ventilation Provide cooling for newly installed or upgraded equipment Summer 2017 Stefano Moccia

Cooling and Ventilation Provide cooling & ventilation infrastructure for BRF2 modifications

Study not yet started; not yet budgeted Stefano Moccia

Cooling and Ventilation Provide cooling for newly installed or upgraded equipment LS2 Stefano Moccia

Electrical Systems General service for new Main Power Supply (MPS) building End 2017 Clement Bovet

Electrical Systems Upgrade of LV general services distribution systems

Replacement of General Services Switchboards (installed circa 1979), update of UPS power, normal and emergency lighting, distribution cabling and socket outlets.

James Devine

Magnets Magnetic measurements of main bending and quadrupole spares To be finished by end 2017 Marco Buzio

New PSB Injection Region Relocate modified KSW1L1 magnet to PSB period 16, build new pulse generator. Wim Weterings no

New PSB Injection Region ~0.36 Tm required from BI.BVT for ~175mrad@160MeV Wim Weterings no

New PSB Injection RegionNew BI.SMV,4 mm thick septum and 70 mm horizontal aperture for ~165 mrad @ 160 MeV with associated new pulse generator.

Wim Weterings no

New PSB Injection Region Performance increase of 1.9 in ∫B•dl ofBI.DVT30, BI.QNO30, BI.QNO40, BI.DVT40 Wim Weterings no

Page 5: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 5

Follow-up of SRR and ECR to be producedPS

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Beam Instrumentation New IPM in SS82 https://indico.cern.ch/event/299582/ M. Sapinski - R. Veness - D. Bodart yes yes

Beam Instrumentation Second IPM Ionization profile monitor BGI Location to be defined All new cables, power and aqn M. Sapinski - D.

Bodart yes yes

Beam Instrumentation New plus faster BLMs BI - Ewald Effinger; Christos Zamantzas yes yes

Beam Instrumentation Slow BLMs BI - Ewald Effinger; Christos Zamantzas yes yes

MagnetsSkew quadrupoles. 20, conception end 2015 - magnets end 2017 - ready for LS2 Can be anticipated during TS yes

Location to be defined D. Bodart no Yes

Magnets New vertical corrector 20 DVT Conception JUNE 2015 - dispo END 2016. Can be anticipated during TS yes Location to be defined D. Bodart yes Yes

MagnetsInsertion quadrupoles magnets can have production started in 2015 or 2016 and then installed Can be anticipated during TS yes

New installation Location to be confirmed D. Bodart yes Yes

MagnetsInjection bumpers 40 41 43 44 JAN 2015 for iteration - Delivery end 2017 - installation LS2 Can be anticipated during TS yes

D. Bodart no Yes

Beam dumpsNew beam dumps (PS internal beam dumps not adequate for safe operation with LIU-type beams) New beam dumps 47 or 48

F.X. Nuiry no Yes

Beam dumps New beam dumps Location tbd (replace ‘ralentisseur’ for first turn dump) F.X. Nuiry yes Yes

2 GeV injection New injection extra kicker New kfa45 or 53 T. Kramer + J. Borburgh yes Yes

2 GeV injection New injection septum 42. . Appropriate new power converters

J. Borburgh – J. M. Cravero yes Yes

Vacuum New vacuum chambers 42 Try to advance the installation of the chambers before LS2 J. Hansen no Yes

Vacuum New vacuum chambers 41 J. Hansen no YesVacuum New vacuum chambers. SS41 J. Hansen no yes

Page 6: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 6

Follow-up of SRR and ECR to be producedSPS

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Beam Instrumentation

Replacement of obsolete MOPOS electronics, plus new fibre backbone. Replacement of obsolete BLM electronics, using MOPOS fibres. Replacement of wirescanners with new devices. Improvement of BGI, BSRT, IMM and Head-Tail monitors

Wire Scanners (LSS4, LSS5) Mechanical Installation L.Jensen Yes

Beam Instrumentation

Replacement of obsolete MOPOS electronics, plus new fibre backbone. Replacement of obsolete BLM electronics, using MOPOS fibres. Replacement of wirescanners with new devices. Improvement of BGI, BSRT, IMM and Head-Tail monitors

Upgrade Fast Ring BCT (LSS3/LSS5) L.Jensen Yes

New TIDVG core Replace present TIDVG core with improved version. Robust against present and future LHC beams Located in LSS1 R.Losito No Yes

ZS improvementsImprovement of pumping, impedance reduction, improvement of ion trap connections, short-circuiting of anodes

All works are located at BA2 B.Balhan Yes

200 MHz low level improvementConsolidation of drivers, cavity controllers, HV power supplies, CV and power couplers. Low-level improvement (replace obsolete system with new digital control)

LSS3 works W.Hofle / P. Baudrenghien Yes

Extraction protection upgrade Replacement of TSPG4/6 by upgraded versions with better robustness and protection of MSE J.Borburgh Yes

200 MHz power upgradeRearrangement of RF cavities into new configuration with 2 additional 1.4 MW power plants, and 2 extra cavities. Reduce impedance by 15% and double RF voltage to allow operation with very high RF current.

Located in LSS3 E.Montesinos No Yes

New wide band transverse damper

New intra-bunch damping system in vertical plane to damp instabilities from TMCI or ECI. W.Hofle No Yes

Page 7: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 7

Follow-up of SRR and ECR to be producedSPS

Not defined

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact Approved? SRR needed(yes or no)

ECR needed(yes or no)

New external high energy beam dump

New dump block based on TED design in existing beamline, using extraction already in place and new switchign series of magnets. Will allow dumping of high intensity LHC beam during setup.

B.Goddard No - July 2015

Replace power supply of MSE septa

Replace MSE/T convertors with higher stability versions, possibly with faster pulse, G.Le Godec No - date tbc?

aC coating of vacuum chambers

Coating of all SPS main magnets and drift chambers to supress electron cloud. Coating to be done with chamber inside magnet, in ECA5 workshop.

P.Cruikshank No - July 2015

Impedance reduction vacuum flanges Jaime Perez Espinos No - July 2015

Page 8: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 8

Follow-up of SRR and ECR to be producedIONS

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

LIU ions SPS injection upgrade Addition of new kicker, thin in-vacuum septum, dump and BI to allow injection of ions with 50 ns rise time. MKP 100 ns rise time BA1 (Surface) J. Uythoven No Yes

LIU ions SPS injection upgrade Addition of new kicker, thin in-vacuum septum, dump and BI to allow injection of ions with 50 ns rise time. MSI-V new septum LSS1 J. Uythoven No Yes

LIU ions SPS injection upgrade Addition of new kicker, thin in-vacuum septum, dump and BI to allow injection of ions with 50 ns rise time. New Ion injection dump LSS1 J. Uythoven No Yes

LIU ions SPS injection upgrade Addition of new kicker, thin in-vacuum septum, dump and BI to allow injection of ions with 50 ns rise time.

Beam instrumention for injection upgrade J. Uythoven No Yes

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

LEIR DumpDump in extraction channel, allowing to safely and cleanly dump the ion beam when not desired by PS or LHC

yes

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Linac3 - LBS New spectrometer line after connection of Linac4 to PSB Magnets

Pierre Alexandre ThonetDominique Bodart

yes

Linac3 - LBS New spectrometer line after connection of Linac4 to PSB Power convertors Jean-Marc Cravero yes

Linac3 -ITL (LEBT) Rematched optics in Low Energy Beam Transport, between source & RFQ Einzel-lens installation Giulia Bellodi

Detlef Kuchler yes

Linac3 -Beam Instrumentation Faraday Cup Federico RoncaroloSergei Sadovich yes

Linac3 -Beam Instrumentation SEMGrids Federico RoncaroloSergei Sadovich yes

Linac3 -Beam Instrumentation PepperPot Federico RoncaroloSergei Sadovich yes

Page 9: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 9

Follow-up of SRR and ECR to be producedLinac4

18-Jun-2015

Space Reservation Requests

Engineering Change Requests

Action Description Details Contact SRR needed(yes or no)

ECR needed(yes or no)

Connection of the Linac4 at 160MeV H-

Dismantling of a part of the Linac2Change of the magnet BHZ.20New sectorization (Civil Engineering, Access System, Chicanes, Shielding)Modification of the power convertersCablingCooling & Ventilation ?Interlock ?

J. Coupard no yes

Modification of the measurment line LBE JB. Lallement no yes

Connection of the Linac4 at 50MeV p

Dismantling of a part of the Linac2Change of the magnet BHZ.20New sectorization (Civil Engineering, Access System, Chicanes, Shielding)Modification of the power convertersCablingCooling & Ventilation ?Interlock ?

J. Coupard no yes

Page 10: LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.

LIU-PLI Report - J.Coupard 10

Follow-up of SRR and ECR

18-Jun-2015


Recommended