+ All Categories
Home > Documents > LTA Ow Chun Nam Presentation

LTA Ow Chun Nam Presentation

Date post: 27-Dec-2015
Category:
Upload: allan-teo
View: 196 times
Download: 9 times
Share this document with a friend
Description:
Planning, Design and Construction of Underground Infrastructure in Singapore
Popular Tags:
46
Planning, Design and Construction of Underground Infrastructure in Singapore Ow Chun Nam Director, Land Transport Authority
Transcript
Page 1: LTA Ow Chun Nam Presentation

Planning, Design and Construction of Underground Infrastructure in Singapore

Ow Chun Nam Director, Land Transport Authority

Page 2: LTA Ow Chun Nam Presentation

• Underground Infrastructure in Singapore

• Challenges • Site Investigation

• Deep Excavation

• Bored Tunnelling

• Conclusions

Planning, Design and Construction of Underground Infrastructure

Page 3: LTA Ow Chun Nam Presentation

Rail Network Expansion by 2030

Page 5: LTA Ow Chun Nam Presentation

• Singapore to Kuala Lumpur

• 315km, 90mins travelling time

• Operational in 2020

• Possibly part underground

High Speed Rail Link

Page 6: LTA Ow Chun Nam Presentation

Major Underground Road Tunnels

CTE: North Tunnel: 0.7 km; South Tunnel: 1.7 km; Opened: 21 Sep 1991

Fort Canning Tunnel: 0.35 km; Opened 16 Jan 2007

KPE: Total tunnel length: 9km; Opened 26 Oct 2007 and 20 Sep 2008

Woodsville Interchange: Total tunnel length: 0.69km; Opened 28 Jan 2012

MCE Tunnel : 3.5km to be opened at end 2013

Singapore Underground Road System: underground road tunnels

North South Expressway Tunnel and Semi Tunnel : 12.3 km to be completed around 2020

Page 7: LTA Ow Chun Nam Presentation

Transmission Cable Tunnel Route Overview

MARYMOUNT

THOMSON PIE

GAMBAS

SEMBAWANG

MANDAI

NS Tunnel

EW Tunnel

AYER RAJAH

NORTH

BUONA VISTA

HOLLAND

DUNEARN

RANGOON

MAY ROAD

INTERFACE

KALLANG

AIRPORT ROAD

TAGORE

ANG MO KIO

PAYA LEBAR

JIP Tunnel

BENOI

PIONEER

PESEK

WEST JURONG

ISLAND

Page 8: LTA Ow Chun Nam Presentation

• Underground Infrastructure in Singapore

• Challenges • Site Investigation

• Deep Excavation

• Bored Tunnelling

• Conclusions

Planning, Design and Construction of Underground Infrastructure

Page 9: LTA Ow Chun Nam Presentation

• To provide sufficient ground and ground water data • for a proper description of essential ground properties/

behaviour to plan the most appropriate construction method; and

• for a reliable assessment of characteristic values of ground parameters to achieve a safe and cost-effective design

• Continuous process for entire duration of project

Objectives of Site Investigation

Page 10: LTA Ow Chun Nam Presentation

• Boreholes too widely spaced

• To have more boreholes – practical problems

Challenges – Boreholes Spacing

Page 11: LTA Ow Chun Nam Presentation
Page 12: LTA Ow Chun Nam Presentation

Challenges – MRT Tunnel

Tunnel Alignment

Page 13: LTA Ow Chun Nam Presentation

41m

65m

56m 58m

Potential JTC 2nd Link Immersed Tunnel

PUB – NIPE Tunnel DTSS Phase 2 (Future) Upper/Lower Limits

1.6km 3.2km 0.4km

PROPOSED JURONG ISLAND – PIONEER TRANSMISSION CABLE TUNNEL

Challenges – Tunnelling under Water Bodies

Page 14: LTA Ow Chun Nam Presentation

BH-169 (GL-49m)

ABH-216 (GL-49m)

ABH-214 (GL-36m)

Tender stage : 4 Boreholes

▼Approximate Level of Rock Head

Ground LevelRL 102.7m BH-214

FILL

N=0

M

N=0

F2

N=1~12

F1

N=7~19

G-V

N=41~86

G-I, II

N=76~100

G-III

R=20~80%

G-I,II

R=90~100%

E

N=9

G-III

N=54~67

ABH-215 (GL-66m)

• Tender Design

• Rock head level = 70.5m as per GIBR

• Diaphragm wall depth = 32m

• Shotcrete & rockbolt for lower shaft (in G-III/G-II)

Challenges – Variable Rockhead

Deep shaft ~60m depth

Page 15: LTA Ow Chun Nam Presentation

• Tender Stage Borehole = 4 nos

• 1st Stage Add Borehole = 5 nos

• 2nd Stage Add borehole = 10 nos

ABH-D-01 (GL-57m)

ABH-D-05 (GL-42m)

BH-169 (GL-49m)

ABH-216 (GL-49m)

ABH-D-08 (GL-31m)

ABH-D-06 (GL-42m)

ABH-215 (GL-66m)

ABH-D-04 (GL-67m)

ABH-D-07 (GL-62m)

ABH-D-02 (GL-43m)

ABH-D-03 (GL-69m)

Option-2 7m move

ABH-D-09 (GL-57m)

ABH-D-10 (GL-62m)

ABH-D-11 (GL-49.5m)

ABH-214 (GL-36m)

ABH-D-12 (No Rock head)

ABH-D-13 (GL-45m)

ABH-D-14 (GL-65m)

ABH-D-15 (GL-54m)

• From additional SI

• Rock head level (G-III) is much

deeper than original

• Max difference in rock head

level (G-III) is 25m

• Alternative construction

method is needed due to new

geological information

Challenges – Variable Rockhead

Page 16: LTA Ow Chun Nam Presentation

Challenges – Variable Rockhead

Option 1 – To relocate shaft

7m

Page 17: LTA Ow Chun Nam Presentation

Challenges – Variable Rockhead

Option 2 – Original location with redesigned shaft

GIBR Rockhead Level

Page 18: LTA Ow Chun Nam Presentation

Commonly used methods • Electrical resistivity

• Seismic refraction

• Seismic reflection

• Surface wave method

• Geo-tomography

Geophysical Survey

Page 19: LTA Ow Chun Nam Presentation

More efficient and accurate methods are required

to determine

• rock levels

• depth of piles

to minimise risk of underground construction in

urban areas

Challenges

Page 20: LTA Ow Chun Nam Presentation

• Underground Infrastructure in Singapore

• Challenges

• Site Investigation

• Deep Excavation

• Bored Tunnelling

• Conclusions

Planning, Design and Construction of Underground Infrastructure

Page 21: LTA Ow Chun Nam Presentation

Challenges

Deep Excavations in Soft Clay without Ground Treatment

Deep Excavations in Soft Clay with Ground Treatment

Ground Treatment

Page 22: LTA Ow Chun Nam Presentation

Typical Station Excavation Depth

Page 23: LTA Ow Chun Nam Presentation

Deep Excavation – Bras Basah Station

Singapore Art Museum

Cathedral of the Good Shepherd

Bras Basah Rd

B1 Level

B2 Level

B3 Level

B4 Level

B5 Level

Connection SMU

Reflection Pool

Page 25: LTA Ow Chun Nam Presentation

Deep Excavation – Bencoolen Station

Subway

NAFA Campus 1 NAFA Campus 2

Bayview Hotel

Plaza By The Park

SMU

NAFA Campus 1

Page 26: LTA Ow Chun Nam Presentation

Slide 26

Bra

s B

asah

R

oad

Ho

tel

Re

nd

ezvo

us

Strand Hotel

Be

nco

ole

n

Ho

use

Hotel 81

Ho

tel

Be

nco

ole

n

Somerset Bencoolen

Manulife Centre

Bayview Hotel

NAFA Campus 2

New Dev’t. NAFA Campus 1

Pri

nse

p L

ink

Subway link to SMU

Project Challenges

1. Built-up corridor

-- close proximity to existing buildings

-- very deep station box (43m below ground)

-- thick layer of hard ground (boulders)

-- restricted working hours due to stakeholders requests

2. Pedestrian walkway & vehicular access to buildings to be maintained at all times

Space Furniture

C936 Bencoolen Station SM

U

Bayview Hotel

NAFA Campus 2

New Dev’t.

Station Footprint

Page 27: LTA Ow Chun Nam Presentation

Station Excavation – DTL3

CROSS SECTION

BENCOOLEN STREET

43.

2m

Page 28: LTA Ow Chun Nam Presentation

Need for Horizontal Grouting

Top tunnel in Marine Clay Bottom tunnel in OA

Existing Tunnels

Future Tunnels

Existing Piles / Barrettes

Transfer Beams and Barrettes for Underpinning

Page 29: LTA Ow Chun Nam Presentation

Cable Tunnel – Deep Shafts Utility building (above ground)

Shaft (~60m)

Adit

Tunnel enlargement

Cable tunnel

Soil/Rock Interface

Page 30: LTA Ow Chun Nam Presentation

Deep Shaft – Rock Fissure Grouting

Page 31: LTA Ow Chun Nam Presentation

• Underground Infrastructure in Singapore

• Challenges • Site Investigation

• Deep Excavation

• Bored Tunnelling

• Conclusions

Planning, Design and Construction of Underground Infrastructure

Page 32: LTA Ow Chun Nam Presentation

• Phase 1/2 MRT Construction in 1980s: Greathead Shield with hydraulic backhoe excavator or roadheaders / 1 EPBM / 1 TBM

• Compressed air used extensively

• Grouting done through the segments

Construction Methods

Greathead Shield EPBM (C301)

Page 33: LTA Ow Chun Nam Presentation

• NEL: 14 EPBMs (2 Dual Modes), 2 Open Face TBMs

• Face pressure and stability by controlling the extrusion of the spoil through the screw conveyor and the advancement of the machine

• Automatic tail void grouting

Construction Methods

EPBM (C705) EPBM (C706) EPBM (C710)

Page 34: LTA Ow Chun Nam Presentation

• Circle Line: 19 EPBM, 8 Slurry TBMs

• Scanners / belt weighing experimented and adopted subsequently

• Slurry TBM used for sections with granite

Construction Methods

Slurry TBM (C854) Slurry Treatment Plant EPBM (C823)

Page 35: LTA Ow Chun Nam Presentation

• DTL1: 3 EPBMs

• DTL2: 10 EPBMs + 9 Slurry TBMs

• DTL3: 19 TBMs

Construction Methods

EPBM (C902) Slurry TBM (C915) EPBM (C917)

Page 36: LTA Ow Chun Nam Presentation

• Expansion of underground rail system constrained by tight time schedule

• Significant number of TBMs required over a short period of time

• TBM manufacturing and delivering lead time critical

• Client procurement an effective way to manage this

• Possible cost savings from direct procurement from the TBM manufacturers

• Procurement of TBMs restricted to areas with homogeneous soil such as Old Alluvium

• Bulk procured 10 nos Downtown Line Stage 3 TBMs – Novated to successful civil contractors

TBM Bulk Procurement

Page 37: LTA Ow Chun Nam Presentation

10m

20m

30m

40m

50m

60m

70m

Deep Tunnels

Underpasses & Shopping Malls

MRT System

Cable Tunnel

Common Services Tunnel

Deep Tunnel Sewerage System

Underground Expressways

Sewers & Gas Pipes

Source : The Straits Times, 11 Feb 12

Page 38: LTA Ow Chun Nam Presentation

• Specifications beefed up

• 19 inch disc cutters introduced

• 2 x double compartment manlock required

• Probe drills permanently mounted

• Front midget drill provided

TBM Specifications

Page 39: LTA Ow Chun Nam Presentation

Permanently Mounted Drills

Page 39

Page 40: LTA Ow Chun Nam Presentation

TBM Front Drilling

Page 41: LTA Ow Chun Nam Presentation

Tunnelling through Tight Curves

75m radius curve

Page 42: LTA Ow Chun Nam Presentation

Tunnelling through Tight Curves

Page 43: LTA Ow Chun Nam Presentation

• Major underground facilities to be built in Singapore

• Challenges to the industry

• New methods and technologies to address the challenges

Conclusions

Page 44: LTA Ow Chun Nam Presentation

THANK YOU

Page 45: LTA Ow Chun Nam Presentation

MRT Network in Singapore by 2020

Page 46: LTA Ow Chun Nam Presentation

• To match the design of soil improvement methods to

• the groutability of the ground encountered

• the targeted engineering property of soil to be improved

• To have minimum disturbance to surrounding structures

• To develop new method and technology, e.g. horizontal grouting techniques

Challenges


Recommended