  • 7/31/2019 m10x Presentation Session 1

    1/31

    APRESENTATION ON

    TARIFFS & ELECTRICITY BILLCALCULATION

    BY

  • 7/31/2019 m10x Presentation Session 1

    2/31

    DIFFERENT CATEGORIES OFCONSUMERS

    STREETLIGHT: MUNICIPAL

  • 7/31/2019 m10x Presentation Session 1

    3/31

    RECIDENTIAL

  • 7/31/2019 m10x Presentation Session 1

    4/31

    TRANSPORT

  • 7/31/2019 m10x Presentation Session 1

    5/31

    EDUCATIONAL

  • 7/31/2019 m10x Presentation Session 1

    6/31

    MEDICAL

  • 7/31/2019 m10x Presentation Session 1

    7/31

    HOTELS: HT COMMERCIAL

  • 7/31/2019 m10x Presentation Session 1

    8/31

    INDUSTRIAL: LT SMALL SCALE

  • 7/31/2019 m10x Presentation Session 1

    9/31

    AGRICULTURAL

  • 7/31/2019 m10x Presentation Session 1

    10/31

    HT INDUSTRY

  • 7/31/2019 m10x Presentation Session 1

    11/31

    COMMERCIAL COMPLEX

  • 7/31/2019 m10x Presentation Session 1

    12/31

    CLASSES OF CONSUMERSThe different classes of consumers are:ResidentialCommercial: Educational, offices, complex etcIndustrial: Small scale industry, HT industry etc

    AgriculturalPublic sector: Transport, railway etc.

    Municipal; Street light, water pumping etc.Medical: Hospitals, clinics etc.H.T./L.T. consumers

  • 7/31/2019 m10x Presentation Session 1

    13/31

    TYPES OF ELECTRICITY TARIFFS

    1.Block rate tariff :Eg. If 2 blocks are there:

    A] 0 to 100 units: Rs. 2.50/-B] 201 & above units: Rs. 5.50 /-

    2.Two part tariff: Bill is divided in two parts :

    A] Fixed partB] Variable par t

  • 7/31/2019 m10x Presentation Session 1

    14/31

    ELECTRICITY TARIFFS

    3.P.F. Tariff:

    Depends on P. F. maintained (It is to be maintained atunity )

    4.M.D. tariff :

    Depend on Maximum demand of consumer in kVA

  • 7/31/2019 m10x Presentation Session 1

    15/31

    ELECTRICITY TARIFFS

    5. T.O.D . Tariff: Time of day tariff.Depends on various time zone of a day:

    Zone A:22.00 HRS TO 0600 HRS: Rs.-85 p / uZone B: 06.00 HRS TO 0900 HRS: Rs.0 p / uZone C: 09.00 HRS TO 1200 HRS: Rs.80 p / uZone D: 12.00 HRS TO 18.00 HRS: Rs110 p / u

    18.00 HRS TO 22.00 HRS: Rs110 p / u

  • 7/31/2019 m10x Presentation Session 1

    16/31

    ELECTRICITY TARIFFS

    6.Flat rate tariff: A common rate is given to all units in paisa / unit

    7.Agricultural tariff:

    Only applicable to agricultural consumers , it is

    based on connected load in HP

  • 7/31/2019 m10x Presentation Session 1

    17/31

    ELECTRICITY TARIFFS

    8.H.T./ L.T. Tariff:

    LT: 230 V, single phase & 440 V, three phase A.CSingle phase: up to 5 kWThree phase : up to 15 kWThree phase CT operated; 50/5 A & 100/5 AL.T. special: up to 75 kW

    HT: Above 75 kW, At 11 kV,22 kV, 33 kV etc.

  • 7/31/2019 m10x Presentation Session 1

    18/31

    TARIFFS

    The different types of tariffs are studied with their distinguishing parameters. These are1.Block rate tariff 2.Two/ Three part tariff 3.M.D. tariff 4. T.O.D.5.P.F. Tariff

    6.Flat rate tariff 7.H.T./ L.T. Tariff 8.Agricultural tariff

  • 7/31/2019 m10x Presentation Session 1

    19/31

    PARAMETERS OF ELECTRICITY BILL

    i. Connected Load: in kW: It is the addition of ratings of all the equipmentsconnected to the system.

    ii. Contract demand or billed demand: in kVA :This is the Max. Load that we need at all the time.The billing is based on this demand. Even if you dont use electricity you have to pay50% of contract demand75 % MD in Last 6 months is considered for calculation.Billed demand is the maximum demand.

  • 7/31/2019 m10x Presentation Session 1

    20/31

    Example for Connected Load andContract Demand

    Suppose in your home there are 4 persons & yougo to the market to buy vegetables. You maypurchase 3 Kg of vegetables(Connected load) for aweek.

    This means that this vegetable you will consume ina week, not at once in a day.Per day you may maximum require Kg of

    vegetable(Contract demand) .Demand charges=Billed demand(kVA)* Rate/ kVACalculate CL & CD of this class

  • 7/31/2019 m10x Presentation Session 1

    21/31

    PARAMETERS OF BILL

    iii. Maximum Demand: Maximum load (kVA) the consumer has used inone month. This should not exceed contractdemand. Otherwise penalty for excess demand is

    required to be paid. Its rate is: Rs.100/kVA for LT special

    Rs. 150/kVA for HT II, non continuous, commercialCategory

    Calculation: MD ( kVA) * Demand charges

  • 7/31/2019 m10x Presentation Session 1

    22/31

    PARAMETERS OF BILL

    iv. Energy Charges: These are depending on No of units consumed in

    kWHEnergy charges: No of units * per unit rate

    v. FAC: Fuel Adjustment Charges; These are common to all & they are: 37 p / unit

  • 7/31/2019 m10x Presentation Session 1

    23/31

    PARAMETERS OF BILL

    vi. Electricity Duty:It is central Government duty & its % is:

    Industrial: 9%Residential: 15 %Commercial: 17 %

    Calculation:E.D.= ( Demand charges + Energy charges + TODtariff + FAC) * % of ED applicable for that class

  • 7/31/2019 m10x Presentation Session 1

    24/31

    PARAMETERS OF BILL

    vii. TOD charges: Charges of that zone* No of units consumed in thatzoneZone A:22.00 HRS TO 0600 HRS: Rs.-85 p / u

    Zone B: 06.00 HRS TO 0900 HRS: Rs.0 p / uZone C: 09.00 HRS TO 1200 HRS: Rs.80 p / uZone D: 12.00 HRS TO 18.00 HRS: Rs110 p / u

    18.00 HRS TO 22.00 HRS: Rs110 p / u

    Calculation:TOD Charges: Charges for zone(A+B+C+D)

  • 7/31/2019 m10x Presentation Session 1

    25/31

    PARAMETERS OF BILL

    viii. P.F. charges

    If PF is below 0.95 the penalty has to be paidIf It is improved then incentive is given on each0.01 improvement on power factor.

  • 7/31/2019 m10x Presentation Session 1

    26/31

    PARAMETERS OF BILL

    ix. Excess load or demand charges:

    If The load of the consumer increases above itscontract demand or sanctioned load , then thecharges are:

    1.5 times of the per kVA billed demand charges(75 % MD in Last 6 months)

  • 7/31/2019 m10x Presentation Session 1

    27/31

    PARAMETERS OF BILL

    x. RGPPL charges: Ratnagiri Gas Power ProjectLimited charges These are:28p/u

    xi. Reliability Charge: These are: 21 p/ unit

    xii. Sales tax: It is 8 p / unit

  • 7/31/2019 m10x Presentation Session 1

    28/31

    CALCULATION OF SAMPLE L.T. BILL

    Data given: Area: Pune, MaharashtraCategory of consumer: ResidentialConnected load: 0.5 kW

    No of units consumed: 48Fixed charges: Rs 30/ month for residentialED: 15% for residentialFAC : 5 p/uReliability charge: 21 p/uBlocks:

    0-100 units: Rs. 2.35 p/u101-300 units: Rs. 4.25 p/u

  • 7/31/2019 m10x Presentation Session 1

    29/31

    CALCULATION OF SAMPLE L.T. BILL

    Fixed charges : Rs 30/-Electricity charges :No of units * per unit Rate as per slotEC = 48*2.35=Rs.112.8/-

    Other charges : Rs.5.76/-

    ED : Rs. (30+112.8+5.76)*015=23.65/-

    FAC : 48 * 0.05=Rs.2.4/-

  • 7/31/2019 m10x Presentation Session 1

    30/31

    CALCULATION OF SAMPLE L.T. BILL

    Reliability charge = 48*0.21=Rs.10.08/-

    Additional reliability charges= Rs 6.72/-

    Total bill amount: = Rs (30+118.56+23.65+2.4+10.08+6.72)=Rs.191.41/-

  • 7/31/2019 m10x Presentation Session 1

    31/31

    THANK YOU!