piScama xao~Iya Baar p`oYaNa kI vaaiYa-k irpaoT-
ANNUAL REPORT OF
W R L D C
Western Regional Load Dispatch Centre,
Plot No. F-3, MIDC Area, Marol, Andheri (East), MUMBAI. Pin:400 093
2014-2015
WRLDC
Page 2 of 146
Document Management Information:
Document Name
Annual Report 2014-15
Document ID WRLDC/Annual Report/2014- 15/V00
Version No. 00 Date 30th June 2015
Classification Public
Document Modification History
Date Version Name Comment
Disclaimer This is an operational report with data analysis of the year 2014-15. Data/information in this report are indicative only and should not be used for any Commercial purpose.
WRLDC
Page 3 of 146
WRLDC
Page 4 of 146
INDEX
CHAPTER
NO
CONTENTS PAGE
NO
Western Region Highlights & Assets 6-7
I. INTRODUCTION
1.1 Mission 8
1.2 Functions of RLDC 8
1.3 IMS policy 8
1.4 Western Region Load Despatch Center & Salient Features 12
II. REGIONAL GRID PERFORMANCE
2.1 Installed capacity of WR and Capacity Addition in 2014-15 14
2.2 Transmission System 18
2.3 Power supply position 24
2.3.1 Demand Profile 24
2.3.2 Load Pattern inWR 25
2.3.3 Growth of Peak Demand Met 26
2.3.4 Annual Load Duration Curve 27
2.3.5 System Load Factor 27
2.3.6 Energy Profile 28
2.3.7 Demand Management in Exceptional Days 30
2.4 Energy generation 32
2.4.1 Fuel wise Generation Data 33
2.4.2 Ghatghar Pump Storage Generation Data 39
2.4.3 Reservoir Level 42
2.5 Frequency profile 43
2.6 Voltage profile 44
2.7 Inter-Regional Links 46
2.8 Unit outages 47
2.9 RGMO details 48
2.10 Automatic Defence Mechanism 49
2.11 Grid Disturbances 50
2.12 Transmission Constraints 50
2.13 Contract details 50
WRLDC
Page 5 of 146
III. CONSTITUENTS OF WESTERN REGION
3.1 Gujarat 52
3.2 Maharashtra 56
3.3 Madhyapradesh 61
3.4 Chhattisgarh 67
3.5 Goa 70
3.6 Daman & Diu 72
3.7 Dadra Nagar Haveli 74
V. MARKET OPERATIONS
4.1 Schedule vs Drawal 77
4.2 Settlement of DSM Pool Account 98
4.3 Open Acess (OA) 104
4.4 Buy and Sale through exchanges 107
4.5 RLDC Fees and charges 108
V. EMS/SCADA & PMU - Monitoring and Control Facilities inWR
5.1 EMS/SCADA System 110
5.2 Wide Area Monitoring System (WAMS) 111
5.3 Common Information Model (CIM) 112
5.4 Publications 112
5.5 Communication Network 112
5.6 RTU Loacations in WR 113
VI. MISCELLANEOUS
6.1 Training 114
6.2 Workshop 115
6.3 115
VII. ANNEXURES
I Unitwise Installed Capacity 117
II Hourly Demand curves on peak day & Minimum day 123
III Transmission Constraints 127
IV List of Grid Disturbances 132
V Contracts in 2014-15 140
VI Power Map of WR 145
WRLDC
Page 6 of 146
Western Region Highlights
Western Region have highest Installed Capacity compared to all region i.e ~ 99
GW as on 31.03.2015. It is 36 % of all India Installed capacity of 272 GW.
Total Renewable installed capacity was 12795 MW in WR as on 31.03.2015.
RES energy capacity growth was 28.91% compared to 2013-14.
Total capacity of 13056 MW added in WR Grid in this year. Capacity addition
around 1.5 MW/hr.
Transmission lines of 9536 ckt Km added in 2014-15 which was more than 1 ckt
Km/hr. Western Region have highest nos (53 Nos) of 765 KV lines out of which
22 Nos of 765 KV lines added in this year.
System frequency was in IEGC band (49.9 50.05) for 52.78 % of time.
Average frequency was 49.97 Hz.
Maximum Demand of 45283 MW achieved on 26th March 2015 at 12:00 hrs.
Compound Annual Growth Rate in Max Demand Met over a decade is 8.30 %
WR recorded Maximum Energy Consumption of 1028 Mus on 29th Sept 2014.
Average Energy consumption was increased by 10.5% compared to 2013-14.
Total 3109 Nos of STOA transactions and 8812.51 Mus energy approved in this
year.
DSM charges collected and disbursed was Rs. 2207 Cr ( Doubled compared to
2013-14 ( Rs.1109.3 Cr ) due to implementation of DSM regulation)
WRLDC
Page 7 of 146
WR ASSET
S.No Element Total no. of
Elements
1 765kV Substations 25
2 400kV Substations 148
3 765kV Lines 53
4 400kV Lines 362
5 HVDC Bipoles 2
6 HVDC Back to Back links 2
7 FSCs 8
8 TCSCs 2
9 1500 MVA ICTS (765/400) 43
10 1000 MVA ICTs (765/400) 8
11 500 MVA ICTS (400/220) 41
12 315 MVA ICTs (400/220) 157
13 Important 220kV Lines 116
GENERATING UNITS IN WR
1 830 MW 5
2 685 MW 2
3 660 MW 21
4 600 MW 15
5 540 MW 2
6 500 MW 28
7 300 MW-400 MW 23
8
WRLDC
Page 8 of 146
CHAPTER 1
1.1 MISSION:
Ensure Integrated Operation of Regional and National Power Systems to facilitate transfer of electric power within and across the regions and trans-national exchange of power with Reliability, Security and Economy.
1.2 Functions of RLDC
(Section 28 of Electricity Act, 2003) (i) Be responsible for optimum scheduling and despatch of electricity within the region, in
accordance with the contracts entered into with the licensees or the generating companies operating in the region;
(ii) Monitor grid operations; (iii) Keep accounts of quantity of electricity transmitted through the regional grid; (iv) Exercise supervision and control over the inter-State transmission system; and (v) Be responsible for carrying out real time operations for grid control and despatch of
electricity within the region through secure and economic operation of the regional grid in accordance with the Grid Standards and the Grid Code.
(vi) To levy and collect such fees & charges from the generating companies or licensees engaged in inter-state transmission of electricity as may be specified by the Central Commission.
1.3 Integrated Management System Policy of WRLDC
WRLDC is committed to:
1. Ensure reliable and integrated power system operation in an efficient and effective manner,
with safety, security and optimal utilization of national resources, in conformity to legal and
regulatory provisions deploying the latest technologies.
2. Achieve this through continual improvement in effective monitoring of processes and the
ISMS/QMS/ EMS/ OHSAS Systems.
3. Facilitate & promote environment friendly technologies.
4. Ensure safe, occupational hazard free and healthy work environment.
5. Compliance of all applicable legal and regulatory requirements relating to all four Systems
(ISMS/QMS/EMS/OHSAS)
6. Continually improve our IMS to enhance the security of the information and services, quality
of our services, and also continually reduce the Environmental impact of our activities and
services, and control of pollution, and also continual improvement in our OH&S performance
This policy would be reviewed annually and be made available to the public and all other stake holders, viz. Customers, Employees, Suppliers and the shareholders of POWER GRID CORPORATION OF INDIA LIMITED
WRLDC
Page 9 of 146
WRLDC
Page 10 of 146
WRLDC
Page 11 of 146
WRLDC
Page 12 of 146
1.4 Western Regional Load Despatch Centre (WRLDC) & Salient features:
Western Regional Load Despatch Centre is responsible for reliable operations of the Western regional electricity grid covering the states of Gujarat, Maharashtra, Madhya Pradesh, Chhattisgarh, Goa and the Union Territories of Daman & Diu, Dadra and Nagar Haveli and the Central Generating Companies such as NTPC Ltd., NPCIL and Joint Venture companies as well as several Independent Power Producers (IPPs) whose generating stations connected to the Western grid. The Western region electricity grid which is a part of the synchronous NEWS grid comprising area of 951.488 sq. kms and population of 289 Million covers nearly 30% of the countrys area and population. It has the highest installed capacity of 98822 MW which is 36% of total installed capacity of Indian Power system including central sector, sate sector , private sector and Independent power plants and shares as on 31.03.2015. Per capita consumption of Western Region is 1201kWh.
2014-15 2013-14 2012-13
Installed Capacity
Hydro 7448 MW 7448 MW 7448 MW
Gas 10915 MW 10139 MW 9185 MW
Thermal (Coal) 65807 MW 58020 MW 50879 MW
Nuclear 1840 MW 1840 MW 1840 MW
Total (H + G + T + N) 86010 MW 77446 MW 69352 MW
Diesel 17.48 MW 17.48 MW 17.48 MW
RES 12795 MW 9925 MW 8987 MW
Grand Total 98822 MW 87389 MW 765374 MW
Net Increase Over Previous
Year 13.08 % 14.18 % 18.86 %
Demand
Max. Peak Load Catered 45283 MW 42253 MW 40890 MW
Increase Over Previous Year 7.17 % 3.33 % 7.40 %
Max. Unrestricted Demand 46490 MW 43215 MW 41478 MW
Min. Demand 25460 MW 24713 MW 25139 MW
Shortage (MW) 182 to 2481 MW 40 to 1377 MW 244 to 2422 MW
Shortage (%) 0.40 to 5.83 % 0.1 to 3.2 % 0.65 to 6.71 %
Energy Generation & Requirement
Energy Gen(H+G+T+N) 358926 Mus 320317 Mus 289666 Mus
Increase Over Previous Year 12.05 % 10.58 % 4.51 %
Wind & Solar Energy
Injection 13531 Mus 9416 Mus 9271 Mus
Increase Over Previous Year 43.70 % 1.56 % 27.37 %
WRLDC
Page 13 of 146
EnergyGen(H+G+T+N+wind
+solar) 372457 Mus 329733 Mus 298937 Mus
Increase Over Previous Year 12.96 % 10.30 % 5.10 %
Net Energy Availability 332278 Mus 299152 Mus 281165 Mus
Net Unrestricted Energy Req. 334712 Mus 302057 Mus 301213 Mus
Energy Shortage(%) 0.73 % 0.96 % 6.66 %
Peak Demand Met (MW)
Gujrat 14005 MW 12577 MW 12348 MW
Madhya Pradesh 10050 MW 9972 MW 9692 MW
Chattisgarh 3770 MW 3459 MW 3320 MW
Maharastra 20424 MW 18803 MW 17268 MW
Goa 489 MW 489 MW 418 MW
Daman and Diu 331 MW 283 MW 278 MW
DNH 721 MW 653 MW 652 MW
ESIL 621 MW 618 MW
Frequency Regime
Average Grid Frequency (Hz) 49.97 50.07 49.93
% time Grid Frequency
Below IEGC Range (50.2) %
Transmission Lines - Ckt Km
765 kV 11773 Ckt.
Km 6502
Ckt.
Km 3627
Ckt.
Km
Increase Over Previous Year 81.07 % 79.27 % 26.03 %
400 kV 47523 Ckt.
Km 43258
Ckt.
Km 38100
Ckt.
Km
Increase Over Previous Year 9.86 % 13.54 % 3.81 %
220 kV 45344 Ckt.
Km 43777
Ckt.
Km 41063
Ckt.
Km
Increase Over Previous Year 3.58 % 6.61 % 3.80 %
WRLDC
Page 14 of 146
CHAPTER 2
WESTERN REGIONAL GRID PERFORMANCE 2014-15
2.1 Installed Capacity:
Installed Generation capacity of WR including shares
State sector 30183 MW , 30%
Private sector 50008 MW , 51 %
Central(firm allocation) 18631 MW , 19%
TOTAL 98822 MW
Unitwise installed capacity of Western Region is enclosed as Annexure - I.
WRLDC
Page 15 of 146
Detailed statewise generation capacity of the states including shares as on 31.03.2015 is as follows
Source- cea
WRLDC
Page 16 of 146
Fuelwise break up of installed capacity is as follows.
HYDRO 7448 MW 7%
COAL 65807 MW 67%
GAS 10915 MW 11%
NUCLEAR 1840 MW 2%
RES 12795 MW 13%
Total Installed Capacity of WR - 98822 MW
WRLDC
Page 17 of 146
Growth Of Installed capacity in Western Region(Past Decade)
Most of the thermal power plants are located in the Eastern part of the region and load centres
are in the Western part. The region is predominantly thermal with hydro-thermal mix being in
the ratio of 7:78 and renewables of 13:78. Growth of Installed capacity is more prominent in
last 5 years due to addition of many independent power plants.
Capacity addition 2014-15:
13056 MW of capacity added in the year 2014-15. The details of units commissioned are given as
below:
SL.NO. STATE/ISGS/IPP STATION
NAME
CAPACITY
(MW) UNIT DATE
1 IPP APL Tiroda Ph II 660 IV 14/04/2014
2 IPP(Reliance Power) Sasan UMPP 660 IV 12/4/2014
3 Vandana Vidyut Vandana-1 (Salora) 135 I 10/4/2014
4 GSECL (Gujarat) Dhuvaran 376 I 21/05/2014
5 IPP(Reliance Power) Sasan UMPP 660 I 27/05/2014
6 IPP Dhariwal 300 II 02/08/2014
7 IPP(KSK Mahanadi) KSK Mahanadi 600 IV 26/8/2014
8 IPP(Jay Prakash Nigrie) JNSTPP 660 I 3/9/2014
9 APL Tirora Ph-II 660 V 25/09/2014
10 GMR Energy GMR Chhatisgarh 685 I 2/10/2014 (Syn)
11 Gujarat/Torrent Power DGEN-52 400 2 11/12/2014
12 MP Shree Singhaji Ph-II 600 II 28/12/2014
13 IPP(Reliance Power) Sasan UMPP 660 V 26/12/2014
14 MSPGCL Chandrapur 500 8 11/1/2015
Compound Annual growth rate(CAGR) -11.51%
WRLDC
Page 18 of 146
SL.NO. STATE/ISGS/IPP STATION
NAME
CAPACITY
(MW) UNIT DATE
15 IPP,Chhattisgarh JPL Stage -II
(Tamnar) 600 III
15/01/2015
16 IPP, Maharashtra (Ratan
India Pvt Ltd.,) Amaravati 270 3 02/02/2015
17 GSECL (Gujarat) Sikka 250 3 9/2/2015
18 IPP,Madhyapradesh JP Nigrie 660 II 21/2/2015
19 IPP, Chattisgarh Balco 300 I 22/02/2015
(SYN)
20 MSPGCL,Maharashtra Koradi 660 8 25/02/15
21 IPP (Chhatisgarh) RKM Powergrn Ltd. 360 28/02/2015(Syn)
22 IPP, Maharashtra (Ratan
India Pvt Ltd.,) Amaravati 270 4 07/03/2015
23 IPP, Maharashtra (Ratan
India Pvt Ltd.,) Amaravati 270 5 13/03/2015
25 IPP (Chhatisgarh) D B power 600 2 24/03/2015(Syn)
26 IPP (Chhatisgarh) JPL Stage -II
(Tamnar) 600 IV
26/03/2015 (Syn)
27 IPP(Reliance Power) Sasan UMPP 660 VI 27/03/2015
Total 13056
2.2 Transmission system
During 2014-15, 5271 ckt. km.of 765 kV, 4265 Ckt.km of 400 kV and 1567 ckt. km of
220 kV transmission lines were added in Western Region Transmission System. The growth
of 220 kV, 400 kV and 765 kV transmission line in ckt.km during the period 2005-06 to 2014-
15 is shown below.
Growth of Transmission line 765 kV 400 kV 220 kV
2005-06 21974 31801
2006-07 235 23331 32784
2007-08 586 26653 34219
2008-09 1212 28381 35275
2009-10 1697 30109 36331
2010-11 1989 34294 37891
2011-12 2878 36700 39558
2012-13 3627 38100 41063
2013-14 6502 43258 43777
2014-15 11773 47523 45344
WRLDC
Page 19 of 146
COMMISSIONING OF TRANSMISSION LINES : 2014-15
List of 765 kV lines:
SL.
NO. CONSTITUENT LINE NAME
CKT
NO KV DATE
Line Length
Ckt.Km
1 POWERGRID Bina-Gwalior III 765 2/5/2014 231.37
2 POWERGRID Dharamjaygarh-Durg II 765 21/5/2014 200
3 MSETCL Akola-II-Taptitanda* I 765 22/5/2014 219
4 RSTCL Raichur-Solapur II 765 29/6/2014 208
5 POWERGRID Wardha-Aurangabad II 765 3/7/2014 347.58
6 POWERGRID Wardha-Aurangabad I 765 5/7/2014 347.58
7 POWERGRID Dharamjaygarh-Jharsuguda II 765 28/7/2014 148.93
8 POWERGRID Dharamjaygarh-Jharsuguda I 765 29/7/2014 148.93
9 POWERGRID Satna-Gwalior II 765 4/8/2014 337
10 POWERGRID Wardha-Raipur (Durg) I 765 15/11/2014 370
11 POWERGRID Wardha-Raipur (Durg) II 765 15/11/2014 370
12 BDTCL Indore - Bhopal S/C 765 19/11/2014 176
13 BDTCL BDTCL Dhule-Aurangabad I 765 4/12/2014 192
14 MEGPTL Koradi III-Tirora II 765 20/12/2014 136
15 MEGPTL Koradi III-Akola-2 I 765 6/2/2015 222.38
16 MEGPTL Koradi III-Tirora I 765 7/2/2015 138.40
17 MEGPTL Koradi III-Akola-2 II 765 24/02/2015 222.38
18 Powergrid Solapur- Pune GIS
(Shikrapur) s/c 765 28/02/2015 270.07
19 Powergrid Wardha-Aurangabad III 765 30/03/2015 370
20 Powergrid Wardha-Aurangabad IV 765 30/03/2015 370
21 Powergrid Sasan-Vindhayachal PS-I s/c 765 31/03/2015 8
22 Powergrid Satna-Vindhyachal I 765 31/03/2015 237
Total 5271 * charged at 400 KV level
WRLDC
Page 20 of 146
List of 400 kV lines commissioned in 2014-15-
SL.
NO. CONSTITUENT LINE NAME CKT NO KV DATE
Line
Length
Ckt.Km
1 MEGPTL Akola(1)-Akola(2) I 400 18/4/2014 30.63
2 CSPTCL Bhilai-Raita III 400 2/4/2014 56
3 POWERGRID LILO of Bhadrawati-Parli-2
at Dhariwal II 400 21/4/2014 405
4 POWERGRID Aurangabad(PG)-
Aurangabad(MSETCL) I 400 27/4/2014 54.11
5 POWERGRID Aurangabad(PG)-
Aurangabad(MSETCL) II 400 28/4/2014 54.11
6 POWERGRID Akola(MSETCL)-
Aurangabad(PG) I 400 28/4/2014 294
7 POWERGRID Indore-Asoj III 400 3/5/2014 381
8 MSETCL Aurangabad - Taptithanda-
Deepnagar ckt I
LILO at
Taptithanda 400 21/5/2014 78
9 D B Power D B Power-Kotra I 400 20/06/2014 18
10 D B Power D B Power-Kotra II 400 20/06/2014 18
11 Sterlite, BDTCL Bhopal(Sterlite)-
Bhopal(MP) I 400 29/6/2014 8.6
12 POWERGRID Vindhyachal-Rihand I 400 3/7/2014 59.55
13 GETCO Kosamba-Chorania I 400 5/7/2014 230
14 GETCO Kosamba-Chorania II 400 5/7/2014 230
15 BDTCL Bhopal(BDTCL)-
Bhopal(MP) I 400 16/7/2014 8.64
16 POWERGRID LILO of Raipur-Raigarh-4 at
KSK IV 400 18/7/2014 282
17 MPPTCL Indore-Pitampura II 400 21/07/2014 150
18 POWERGRID Anooppur-Jabalpur I 400 6/8/2014 246.4
19 POWERGRID Anooppur-Jabalpur II 400 6/8/2014 246.4
20 JP Nigrie Satna-JP Nigrie I 400 19/8/2014 161
21 MPPTCL Indore-Pitampura I 400 4/9/2014 150
22 LANCO LANCO-Bilaspur I 400 6/9/2014 45
23 LANCO LANCO-Bilaspur II 400 9/9/2014 45
24 RKM Powergrn
Ltd
RKM LILO Line connect
with Raipur -Raigarh III 400 10/10/2014 26
25 MPPTCL Chhegaon-Julwania D/C 400 31/10/2014 114
26 POWERGRID Navsari-Kala
LILO at
Magadwada
GIS
400 3/11/2014 16
27 BDTCL BDTCL Dhule-Dhule(MS) I 400 5/12/2014 18
28 BDTCL BDTCL Dhule-Dhule(MS) II 400 5/12/2014 18
29 MSETCL Taptithanda-Bableshwar I 400 31/12/2014 127
30 MSETCL Taptithanda-Bableshwar II 400 31/12/2014 127
31 Bahachau (PG) &
Varsana (GETCO) Bachau-Varsana I 400 6/1/2015 10
WRLDC
Page 21 of 146
SL.
NO. CONSTITUENT LINE NAME CKT NO KV DATE
Line
Length
Ckt.Km
32 Bahachau (PG) &
Varsana (GETCO) Bachau-Varsana II 400 6/1/2015 10
33 GETCO Chornia-Mundra II (LILO at
Mansar) 400 23/01/2015 0.5
34 Powergrid Parli- Pune GIS (Shikrapur)-
Pune ckt II
LILO of Pune
Parli-II 400 24/02/2015 22
35 Powergrid Parli- Pune GIS (Shikrapur)-
Pune ckt I
LILO of Pune
Parli-I 400 24/02/2015 22
36 Powergrid
Navsari-Magarwada LILO of
Navsari-Vapi
ckt-II
400 27/02/2015 106 Magarwada-Kala
Kala-Vapi
37 MEGPTL Akola(2) -RIPL (Ratan India
Power Ltd) I 400 20/03/2015 104
38 MEGPTL Akola(2) -RIPL (Ratan India
Power Ltd) II 400 20/03/2015 104
39 Powergrid Sasan-Vindhayachal PS-I 400 26/03/2015 8
40 Powergrid Powergrid Solapur- NTPC
Solapur d/c 400 30/03/2015 11
41 GETCO Mundra-Varsana* II 400 31/03/2015 85
42 GETCO Mundra-Varsana* III 400 31/03/2015 85
Total 4265 * Interim arrangement of Mundra-Zerda Line.
COMMISSIONING OF NEW LINE REACTORS
SL.
NO. CONSTITUENT STATION NAME LINE NAME KV
CAPACITY
(MVAR) DATE
1 POWERGRID Seoni Seoni-Wardha 1 765 240 30/04/2014
2 POWERGRID Dharamjaygarh* Ranchi-Dharamjaygarh 1 765 330 16/04/2014
3 POWERGRID Raipur PS(Durg) Dharamjaygarh - Durg II 765 240 21/05/2014
4 BDTCL BDTCL Indore-BDTCL I 765 240 23/7/2014
5 POWERGRID Dharamjaygarh Dharamjaygarh-Jharsuguda II 765 330 28/07/2014
6 POWERGRID Dharamjaygarh Dharamjaygarh-Jharsuguda I 765 330 29/7/2014
7 POWERGRID Satna Satna-Gwalior-II 765 240 29/7/2014
8 POWERGRID Aurangabad Padghe-Aurangabad-1 765 240 31/07/2014
9 POWERGRID Satna Satna-Gwalior-2 765 240 4/8/2014
10 POWERGRID Aurangabad* Padghe-Aurangabad-2 765 240 5/8/2014
11 POWERGRID Durg Wardha-Durg-1 765 240 12/8/2014
12 POWERGRID Aurangabad Boisar- Aurangabad-I 400 125 30/9/2014
13 POWERGRID Indore Indore-Bhopal 765 240 3/10/2014
14 POWERGRID Bhopal Jabalpur-Bhopal 765 240 6/10/2014
15 POWERGRID Jabalpur Bina-Jabalpur Ckt III 765 240 3/10/2014
16 POWERGRID Jabalpur Jabalpur-Bhopal 765 240 18/10/2014
17 POWERGRID Solapur Solapur-Karad 400 80 25/11/2014
WRLDC
Page 22 of 146
SL.
NO. CONSTITUENT STATION NAME LINE NAME KV
CAPACITY
(MVAR) DATE
18 POWERGRID Jabalpur Pool Jabalpur pool-Dharamjaygarh
ckt-2 765 240 29/11/2014
19 POWERGRID Gwalior Jaipur-Gwalior ckt-2 765 240 22/11/2014
20 POWERGRID Bina Jabalpur-Bina Ckt-3 765 240 11/11/2014
21 POWERGRID Satna Satna-Vindhyachal ckt-I 765 240 11/11/2014
22 BDTCL BDTCL BDTCL Dhule-A'bad-I 765 240 4/12/2014
23 POWERGRID Boisar* Boisar-Aurangabad ckt I 400 80 9/1/2015
24 POWERGRID Boisar* Boisar-Aurangabad ckt II 400 80 9/1/2015
25 POWERGRID Satna* Vindhyachal-Satna ckt II 765 240 12/1/2015
26 IPP(Reliance
Power) Sasan SASAN-Satna Ckt-II 765 240 21/01/2015
27 MEGPTCL Koradi-III Koradi-III-Akola-II 765 240 24/02/2015
28 POWERGRID Pune GIS
(Shikhrapur) Solapur-Pune s/c 765 240 27/02/2015
29 MPPTCL Astha Sarni -Astha ckt I 400 50 27/03/2015
30 MPPTCL Astha Sarni -Astha ckt II 400 50 27/03/2015
31 POWERGRID Aurangabad Wardha-Aurangabad ckt-IV 765 240 27/03/2015
32 POWERGRID Wardha Wardha-Aurangabad ckt-III 765 330 28/03/2015
33 POWERGRID Wardha Wardha-Aurangabad ckt-IV 765 330 28/03/2015
34 POWERGRID Vindhyachal Satna-Vindhyachal ckt-I 765 240 29/03/2015
35 MEGPTCL Koradi-III Koradi-III-Tiroda line-II 765 240 30/03/2015
* Line Reactor charged as Bus Reactor Total 7875
COMMISSIONING OF NEW BUS REACTORS
SL.NO. CONSTITUENT STATION NAME KV CAPACITY
(MVAR) DATE
1 POWERGRID Aurangabad 400 125 28/04/2014
2 Sterlite Bhopal(Sterlite) 400 125 29/06/2014
3 POWERGRID Bhatapara 400 125 24/7/2014
4 POWERGRID Raigarh 400 125 30/07/2014
5 POWERGRID Indore 765 240 31/7/2014
6 POWERGRID Sujalpur 400 125 31/7/2014
7 POWERGRID Itarsi (B/R 1) 400 125 5/8/2014
8 JP Nigrie JNSTPP 400 125 19/8/2014
9 POWERGRID Damoh 400 125 30/9/2014
10 POWERGRID Gwalior 765 240 28/9/2014
11 POWERGRID Raipur 400 125 30/9/2014
12 POWERGRID Pirana 400 125 2/10/2014
13 POWERGRID Itarsi 765 125 13/10/2014
14 POWERGRID Bhopal 765 240 2/10/2014
15 POWERGRID WARDHA 765 330 1/11/2014
16 POWERGRID Bilaspur 765 240 29/11/2014
17 POWERGRID Bachau 400 125 1/12/2014
WRLDC
Page 23 of 146
SL.NO. CONSTITUENT STATION NAME KV CAPACITY
(MVAR) DATE
18 BDTCL BDTCL-Dhule 765 240 4/12/2014
19 RKM Powergrn Ltd RKM Powergrn Ltd 400 50 5/12/2014
20 POWERGRID Seoni-PG 400 125 11/12/2014
21 MPPTCL Julwania 400 50 13/12/2014
22 POWERGRID Jabalpur (Pooling) 400 125 29/12/2014
23 POWERGRID Magarwada GIS (DAMAN) 400 80 9/1/2015
24 POWERGRID Parli 400 125 8/1/2015
25 POWERGRID Pune GIS (Shikhrapur) 765 240 25/02/2015
Total 3825
COMMISSIONING OF NEW ICTs:
SL.NO. CONSTITUENT STATION NAME KV RATIO CAPACITY
(MVA) DATE
1 POWERGRID Aurangabad 765 / 400 1500 29/06/2014
2 POWERGRID Dharamjaygarh(ICT 1) 765/400 1500 9/7/2014
3 POWERGRID Korba (ICT 2) 765/400 1500 19/6/2014
4 BDTCL BDTCL(Bhopal)ICT 1 765/400 1500 3/7/2014
5 POWERGRID Navasari(ICT 3) 400/220 500 8/7/2014
6 MPPTCL Ashta ICT -I 400/200 315 6/9/2014
7 Sterlite BDTCL ICT II 765/400 1500 29/09/2014
8 MPPTCL Julwania ICT-I 400/200 315 31/10/2014
9 POWERGRID Magarwada GIS (DAMAN) 400/220 315 7/11/2014
10 POWERGRID Magarwada GIS (DAMAN) 400/220 315 7/11/2014
11 BDTCL BDTCL-Dhule(ICT-I) 765/400 1500 5/12/2014
12 BDTCL BDTCL-Dhule(ICT-II) 765/400 1500 5/12/2014
13 MPPTCL Ashta ICT -II 400/200 315 27/12/2014
14 MPPTCL Julwania ICT-II 400/200 315 13/12/2014
15 Powergrid Boisar (ICT-III) 400/220 500 31/12/2014
16 Powergrid Pune GIS (ICT 1) 765/400 1500 26/02/2015
17 Powergrid Pune GIS (ICT 2) 765/400 1500 26/02/2015
18 GETCO Asoj 400/220 315 17/03/2015
19 Powergrid Bhadrawati 400/220 315 17/03/2015
20 MEGPTCL Koradi ICT-I 765/400 1500 26/03/2015
21 MEGPTCL Koradi ICT-II 765/400 1500 28/03/2015
22 Powergrid Vindhayachal PS ICT-II 765/400 1500 29/03/2015
Total 21520
WRLDC
Page 24 of 146
2.3 Power Supply Position :
Region WR Demand (in MW)
Month Unrest. Dmd Availability Shortage Shortage (in %) 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 44773 39540 43968 39009 805 531 1.80 1.34
May 43523 39597 42956 38760 567 837 1.30 2.11
June 43802 37566 42934 36657 868 909 1.98 2.42
July 43419 34541 43034 34317 385 224 0.89 0.65
Aug 42544 36727 40063 35680 2481 1047 5.83 2.85
Sep 46490 39563 45081 38807 1410 756 3.03 1.91
Oct 46100 39273 44988 39233 1112 40 2.41 0.10
Nov 45380 42652 44549 41927 831 725 1.83 1.70
Dec 45128 43215 44946 42183 182 1032 0.40 2.39
Jan 44533 43092 43839 41715 694 1377 1.56 3.20
Feb 44966 43106 44750 42253 216 853 0.48 1.98
Mar 45718 42142 45283 41535 435 607 0.95 1.44
Average 1.87 1.84
2.3.1 Demand Profile :
The maximum demand met in the year 2014-15 was 45283 MW on 26th Mar, 2015 at 12:00 hrs.which
is so far highest demand met in Western Region. Peak demand growth was 7.17% against last year
whereas the unrestricted demand growth is 8.49%. The minimum demand of 25460 MW observed on
2nd March 2015 at 04:00 Hrs.
Hourly Demand curve on Maximum and Minimum day is enclosed in Annexure-II.
WRLDC
Page 25 of 146
2.3.2 Load Pattern in Western Region :
Load in the quarter April-June is mainly residential and commercial loads due to
summer conditions. July-September is generally lean period due to rainy season but in the year
2014-15 due to less monsoon the peak demand met did not decrease much except the August
month. In August Demand met was in the range of 40000 MW and for rest of the quarter
demand met varies in the range of 43000MW to 45000 MW. In september month high demand
was observed due to starting of festival season.The quarter October-December is high demand
period due to onset of Rabi season when agricultural demand is predominant with many pump
sets operating. This quarter, being the festival season, commercial and residential demands
are also on the higher trajectory.The quarter January-March is high demand period similar to
that of previous quarter due to continuation of agricultural activities. The industrial demand is
also at its peak as this is the last quarter of the financial year and target needs to be achieved
before the budget. Regional peak demand met varied in the year from 40000 MW to 45000
MW. Seasonal load curve for Quarterly hourly average summer, winter and monsoon is as
below.
WRLDC
Page 26 of 146
2.3.3 Growth Of Peak Demand Met(Past Decade)
Demand availability is more in last five years as more addition of generation in Western Region.
Compound Annual Growth Rate(CAGR) 8.30%
WRLDC
Page 27 of 146
2.3.4 Annual Load Duration Curve
2.3.5 System Load factor-
System Load Factor - %
.
Month Peak Demand Met (in MW) Energy Met (in Mus)
Monthly System Load Factor (%)
2013-14 2014-15 2013-14 2014-15 2013-14 2014-15
Apr 39009 43968 25734 28534 91.62 90.14
May 38760 42956 26971 29340 93.53 91.81
June 36657 42934 22185 27851 84.06 90.09
July 34317 43034 22085 26487 86.50 82.73
Aug 35680 40063 22349 25638 84.19 86.01
Sept 38807 45081 24384 26054 87.27 80.27
Oct 39233 44988 24672 30181 84.52 90.17
Nov 41927 44549 25832 29140 85.57 90.85
Dec 42183 44946 27513 28482 87.67 85.17
Jan 41715 43839 26367 26761 84.96 82.05
Feb 42253 44750 24333 26126 85.70 86.88
Mar 41535 45283 26587 27686 86.04 82.18
Regional peak demand met in 2014-15
remained above 38200 MW for 50% of
the time (2013-14- 34200 MW)
WRLDC
Page 28 of 146
2.3.6 Energy Profile: In the year 2014-15, total energy availability of Western region was 333 billion units
against the requirement of 334 billion units. Energy shortages varied from 0.25% to
max.1.47%. The maximum energy consumption per day was 1028 Mus on 29.09.2014. Charts
for growth of Energy consumption from 2004 onwards yearwise and energy cosumption
pattern for the year 2014-15 monthwise and daywise energy consumption for the last five
years are below.
WRLDC
Page 29 of 146
WRLDC
Page 30 of 146
2.3.7 Demand Management in exceptional Days
Proper action has been taken to manage the load and generation balance in exceptional days like
Diwali,Republic day,Kite festival and Holi to keep the grid parameters safe and within standard.
WRLDC
Page 31 of 146
WRLDC
Page 32 of 146
2.4 Energy Generation: Total energy generated was 372 BU including state, central and private sector. Month-
wise Break-up of energy generation in 2014-15 is given below.
Generation 2014-15 (in Mus)
State Sector Central Sector Private/IPP Total
Apr/14 19463 7946 4854 32263
May/14 19416 8580 4754 32750 Jun/14 18737 7077 4856 30669
Jul/14 17359 6995 5094 29448
Aug/14 17129 6995 5088 29212
Sep/14 16046 7891 5230 29166
Oct/14 19413 8441 5306 33159
Nov/14 19064 7546 6089 32700 Dec/14 19079 7015 6287 32381
Jan/15 17957 7142 5637 30736 Feb/15 16644 7269 5910 29823
Mar/15 18118 7198 4832 30148
Total 218425 90096 63936 372457
WRLDC
Page 33 of 146
2.4.1. Fuel Wise Generation
Months Hydro Generation 2014-15(in Mus)
April'14 1900
May'14 1264
June'14 758
July'14 691 Aug'14 1771
Sep'14 2700
Oct'14 1344
Nov'14 1274
Dec'14 1294
Jan'15 1482
Feb'15 1343
Mar'15 1383 Total 17204
Months Thermal Generation 2014-15(in Mus)
April'14 28049
May'14 29338
June'14 27048
July'14 26085 Aug'14 19714
Sep'14 18730
Oct'14 23206
Nov'14 22892
Dec'14 21606
Jan'15 20229
Feb'15 19265
Mar'15 20372 Total 276533
WRLDC
Page 34 of 146
Months Nuclear Generation 2014-15(in Mus)
April'14 1095
May'14 1188
June'14 1145
July'14 1317
Aug'14 1308
Sep'14 1291
Oct'14 1247
Nov'14 1170
Dec'14 1064
Jan'15 797
Feb'15 1193
Mar'15 1284
Total 14098
WRLDC
Page 35 of 146
Renewable in WR-
RES Installed Capacity (in MW)
Gujarat Maharashtra Madhya Pradesh Total
Wind 3581 4369 567 8517
Solar 974 341 393 1708
WIND GENERATION: In Western Region,Wind energy is mainly available in Gujarat,Maharashtra
and Madhya Pradesh. Following table shows generation for the year 2014-15 and 2013-14.
Month
Wind Generation in MUs %of wind energy on
total energy met
Total Energy Met (in Mus)
Mah Guj MP Total
Apr-14 228 338 40 607 2.13 28534
May-14 422 629 51 1102 3.76 29340
Jun-14 856 962 67 1885 6.77 27851
Jul-14 1083 844 109 2036 7.69 26487
Aug-14 616 540 71 1226 4.78 25638
Sep-14 550 308 51 909 3.53 26054 Oct-14 178 169 23 369 1.22 30181
Nov-14 175 227 21 422 1.45 29140
Dec-14 221 487 26 734 2.58 28482
Jan-15 141 428 36 604 2.26 26761
Feb-15 164 352 45 561 2.15 26126
Mar-15 214 369 54 636 2.30 27686
Total 4857 5652 593 11091 332278
Generation in Mus Total (2013-14)
%of wind energy on total energy met
Total Energy met
Month Mah Guj
APR'13 304 425 728 2.83 25734
MAY'13 552 752 1305 4.84 26971
JUNE'13 630 486 1116 5.03 22185
JULY'13 869 692 1561 7.07 22085
AUG'13 672 550 1223 5.47 22349
SEP'13 322 453 775 3.18 24384
OCT'13 179 152 331 1.34 24672
NOV'13 128 305 433 1.67 25967
DEC'13 118 321 440 1.60 27513
JAN'14 132 486 618 2.34 26369
FEB'14 184 159 343 1.41 24333
MAR'14 182 360 543 2.04 26587
TOTAL 4273 5141 9416 299152
WRLDC
Page 36 of 146
Compared to last year,wind generation in 2014-15 was increased by 18%. In Western Region wind
generation was more during the period April to August whereas less in rest of the year as shown in the
graph below. Maximum wind energy contribution of 7.69% out of total energy consumption of WR
observed in the month of July,2014.
WRLDC
Page 37 of 146
SOLAR POWER IN WESTERN REGION-
The Installed capcity of Solar power in Western region is 1708 MW. The break up is as mentioned below-
Name of the Constituents Capacity in MW
Gujarat 974
Maharashtra 341
Chhattisgarh ----
Madhyapradesh 393
TOTAL 1708
WRLDC
Page 38 of 146
Solar Generation in Mus
Month Guj MP Mah Total %of solar
energy on total energy met
Energy Met (in Mus)
Apr-14 139 50 30 219 0.77 28534
May-14 138 51 32 221 0.75 29340
Jun-14 120 52 29 202 0.72 27851
Jul-14 95 36 22 154 0.58 26487
Aug-14 100 39 24 163 0.64 25638
Sep-14 104 48 26 178 0.68 26054
Oct-14 123 54 31 209 0.69 30181
Nov-14 116 50 30 196 0.67 29140
Dec-14 126 51 30 206 0.72 28482
Jan-15 127 50 31 209 0.78 26761
Feb-15 130 60 34 225 0.86 26126
Mar-15 153 70 37 259 0.94 27686
Total 1471 612 357 2440 332278
WRLDC
Page 39 of 146
2.4.2 Performance of Ghatghar Pump Storage -
Installed Capacxity in MW :-- 2x125 MW Units
GENERATION & PUMPING DATA for the year 2014-15
Month
GENERATION PUMPING
UNIT-1 UNIT-2 UNIT-1 UNIT-2
Gen. (in Mus)
Geneartion Service
Hrs
Gen. (in
Mus)
Gen. Service
Hrs
Pumping Consumpti
on (in Mus)
Pumping Service
Hrs
Pumping Consumption (in Mus)
Pumping Service
Hrs
April'14 9.915 80:30:00 8.809 71:43:00 13.732 88:50:00 10.427 69:35:00
May'14 14.79 120:08:00 12.623 103:00:00 18.721 123:20:00 16.283 108:55:00
June'14 16.018 129:20:00 13.607 111:41:00 23.207 153:29:00 16.869 113:27:00
July'14 18.926 153:20:00 16.445 134:51:00 24.923 165:41:00 25.227 170:12:00
Aug'14 10.385 84:05:00 13.694 112:10:00 16.795 111:04:00 19.727 134:10:00
Sept'14 6.778 54:55:00 11.709 95:42:00 13.169 86:00:00 12.718 84:00:00
Oct'14 12.244 99:30:00 10.796 86:25:00 16.574 107:00:00 14.957 100:00:00
Nov'14 10.85 87:46:00 6.33 52:10:00 9.252 60:43:00 13.818 93:08:00
Dec'14 20.989 162:43:00 11.736 96:00:00 26.042 170:30:00 15.468 103:45:00
Jan'15 22.627 183:50:00 0 0:00:00 30.531 200:40:00 0.153 0:00:00
Feb'15 24.912 196:25:00 9.479 75:15:00 32.463 207:40:00 11.464 77:58:00
Mar'15 16.867 133:13:00 13.771 109:20:00 19.326 123:20:00 17.55 118:50:00
219 221
202
154163
178
209196
206 209
225
259
0.77 0.750.72
0.580.64
0.68
0.690.67
0.72 0.78
0.86
0.94
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
0
50
100
150
200
250
300
Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15
%
MU
s
Total Solar Generation in WR
Total Solar Energy Met %of Total energy met
WRLDC
Page 40 of 146
WRLDC
Page 41 of 146
Ghatghar Generation and Pumping operation in Jan15
1st Jan 2015 (New Year Day)
14th Jan 2015 (Kite Festival)
26th Jan 2015 (Republic Day)-
WRLDC
Page 42 of 146
2.4.3 WR constituent- Reservior Levels (in feet)
Months Madhya Pradesh Gujarat Maharashtra
GandhiSagar Indira sagar Ukai Kadana Koyna
Apr'14 1299 827 320 417 2067
May'14 1298 811 313 415 2045
Jun'14 1296 807 305 411 2038
Jul'14 1297 837 327 406 2130
Aug'14 1300 848 332 406 2157.2
Sep'14 1303 858 340 419 2159
Oct'14 1303 857 336 418 2155.4
Nov'14 1301.2 852 332.2 416.4 2152.2
Dec'14 1297.66 847 339.00 417.1 2146.2
Jan'15 1293.4 840 325.95 413.1 2141.7
Feb'15 1289.2 834 321.36 411 2135.2
Mar'15 1286.88 828 315.3 410.11 2126.1
FRL
Ft
WRLDC
Page 43 of 146
2.5 Frequency Profile:
The frequency profile for the year 2014-15 as per the IEGC Band is mentioned hereunder:
Months 50.05 FVI IEGC Band
April'14 30.64 52.33 17.03 0.16
May'14 22.48 53.19 24.33 0.13
June14 37.15 45.36 17.49 0.24
July14 34.51 50.16 15.33 0.2
Aug14 37.87 49.5 12.63 0.19
Sept14 28.13 55.7 16.16 0.43
Oct14 25.55 52.94 21.52 0.13
Nov'14 16.49 53.60 29.90 0.10
Dec'14 23.85 48.29 27.86 0.14
Jan'15 17.46 53.73 28.81 0.12
Feb'15 12.30 60.15 27.56 0.08
Mar'15 17.77 58.47 23.76 0.10
MAX 37.87 60.15 29.90 0.43
MIN 12.30 45.36 12.63 0.08
AVG. 25.35 52.78 21.86 0.17
Ft
WRLDC
Page 44 of 146
Maximum, Minimum & Average Frequency
Month Max(Hz) Min(Hz) Avg(HZ)
April'14 50.56 49.49 49.95
May'14 50.59 49.41 49.98
June'14 50.67 49.32 49.94
July'14 50.36 49.41 49.93
Aug'14 50.34 49.36 49.93
Sep'14 50.37 49.34 49.95
Oct'14 50.48 49.53 49.96
Nov'14 50.42 49.58 50.00
Dec'14 50.58 49.54 49.98
Jan'15 50.56 49.55 49.99
Feb'15 50.55 49.58 50.00
Mar'15 50.54 49.52 49.98
MAX 50.67 49.58 50.00
2.6 Voltage Profile:
High voltage prevailed in the month of monsoon months of June, July, August and September
during night hours. High Voltage areas were Khandwa, Damoh, Rajgarh, Dhule, Karad, Akola,
Chandrapur and Bhusawal. About 15-20, 400KV lines kept open continuously to control high
voltages. Lines kept out on high voltage were SSP-Rajgarh, SSP-Dhule, Kolhapur-Mapusa,
Damoh-Birsinghpur, Damoh-Bhopal, Kolhapur-Solapur, Khandwa- Rajgarh, Nagda-Dehgam,
765 KV Wardha Aurangabad and 765 KV Seoni-wardha. Flow on HVDC, Cpur-Padghe
WRLDC
Page 45 of 146
kept at minimum possible limit during night off-peak hours to nullify the effect of filter banks
of HVDC.
During the Rabi season, agricultural loads picked up and the voltage profile begins to
deteriorate, Due to high reactive power requirement of agricultural loads specifically during
morning time low voltage observed at places Indore, Gwalior, Jetpur and Bina. Month-wise
maximum and minimum voltages observed at important 400 and 765 kV substations in the grid
is as below.
Voltage Profile 2014-15
Date Indore Itarsi Karad Dhule Asoj Kasor Bhilai Jetpur
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Apr'14 420 389 426 394 435 400 434 394 421 397 422 401 422 401 424 395
May'14 421 388 428 395 438 400 435 393 420 396 422 400 427 400 419 398
Jun'14 422 390 426 396 437 404 435 394 420 397 430 400 426 402 419 392
July'14 423 393 427 397 439 400 431 396 424 400 430 403 428 400 422 389
Aug'14 421 397 423 398 440 400 437 396 424 404 430 406 425 407 431 407
Sep'14 421 389 425 396 440 400 439 388 428 399 430 403 425 400 426 387
Oct'14 421 388 421 390 440 397 434 381 426 397 430 409 423 397 419 381
Nov'14 423 389 421 389 439 397 435 378 421 400 430 408 424 398 419 387
Dec'14 424 395 419 389 440 400 437 388 425 397 430 403 425 400 419 390
Jan'15 424 398 419 390 440 406 435 388 426 398 421 402 426 404 415 388
Feb'15 424 394 419 389 440 400 435 383 422 397 422 405 421 403 414 391
Mar'15 423 399 418 394 440 400 439 395 424 398 424 400 424 400 413 391
MAX 424 388 428 389 440 397 439 378 428 396 430 400 428 397 431 381
Date Bina Gwalior Nagda Khandwa Sipat seoni Gwalior Bina
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Max. Kv
Min. Kv
Apr'14 423 399 418 383 425 396 432 396 767 733 796 733 800 746 805 750
May'14 425 401 417 392 425 396 432 390 789 746 792 750 799 752 805 760
Jun'14 425 398 426 388 424 397 431 395 790 751 795 743 806 734 805 751
July'14 425 397 418 386 427 397 432 399 789 748 797 751 799 745 808 755
Aug'14 429 405 423 390 425 400 430 401 789 739 792 749 805 753 805 765
Sep'14 426 402 426 392 426 393 434 400 765 742 797 748 811 758 810 765
Oct'14 430 397 411 386 425 394 430 391 796 741 783 730 802 743 799 753
Nov'14 425 393 415 386 427 392 431 394 789 740 792 736 796 744 800 748
Dec'14 425 396 413 386 425 392 431 397 792 746 792 747 797 749 801 752
Jan'15 427 396 418 384 426 395 429 396 789 740 796 744 800 742 804 747
Feb'15 422 394 416 389 426 394 430 394 773 744 790 749 795 748 795 753
Mar'15 421 400 410 390 425 400 429 404 772 748 793 753 789 751 791 754
MAX 430 393 426 383 427 392 434 390 796 733 797 730 811 734 810 747
WRLDC
Page 46 of 146
2.7 Inter-regional Link: Western region is synchronously connected with ER through 765 kV Dharamjaygarh-Ranchi S/C, 765
KV Dharamjaygarh-Jharsguda D/C, 400kV Raigarh-IBEUL S/C, 400 kV Raigarh-Jharsuguda S/C,
Raigarh-Sterlite S/C, 400 KV Raigarh-Raurkella S/C, Ranchi-Sipat D/C and three 220 kV lines Korba-
Budhipadar D/C & Raigarh-Budhipadar S/C. WR is connected asynchronously with NR through
HVDC back to back at Vindhyachal with transfer capability of 2x250 MW and Mundra-Mohindergarh
Bipolar HVDC with transfer capability 2x1500 MW in either direction and synchronously with NR
with 765 kV Agra-Gwalior D/C , 400 kV Zerda-Kankroli, 400 kV Zerda-Bhinmal and 220 kV lines
Kota-Badod, Modak-Badod, Auraiya-Mehgaon and Auraiya-Malanpur line. WR has asynchronous
connection with Southern region at Bhadravati back to back having transfer capability of 2x500 MW
in either direction.WR is connected synchronously with Southern Region through 765 kV Raichur-
Solapur 2xS/C and 400 kV Bhadrawati-Ramagundam D/C. WR is connected with SR by two 220 kV
Kolhaphur(Mudshingi)-Chikkodi S/C, 220 KV Kolhaphur(Talandage)-Chikkodi S/C 220 KV
Ambewadi-Xeldem S/C and 220 KV Ambewadi-Ponda D/C.
Path Details
Voltage(kV) Link Details Owner No. of Circuits
Length (in circuit km)
WR
-NR
500 HVDC Vindhyachal Back to Back (500 MW)
NRTS-1 2 blocks -
500 HVDC APL(Mundra)-Mohindargarh (2500MW)-Bipole
Adani Bipole 1978
765 Agra-Gwalior WRTS-2 D/C 258
400
Kankroli-Zerda WRTS-2 S/C 234
Bhinmal-Zerda WRTS-2 S/C 143
VSTP-IV-Rihand WRTS-2 S/C 60
220
Sakatpur-Badod Rajasthan/ Madhya Pradesh
S/C 199
Modak-Badod Rajasthan/ Madhya Pradesh
S/C 151
Auraiya-Mehgaon Uttar Pradesh/ Madhya Pradesh
S/C 113
Auraiya-Malanpur Uttar Pradesh/ Madhya Pradesh
S/C 146
Neemuch-Nimbahera Madhya Pradesh / Rajasthan
S/C 45
Seopur Kalan-Sawai Madhopur (Khandar)
Madhya Pradesh / Rajasthan
S/C 62
Gandhi Sagar-Ranapratap Sagar-I&II
Madhya Pradesh / Rajasthan
D/C 102
Morwa-Bina Madhya Pradesh / Uttar Pradesh
S/C 9
Rajghat-Lalitpur Madhya Pradesh / Uttar Pradesh
S/C 23
WRLDC
Page 47 of 146
Path Details
Voltage(kV) Link Details Owner No. of Circuits
Length (in circuit km)
WR
-SR
765 Raichur-Sholapur SRTS-2 S/C 208
765 Raichur-Sholapur RSTCL S/C 208
400
Bhadravati Back to Back (2x500 MW)
WRTS-1 2 blocks -
Bhadravati-Ramagundam
SRTS-2 D/C 356
220 Kolhaphur(Mudshingi)-Chikkodi
MSETCL,KPTCL S/C 155
220
Kolhaphur(Talandage)-Chikkodi
MSETCL,KPTCL S/C 150
Ambewadi-Xeldem* GED, KPTCL S/C 48
Ambewadi-Ponda* GED, KPTCL D/C 42
WR
-ER
400
Raigarh-IBEUL WRTS-1 S/C 114
Raigarh-Jharsuguda WRTS-1 S/C 142
Raigarh-Sterlite WRTS-1 S/C 99
Raigarh-Rourkella WRTS-1 S/C 209
Sipat-Ranchi WRTS-1 D/C 810
765
Dharamjaigarh-Ranchi WRTS-1 S/C 303
Dharamjaigarh-Jharsuguda
WRTS-1 D/C 606
220KV
Budhipadar-Raigarh OPTCL/CSPTCL S/C 105
Budhipadar-Korba(East)-II
OPTCL/CSPTCL S/C 176
Budhipadar-Korba(East)-III
WRTS-1 S/C 176
D/C : Double Circuit, S/C: Single Circuit
2.8 Unit Outages:
Thermal Outages 2014-15
Month
Installed
Capacity ( in
MW)
(Th+G+N)
Maximum in MW % of Inst.
Cap ( Th.+
G+N) Planned Max Forced Max Total Max
April'14 70134 2770 14795 17502 24.95
May'14 71870 3384 16860 18620 25.91
June'14 71870 3434 17760 20818 28.97
July'14 70220 4527 21766 26128 37.21
Aug'14 71615 4660 22996 26368 36.82
Sep'14 71615 4160 26783 30044 41.95
Oct'14 72875 665 21439 21794 29.91
WRLDC
Page 48 of 146
Nov'14 72875 940 20125 20926 28.71
Dec'14 72925 3175 19762 22697 31.12
Jan'15 73795 3241 22501 25598 34.69
Feb'15 75140 2380 23246 25296 33.67
Mar'15 78975 5096 26652 28098 35.58
MAX 78975 5096 26783 30044 41.95
Generally more unit outages were planned to take annual maintenance during monsoon period
i.e low demand period mainly in July to September. During 2014-15 maximum unit outages of 30044
MW was taken in the month of Sept14 including planned and forced outages which was 41.95% of
thermal capacity of Western Region.
2.9 RGMO unit details :
In Western Region, there are 267 RGMO eligible units of total capacity 68826 MW, out of which 126
units of total capacity 42562 MW only have RGMO/FGMO response.
Summary of Units and their Capacities for RGMO monitoring
RGMO Eligible units RGMO/FGMO available at
RGMO/FGMO Not available at
Name of Entity Number MW Number MW Number MW
Maharashtra 97 19631 35 7607 62 12024
Madhya Pradesh 56 6860 13 3300 43 3560
Gujarat 33 9570 18 5385 15 4185
Chhattisgarh 10 1960 3 120 7 1840
CGPL 5 4150 5 4150 0 0
WRLDC
Page 49 of 146
RGMO Eligible units RGMO/FGMO available at
RGMO/FGMO Not available at
Name of Entity Number MW Number MW Number MW
NCA 11 1450 10 1400 1 50
SASAN 6 3960 6 3960 0 0
NTPC 26 10840 18 8420 8 2420
ESSAR_Mahan 1 600 1 600 0 0
NSPCL 2 500 2 500 0 0
KSK 2 1200 2 1200 0 0
KWPCL 1 600 0 0 1 600
DB POWER 1 600 1 600 0 0
JPL 7 2800 7 2800 0 0
LANCO 2 600 2 600 0 0
EMCO 2 600 0 0 2 600
JP Nigrie 2 1320 2 1320 0 0
MB Power 1 600 1 600 0 0
Dhariwal 1 300 0 0 1 300
GMR-CG 1 685 0 0 1 685
WR_Total 267 68826 126 42562 141 26264
2.10 Automatic Defence Mechanism :
The approved AUFLS scheme in Western region and the recommended df/dt with changed scenario
in NEWS grid is as follows. AUFLS is basically defense mechanism against disturbances and
includes both discrete relays and trend relays. The feeders for discrete and trend automatic under
frequency relays need to be widely dispersed as operation of these relays is sensitive to the location
of the disturbance.
APPROVED UNDER FREQUENCY LOAD SHEDDING SCHEME IN WESTERN REGION
A. Discrete Under Frequency Relays (UFR):
StatesRequired
Load relief
Implemented
Load relief
Required
Load relief
Implement
ed Load
relief
Required
Load
relief
Implement
ed Load
relief
Required
Load
relief
Implemen
ted Load
relief
GUJARAT 580 773 580 726 580 1117 590 1025
MADHYA PRADESH 460 468 460 450 460 460 465 490
CHATTISGARH 150 110 150 114 155 117 155 91
MAHARASHTRA 805 1108 810 1200 815 765 820 851
GOA 25 25 25 25 25 25 25 25
UT: DD 10 * 15 * 15 * 15 *
UT: DNH 30 * 30 * 35 * 35 *
Total load relief 2060 2483 2070 2515 2085 2484 2105 2482
* UFRs under procurement
Stage - I 49.2 Hz Stage - II 49.0 Hz Stage - III 48.8 Hz Stage - IV 48.6 Hz
WRLDC
Page 50 of 146
B. Recommended Frequency Trend Relays (df/dt) with changed scenario:
2.11 Transmission Constraints :
Transmission Constraints of Western Region are attached at Annexure III.
2.12 Grid Disturbance: As per CEA guidelines on Grid standards 2010, total 135 Grid disturbances occurred including GD1,
GI-1 and GI-2 in 2014-15. GD-1 56 Nos. , GI1 30 Nos. and GI2 49 Nos.
Detail of disturbance list is enclosed as per Annexure IV.
2.13 Contracts Details in 2014-15:
Details of LOA awarded in 2014-15 are attached at Annexure-V.
DF/DT Scheme in Western Region
STATERequired
Load relief
Implemented
Load relief
Required
Load relief
Implemented
Load relief
Required
Load relief
Implemented
Load relief
GUJARAT 1006 * 905 1454 1001 1610
MADHYA PRADESH 361 475 355 415 392 445
CHATTISGARH 27 120 37 40 120 40
MAHARASHTRA 546 370 621 1131 686 522
**TPC 60 82 273
Total load relief 2000 965 2000 3040 2472 2617
* Gujarat changed the setting of 49.9/0.1Hz/sec to 49.9/0.2 Hz/sec as per discussion in 119th Protection Committee.
The other stage is set at 49.9 /0.3 Hz/sec - Total Load Relief 399 MW
** TPC -Load Relief of 931 MW at 49.9 Hz/0.5 Hz/sec
Stage - I 49.9/0.1 Hz/sec Stage - II 49.9/0.2 Hz/sec Stage - III 49.9/0.4 Hz/sec
WRLDC
Page 51 of 146
CHAPTER - 3
CONSTITUENTS OF WESTERN REGIONS
Western Region comprises states of Gujarat, Maharashtra, Madhya Pradesh, Chhattisgarh, Goa and the Union Territories of Daman & Diu, Dadra and Nagar Haveli
WRLDC
Page 52 of 146
3.1 GUJARAT Gujarat is dense with the population of 6.51 Cr. within an area of 196024 sq. km. The per
capita consumption of this state is 1663 kWh. Installed capacity of Gujarat is 28961 MW as on
31.03.15.
Installed Capacity of Gujarat 28961 MW(Fuel wise break-up)
Source-cea
Central Sector share Allocation-
States Installed
Capacity(MW)
Gujarat share (MW)
% share
KSTPS 2100 360.0 17.14
VSTPS-I 1260 230.0 18.25
VSTPS-II 1000 239.0 23.90
VSTPS-III 1000 266.0 26.60
KGPP 656.2 187.0 28.50
GGPP 657.39 237.0 36.05
SIPAT 1000 273.0 27.30
KAPP 440 125.0 28.41
TAPS 1&2 320 160.0 50.00
TAPP3&4 1080 274.0 25.37
KSTPS7 500 96.0 19.20
SIPAT1 1980 540.0 27.27
VSTPS-IV 1000 239.9 23.99
MSTPS 1000 239.9 23.99
SSP 1450 246.5 17.00
CGPL 3800 1805 47.50
Kahalgaon 1500 141.0 9.40
Total 5659
WRLDC
Page 53 of 146
Demand Profile Gujarat achieved Max demand 14005 MW on 11th October, 2014 at 15:00 hrs. Maximum energy
consumption per day was 312 Mus on 11th October,2014. Gujarat has declared zero load shedding
state. In some of the month even demand availability is more than requirement.
Month Unrest. Dmd Availability Shortage (MW) Shortage (in %)
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 13793 12063 13740 12042 53 21 0.38 0.17
May 13466 12153 13471 12111 -5 42 -0.04 0.35
June 13906 12000 13755 11987 151 13 1.09 0.11
July 13969 10641 13833 10675 136 -34 0.97 -0.32
Aug 12788 11296 12726 11201 62 95 0.48 0.84
Sep 13824 12573 13776 12577 48 -4 0.35 -0.03
Oct 14010 11351 14005 11357 5 -6 0.04 -0.05
Nov 13386 11759 13424 11747 -38 12 -0.28 0.10
Dec 12414 11642 12418 11646 -4 -4 -0.03 -0.03
Jan 12457 11501 12418 11472 39 29 0.31 0.25
Feb 12939 11560 12934 11532 5 28 0.04 0.24
Mar 13419 12087 13414 12083 5 4 0.04 0.03
April May June July Aug Sep Oct Nov Dec Jan Feb Mar
Unrest. Dmd 13793 13466 13906 13969 12788 13824 14010 13386 12414 12457 12939 13419
Availability 13740 13471 13755 13833 12726 13776 14005 13424 12418 12418 12934 13414
9500
10500
11500
12500
13500
14500
De
man
d (
in M
W)
Gujarat Demand 2014-15
April May June July Aug Sep Oct Nov Dec Jan Feb Mar
Unrest. Dmd 12063 12153 12000 10641 11296 12573 11351 11759 11642 11501 11560 12087
Availability 12042 12111 11987 10675 11201 12577 11357 11747 11646 11472 11532 12083
9500
10500
11500
12500
13500
14500
De
man
d (
in M
W)
Gujarat Demand 2013-14
WRLDC
Page 54 of 146
Seasonal Pattern in Daily Max. Demand Met-
312
80
130
180
230
280
330A
pr
May Jun
Jul
Au
g
Sep
Oct
No
v
Dec Jan
Feb
Mar
CO
NSU
MP
TIO
N IN
MU
s -
--->
MONTHS ---->
DAILY CONSUMPTION OF GUJARAT (20010-11 TO 2014-15)
2012-13 2011-12 2010-11 2013-14 2014-15
WRLDC
Page 55 of 146
Load Pattern in Gujarat
Captive Power Plants having black start facilities- GUJARAT
Sr. Name of Voltag
e GETCO S/S
CPP Plant Unit Primary
BSDG BSDG
No. CPP Level Connectivity Capacity
in MW Capacity fuel
Sourc Capacity
1 UPL, Zaghadia
66 220 KV
Zaghadia 48.5 (41+7.5) Gas DG Set 1250 KVA
2 Petronet LNG
220 220 KV Dahej 38 (7.6x 5) Gas DG Set 1750 KVA
3 Videocon Industries Ltd
66 220 KV
Haldarwa 42.14
(3x7.5) (1x9)
(1x7.6) (1x3.0)
Gas DG Set 1250 KVA
4 GNFC 132 220 KV
Achhalia 90.9
(1x33.3) (2x25) (1x7.6)
Gas Coal Gas
DG Set 1000 KVA
5 GACL, Dahej 220 220 KV Dahej 114.03
(2x 39) + 35.2
Mini STG 0.80 MW
Gas DG Set 1000 KVA
6 Essar Oil, Jamnagar
220 220 KV
Jamnagar 599.8
(2x38.5) (2x110) (2x105) (1x92.8)
FO Gas/Napt
hal Coal Coal
DG Set (2x3000
KVA)
7 ONGC, Ankleshwar
66 Wagara 32 (21x11) Gas DG Set 630 KVA
8 RIL, Dahej 220 148.5 Lean Gas DG Set 800 KVA
Total 1114
135801344513119
12848
10000
11000
12000
13000
14000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Hours
GUJARAT Demand 2014-15 (Peak day Quarterly average )
Apr14-Jun14 Jul14-Sep14 Oct14-Dec14 Jan15-Mar15
WRLDC
Page 56 of 146
3.2 MAHARASHTRA
Population of Maharashtra is 11.7 Cr. And area is 3,08,731 sq. km. The per
capita consumption of this state is 1204 kWh. Installed capacity of Maharashtra is 38355 MW
including share from central sector allocation. Maximum energy consumption per day was 434 Mus
on 21st Oct 2014 and Maximum demand met 20424 MW on dt. 26.03.2015 at 12:00 hrs.
Fuel-wise break-up of Installed Capacity 38355 MW
Source-cea
Central Sector Share Allocation
Sl.No. Station Installed Capacity
(in MW) Total
(in MW) % share
1 KSTPS 2100 665.3 31.68
2 KSTPS-7 500 134.3 26.86
3 VSTPS-I 1260 459.34 36.46
4 VSTPS-II 1000 356.29 35.63
5 VSTPS-III 1000 295.29 29.53
6 VSTPS-IV 1000 322.69 32.27
7 KGPP 656.2 204.31 31.14
8 GGPP 657.39 200.37 30.48
9 SIPAT-I 1980 613.37 30.98
10 SIPAT-II 1000 293.44 29.34
11 KAPP 440 150.57 34.22
12 TAPS 1&2 320 160 50.00
13 TAPS 3&4 1080 442.59 40.98
14 MAUDA-I&II 1000 422.69 42.27
15 ER(KHSTPS-II) 1500 148 0.09
16 27% in SSP (1450MW) 1450 391.5 27.00
17 CGPL(20%) 3800 760 20.00
18 Solar power - 20 -
19 EMCO 600 200 33.33
20 Allocation to BARC - 10 -
Total 6250
WRLDC
Page 57 of 146
Power Supply Position
Month Unrest. Dmd Availability Shortage (MW) Shortage (in %)
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 20581 17921 19386 17210 1195 711 5.81 3.97
May 20137 17862 19326 17199 811 811 4.03 4.54
June 19755 16679 19452 16075 303 303 1.54 1.82
July 19385 15040 19283 14919 102 102 0.53 0.68
Aug 18386 16177 17700 15619 686 686 3.73 4.24
Sep 20785 17482 19346 16732 1439 1439 6.92 8.23
Oct 20892 17291 20399 16925 493 493 2.36 2.85
Nov 20469 18325 19629 17591 840 840 4.10 4.58
Dec 19370 18454 19204 17627 166 166 0.86 0.90
Jan 19006 18928 18408 17901 598 598 3.15 3.16
Feb 19702 19622 19372 18510 330 330 1.68 1.68
Mar 20556 19586 20424 18803 132 132 0.64 0.67
WRLDC
Page 58 of 146
Seasonal Pattern in Daily Max. Demand Met-
434
140
190
240
290
340
390
440
490
Ap
r
May Jun
Jul
Au
g
Sep
Oct
No
v
Dec Jan
Feb
Mar
CO
NSU
MP
TIO
N IN
MU
s -
--->
MONTHS ---->
DAILY CONSUMPTION OF MAHRASHTRA(2010-11 TO 2014-15)
2010-11 2011-12 2012-13 2013-14 2014-15
WRLDC
Page 59 of 146
Load Pattern in Maharashtra:
Captive Power Plants having black start facilities - Maharashtra
Sr. No.
Name of CPP Voltage
Level
MSETCL S/S
Connectivity
CPP Plant
capacity (in MW)
Unit capacity
Primary fuel
BSDG source BSDG capac
ity Remark
1 Uttam Galva
Steels Ltd 100 KV
Tambati s/s
60 2*30 MW
Coal
Not avilable ( remark -
we have DG set capacity of -500 KVA, o/p voltage-
415 volt, besically it is
lighting purpose and emergancy oil system,
not for synchronzat
ion)
19323
18624
1954319263
14000
15000
16000
17000
18000
19000
20000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Hours
MAH. Demand 2014-15 (Peak day Quarterly average )
Apr14-Jun14 Jul14-Sep14 Oct14-Dec14 Jan15-Mar15
WRLDC
Page 60 of 146
Sr. No.
Name of CPP Voltage
Level
MSETCL S/S
Connectivity
CPP Plant
capacity (in MW)
Unit capacity
Primary fuel
BSDG source BSDG capac
ity Remark
2
Sai Wardha Power
Limited,Warora
220 KV 220KV
Warora S/S
270 MW(CP
P)
2*135MW
Coal 2 DG Set 2*875KVA
During Station
black out condition
DG Set available for Emergency equipment
start up only (like TG
Barring,Scanner fan&
emergency lighting etc) not for unit
startup.
3 GEPL POWER
PLANT 220 KV
MIDC CHANDRAPUR 220 KV DOUBLE CKT LINE
120 MW 2*60 MW
COAL AND
WASHERY
REJECT
DG SET 2*
600 KVA
4
MVNL BIOMASS POWER PLANT
132 KV
MIDC DEOLI 132 KV SINGLE
CKT LINE
10 MW 1*10 MW
BIOMASS
DG SET 180 KVA
5 Dhariwal
Infrastructure Ltd
DG SET 2 X
1500 KVA
do not have black start facility & provide power
supply for emergency auxiliaries
only.
6 JSWEL
1200 MW (TPS)
DG SET
Dont have any
blackstart capability &
only capablefor providing
power forsafe
shutdown during
blackout.
WRLDC
Page 61 of 146
Sr. No.
Name of CPP Voltage
Level
MSETCL S/S
Connectivity
CPP Plant
capacity (in MW)
Unit capacity
Primary fuel
BSDG source BSDG capac
ity Remark
7 VIPL 220 KV
VIPL 220 KV switchy
ard connectivity at Butibori S/S-1
and S/S-3
600 MW 2*300 MW
DG SET 3*10
50 KVA
Black Start facility not available in VIPL & for keeping
emergency equipment in service
during AC failure or
Station black out condition
only
Total 1060
3.3 MADHYA PRADESH :
Population of Madhya Pradesh is 7.7 Cr. within an area of 308144 sq. km. The per capita
consumption of this state is 672 kWh. Installed capacity of Madhya Pradesh is 15845 MW.
Fuel-wise break-up of Installed Capacity 15845 MW:
Source -cea
WRLDC
Page 62 of 146
Central Sector Share Allocation-
States Installed Capacity
(in MW)
Shared Capacity (in
MW) % Share
KSTPS 2100 478 22.78
VSTPS-I 1260 440 34.94
VSTPS-II 1000 316 31.59
VSTPS-III 1000 243 24.29
KGPP 656.2 140 21.36
GGPP 657.39 117 17.82
SIPAT 1000 185 18.50
KAPP 440 111 25.12
TAPP3&4 1080 229 21.20
KSTPS7 500 75 14.94
SIPAT1 1980 331 16.73
VSTPS-IV 1000 281 28.08
MSTPS 1000 181 18.08
SSP 1450 812 56.00
*Sasan 2640 1396 37.5
J P nigrie 1320 465 35.25
M B power 1200 395 32.90
DVC - 400 -
DSTPS 1000 100 10.00
Kahalgaon 1500 70 4.65
Torrent Power 400 100 25.00
NR (Rihand and
Matatila) - 55 -
Total 6920
* allocation on contract capacity of 620.5 MW/unit.
Power Supply Position
The maximum demand met of MP was 10050 MW on 9th December14 at 09:00 hrs. The maximum
energy consumption was 207 Mus on 2nd December 2014.
Month Unrest. Dmd Availability Shortage (MW) Shortage (%)
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 7275 7579 7271 7543 4 36 0.05 0.47
May 7215 7234 7159 7260 56 -26 0.78 -0.36
June 7434 7817 7120 7832 314 -15 4.22 -0.19
July 7121 5811 7090 5821 31 -10 0.44 -0.17
Aug 8227 5949 7669 5919 558 30 6.78 0.50
Sep 8414 7804 8419 7558 -5 246 -0.06 3.15
Oct 8717 7932 8750 7937 -33 -5 -0.38 -0.06
Nov 9812 9816 9832 9807 -20 9 -0.20 0.09
Dec 10089 9963 10050 9972 39 -9 0.39 -0.09
Jan 9812 9445 9766 9334 46 111 0.47 1.18
Feb 9307 9385 9345 9346 -38 39 -0.41 0.42
Mar 7180 6988 7185 7008 -5 -20 -0.07 -0.29
WRLDC
Page 63 of 146
April May June July Aug Sep Oct Nov Dec Jan Feb Mar
Unrest. Dmd 7275 7215 7434 7121 8227 8414 8717 9812 10089 9812 9307 7180
Availability 7271 7159 7120 7090 7669 8419 8750 9832 10050 9766 9345 7185
0
2000
4000
6000
8000
10000
12000
De
man
d (
in M
W)
Madhya Pradesh Demand 2014-15
April May June July Aug Sep Oct Nov Dec Jan Feb Mar
Unrest. Dmd 7579 7234 7817 5811 5949 7804 7932 9816 9963 9445 9385 6988
Availability 7543 7260 7832 5821 5919 7558 7937 9807 9972 9334 9346 7008
0
2000
4000
6000
8000
10000
12000
De
man
d (
in M
W)
Madhya Pradesh Demand 2013-14
WRLDC
Page 64 of 146
Seasonal Pattern in Daily Max. Demand Met-
WRLDC
Page 65 of 146
Load Pattern in Madhya Pradesh
List of Captive Power Plants (CPP) - MP
S.No.
NAME
VOLTAGE
LEVEL(KV)
FEEDERNAME
TOTAL CAPACITY MW
INSTALLED CAPACITY IN
MW
PRIMARY
FUEL USED
BSDG SOURC
E
BSDG CAPACI
TY
1 MAHAN ALUMINIUM PROJECT PLANT OF
M/S HINDALCO 220
220 KV MAHAN
ALUMINIUM 600
1st Unit-1x150 w.e.f -
09.03.2013
Coal DG SET
2x2000 KVA
3x7500 KVA
2nd Unit-1x150 w.e.f-
21.05.2013
3rd Unit-1x150 w.e.f-
07.12.2014
4th Unit-1x150
2 M/s VARDHMAN
FABRICS BUDHNI 132
132 KV VARDHMAN
FABRICS 24 1x24 Coal DG SET
5X2000 KVA
3 M/s HEG LTD MANDIDEEP 132
132 KV HEG LTD
MANDIDEEP 63 1x30+1x33 Coal DG SET
2X500 KVA
4 M/s VARDHMAN
YARNS 132
132 KV VARDHMAN
YARNS 30.75 1x30.75 Coal DG SET
4X2000 KVA
WRLDC
Page 66 of 146
S.No.
NAME
VOLTAGE
LEVEL(KV)
FEEDERNAME
TOTAL CAPACITY MW
INSTALLED CAPACITY IN
MW
PRIMARY
FUEL USED
BSDG SOURC
E
BSDG CAPACI
TY
5 M/s ACC KYMORE 132 132KV ACC KYMORE 50 2x25 Coal
DG SET
1X3250 KVA
6 M/s JP Rewa Cement
,REWA 132
132 KV JP Rewa
Cement 63.5 1x63.5
7 M/s J P SIDHI
CEMENT PLANT 132 132KV J P
SIDHI 95 1x35+1x60 Coal DG SET
2x7875 KVA
8
M/s VIKARAM CEMENT
,NEEMUCH(ULTRATECH) 132
132KV VIKARAM CEMENT 46 2x23 Coal
DG SET
3X6000 KVA
9 M/s GRASIM
INDUSTRIES NAGDA 132
132KV GRASIM
INDUSTRIES 116.5 40+30+30+16.
5 Coal DG SET
3X6000 KVA
10 M/s BIRLA CORP LTD
SATNA 132
132 KV Satna
Cement 43.5 1x27+2x7.5+1x
1.5
11 M/s HEG TAWA 33 33KV HEG
TAWA 13.5 2x6.75 Hydro DG SET
1X200 KVA
12 M/s MCPL
MALANPUR 33 33 KV MCPL 26.19 3x8.73 RLNG DG SET
1X160 KVA
13
M/s NATIONAL STEEL & AGRO
LTD,GHATABILLOD 33
33KV NATIONAL
STEEL 6.03 3x2.01 RLNG DG SET
1X437.5 KVA
1X1.25 KVA
14 M/s MARAL
OVERSEAS NIMRANI 33
33KV MARAL
OVERSEAS NIMRANI 10 1x10 Coal
DG SET
1X5477 KVA
1X5213 KVA
15 M/s KAMAL SPONG
POWER LTD 33
33KV KAMAL SPONG
POWER LTD 12 1x12 Coal DG SET
1X750 KVA
16
M/s Bharat Oman Refineries Ltd. (BORL), Bina 132
132KV BINA-BORL CKT-I
& II 99 3x33
17 M/s J.P. Cement, Bela 132 132KV JP BELA CKT 25 1x25
18 M/s Maihar Cement
Ltd., Maihar 132
132 KV Maihar
Cement Ckt 30.3 1x30.3
19 M/s Raymonds Ltd.,
Sausar 33
33KV Raymonds
Ckt 10 1x10
20
M/s HJI-Division of Orient Paper Mills,
Amlai 132
132KV AMARKANTAK-HJM CKT 77 6+16+25+30 Coal
21
M/s Trimula Industries Ltd., Singrauli (Waste
Heat Recovery) 33 33kV Trimula
Industries 12 12
22 M/s KJS Cement Ltd.
Maihar 132 132KV KJS 27 1x27 Coal DG SET
3X1500 KVA
TOTAL 1480
WRLDC
Page 67 of 146
3.4 CHHATTISGARH :
Chhattisgarh is power surplus state with installed capacity of 13085 MW. It is dense with the
population of 2.55 Cr. within an area of 1,35,194 sq. km. The per capita consumption of this
state is 1320 kWh.
Fuel-wise break-up of Installed Capacity 13085 MW
Source-cea
Allocation from Central Sector Generating Stations
Chhattisgarh
Utility Installed
Capacity(MW)
Chhattisgarh
share(MW) % share
KSTPS 2100.00 210.00 10.00
VSTPS-III 1000.00 105.00 10.50
SIPAT 1000.00 158.00 15.80
TAPP3&4 1080.00 48.00 4.44
KSTPS7 500.00 150.00 30.00
SIPAT1 1980.00 313.00 15.81
VSTPS-IV 1000.00 62.55 6.26
MSTPS 1000.00 62.55 6.26
Kahalgaon 1500.00 30.00 2.00
Total 1139
120, 1%
12593, 96%
0, 0%
48, 0%324, 3%
CHHATISGARH
Hydro Coal Gas Nuclear RES
WRLDC
Page 68 of 146
Power Supply Position Chhattisgarh has met its maximum demand of 3770 MW on dt.24th Mar 2015 at 20:00 hrs and
maximum energy consumption of 88.34 Mus achieved on 27th March,2015.
Month Unrest. Dmd Availability Shortage (MW) Shortage (%)
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 3638 3505 3486 3459 152 46 4.18 1.31
May 3340 3355 3336 3254 4 101 0.12 3.01
June 3473 2917 3472 2793 1 124 0.03 4.25
July 3414 3089 3118 3050 296 39 8.67 1.26
Aug 3519 3268 3354 3091 165 177 4.69 5.42
Sep 3654 3314 3295 3292 359 22 9.82 0.66
Oct 3530 3048 3438 3048 92 0 2.61 0.00
Nov 3240 2773 3078 2770 162 3 5.00 0.11
Dec 3348 2991 3249 2993 99 -2 2.96 -0.07
Jan 3372 3183 3269 3151 103 32 3.05 1.01
Feb 3777 3246 3625 3210 152 36 4.01 1.11
Mar 3950 3702 3770 3448 180 254 4.56 6.86
WRLDC
Page 69 of 146
Seasonal Pattern in Daily Max. Demand Met-
WRLDC
Page 70 of 146
Load Pattern in Chhattisgarh
3.5 GOA :
Goa is dense with the population of 0.18 Cr. within an area of 3702 sq. km. The per capita
consumption of this state is 2025 kWh. Allocation from central sector stations to Goa is 400 MW, out
of which coal, gas and neuclear fuel are in the ratio of 82% : 12% : 6%.
Source-cea
Allocation from Central Sector-
States Installed
Capacity(MW) Goa Share (MW) % share
KSTPS 2100.00 210.55 10.03
VSTPS-I 1260.00 35.50 2.82
0.00, 0%
326.17, 82%
48.00, 12% 25.80, 6%
0.05, 0%GOA
Hydro Coal Gas Nuclear RES
WRLDC
Page 71 of 146
States Installed
Capacity(MW) Goa Share (MW) % share
VSTPS-II 1000.00 12.37 1.24
VSTPS-III 1000.00 10.37 1.04
KGPP 656.20 12.37 1.89
GGPP 657.39 12.63 1.92
SIPAT 1000.00 10.36 1.04
KAPP 440.00 15.14 3.44
TAPP3&4 1080.00 11.50 1.06
KSTPS7 500.00 4.76 0.95
SIPAT1 1980.00 21.04 1.06
VSTPS-IV 1000.00 11.72 1.17
MSTPS 1000.00 11.72 1.17
RGPPL (Dabhol) 1967 19.67 1.00
Total 399.67
WRLDC
Page 72 of 146
3.6 DAMAN & DIU :
Month Unrest. Dmd Availability Shortage (MW) Shortage
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 290 279 290 276 0 3 0.00 1.08
May 272 273 272 248 0 25 0.00 9.16
June 290 248 290 247 0 1 0.00 0.40
July 287 269 287 239 0 30 0.00 11.15
Aug 287 267 287 264 0 3 0.00 1.12
Sep 287 263 287 262 0 1 0.00 0.38
Oct 261 271 261 266 0 5 0.00 1.85
Nov 280 253 279 238 1 15 0.36 5.93
Dec 272 283 272 283 0 0 0.00 0.00
Jan 271 258 270 258 1 0 0.37 0.00
Feb 289 268 289 268 0 0 0.00 0.00
Mar 291 270 291 270 0 0 0.00 0.00
WRLDC
Page 73 of 146
WRLDC
Page 74 of 146
Allocation from Central Sector Generating Stations DD
States Installed
Capacity(MW) DD Share (MW) % share
KSTPS 2100 43.81 2.09
VSTPS-I 1260 8.40 0.67
VSTPS-II 1000 5.57 0.56
VSTPS-III 1000 7.57 0.76
KGPP 656 31.01 4.73
GGPP 657 31.34 4.77
SIPAT 1000 6.44 0.64
KAPP 440 6.93 1.58
TAPP3&4 1080 8.42 0.78
KSTPS7 500 3.40 0.68
SIPAT1 1980 15.12 0.76
VSTPS-IV 1000 7.49 0.75
MSTPS 1000 7.49 0.75
NSPCL 500 70 14.00
RGPPL(Dabhol) 1967 38.36 2.00
Total 291
3.7 DADRA NAGAR HAVELI :
Month Unrest. Dmd Availability Shortage (MW) Shortage
2014-15 2013-14 2014-15 2013-14 2014-15 2013-14 2014-15 2013-14
April 685 612 685 609 0 3 0.00 0.49
May 665 606 665 583 0 23 0.00 3.80
June 685 598 685 596 0 2 0.00 0.33
July 721 639 721 610 0 29 0.00 4.54
Aug 721 639 721 637 0 2 0.00 0.31
Sep 721 640 721 637 0 3 0.00 0.47
Oct 681 658 681 653 0 5 0.00 0.76
Nov 658 646 656 645 2 1 0.30 0.15
Dec 681 646 681 646 0 0 0.00 0.00
Jan 674 654 672 654 2 0 0.30 0.00
Feb 693 644 692 644 1 0 0.14 0.00
Mar 712 640 712 640 0 0 0.00 0.00
WRLDC
Page 75 of 146
WRLDC
Page 76 of 146
Allocation from Central Sector Generating Stations DNH
States Installed
Capacity(MW) DNH Share (MW) % share
KSTPS 2100.00 63.69 3.03
VSTPS-I 1260.00 52.90 4.20
VSTPS-II 1000.00 40.20 4.02
VSTPS-III 1000.00 42.20 4.22
KGPP 656.20 81.29 12.39
GGPP 657.39 58.81 8.95
SIPAT 1000.00 38.41 3.84
KAPP 440.00 15.17 3.45
TAPS 1&2 320.00 0.00 0.00
TAPP3&4 1080.00 55.15 5.11
KSTPS7 500.00 27.54 5.51
SIPAT1 1980.00 109.36 5.52
VSTPS-IV 1000.00 56.24 5.62
MSTPS 1000.00 56.24 5.62
NSPCL 500 100 20.00
RGPPL(Dabhol) 1967 38.36 2.00
EMCO 600 200 33.33
Total 1036
WRLDC
Page 77 of 146
CHAPTER - 4
MARKET OPERATIONS
4.1 Schedule Vs Drawal for WR constituents and generators (SEM data)-
Constituent-wise Drawal Data (MU)- Gujarat
Maharashtra
Month MUs
Schedule Drawal Deviation
Apr'14 1595.06 1530.07 -64.99
May'14 1407.39 1306.06 -101.33
Jun'14 1327.33 1198.91 -128.42
July'14 1190.82 1129.75 -61.07
Aug'14 1281.42 1236.38 -45.04
Sep'14 2370.43 2333.04 -37.39
Oct'14 1681.37 1638.01 -43.37
Nov'14 1760.27 1695.85 -64.42
Dec'14 1433.99 1376.53 -57.46
Jan'15 1488.73 1427.37 -61.36
Feb'15 1832.48 1848.46 15.99
Mar'15 2125.02 2136.20 11.17
2014-15 19494.32 18856.63 -637.69
Month MUs
Schedule Drawal Deviation
Apr'14 3681.62 3781.15 99.53
May'14 3701.50 3731.03 29.53
Jun'14 3398.47 3450.99 52.52
July'14 2906.18 2806.95 -99.23
Aug'14 3070.32 3042.65 -27.68
Sep'14 3620.01 3522.03 -97.98
Oct'14 4467.31 4371.79 -95.52
Nov'14 3399.89 3251.96 -147.92
Dec'14 3191.24 3018.29 -172.95
Jan'15 3093.24 3025.07 -68.17
Feb'15 3347.57 3249.86 -97.71
Mar'15 3057.10 2994.88 -62.22
2014-15 40934.47 40246.65 -687.82
WRLDC
Page 78 of 146
Madhya Pradesh
Chhattisgarh
Month MUs
Schedule Drawal Deviation
Apr'14 2255.69 2240.85 -14.84
May'14 2436.07 2426.06 -10.01
Jun'14 2342.85 2288.95 -53.90
July'14 2385.13 2365.27 -19.85
Aug'14 2333.48 2259.05 -74.43
Sep'14 2164.38 2170.36 5.98
Oct'14 3008.25 3008.38 0.13
Nov'14 3694.78 3680.89 -13.88
Dec'14 3345.46 3318.54 -26.92
Jan'15 2565.00 2531.23 -33.77
Feb'15 2693.63 2652.48 -41.15
Mar'15 2183.64 2128.23 -55.41
2014-15 31408.36 31070.30 -338.06
Month MUs
Schedule Drawal Deviation
Apr'14 660.51 661.58 1.07
May'14 600.35 574.03 -26.32
Jun'14 490.11 498.53 8.42
July'14 558.14 574.72 16.58
Aug'14 549.72 580.77 31.05
Sep'14 656.07 673.79 17.72
Oct'14 427.85 416.72 -11.13
Nov'14 317.76 309.05 -8.71
Dec'14 471.21 474.76 3.55
Jan'15 617.12 615.24 -1.88
Feb'15 663.17 665.72 2.55
Mar'15 839.17 864.00 24.83
2014-15 6851.18 6908.91 57.73
WRLDC
Page 79 of 146
Goa
Daman & Diu
Month MUs
Schedule Drawal Deviation
Apr'14 230.89 244.39 13.49
May'14 254.74 262.84 8.10
Jun'14 227.39 248.12 20.72
July'14 213.07 234.58 21.50
Aug'14 207.22 230.45 23.23
Sep'14 230.32 241.71 11.40
Oct'14 257.80 260.00 2.20
Nov'14 224.04 227.28 3.24
Dec'14 220.25 224.65 4.40
Jan'15 223.12 217.57 -5.55
Feb'15 209.88 213.48 3.60
Mar'15 244.59 251.36 6.77
2014-15 2743.31 2856.43 113.13
Month MUs
Schedule Drawal Deviation
Apr'14 180.40 183.02 2.62
May'14 180.08 180.66 0.58
Jun'14 180.17 183.02 2.86
July'14 171.65 187.39 15.74
Aug'14 161.58 180.12 18.54
Sep'14 178.50 178.63 0.13
Oct'14 170.99 168.52 -2.47
Nov'14 178.37 174.88 -3.49
Dec'14 181.19 177.58 -3.60
Jan'15 174.11 169.79 -4.31
Feb'15 171.13 171.19 0.06
Mar'15 189.72 193.26 3.54
2014-15 2117.87 2148.05 30.18
WRLDC
Page 80 of 146
Dadar Nagar Haveli
Essar Steel(Hazira)
Month DNH
Schedule Drawal Deviation
Apr'14 439.66 446.19 6.54
May'14 467.24 474.10 6.86
Jun'14 441.81 447.06 5.25
July'14 465.91 463.73 0.14
Aug'14 445.85 458.13 12.29
Sep'14 444.37 443.40 -0.98
Oct'14 441.52 440.40 -1.12
Nov'14 437.62 440.67 3.06
Dec'14 471.72 470.78 -0.94
Jan'15 461.70 463.06 1.36
Feb'15 435.89 430.64 -5.25
Mar'15 488.30 479.63 -8.67
2014-15 5441.58 5457.78 18.53
Month ESIL
Schedule Drawal Deviation
Apr'14 307.40 296.00 -11.40
May'14 332.57 313.74 -18.84
Jun'14 291.15 279.94 -11.21
July'14 252.53 203.59 -48.95
Aug'14 243.86 245.23 1.37
Sep'14 176.23 186.81 10.58
Oct'14 221.56 220.89 -0.67
Nov'14 245.50 238.32 -7.18
Dec'14 233.41 235.65 2.24
Jan'15 213.67 218.24 4.58
Feb'15 185.76 191.91 6.16
Mar'15 321.88 315.39 -6.49
2014-15 3025.52 2945.72 -79.80
WRLDC
Page 81 of 146
Station-wise Injection Data (MU)-
(Schedule, Injection & Deviation)
KSTPS
KSTPS III
Month MUs
Schedule Injection Deviation
Apr'14 1222.10 1234.54 12.44
May'14 1270.05 1281.09 11.04
Jun'14 1293.08 1309.97 16.90
July'14 1015.07 1024.91 9.84
Aug'14 1109.68 1121.10 11.43
Sep'14 1256.45 1262.10 5.65
Oct'14 1372.20 1384.78 12.59
Nov'14 1204.70 1208.36 3.66
Dec'14 1289.39 1288.62 -0.77
Jan'15 1397.03 1400.13 3.10
Feb'15 1321.79 1320.12 -1.67
Mar'15 1263.77 1273.91 10.14
2014-15 15015.29 15109.64 94.35
Month MUs
Schedule Injection Deviation
Apr'14 286.65 288.98 2.33
May'14 346.96 348.71 1.75
Jun'14 334.09 336.15 2.06
July'14 282.67 285.62 2.95
Aug'14 130.14 131.45 1.31
Sep'14 305.10 308.00 2.90
Oct'14 334.20 337.47 3.27
Nov'14 305.41 305.97 0.56
Dec'14 338.68 339.85 1.17
Jan'15 346.56 347.62 1.07
Feb'15 317.75 317.91 0.17
Mar'15 344.42 346.85 2.43
2014-15 3672.62 3694.58 21.96
WRLDC
Page 82 of 146
VSTPS I
VSTPS II
Month MUs
Schedule Injection Deviation
Apr'14 663.58 673.89 10.32
May'14 729.94 733.41 3.47
Jun'14 787.32 789.90 2.58
July'14 660.25 665.14 4.89
Aug'14 480.57 485.78 5.22
Sep'14 613.79 620.32 6.53
Oct'14 685.88 695.12 9.24
Nov'14 682.36 693.07 10.70
Dec'14 617.95 606.83 -11.12
Jan'15 541.70 563.59 21.89
Feb'15 595.84 605.05 9.20
Mar'15 542.76 567.71 24.95
2014-15 7601.95 7699.82 97.87
Month MUs
Schedule Injection Deviation
Apr'14 654.94 657.73 2.79
May'14 674.59 672.31 -2.28
Jun'14 329.14 328.33 -0.81
July'14 488.29 491.55 3.26
Aug'14 453.92 458.56 4.65
Sep'14 586.88 592.88 6.00
Oct'14 432.87 439.00 6.14
Nov'14 591.09 593.35 2.26
Dec'14 522.56 539.62 17.05
Jan'15 573.83 589.89 16.05
Feb'15 569.65 570.66 1.01
Mar'15 573.10 588.73 15.63
2014-15 6450.86 6522.61 71.74
WRLDC
Page 83 of 146
VSTPS III
VSTPS IV
Month MUs
Schedule Injection Deviation
Apr'14 691.87 700.44 8.58
May'14 631.19 635.91 4.72
Jun'14 679.94 685.01 5.07
July'14 600.50 606.35 5.84
Aug'14 379.76 384.26 4.50
Sep'14 193.58 196.19 2.62
Oct'14 619.99 633.95 13.96
Nov'14 597.06 604.83 7.77
Dec'14 547.16 564.52 17.36
Jan'15 582.79 600.46 17.66
Feb'15 559.22 562.14 2.91
Mar'15 575.06 585.02 9.96
2014-15 6658.12 6759.07 100.95
Month MUs
Schedule Injection Deviation
Apr'14 629.74 635.78 6.04
May'14 646.85 645.68 -1.17
Jun'14 641.72 642.53 0.81
July'14 409.07 410.51 1.43
Aug'14 365.54 370.85 5.31
Sep'14 507.09 516.04 8.95
Oct'14 552.93 560.47 7.53
Nov'14 591.83 594.65 2.81
Dec'14 552.64 561.01 8.37
Jan'15 575.01 583.32 8.31
Feb'15 599.89 595.11 -4.79
Mar'15 534.97 544.33 9.35
2014-15 6607.28 6660.25 52.97
WRLDC
Page 84 of 146
Mauda
Sipat I
Month MUs
Schedule Injection Deviation
Apr'14 358.60 347.34 -11.26
May'14 321.89 302.43 -19.46
Jun'14 205.05 194.05 -11.00
July'14 204.88 193.51 -11.37
Aug'14 291.81 258.58 -33.23
Sep'14 314.10 290.00 -24.10
Oct'14 268.86 240.06 -28.80
Nov'14 64.99 34.82 -30.17
Dec'14 50.44 6.81 -43.63
Jan'15 68.03 18.89 -49.14
Feb'15 62.42 20.48 -41.93
Mar'15 197.90 189.41 -8.49
2014-15 2408.96 2096.39 -312.57
Month MUs
Schedule Injection Deviation
Apr'14 1288.40 1303.73 15.33
May'14 848.27 853.56 5.28
Jun'14 822.14 831.78 9.65
July'14 905.65 923.75 18.10
Aug'14 1277.37 1293.34 15.97
Sep'14 1256.80 1261.98 5.19
Oct'14 1190.94 1188.32 -2.62
Nov'14 1277.13 1268.82 -8.31
Dec'14 1282.67 1275.28 -7.39
Jan'15 1122.04 1138.20 16.15
Feb'15 1161.83 1162.10 0.27
Mar'15 1068.61 1074.67 6.05
2014-15 13501.85 13575.52 73.67
WRLDC
Page 85 of 146
Sipat-II
Kawas
Month MUs
Schedule Injection Deviation
Apr'14 596.77 606.73 9.96
May'14 652.00 654.98 2.98
Jun'14 618.52 629.50 10.98
July'14 542.85 555.75 12.89
Aug'14 300.82 306.16 5.34
Sep'14 500.05 505.10 5.05
Oct'14 607.86 608.11 0.24
Nov'14 640.12 633.27 -6.85
Dec'14 690.76 682.43 -8.33
Jan'15 592.09 598.07 5.98
Feb'15 596.34 595.51 -0.82
Mar'15 630.50 632.57 2.16
2014-15 6968.69 7008.19 39.58
Month MUs
Schedule Injection Deviation
Apr'14 175.69 179.71 4.02
May'14 214.88 215.38 0.50
Jun'14 166.59 169.23 2.64
July'14 99.57 99.93 0.35
Aug'14 169.07 169.99 0.92
Sep'14 162.61 164.44 1.83
Oct'14 181.02 182.15 1.14
Nov'14 117.95 117.89 -0.06
Dec'14 114.40 113.69 -0.70
Jan'15 72.92 71.38 -1.54
Feb'15 104.73 102.56 -2.17
Mar'15 102.00 100.30 -1.70
2014-15 1681.43 1686.65 5.22
WRLDC
Page 86 of 146
Gandhar
CGPL
Month MUs
Schedule Injection Deviation
Apr'14 179.97 184.60 7.11
May'14 251.06 256.33 5.27
Jun'14 190.64 198.58 7.94
July'14 154.68 156.34 1.66
Aug'14 181.70 182.75 1.05
Sep'14 161.55 162.29 0.74
Oct'14 206.36 208.40 2.04
Nov'14 93.57 92.26 -1.31
Dec'14 13.40 9.05 -4.35
Jan'15 7.94 5.65 -2.29
Feb'15 27.82 25.73 -2.09
Mar'15 83.36 82.55 -0.82
2014-15 1552.05 1564.53 14.96
Month MUs
Schedule Injection Deviation
Apr'14 1970.61 1976.01 5.40
May'14 2045.15 2042.56 -2.59
Jun'14 2055.49 2059.54 4.05
July'14 1805.64 1812.20 6.56
Aug'14 1670.12 1686.06 15.94
Sep'14 1757.94 1766.60 8.66
Oct'14 1831.14 1831.11 -0.03
Nov'14 2484.64 2477.18 -7.46
Dec'14 2438.97 2432.88 -6.10
Jan'15 2353.45 2357.55 4.09
Feb'15 2104.59 2102.66 -1.93
Mar'15 1936.77 1944.48 7.71
2014-15 24454.53 24488.83 34.31
WRLDC
Page 87 of 146
Sasan
Jindal Power Ltd.
Month MUs
Schedule Injection Deviation
Apr'14 919.90 927.60 7.71
May'14 882.16 887.54 5.38
Jun'14 1196.84 1205.14 8.30
July'14 1411.33 1423.32 11.99
Aug'14 1426.58 1443.01 16.44
Sep'14 1255.49 1288.01 32.52
Oct'14 1030.13 1066.91 36.78
Nov'14 1429.23 1448.38 19.15
Dec'14 1465.56 1473.96 8.41
Jan'15 790.50 798.56 8.07
Feb'15 1526.70 1543.62 16.91
Mar'15 1323.54 1352.60 29.07
2014-15 14657.95 14858.67 200.72
Month MUs
Schedule Injection Deviation
Apr'14 582.06 586.82 4.76
May'14 600.61 605.04 4.43
Jun'14 570.21 561.06 -9.15
July'14 584.49 584.97 0.48
Aug'14 530.16 547.32 17.16
Sep'14 569.24 572.82 3.58
Oct'14 582.25 594.70 12.45
Nov'14 562.36 576.12 13.77
Dec'14 561.17 568.85 7.68
Jan'15 582.94 599.05 16.11
Feb'15 392.58 402.93 10.36
Mar'15 402.44 407.23 5.05
2014-15 6520.50 6606.92 86.67
WRLDC
Page 88 of 146
LANCO
KAPS
Month MUs
Schedule Injection Deviation
Apr'14 185.98 188.46 2.49
May'14 193.56 194.84 1.28
Jun'14 191.06 193.44 2.37
July'14 191.43 195.07 3.64
Aug'14 113.73 114.52 0.79
Sep'14 131.31 132.42 1.11
Oct'14 202.07 204.03 1.96
Nov'14 179.68 179.72 0.04
Dec'14 165.83 167.70 1.87
Jan'15 162.79 165.51 2.73
Feb'15 144.58 146.19 1.61
Mar'15 151.01 153.07 2.06
2014-15 2013.04 2034.99 21.95
Month MUs